15-R-0035_Amd_2.docx

DOCX document 258 KB Posted

Attached to
Regional Environmental Acquisition Tool: Military Munitions Response Program (MMRP) Federal contract opportunity
Solicitation number
W912HN-15-R-0035
Issued by
Department of the Army Corps of Engineers Engineering District Savannah

About this file

15-R-0035 Amd 2

View the file

Other files for this federal contract opportunity

Other files attached to Regional Environmental Acquisition Tool: Military Munitions Response Program (MMRP), newest first.
File Type Posted
15-R-0035_Amd_4.docx DOCX document
15-R-0035_Amd_4_Conformed.doc DOC document
Bid_Schedule_SEED_Proj.docx DOCX document
15-R-0035_Amd_3_Conformed.doc DOC document
15-R-0035_Amd_3.doc DOC document
SF33-14a.pdf PDF
15-R-0035_Amd_2_Conformed.docx DOCX document
I04GA004401_01.08_0500_a.pdf PDF
W912HN-15-R-0035.pdf PDF
I04GA004401_01.09_0500_p.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912HN-15-R-0035

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time 04-Dec-2015 12:00 PM has been deleted.

SECTION B - SUPPLIES OR SERVICES AND PRICES

The following have been modified:

HOURLY RATES VERBIAGE

TRAVEL IAW FAR NEGOTIATED PER TASK ORDER. TRAVEL AND PER DIEM SHALL BE NEGOTIATED AND DETERMINED IN ACCORDANCE WITH THE GOVERNMENT’S FEDERAL ACQUISITION REGULATION (FAR PART 31.205-46).

OVERHEAD – INCLUDED IN RATES. THE UNIT PRICES IN THIS SCHEDULE SHALL BE LOADED RATES WHICH INCLUDE RAW LABOR, OVERHEAD, FRINGE AND G&A. PROFIT WILL BE NEGOTIATED PER TASK ORDER.

PROFIT – NOT INCLUDED IN RATES.

THIS IS AN INDEFINITE DELIVERY INDEFINITE QUANTITY CONTRACT.

THE MAXIMUM AMOUNT OF THIS CONTRACT SHALL NOT EXCEED $48,000,000.00. THE ESTIMATED DOLLAR AMOUNT IS $28,800,000.00 FOR THE BASE (FIRST 3 YEARS) AND $19,200,000.00 FOR THE FOURTH AND FIFTH YEAR. ACTUAL OBLIGATION PER YEAR MAY BE GREATER THAN OR LESS THAN THESE AMOUNTS.

THE CONTRACTOR SHALL FURNISH THE NECESSARY PERSONNEL, FACILITIES, MATERIAL, AND EQUIPMENT TO FULFILL ANY AND ALL REQUIREMENTS WITHIN THE SCOPE OF THIS CONTRACT IN ACCORDANCE WITH SECTION C, DESCRIPTION/SPECS/WORK STATEMENT.

PERSONNEL REQUIRED FOR EACH OF THE FOLLOWING LABOR CATEGORIES INCLUDES BUT IS NOT LIMITED TO THOSE DISCIPLINES IDENTIFIED IN THE HOURLY FIXED RATE MATRIX.

OTHER DIRECT COSTS FOR SPECIALIZED EQUIPMENT AND SUPPLIES WILL BE NEGOTIATED FOR EACH TASK ORDER AS REQUIRED.

SUBCONTRACTING COSTS AND OTHER DISCIPLINES WILL ALSO BE NEGOTIATED FOR EACH TASK ORDER AS REQUIRED.

UNIT OF MEASURE

HR– Hour Rate

The following table is that portion of the Pricing Schedule which will pertain to all costs other than prime labor already priced as shown above. These rates will be applied and paid to other direct negotiated costs such as, but not limited to, reproduction, travel, subcontracting effort, specialized equipment and so forth.

Rates / Markups (Costs Other Than Hourly Labor Rates Shown in Table above):

Base Period Year 1 Base Period Year 2 Base Period Year 3 Option Period Year 4 Option Period Year 5

G&A Rate*
%
%
%
%
%

*Must be substantiated by DCAAater time

For ordering purposes, the “Hourly Labor Rate (Firm Fixed Price)” table and information shown above are part of this solicitation. Each successful offeror will have a completed Schedule A attached to their assigned contract. Prices used in formulating proposals shall be dictated by the date of task order requirement. These rates will be the maximum rates that can be proposed at the task order level. A contractor may utilize lower rates during the task order proposal process. Modifications to task orders will reflect the applicable labor rates to be used at the time the modification is issued. For example, assume that the rate schedule changes over on 1 November of each year; a task order that is issued on 1 Sep 2015 for 12 months work, shall apply the labor rates that were effective on 1 Nov 2014. If a modification to this task order is required in December 2015, labor rates effective on 1 Nov 2015 will be applied.

NOTES TO OFFERORS

REGIONAL ENVIRONMENTAL ACQUISITION TOOL-ENVIRONMENTAL MILITARY MUNITIONS RESPONSE PROGRAM (MMRP)

W912HN-15-R-0035

SECTION B - NOTES TO OFFERORS

This Acquisition is 100% Set-Aside for 8(a) competition. This is a Multiple Award Task Order Contract (MATOC) for Military Munitions Response Program.

