This document contains an abstract of bids received in response to Solicitation Number W912HN21B3005 for Project Number 95039 to repair Barracks Building 315 at Fort Gordon, Georgia.
The solicitation was for repair and renovation work including replacement of HVAC systems, windows, doors, ceiling tiles and plumbing fixtures. The project also required abatement of lead-based paint, asbestos and other hazardous materials. Fourteen contractors submitted bids ranging from $15.3 million to $23.3 million. The apparent low bidder was Collins Construction Services, Inc. at $15.3 million. The government estimate was $12.5 million. Work was to be completed by June 2023 under a firm-fixed-price contract awarded to the responsible bidder submitting the lowest priced, responsive bid meeting the government's requirements.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABSTRACT OF OFFERS - CONSTRUCTION 1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES
7/8/2021 8/24/2021 1 4
4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation. SIGNATURE DATE SIGNED
9. OFFERS
5. PROJECT TITLE (IFB) 8. GOVERNMENT ESTIMATE NO. 1 NO. 2
(Check A, B, C and complete D, E, and F) A. OFFEROR A. OFFEROR
A. HIRED LABOR
B. REASONABLE CONTRACT B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT)
Small Business 100% Set Aside X (Without Profit)
6. NUMBER OF AMENDMENTS ISSUED C. REASONABLE CONTRACT C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED
(Including Profit)
7A. ITEM
NUMBER 7B. DESCRIPTION OF OFFERED ITEM
7C. EST.
QUANTITY D. UNIT E. UNIT PRICE
F. ESTIMATED
AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT
Repair Barracks Building 315 Fort Gordon 1 JOB $12,008,214.00 $12,008,214.00 $15,738,264.00 $15,738,264.00 $16,075,783.00 $16,075,783.00
0002 Privatized Utility 1 JOB $497,811.22 $497,811.22 $497,811.22 $497,811.22 $497,811.22 $497,811.22
ESTIMATED TOTAL AMOUNT BASE $12,506,025.22 $16,236,075.22 $16,573,594.22
W912HN21B3005
Project Number: 95039 - Repair Barracks BLDG 315, Fort Gordon, GA. 309050 4K Global - ACC JV LLC
Magdalena Bernard Bid Opening Officer
US ARMY ENGINEER DISTRICT, NEW
ENGLAND
696 VIRGINIA ROAD
CONCORD, MA 01742
2 2
Bid Bond 20% Bid Bond 20%
Ashford Leebcor Enterprises IV, LLC
25 August 2021
1. SOLICITATION NUMBER PAGE OF PAGES
2 4
ABSTRACT OF OFFERS - CONSTRUCTION INSTRUCTIONS - Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on CONTINUATION SHEET a construction project. Each Continuation Sheet will accommodate 14 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 14 and attach additional Continuation Sheets (OF 1419A) as needed.
2. PROJECT TITLE
NO. 3 NO. 4 NO. 5 NO. 6
A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR
B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT)
3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED A. B. C.
ITEM ESTIMATED UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
0001 1 JOB $17,404,000.00 $17,404,000.00 $19,282,000.00 $19,282,000.00 $14,849,188.78 $14,849,188.78 $22,823,188.78 $22,823,188.78 0002 1 JOB $497,811.22 $497,811.22 $497,811.22 $497,811.22 $497,811.22 $497,811.22 $497,811.22 $497,811.22
ESTIMATED TOTAL AMOUNT BASE $17,901,811.22 $19,779,811.22 $15,347,000.00 $23,321,000.00
W912HN21B3005
Bid Bond 20% Bid Bond 20% Bid Bond 20%
Brantley Construction Services, LLC
Project Number: 95039 - Repair Barracks BLDG 315, Fort Gordon, GA.
309050
2 2
Bid Bond 20%
2 2
Copper Construction Co. Inc.Collins Construction Services, Inc. Debcon, Inc.
3 4
ABSTRACT OF OFFERS - CONSTRUCTION INSTRUCTIONS - Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on CONTINUATION SHEET a construction project. Each Continuation Sheet will accommodate 14 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 14 and attach additional Continuation Sheets (OF 1419A) as needed.
2. PROJECT TITLE
NO. 7 NO: 8 NO: 9 NO: 10
A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR
B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT)
3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED A. B. C.
ITEM ESTIMATED UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
0001 1 JOB $21,798,478.00 $21,798,478.00 $20,312,561.00 $20,312,561.00 $17,960,344.72 $17,960,344.72 $18,069,000.00 $18,069,000.00 0002 1 JOB $497,811.22 $497,811.22 $497,811.22 $497,811.22 $497,811.22 $497,811.22 $497,811.22 $497,811.22
ESTIMATED TOTAL AMOUNT BASE $22,296,289.22 $20,810,372.22 $18,458,155.94 $18,566,811.22
Peachtree Mechanical Inc.
Project Number: 95039 - Repair Barracks BLDG 315, Fort Gordon, GA. 309050
222 2
W912HN21B3005
Bid Bond 20%Bid Bond 20%Bid Bond 20%Bid Bond 20%
Koman Construction Lubin Enterprises Inc. Nisou LGC JV II, LLC
4 4
ABSTRACT OF OFFERS - CONSTRUCTION INSTRUCTIONS - Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on CONTINUATION SHEET a construction project. Each Continuation Sheet will accommodate 14 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 14 and attach additional Continuation Sheets (OF 1419A) as needed.
2. PROJECT TITLE
NO. 11 NO: 12 NO: 13 NO: 14
A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR
B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT)
3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED A. B. C.
ITEM ESTIMATED UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
0001 1 JOB $17,450,817.00 $17,450,817.00 $21,384,000.00 $21,384,000.00 $21,118,994.70 $21,118,994.70 0002 1 JOB $497,811.22 $497,811.22 $497,811.22 $497,811.22 $497,811.22 $497,811.22
ESTIMATED TOTAL AMOUNT BASE $17,948,628.22 $21,881,811.22 $21,616,805.92
Project Number: 95039 - Repair Barracks BLDG 315, Fort Gordon, GA.
309050
W912HN21B3005
Bid Bond 20%Bid Bond 20%Bid Bond 20%
The Clement Group, LLC W-T Federal Joint Venture
22 2.00
TDX Quality, LLC.
Date
Bid No.
$21,881,811.22
$22,296,289.22 $20,810,372.22 $18,458,155.94 $18,566,811.22 $17,948, .00
WT FEDERAL JV $21,616,805.92
TDX QUALITY
Debcon, Inc.
Koman Construction
The Clement Group, LLC
$15,347,000.00 $23,321,000.00
Lubin Enterprises Nisou LGC JV
Peachtree Mechanical Inc
BrantleyConstruction $16,573,594.22 $17,901,811.22
$19,779,811.22COLLINS CONSTRUCTION SERVICES, INC
Ashford Leebcor Enterprises IV 4K Global -ACC JV $16,236,075.00 Contractor Name Bid Amount
$15,347,000.00Co per Construction5
Apparent Low Bidder Contractor Bid Amount
08/24/21 Government Estimate $12,506,025.22
Bid Opening Officer Magdalena Bernard
Solicitation No.
Project Number: 95039 - Repair Barracks BLDG 315, Fort Gordon, GA. 309050
Bids Opened By
Recorded By
Project Description
Magdalena Bernard / Lennie K.Mattis
Lennie K. Mattis
W912HN21B3005
Digitally signed by
BERNARD.MAGDALEN
A.1247549117