C.04 - Bid Abstract W912HN23R4003 (signed).pdf

PDF 278 KB Posted

Attached to
Solicitation -W912HN23R4003 - Project No: UHHZ113000 Building 231 Second Story Addition Robins Air Force Base, Georgia
Solicitation number
W912HN23R4003
Issued by

About this file

This solicitation notice synopsis announces an invitation for bid for construction services. The U.S. Army Corps of Engineers Savannah District is seeking a firm-fixed-price contract to complete a 20,654 square foot second story addition to an existing administration building at Robins Air Force Base in Warner Robins, Georgia. The project is estimated between $10-25 million and is set aside 100% for small businesses. The scope of work includes adding a second floor over an existing structure as well as mechanical, plumbing and electrical system upgrades. The bid due date is February 24, 2023 and the period of performance is 900 calendar days from notice to proceed. A mandatory site visit will be held on January 30, 2023. Questions must be submitted through the project management system. The solicitation will be posted on the System for Award Management and all bids must be submitted electronically through the Procurement Integrated Enterprise Environment module.

View the file

Other files

File Type Posted
W912HN-23-R-4003_SPECS_AMD6.pdf PDF
B.08 - Amendment 0006 (SF30) - W912HN22R4003 - UHHZ113000 B231 Addition RAFB.pdf PDF
W912HN-23-R-4003_DRAWINGS_AMD6.pdf PDF
B.08 - Amendment 0006 (Conformed Copy) - W912HN22R4003 - UHHZ113000 B231 Addition RAFB.pdf PDF
2023.02.16 sign in sheet.pdf PDF
B.08 - Amendment 0005 (SF30) - W912HN22R4003 - UHHZ113000 B231 Addition RAFB.pdf PDF
B.08 - Amendment 0005 (Conformed Copy) - W912HN22R4003 - UHHZ113000 B231 Addition RAFB.pdf PDF
B.08 - Amendment 0004 (SF30) - W912HN22R4003 - UHHZ113000 B231 Addition RAFB.pdf PDF
W912HN-23-R-4003_SPECS_AMD4.pdf PDF
B.08 - Amendment 0004 (Conformed Copy) - W912HN22R4003 - UHHZ113000 B231 Addition RAFB.pdf PDF
W912HN-23-R-4003_DRAWINGS_AMD4.pdf PDF
B.08 - Amendment 0003 (SF30) - W912HN22R4003 - UHHZ113000 B231 Addition RAFB.pdf PDF
B.08 - Amendment 0003 (Conformed Copy) - W912HN22R4003 - UHHZ113000 B231 Addition RAFB.pdf PDF
2023.01.30 Bldg 231 Contractor's Walk Sign in Sheet.pdf PDF
B.08 - Amendment 0002 (SF30) - W912HN22R4003 - UHHZ113000 B231 Addition RAFB.pdf PDF
B.08 - Amendment 0002 (Conformed Copy) - W912HN22R4003 - UHHZ113000 B231 Addition RAFB.pdf PDF
B.08 - Amendment 0001 (SF30) - W912HN22R4003 - UHHZ113000 B231 Addition RAFB.pdf PDF
B.08 - Amendment 0001 (Conformed Copy) - W912HN22R4003 - UHHZ113000 B231 Addition RAFB.pdf PDF
B231 Addition_Geotechnical Report.pdf PDF
B231 Addition_Hazard_Material_Survey.pdf PDF
B.08 - Solicitation (released) - W912HN22R4003 - UHHZ113000 B231 Addition RAFB.pdf PDF
Robins AFB Access Affidavit (Revised 31 Oct 2022).pdf PDF
W912HN-23-R-4003_SPECS.pdf PDF
W912HN-23-R-4003_DRAWINGS.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Yes/No/NA Yes/No/NA Yes/No/NA Yes/No/NA Yes/No/NA Yes/No/NA Yes/No/NA Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes

CLIN Quantity Unit of Issue Unit Price Quantity Grand Total Unit Price Quantity Grand Totals Unit Price Quantity Grand Totals Unit Price Quantity Grand Totals Unit Price Quantity Grand Totals Unit Price Quantity Grand Totals Unit Price Quantity Grand Totals Unit Price % Total Grand Totals

CLIN 0001 1 Job $11,290,977.00 1 $11,290,977.00 $14,046,000.00 1 $14,046,000.00 $11,275,000.00 1 $11,275,000.00 $9,585,130.80 1 $9,585,130.80 $13,719,339.00 1 $13,719,339.00 $14,386,000.00 1 $14,386,000.00 $14,739,600.00 1 $14,739,600.00 $12,776,278.00 $12,776,278.00 SUB-TOTAL $11,290,977.00 SUB-TOTAL $14,046,000.00 SUB-TOTAL $11,275,000.00 SUB-TOTAL $9,585,130.80 SUB-TOTAL $13,719,339.00 SUB-TOTAL $14,386,000.00 SUB-TOTAL $14,739,600.00 SUB-TOTAL 0.00% $12,776,278.00

TOTAL $11,290,977.00 TOTAL $14,046,000.00 TOTAL $11,275,000.00 TOTAL $9,585,130.80 TOTAL $13,719,339.00 TOTAL $14,386,000.00 TOTAL $14,739,600.00 TOTAL $12,776,278.00 88.37% 109.94% 88.25% 75.02% 107.38% 112.60% 115.37%

DATE:

4K Global-ACC JV LLC Brantley Construction SES Electrical LLC

Bid Signed?

Percent of IGE:

Gregory M. Graham

I CERTIFY THAT I HAVE OPENED, READ AND RECORDED ON THIS ABSTRACT

(AND CONTINUATION SHEETS, IF ANY) ALL OFFERS RECEIVED IN RESPONSE TO

THE SOLICITATION

SIGNATURE:

Amendments Acknowledged?

Percent of IGE:Percent of IGE:

Remarks: Remarks:

TYPED NAME OF BID OPENING OFFICIAL:

Percent of IGE:

Project No: UHZ113000 Building 231 Second Story Addition Robins Air Force Base, Georgia Bid Time: 11:00 a.m. Bid Opening 12:00pm

Bid Signed?

Bid Bond Furnished?

Remarks: Remarks:

Independent Government Estimate (IGE)

Amendments Acknowledged?

Remarks:

Bid Signed?

Bidder/Offeror #1: Bidder/Offeror #2:

Bid Bond Furnished?

Amendments Acknowledged? Amendments Acknowledged?

Bid Bond Furnished?

Solicitation Number: Bidder/Offeror #7:

Bid Bond Furnished?

Bidder/Offeror #5:

Roundhouse PBN, LLC

W912HN-23-R-4003

Project Description:

Bid Signed?

Percent of IGE:

Bidder/Offeror #4:

NISOU LGC JV LLC

Bid Signed?

Amendments Acknowledged?

Bid Bond Furnished?

Remarks:

Percent of IGE:

Remarks:

Bid Signed?

Remarks:

Percent of IGE:

Bidder/Offeror #6:

Seawolf Construction Corp

Bid Signed?

Amendments Acknowledged?

Bid Bond Furnished?

Remarks:

Percent of IGE:

Amendments Acknowledged?

Bid Bond Furnished?

Bidder/Offeror #3:

Copper Construction Company, Inc.

2023-03-03T12:18:17-0500
GRAHAM.GREGORY.MICHAEL.1283656345

File details come from the government source that posted it. Updated .