ELECTRONIC PROPOSAL SUBMISSION IS REQUIRED THROUGH THE WEBSITE LISTED BELOW. ELECTRONIC SUBMISSION SENT VIA EMAIL OR FACSIMILE WILL NOT BE ACCEPTED. HAND CARRIED PROPOSAL SUBMISSION IS NOT AUTHORIZED.

DIRECTIONS FOR SUBMITTING PROPOSALS

a. In an effort to reduce paperwork and reduce cost, all proposals shall be submitted electronically. All submissions shall be in Adobe PDF format. The Price Proposal and Technical Proposal shall be submitted as “separate” single files. Offerors may use compressions utility software such as WinZip or PKZip to reduce file size and facilitate transmission.

Title the file(s) in the following format:

W912HN-15-R-0035_COMPANY NAME_VOLUME I

W912HN-15-R-0035_COMPANY NAME_VOLUME II

Submit the Price and Technical proposals electronically via the AMRDEC SAFE website at: https://safe.amrdec.army.mil/SAFE/Welcome.aspx. At the AMRDEC SAFE website select the link: I do not have a CAC or this machine is not configured to read my CAC and I would like to access SAFE as a Guest User, to register, access the site and submit your proposal(s).

When completing the information for transmittal at the AMRDEC SAFE website, you will be asked to enter e-mail addresses for the recipients. When your proposal is submitted via the AMRDEC SAFE website, the website will provide notification of the submittal to the recipients. For this solicitation, the recipients will be the Contracting Officer and Contract Specialist. The Contract Specialist for this project is Mr. Mark Hiscox whose e-mail address is mark.a.hiscox@usace.army.mil. The Contracting Officer for this project is Mr. Adrian Goolsby, whose e-mail address is adrian.e.goolsby@usace.army.mil. These e-mail addresses are the ones you will enter as recipients.

SITE VISIT INFORMATION:

Date: TBD
Time: TBD
Meeting Place: Rayonier, U.S. Forest Resources
6830 Floyd James Road
Manor, GA 31550

Proposal Due Date and Time:

Request For Proposal No: W912HN-15-R-0035 Due Date of Proposal: TBD Time by which Proposals are Due: TBD Title of Project: Regional Environmental Acquisition Tool-Environmental Military Munitions Response Program (MMRP)

The date and time of delivery will be established by the time of receipt of the e-mail notification to the Contract Specialist and Contracting Officer by the AMRDEC SAFE website, not by the date and time of uploading of the proposal into the AMRDEC SAFE website. Do not assume that electronic communication is instantaneous. Please make allowances for delays in transmittal. If an electronic submission is uploaded minutes before the deadline but notification is not actually received in the recipients’ e-mail inboxes until after the deadline, the submission will be considered late.

The Government will not be responsible for proposals delivered to any location or to anyone other than those designated to receive proposals on its behalf. Offerors are responsible for ensuring that proposals are submitted so as to reach the designated recipient of proposals. Offerors are responsible for allowing sufficient time for the proposal to be received in accordance with the information provided.

WAGE DETERMINATIONS: The appropriate wage determination will be incorporated on a task order by task order basis.

TECHNICAL MATTERS: Submit technical inquiries and questions relating to this solicitation via Bidder Inquiry in ProjNet at (https://www.projnet.org) at least 10 calendar days prior to the date established in the solicitation for receipt of proposals. The Government reserves the right to decline addressing questions received less than 10 calendar days prior to receipt of proposals.

If an Offeror believes that the requirements in this Request for Proposal contain an error, omission, or are otherwise unsound; immediately notify the Contract Specialist in writing with supporting rationale. The Government reserves the right to award this Request for Proposal based on the initial proposal, as received, without discussion.

To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment or question will receive an acknowledgement via e-mail, followed by an answer after it has been processed by our technical team. All timely questions and approved answers will be made available through ProjNet. Approved answers to all timely questions will also be posted on the FedBizOps in the form of a report generated from ProjNet as soon as the comment/question entering period is over and answers are all finalized.

W912HN-15-R-0035

Regional Environmental Acquisition Tool-Environmental Military Munitions Response Program (MMRP) Bidder Inquiry Key: XK9489-PVXEV8

Specific Instructions for Initial ProjNet Bid Inquiry Access:

1. From the ProjNet home page, click on Quick Add on the upper right side of the screen.

2. Identify the Agency as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. E-mail. Enter the e-mail address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, E-mail, Secret Question, Secret Answer, and Time Zone. Remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access:

Steps 1 through 3: same as above.

