Abstract (PCO Signed) W912HN25B4003 - UHHZ220096 Repair SW Annex B125 RAFB.pdf

PDF 277 KB Posted

Attached to
Solicitation - W912HN25B4003 Repair/Renovate Southwest Annex B125 Robins Air Base, GA
Solicitation number
W912HN25B4003
Issued by

About this file

This document is an Abstract of Bid Tabulation for Solicitation W912HN25B4003, a federal construction contract for repairing and renovating the Southwest Annex of Building 125 at Robins Air Force Base in Georgia. The project is a 100% Small Business Set-Aside with an anticipated construction magnitude between $5 million and $10 million, involving a 540-calendar-day period of performance for a Firm-Fixed-Price contract.

The project scope includes comprehensive renovation of a 16,000-square-foot, three-floor administrative area within a larger 593,000-square-foot building constructed in 1941. Specific work requirements include removing interior partitions, reconstructing toilet rooms, installing new finishes, ceilings, HVAC, plumbing, electrical systems, fire suppression and alarm systems, a mass notification system, and a new elevator. The abstract shows bid submissions from seven contractors, with total bid prices ranging from approximately $6.37 million to $15.19 million. The bid opening official is Gregory M. Graham, and the proposal due date is 24 July 2025 at 1100 hours EDT, to be submitted electronically through the Procurement Integrated Enterprise Environment (PIEE) Solicitation Module.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Yes/No/NA Yes/No/NA Yes/No/NA Yes/No/NA Yes/No/NA Yes/No/NA Yes/No/NA Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes

CLIN Quantity Unit of Issue Unit Price Grand Totals Unit Price Grand Totals Unit Price Grand Totals Unit Price Grand Totals Unit Price Grand Totals Unit Price Grand Totals Unit Price Grand Totals Unit Price Grand Totals 0001 - Primary Facility 1 JOB $12,209,203.00 1 $12,209,203.00 $8,909,098.00 1 $8,909,098.00 $10,388,000.00 1 $10,388,000.00 $11,470,237.91 1 $11,470,237.91 $10,640,112.00 1 $10,640,112.00 $14,694,000.00 1 $14,694,000.00 $10,153,686.00 1 $10,153,686.00 $6,261,681.85 $6,261,681.85 0002 - Sitework 1 JOB $611,360.00 1 $611,360.00 $468,900.00 1 $468,900.00 $78,000.00 1 $78,000.00 $312,074.37 1 $312,074.37 $14,453.00 1 $14,453.00 $500,000.00 1 $500,000.00 $132,314.00 1 $132,314.00 $110,107.86 $110,107.86

TOTAL $12,820,563.00 TOTAL $9,377,998.00 TOTAL $10,466,000.00 TOTAL $11,782,312.28 TOTAL $10,654,565.00 TOTAL $15,194,000.00 TOTAL $10,286,000.00 TOTAL $6,371,789.71

DATE:

Percent of IGE:

Bidder/Offeror #7:

Imperial Construction & Electric Inc.

Bid Signed?

Amendments Acknowledged?

Bid Bond Furnished?

Bid Schedule Complete?

Remarks:

Percent of IGE:

Solicitation Number: Bidder/Offeror #5:

Bid Bond Furnished?

W912HN-25-B-4003

Project Description:

Bidder/Offeror #1:

Bid Schedule Complete?

Bidder/Offeror #3:

Bid Bond Furnished?

Amendments Acknowledged?

4K Global - ACC MP, LLC Brantley Construction Company, LLC

Bidder/Offeror #2:

Aleut Construction, LLC

Bidder/Offeror #4:

C&C Contractors, LLC

Remarks Bid Signed?

Independent Government Estimate

(IGE)

Copper Construction Company, Inc.

Bidder/Offeror #6:

Global-Go, LLC

Bid Signed?

Amendments Acknowledged?

Bid Bond Furnished?

Bid Schedule Complete?

Remarks:

Percent of IGE:

Solicitation No. W912HN25B4003, Project No: UHHZ220096 Repair SW Annex B125 Robins AFB, GA. Bid Date: 24 July 2025

Bid Signed?

Bid Bond Furnished?

Bid Schedule Complete?

Remarks: Remarks:

Bid Schedule Complete?

Amendments Acknowledged?

Percent of IGE:Percent of IGE:

Remarks: Remarks:

TYPED NAME OF BID OPENING OFFICIAL:

Gregory M. Graham

I CERTIFY THAT I HAVE OPENED, READ AND RECORDED ON THIS ABSTRACT (AND

CONTINUATION SHEETS, IF ANY) ALL OFFERS RECEIVED IN RESPONSE TO THE

SOLICITATION

SIGNATURE:

Bid Signed?

Amendments Acknowledged?

Bid Signed?

Amendments Acknowledged?

Bid Bond Furnished?

Bid Schedule Complete?

Remarks:

Percent of IGE:

Bid Signed?

Remarks:

Percent of IGE:

Amendments Acknowledged?

Bid Bond Furnished?

Bid Schedule Complete?

2025-07-29T07:40:55-0400
GRAHAM.GREGORY.MICHAEL.1283656345