C.04 - Bid Abstract W912HN24B4004 (signed).pdf
PDF 281 KB Posted
- Solicitation number
- W912HN24B4004
About this file
This document is a Bid Abstract for Solicitation Number W912HN-24-B-4004, Project Number 097292, which involves constructing an addition to the Child Development Center at Fort Eisenhower, Georgia.
The solicitation is for a Firm-Fixed-Price contract under NAICS code 236220 (Commercial and Institutional Building Construction) with a small business size standard of $45 million. The magnitude of the construction project is anticipated to be between $10 million and $25 million. The solicitation is a Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside. The bid abstract shows the bid prices from three offerors, with the apparent low bidder being Advon Construction at $19,543,513.34, which is 92.6% of the Independent Government Estimate (IGE). The proposal due date is July 22, 2024, and the period of performance is 1,350 calendar days after the notice to proceed. The project scope includes constructing an addition to the existing Child Development Center, with supporting site development, utilities, and other infrastructure.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Geotech Report Child Development Center PN 97292.pdf | ||
| Site Visit Roster 20240710.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Yes/No/NA Yes/No/NA Yes/No/NA Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
CLIN Quantity Unit of Issue Unit Price Grand Totals Unit Price Grand Totals Unit Price Grand Totals Unit Price Grand Totals 0001 - Primary Facility 1 JOB $16,258,940.00 1 $16,258,940.00 $20,961,000.00 1 $20,961,000.00 $16,325,149.00 1 $16,325,149.00 $14,223,286.46 $14,223,286.46 0002 - Site Preparation & Development 1 JOB $2,803,059.70 1 $2,803,059.70 $4,769,059.70 1 $4,769,059.70 $3,403,787.00 1 $3,403,787.00 $3,682,060.55 $3,682,060.55 0003 - Georgia Power Primary and Lighting 1 JOB $190,058.07 1 $190,058.07 $190,058.07 1 $190,058.07 $190,058.07 1 $190,058.07 $190,058.07 $190,058.07 0004 - Atlanta gas & Light Connection 1 JOB $79,500.00 1 $79,500.00 $79,500.00 1 $79,500.00 $79,500.00 1 $79,500.00 $79,500.00 $79,500.00 0005 - Augusta Utilities Privatized Water And sanitary Sewer $733,382.23 1 $733,382.23 $733,382.23 1 $733,382.23 $733,382.23 1 $733,382.23 $733,382.23 $733,382.23
SUB-TOTAL $20,064,940.00 SUB-TOTAL $26,733,000.00 SUB-TOTAL $20,731,877 SUB-TOTAL $18,908,287.31
0006 - Opt 1 - Food Service Equipment 1 JOB $311,000.00 1 $311,000.00 $442,000.00 1 $442,000.00 $267,137.00 1 $267,137.00 $634,226.03 $635,226.03
SUB-TOTAL $311,000.00 SUB-TOTAL $442,000.00 SUB-TOTAL $267,137.00 $635,226.03
TOTAL $20,375,940.00 TOTAL $27,175,000.00 TOTAL $20,999,014.00 TOTAL $19,543,513.34 106.12% 141.38% 109.64%
DATE:
Bid Signed?
Amendments Acknowledged?
TYPED NAME OF BID OPENING OFFICIAL:
Gregory M. Graham
I CERTIFY THAT I HAVE OPENED, READ AND RECORDED ON THIS ABSTRACT (AND
CONTINUATION SHEETS, IF ANY) ALL OFFERS RECEIVED IN RESPONSE TO THE
SOLICITATION
SIGNATURE:
Percent of IGE:
Solicitation No. W912HN-24-B-4004, Project No: 97292 Construct Addition to Bldg.
18407, Child Development Center, Fort Eisenhower, Georgia. Bid Date: 28 August
Bid Signed?
Bid Bond Furnished?
Bid Schedule Complete?
Remarks: Remarks:
Bid Schedule Complete?
Amendments Acknowledged?
Percent of IGE:Percent of IGE:
Remarks: Remarks:
Remarks Bid Signed?
Independent Government Estimate
(IGE)
Richard Group
Solicitation Number: Bidder/Offeror #3:
Bid Bond Furnished?
W912HN-24-B-4004
Project Description:
Bidder/Offeror #1:
Bid Schedule Complete?
Bidder/Offeror #2:
Bid Bond Furnished?
Amendments Acknowledged?
Advon Construction Boyer Construction
| 2024-09-03T06:06:11-0400 | |
| GRAHAM.GREGORY.MICHAEL.1283656345 |
File details come from the government source that posted it. Updated .