4. E-mail. Enter the e-mail address you used to register previously in ProjNet.

5. Click Continue. A page will then open asking for the answer to your Secret Question.

6. Enter your Secret Answer and click Login. Once this is completed, you are logged into the system.

S o u rce

S elect i o n I n f o r m a t i o n –

S ee

FA

R a n d W

HN

-R-

)W912HN-15-R-0035

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been added by full text:

SEED PROJECT PRICING

Seed Project Schedule
(Schedule B)
Task 1
Task 2
Task 3
Task 4
Task 5
Task 6
Totals
Direct Labor
Disciplines
Cost/hr
Hrs
Cost
Hrs
Cost
Hrs
Cost
Hrs
Cost
Hrs
Cost
Hrs
Cost
Total Hrs
Total Cost

Sub-total

Travel

Travel Rate/Day
Days
Cost
Days
Cost
Days
Cost
Days
Cost
Days
Cost
Days
Cost
Total Days
Total Cost

Sub-total

Other Direct Costs

Sub-total

Sub-Contractor Costs

Profit on Sub-Contractor
%

Sub-total

G&A
%
Profit
%

TOTAL TASK COST

TOTAL PROJECT COST

The following have been modified:

INITIAL TASK ORDER PWS

PERFORMANCE WORK STATEMENT

for MMRP Site Inspection at Former Homerville Bombing and Gunnery Range Homerville, Georgia FUDS Property No. I04GA0044

29 June 2015

1 INTRODUCTION AND OBJECTIVES

1.1 Introduction

This PWS supports the Environmental Compliance and Environmental Restoration programs within the FUDS Program. These missions are covered under the basic scope of the contract. The work required under this Performance Work Statement (PWS) falls under the Formerly Used Defense Sites (FUDS) Installation Restoration (IR) Military Munitions Response Program (MMRP) category. All activities in this PWS shall be conducted in full compliance with USACE, Department of the Army (DA), and Department of Defense (DOD) regulations, guidance, standards, and manuals.

1.2 Project Objectives

The primary goal of the MMRP Site Inspection (SI) is to collect the minimum amount of information necessary to make one of the following decisions: 1) whether or not a Remedial Investigation/ Feasibility Study (RI/FS) is required at a site, 2) whether or not an immediate response is needed, or 3) whether the site qualifies for no further action. The SI will address Munitions and Explosives of Concern (MEC) hazards (including both UXO and DMM) as well as Munitions Constituents (MC) issues for the MMRP eligible sites. The secondary goal of the SI is to collect information to complete the Munitions Response Site Prioritization Protocol (MRSPP) for risk prioritization of the Munitions Response Sites (MRS).

2 BACKGROUND

2.1 Description of Former Homerville Bombing and Gunnery Range The former Homerville Bombing and Gunnery Range (HBGR) property is located near Homerville, Georgia, in Clinch and Ware Counties. The property lies approximately 21 miles southwest of Waycross, Georgia, along the western edge of the Okefenokee National Wildlife Refuge.

2.2 History of the FUDS Property

In 1942, the Army Air Forces built Homerville Bombing and Gunnery Range to support the mission of Waycross Army Air Field dive bombing and fighter training program. Land acquisition (21,697 acres under permit from the Department of Interior and 10,290 acres leased from private owners for a total of 31,987 acres) commenced in 1942 and the range opened on 4 June 1943. Potentially, HBGR included another 10,220 acres of land used as a range safety fan buffer zone located to the northeast and south of the confirmed 5.5 mile wide by 9.5 mile long boundary, for a total of 42,207 acres. Another document stated that the HBGR was 42,240 acres in size. An unlabeled map dated September 1943 shows the Homerville Bombing and Gunnery Range boundary extending outside the rectangular shaped property boundary.

Targets were located on leased property on the western third of the property. The remaining eastern two thirds of land, located in the Okefenokee National Wildlife Refuge which were acquired through permit, were used as a range safety fan buffer area.

The Homerville Bombing and Gunnery Range was used by combat units of the Third Air Force at Waycross, Georgia. Range activities at Homerville Bombing and Gunnery Range included a combination dive bombing/ practice rocket range, a skip bombing range, two submachine gun ranges, one rifle range, one pistol range, one combination air to ground gunnery range/rocket range, and an air to ground strafing range. None of the acquired historical documentation, aerial photography, or the 2011 property inspection indicates high explosives use. Confirmed munitions used on Homerville Bombing and Gunnery Range included practice bombs, small arms ammunition, and practice rockets.

On 4 June 1943, the Homerville Bombing and Gunnery Range opened with one bombing range, one aerial gunnery range, and five buildings. By July 1943, the Third Air Force authorized the construction of a skip bombing range; and additional range construction requirements for a rifle range, a pistol range, and two sub-machine gun ranges were undertaken. In September 1943, a landing strip was built near the skip bombing range; and conversion of the ground gunnery range to a ground rocket range was scheduled for completion in May 1945. Twelve targets were constructed, of which two targets were designated by the installation to be fifty foot radii white circles for the rocket range. Additionally the dive bomb range was converted into a combination dive bomb rocket range.

During 1944, a chemical spray range was approved for the use of FS smoke (screening smoke) and colored water dispersed from tanks located within airplanes. The range was located 0.5 miles southeast of the skip bombing range and was used until 1945. There is no explosive hazard from dispersing FS smoke from the spray tanks.

During September 1945, the Homerville Bombing and Gunnery Range was used for the last time and close down procedures commenced. By October 1945, all areas of the Homerville Bombing and Gunnery Range had reportedly been decontaminated, cleared of all scrap metal, and inspected for duds, unexploded projectiles and bombs. The range was closed on 25 October 1945. By the end of January 1946, the range was inactivated and all installed government property was removed and returned to Waycross AAF. In 1947, the U.S. Dept. of Interior terminated the permit covering 21,697 acres of land. The actual termination date of the leased portion of the range is thought to be 1952. The Department of Interior property is currently part of the Okefenokee National Wildlife Refuge and the former leased portion of the range is privately owned and used for timber harvesting.

