Bidding_Schedule_AM_1.pdf

PDF 16 KB Posted

Attached to
CHARLESTON LOWER HARBOR DREDGING Federal contract opportunity
Solicitation number
W912HP-17-B-0006
Issued by
Department of the Army Corps of Engineers Engineering District Charleston

About this file

Bidding Schedule

View the file

Other files for this federal contract opportunity

Other files attached to CHARLESTON LOWER HARBOR DREDGING, newest first.
File Type Posted
B.01.02_Bid_Opening_Sign-In_Sheet_W912HP17B0006_20170831..pdf PDF
B.01.02_Abtracts_of_Offers_W912HP-17-B-0006_20170831..pdf PDF
20170801_CHL_SH5-MB_MB_CT.xyz XYZ file
A.01.24_Solicitation_Amendment_W912HP17B000601_20170817.pdf PDF
20170801_CHL_SH6_DIR_MB_CT.xyz XYZ file
20170801_CHL_SH7_WRLR_MB_CT.xyz XYZ file
20170802_CHL_SH1_HIR_MB_CT.xyz XYZ file
20170801_CHL_SH8-9_WRUR-WRTB_MB_CT.xyz XYZ file
9_Section_01_57_20.00_10_Environmental_AM_1.pdf PDF
Contract_Drawings_REVa.pdf PDF
20170718_CHL_DIR_MB_CT.xyz XYZ file
RTA_Specifications.pdf PDF
A.01.23_Solicitation_W912HP17B0006_20170801.pdf PDF
RTA_Drawings.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY17 CHARLESTON LOWER HARBOR W912HP-17-B-0006

MAINTENANCE DREDGING

Section 00 10 00 Page 2

SECTION 00 10 00

BIDDING SCHEDULE

ITEM

NO. DESCRIPTION ESTIMATED

QUANTITY U/I UNIT PRICE AMOUNT

BASE

0001 MOBILIZATION AND

DEMOBILIZATION –

MAINTENANCE DREDGING IN

CHARLESTON LOWER HARBOR

1 JA LUMP SUM $_________

0002 DREDGING OF UNCLASSIFIED

MAINTENANCE MATERIAL IN

SHOALS 1, 5, 6, 7, 8, 9, 10

820,000 CY $_________ $_________

0003 COMPLIANCE WITH ENDANGERED

SPECIES ACT AND MARINE

MAMMALS PROTECTION ACT

(HOPPER ONLY)

1 JA LUMP SUM $_________

0004 NON-CAPTURE TRAWL SWEEPING

(24 HOURS/DAY) (HOPPER

ONLY)

10 DAY $_________ $_________

TOTAL (COMBINATION OF BASE

BID ITEMS 0001-0004)

TOTAL

TOTAL (COMBINATION OF ALL

BID ITEMS 0001-0004)

STATEMENT

Enter prices where space is provided for ALL items. Failure to follow this instruction may render the bid non-responsive and the bid will not be considered for award.

All bidders are advised materially unbalanced bids may be rejected as non-responsive. See FAR 52.214-19 Contract Award – Sealed Bidding – Construction.

Quantities indicated are ESTIMATED and are comprised of material within the required channel prism including the maximum optional pay slope material and two foot (2’) allowable overdepth.

k2tsoh9c Line k2tsoh9c Text Box 1,000,000