AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to extend the Bid Opening Date and to update Sections 00 10 00, 00 70 00, and Specifications under Section 35 20 23.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 19-Oct-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912HP18B0004
X 9B. DATED (SEE ITEM 11)
06-Sep-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Oct-2018
CODE
U.S. ARMY CORPS OF ENGINEERS, CHARLESTON
DISTRICT, CONTRACTING DIVISION
69-A HAGOOD AVENUE
CHARLESTON SC 29403
W912HP 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912HP18B0004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
SUMMARY OF CHANGES
1. SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 25-Oct-2018 2:00 PM to 1-Nov-2018 2:00 PM.
2. SECTION 00 10 00 - SOLICITATION
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) - ALTERNATE I (APR 1984), (a) Prosecution of Work, DELETE “The actual dredging work required shall be completed in its entirety, including cleanup operations by 30 September 2020, with the maintenance dredging requirement of Acceptance Sections 5, 6, 7, and 8 being completed within 120 days of receipt of the NTP.” and REPLACE with “The actual dredging work required shall be completed in its entirety, including cleanup operations by 12 February 2021, with the maintenance dredging requirement of Acceptance Sections 5, 6, 7, and 8 being completed within 120 days of receipt of the NTP.”
3. SECTION 35 20 23 DREDGING, SUBPARAGRAPH “ESTIMATED QUANTITIES”
DELETE table from subparagraph, and REPLACE with the table below. Stations in RED have been corrected, and match the stationing on the contract drawings.
REQUIRED
MAINTENANC
E DREDGING
PRISM
REQUIRE
D NEW
WORK
DREDGIN
G PRISM
ALLOWABL
E
OVERDEPT
H PRISM
TOTAL ACCEPTANC
E
SECTION
NO. LOCATION CY MEAS. *
CY
MEAS.*
CY MEAS.** CY MEAS.
BASE
1 Mt. Pleasant Reach 6,000 419,000 370,000 795,000
1084+79 to 1195+00
2 Rebellion Reach 24,000 613,000 337,000 974,000
1195+00 to 1262+71
3 Bennis Reach 24,000 910,000 428,000 1,362,000
1267+71 to 1340+67
4 Horse Reach 8,000 256,000 91,000 355,000
1340+67 to 1369+67
5 Hog Island Reach 183,000 1,618,000 333,000 2,134,000
1369+67 to 1465+80 165,000*** 165,000***
6 Lower Wando Reach 100,000 1,324,000 205,000 1,629,000
1+54 to 78+86 90,000*** 90,000***
W912HP18B0004
7 Upper Wando Reach 145,000 472,000 107,000 724,000
78+86 to 126+43 73,000*** 73,000***
Wando River Turning Basin
135,000 2,316,000 150,000 2,601,000
78+86 to 123+20 68,000*** 68,000***
OPTIONS
Wando Welch Terminal Berth -
155,000 45,000 200,000
84+88 to 126+20
TOTAL
S
1,021,000 8,083,000 2,066,000 11,170,000
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 25-Oct-2018 02:00 PM to 01-Nov-2018 02:00 PM.
(End of Summary of Changes)