No evidence of the storage or use of chemical warfare materials was found at Homerville Bombing and Gunnery Range.

2.3 History of USACE Environmental Work at Former Homerville Bombing and Gunnery Range A Preliminary Assessment (PA) was completed for HBGR in September 2012. On the basis of the PA, four MMRP projects were identified with the potential for Military Munitions contamination. The Site Inspection is the next step in the CERCLA process to identify risk at each of these project sites.

2.4 Project Descriptions

2.4.1 Project 01: (MMRP) – Bombing/Rocket Range

The 3,108 acre Bombing/Rocket Range is located in the northwestern portion of the Homerville Bombing and Gunnery Range FUDS. It consists of portions of the submachine gun range (north) and submachine gun range (east), and the entire pistol range, dive bombing target, and combination dive bombing target/rocket range. The munitions used consist of small arms, practice bombs, and practice rockets. On 4 June 1943 the bombing range opened and was converted into a combination bombing/rocket range by May 1945. The last known use of the range was during September 1945. None of the acquired historical documentation indicates high explosives use. No munitions debris or any remaining indication of past military use was found during the property visit conducted during September 2011.

2.4.2 Project 02: (MMRP) – Small Arms Range

The 1,412 acre Small Arms Ranges consists of the rifle range and portions of submachine gun range (north) and submachine gun range (east). The small arms ranges were constructed during 1943 and the last known use of the entire Homerville Bombing and Gunnery Range was September 1945. None of the historical documentation acquired indicates any other type of munitions being used besides small arms. Only some concrete debris, which may have been from target butts, was observed during the property visit conducted during September 2011. The entire area is a tree farm and has been plowed and replanted several times since government use.

2.4.3 Project 03: (MMRP) – Skip Bombing Range

The 630 acre Skip Bombing Range was constructed in 1943 and used between July 1943 and September 1945. The Skip Bombing Range measures 0.5 miles by 0.75 miles and has an 800 foot by 1,200 foot target area. The southeast corner of the skip bombing range overlaps the Aerial Ground Gunnery Range and is addressed in Project 04. An October 1950 dedudding operations report indicated the removal of six tons of buried M38A2 scrap from this area. Munitions used include practice bombs and small arms. None of the documents obtained indicate high explosives use. A partially buried M1A1 fuse for the M38A2 practice bomb was observed during the September 2011 property visit.

2.4.4 Project 04: (MMRP) – Aerial Ground Gunnery Range

The 3,108 acre Aerial Ground Gunnery/Rocket Range is located in the southwest corner of the Homerville bombing and Gunnery Range FUDS Property. Headquarters Third Air Force authorized the construction of an aerial gunnery ground strafing course on 13 August 1943. Sometime later an aerial ground gunnery range was constructed and then in March 1945 this was rebuilt and converted into a combination aerial ground gunnery and rocket range. The combination ground gunnery rocket range opened in May 1945 and was used until September 1945. A small portion of the Skip Bombing Range overlaps this MRS and is addressed within this project as well. A .50 caliber shell casing and a 6 foot long by 2 foot wide and 12 inch thick concrete pad, likely used for holding strafing targets, were observed during the September 2011 property visit.

3 GENERAL REQUIREMENTS

3.1 Responsibilities

The Contractor shall perform and assume all responsibility for the accuracy and completeness of the work and services for the described project in accordance with established criteria, standards, and instructions. Should the Contractor receive any directions or instructions which are beyond the scope of work, the Contractor shall not proceed with the work but shall notify the Contracting Officer (KO) in writing, describing the changes and the impact on the effort within 10 calendar days.

3.2 Professional Judgment

The Contractor shall continuously review the PWS, and all work during the progress of the task order, for potential changes that would be in the best interest of the Government. If changes are needed, the Contractor shall contact the Project or Technical Manager to discuss the needs or recommendations and follow-up with a Confirmation Notice within three workdays. The Contractor shall use professional judgment to make suggestions to improve the quality of the work, reduce any unnecessary work (and associated costs), and improve the final product (workplan, design, report, etc.). The Contractor shall also ensure that the USACE and its customers (Base, Installation, or other project stakeholders, etc.) meet all reporting requirements under all applicable regulations.

3.3 Release of Information

The Contractor shall not publicize, nor release in any manner, information or data with regard to projects on which they may be working or negotiating with this office; nor discuss prior to public release by this office, a project, any future project/program, or any planning with anyone not directly concerned with the project. Any inquiries regarding these matters shall be referred to the KO.

The above restrictions are not intended to interfere with notification of Federal, state and local agencies as may be required by applicable laws and regulations regarding releases of hazardous materials and substances and other such materials covered therein. To this end, the Contractor is obliged to be familiar with applicable Federal, State, and local laws, regulations and procedures regarding such reporting. Such notifications should also be made when there is a reasonable likelihood of harm to persons on or around the project area resulting from a release of potentially dangerous material. The Contractor shall coordinate such notifications with the KO.

3.4 Contractor Methods

These shall be used to achieve task order objective at the specified level of performance as stated in the PWS. The Contractor will be evaluated periodically during performance of this task order to ensure compliance with the PWS and to document that acceptance criteria, delivery schedule, and the overall completion date are being met. This evaluation will be performed according to a Quality Assurance Surveillance Plan (QASP). A programmatic QASP will be provided by the Government as a starting point for the project specific QASP. A Final QASP will be supplied to the Contractor and used by the Government to evaluate the Contractor’s performance.

Failure to adequately complete any service or submittal to at least a satisfactory level of quality or timeliness shall result in a repeat of the work at no cost to the Government and a poor performance evaluation may be given at the end of the project. If the Contractor is delayed by or through unanticipated Government actions, the completion date will be extended by a comparable number of calendar days before a reduction in compensation to the Contractor begins.

4 TASK REQUIRMENTS

4.1 General

This PWS consists of the following major tasks and subtasks. The Contractor’s proposal should be structured the same as these tasks.

Task 1: Stakeholder Involvement Task 2: Technical Project Planning Task 3: Preparation of Project Plans Task 4: MMRP Site Inspection Field Work Task 5: Reports and Routine Project Reporting Task 6: Contractor Manpower Reporting

4.2 TASK 1: Stakeholder Involvement

OBJECTIVE:

The Contractor will act as the central coordination point in the identification and involvement of all stakeholders in the SI process. Early stakeholder involvement is key to developing the trust necessary for ensuring that the work performed will meet expectations and requirements.

REQUIREMENTS:

The level of effort for this task includes:

· Work closely with the USACE Project Manager (PM) to identify key stakeholders for the site, including regulators and their expected roles and level of involvement in the SI process. Distribute a complete point of contact information sheet to all stakeholders.

· Work with the designated points of contact to plan and coordinate a project kickoff meeting with key stakeholders (to include regulators) on the MMRP SI project at the site. Prepare and present an overview of the MMRP and SI process proposed for the site. Solicit stakeholder input and prepare and submit minutes of comments, agreements, and action items from the meeting.

DELIVERABLES:

The deliverables for this task are the meeting notifications, agendas, handouts, and the execution of the meetings. The Contractor shall provide a conference line and telephone number to all attendees via email prior to all telecom meetings. The agenda and handouts shall be provided NLT 7 days prior to the meetings. Meeting notifications and minutes shall be produced for all meetings, including the teleconferences. Draft minutes should be provided to all attendees within 7 calendar days. Any revisions needed, based on attendee’s comments, will be incorporated into the Final minutes within 5 days.

4.3 Task 2: Technical Project Planning

OBJECTIVE:

Upon completion of the initial stakeholder coordination, the Contractor shall solicit input on the remaining SI work using the formal USACE Technical Project Planning (TPP) process in accordance with EM 200-1-2. Working with the designated stakeholder points of contact, plan and coordinate a facilitated TPP session not to exceed one day for key stakeholders (including regulators).

DELIVERABLE:

The goal of TPP will be to develop, with stakeholder input and concurrence, the scope and data quality objectives (DQOs) for the development of the site specific SI Work Plan.

4.4 TASK 3: Preparation of Project Plans

OBJECTIVE:

As part of this task, the Contractor shall submit a detailed project schedule for review and acceptance by the USACE. The schedule is due no later than 10 days after Notice To Proceed (NTP). The approved schedule will then be included in the Project Plan.

Prepare and submit a site specific SI Work Plan in Army internal draft, stakeholder draft, and final versions. The site specific SI Work Plan should reflect the agreements made during the TPP session. One overall Project Plan shall be created to address all the procedures involved in the implementation of the work agreed to in the TPP meeting. All procedures to be accomplished in the project, especially in the field, shall be described. The Project Plan shall not be generic in nature. The Project Plan will address project management, organization, completion of the fieldwork activities, site safety and health, quality control, descriptions of reporting to be done, and descriptions of planned report contents and formats. The Project Plan will be made available to the field team at all times.

REQUIREMENTS:

At minimum, the Project Plan shall contain a Work Plan, an Accident Prevention Plan (APP) as well as any other applicable sub-plans (including but not limited to a Site-specific Safety and Health Plan (SSHP) and the Site-specific UXO Avoidance Accident Prevention Plan) required. The UXO AAPP must be submitted and accepted prior to any onsite visit to the site(s). Intrusive fieldwork will require USACE review and acceptance of the full APP and all subplans. The UXO AAPP will address intrusive work, i.e. MC sampling. The Project Plan should be organized into separate chapters or sections to describe the distinct tasks and/or sub-tasks of this project. The Plan can be submitted in one or more 3-ring binders. Each binder must include the entire table of contents, which shows how the Plan and multiple volumes are organized. The APP can be submitted in a separate 3-ring binder, if needed. If two volumes are used, the APP is usually placed in Volume 2. The Work Plan shall include a detailed project schedule with all tasks, reviews, and subtasks shown. The Work Plan shall describe how the Contractor will manage the site and all aspects of the work to be done. The Work Plan shall follow the Uniform Federal Policy for Quality Assurance Project Plans (UFP-QAPP) manual found at the following web site: http://www.epa.gov/fedfac/documents/qualityassurance.htm The applicable QAPP worksheets shall be completed with specific information.

The Project Plan shall provide the details for execution of all field work, project management, data management, project reporting, and project safety. At a minimum, the following shall be described in specifics:

· Description of public notice activities planned;

· Site management and layout during field activities;

· The locations of all sampling points for all media;

· Field techniques for sample collection and preparation;

· Sample preservation and transport;

· Chemical testing shall be described and all test methods shall be specified; and the sampling plans shall be approved by the Contractor’s Chemist prior to submittal for Draft review by the USACE.

· Schedule for completion of all fieldwork activities;

· Method for complying with any permit requirements and utility clearances;

· Contractor Quality Control Plan;

· Project reporting methods from the field;

· Organizational chart with team members identified; and

· The content and organization of reports to be produced by implementing the Plan.

The Contractor shall prepare a Project Management Plan (PMP) that shall include a discussion of the technical approach and schedules associated with this project. The PMP shall also include a description of personnel, including subcontractor personnel, required to complete this project. The names of the main project team members shall be specified. An organizational flow chart shall be provided for the project and updated, as needed. The plan shall include a detailed project schedule chart.

The Contractor shall prepare a Data Management Plan (DMP). The DMP shall fully describe the methods, techniques, and procedures that the Contractor will use to ensure that all data produced during the project will be accurately gathered, recorded, maintained, and reported. The plan shall indicate how information from surveys and testing will be presented. It shall also describe the contents and organization of all project documents that will be produced as a result of the plan execution.

The Contractor shall be fully responsible for the administration of health and safety requirements for the project. The Contractor shall prepare a site-specific Accident Prevention Plan (APP) in accordance with all local, State, and Federal regulations. The APP shall be prepared in accordance with the requirements of EM 385-1-1, “Safety and Health Requirements Manual”. The APP shall closely follow Appendix A of the EM 385-1-1, with the exception that medical and training certificates shall be submitted for review and acceptance as an appendix. The version of the EM 385-1-1 that is in effect at the signing of the Contract shall be the version that is applicable to all site work. The APP with SSHP and UXO AAPP will be prepared as a stand alone document.

The Contractor shall utilize the services of a Certified Industrial Hygienist (CIH) or Certified Safety Professional (CSP) experienced in hazardous waste site operations to oversee the development and implementation of the health and safety documents required by this section. The CIH/CSP shall review and sign all drafts, final, and revised final submittals of the APP document. If the information made available is insufficient to allow the Contractor to develop these documents, a description of all additional information required shall be prepared and submitted to the USACE PM.

The Work Plan and the APP shall be submitted for review and comment. Comments shall be provided to the Contractor for discussion and incorporation into the succeeding version(s) of the document. The Contractor shall ensure all necessary certifications and documentations are attached to each document version and are valid, and shall annotate all comments, including location of any changes. Personal identification information (PII) such as social security numbers, full birth dates and personal medical results are to be omitted or removed from all training and medical documents. Work shall not begin until the APP is accepted. Final worker certifications must be submitted no later than 2 weeks prior to initial fieldwork.

DELIVERABLES:

The product for this task is an overall Project Plan in UFP-QAPP format, which will include all appropriate sub-plans. Approval must be obtained with no more than two revisions. A Draft, Draft Final, and Final Project Plan shall be submitted.

4.5 TASK 4: MMRP Site Inspection Field Work

OBJECTIVES:

This task involves the implementation of the field work in accordance with the approved project work plan. The execution of the work must follow the procedures outlined in the Plan documents, prepared herein under Task 3. All field work and field reporting shall be in accordance with the approved Project Plan, the PWS, applicable regulations, and guidance.

The Contractor shall obtain all clearances prior to going on site. The Savannah District will be responsible for obtaining rights of entry from property owners identified in Task 1. The specific requirements and deliverables for this task are described under subtasks, which represent the elements of the work to be performed under Task 3.

REQUIREMENTS:

The Contractor shall utilize a commercial laboratory that is NELAP (will be grandfathered) or ELAP (by October 09) -certified whichever is more recent. Contract shall consult and notify the District Chemist which laboratory will perform the work under this task order. Also, the commercial laboratory shall meet the requirements of USEPA, specific state regulator requirements, and all requirements of the most recently approved Department of Defense (DoD) Quality Systems Manual (QSM) version 4.0.

Data shall be reviewed and assessed by qualified personnel in according with the DoD QSM version 4.0, SOPs, appropriate methodologies and flagged/qualified using the EPA National Functional Guidelines. A Chemical Data Quality Assessment will be performed on all analytical data as part of the Site Inspection.

Perform the minimum MEC field activities necessary to determine whether or not UXO or DMM is present on the site. The conduct of this portion of the SI should be such that exclusion zone impacts, engineering control requirements, clearing and grubbing efforts, and MEC disposal activities are minimized. In most cases, encountering just one MEC item will be sufficient to determine that an RI/FS is necessary for a particular MRS. There is no need during the SI work to confirm all types of MEC present, determine MEC density, or define the exact limits of the problem. Coordinate all of these field efforts with the assigned USACE OE Safety Specialist, so that they are present during any intrusive activities. It is anticipated that all field work will be completed during one mobilization.

Perform the minimum HTW field activities necessary to determine whether or not MC contamination is present on the site. The conduct of this portion of the SI should utilize anomaly avoidance techniques. Sampling and analysis should primarily be only for Target Compound List (TCL) explosives and Target Analyte List (TAL) metals. However, after the TPP process, metal analysis may be reduced to small arms munitions-related constituents only where appropriate. For some sites, perchlorates or chemical agents may be determined during the TPP process as potential contaminants of concern as well. The total number of samples should be kept to a minimum and approved field screening/testing methods should be used to the maximum extent practical. In most cases, contamination findings that exceed MCLs, RBCs (based on current land use), or background levels (based on previous studies) will be sufficient to determine that an RI/FS is necessary for a particular MMRP site. There is no need during the SI work to determine the nature and extent of all contaminants or to develop sufficient information for a baseline risk assessment.

DELIVERABLES:

The deliverable for this task is the completion of all field work associated with the Site Inspection, as agreed to in the TPP Memo, the Project Plan, and this PWS. Furthermore, the Contractor must be able to provide documentation that demonstrates that the fieldwork was completed as planned. The work performed must be documented by photos, field records, site data, diagrams, tables, and lab data. Daily work must be documented in real time via the DQCRs, submitted by the field team leader. These items shall be delivered to the Government 30 days after the completion of Task 4, unless otherwise specified. All field record and other reports shall be written in a neat and clear manner, so they are useful for a permanent record. The site shall be kept orderly at all times and will be returned to the Government in a restored to an acceptable neat condition, once the Contractor leaves the site.

4.6 TASK 5: Reports and Routine Project Reporting

Prepare and submit the SI Report in draft, stakeholder draft, and final versions.

REQUIREMENTS:

The SI Report document shall include an updated Conceptual Site Model (CSM) developed for each site and an Appendix containing the completed Munitions Response Site Prioritization Protocol (MRSPP). The reports shall contain photos, field data sheets, tables, figures, and other inclusions to properly document and describe the remediation and the monitoring completed. Field records and photos are particularly important. Each report will have a table of contents and all pages shall be numbered. Figure title blocks of figures shall include the name of the document they are published in. The Contractor shall also provide all sampling data collected as part of the SI in electronic format for upload to FUDSCHEM. Provide copies of the final SI Report to the information repository.

DELIVERABLES:

The deliverables for this task include the Draft, Draft Final, and Final of the report described above. This must be certified by a Georgia registered PE or a PG.

Additional deliverables under this task would be the Monthly Progress Reports, Daily QC Reports, Invoices, Updated Schedules, and miscellaneous project data produced. These are submitted to the USACE only. These submittals are described further in the Submittals Section of this PWS.

4.7 TASK 6: Contractor Manpower Reporting

Accounting for Contract Services/Contractor Manpower Reporting (UNCLASSIFIED) The Office of the Assistant Secretary of the Army (Manpower & Reserve Affair) operates and maintains a secure Army data collection site where the contractor shall report ALL contractor manpower (including sub-contractor manpower) required for using the following web site: https://contractormanpower.army.pentagon.mil

REQUIREMENTS:

Prepare all specific reports in accordance with applicable, Federal, State, and local regulations. The entries must be acceptable within two revisions.

DELIVERABLES:

Enter all required information and information below into CMRA:

· Contracting Office, Contracting Officer, and Contracting Officer’s Representative.

· Contract number, including task and delivery order number.

· Beginning and ending dates covered by reporting period.

· Contractor names, address, phone number, e-mail address, and identity of contractor employee entering data.

· Estimated direct labor hours (including sub-contractors).

· Estimated direct labor dollars paid this reporting period (including sub-contractors).

· Total payments (including sub-contractors).

· Predominant Federal Service Code (FSC) reflecting services provided by contractor (and separate predominant FSC for each sub-contractor if different).

· Estimated data collection cost.

· Organizational title associated with the Unit Identification Code (UIC) for the Army Requiring Activity (the Army Requiring Activity is responsible for providing the contractor with its UIC for the purpose of reporting this information).

· Locations where contractor and sub-contractors perform the work (specified by zip code in the United States and nearest city, country, when in an overseas location, using standardized nomenclature provided on website).

5 TECHNICAL REQUIREMENTS

5.1 Project Management

The Contractor shall follow the specific Project Management Plan (PMP), prepared under Task 2. Any deviations from the plan shall be documented in writing and approved by the COR. Any corrections needed to the plan shall be documented and described in the report. The organizational chart shall be provided for the project and updated, as needed.

5.2 Sample Collection and Analysis

All sample collection methods will be in accordance with the approved work plan and applicable regulations. It is the responsibility of the Contractor to determine the specific tests required to meet all project goals. State and Federal guidance and requirements are updated periodically. Concurrence with GA EPD requirements is a goal of this project. Plans prepared for this project shall be specific regarding the test methods to be used, QC and QA samples, as well as the number and type of samples and the containers to be used for each sample type.

5.3 Health, Safety, and Emergency Response

The Contractor shall be fully responsible for the administration of health and safety requirements for the project. The Contractor Accident Prevention Plan (APP) shall be written in accordance with all local, State, and Federal regulations. The APP shall be prepared in accordance with the requirements of EM 385-1-1, Safety and Health Requirements Manual (with all current additions/revisions); and shall meet or exceed the requirements in ER 385-1-92, Safety and Occupational Health Requirements for Hazardous, Toxic and Radioactive Waste (HTRW) Activities

Additionally, the Contractor must adhere to all DoD policies, procedures and regulations for munitions response. This includes but is not limited to DoD 6055.09-STD, DoD Ammunition and Explosives Safety Standards; Army Regulation 385-10, the Army Safety Program; Department of Army Pamphlet 385-63, Range Safety; and Department of Army Pamphlet 385-64, Ammunition and Explosives Safety Standards. All UXO technicians and personnel shall meet the minimum qualifications in Department of Defense Explosives Safety Board (DDESB) Technical Pamphlet 18.

The sites are not suspected to contain Chemical Warfare Materiel (CWM); however, if suspect CWM is encountered during any phase of site activities the Contractor shall immediately halt operations and contact the COR for assistance and guidance.

All activities involving work in areas potentially containing MEC hazards shall be conducted in full compliance with Department of Army, state, and local requirements regarding personnel, equipment and procedures, and DoD Standard Operating Procedures and safety regulations.

The APP shall include but not be limited to Activity Hazard Analysis (AHAs), site drawings for field work zones, and other site controls. Any changes or adjustments of the APP needed shall be addressed in a letter addendum that prefaces the accepted APP. Copies of updated certificates of training, medical clearance, fit tests and any new personnel or subcontractors shall also be included in the letter addendum submittal. The letter addendum shall be signed by the CIH/CSP, plan preparer, and the project manager.

For details on how to prepare an APP, please refer to EM 385-1-1, Safety and Health Requirements Manual, Appendix A. All APPs must be in the exact format and numbering as presented in the Appendix A.

5.4 Data Management

All data and information shall be compiled and managed, as outlined in the DMP. Data presented in the report shall be in the following forms: listed, sorted, tabulated, graphed, or charted, or any combination of the above. Figures and charts shall be used to clearly highlight relationships of data on a site or significant contamination in relation to regulatory requirements (e.g., ACLs, MCLs etc.). Reduced data presented in the report shall be of sufficient quantity and quality to ensure the accurate use of common statistical methods.

5.5 Regulatory Requirements

All site investigation activities and health and safety documents required by this PWS shall comply with and reflect the following regulations and appropriate guidance publications, at a minimum:

· Federal Acquisition Regulation, FAR Clause 52.236-13: Accident Prevention.

· U.S. Army Corps of Engineers, Safety and Health Requirements Manual, EM 385-1-1. See the USACE website for the most current edition and latest addendums. The most current edition shall be used. This is a required document.

· U.S. Army Corps of Engineers Safety and Occupational Health Requirements for Hazardous, Toxic, and Radioactive Waste (HTRW) Activities, ER 385-1-92, 1 May 2007. All engineering regulations (ERs) can be viewed at the Huntsville District TECHINFO website page http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx . This is a required document.

· Occupational Safety and Health Administration (OSHA) Construction Industry Standards, 29 CFR 1926, General Industry Standards, 29 CFR 1910, especially 29 CFR 1910.120 - Hazardous Waste Site Operations and Emergency Response.

· NIOSH/OSHA/USCG/EPA, “Occupational Safety and Health Guidance Manual for Hazardous Waste Site Activities,” October 1985.

· EM 385-1-1 requires that the American Conference of Governmental Industrial Hygienists Threshold Limit Values and Biological Exposure Indices be applied over the OSHA Permissible Exposure Limits (PELs) for all site exposure limits. The most current edition shall be used. This is a required document.

· Other applicable Federal, State, and local safety and health requirements.

· Requirements for the Preparation of Sampling and Analysis Plans, EM 200-1-3.

· Department of Defense Explosives Safety Board, Minimum Qualifications for Unexploded Ordnance (UXO) Technicians and Personnel, TP 18, 20 December 2004.

6 SUBMITTALS AND CORRESPONDENCE

6.1 Schedule and Monthly Progress Reports

The Contractor shall include with the proposal a tentative schedule for the completion of all work outlined in this PWS and RFP. Within 10 days of receipt of the notice to proceed, the Contractor shall prepare a progress chart showing the project schedule for completion of work. The schedule shall be prepared in reproducible form and submitted for approval. The actual progress of the work shall be updated and submitted by the 5th day of each month and may be included with the request for payment. Progress charts must be revised to reflect modifications and other approved changes in scheduling.

Along with the progress chart, a Monthly Progress Report, in letter format, shall be addressed to the USACE PM. The letter shall outline the progress during the past month and projected work effort for the next month. All progress reports and schedules shall be submitted via electronic mail.

The Monthly Reports shall be submitted to the USACE PM and TM. The monthly reports shall include at a minimum, but are not limited to:

· Updated project schedule in Gantt Chart format

· Progress made during the preceding month

· Percent completion of the overall task order, and by specific task

· Projected work effort for the next month

6.2 Additional Reporting

Daily Quality Control Reports (DQCRs) These shall be prepared by the technical professional on site during any field work. Each DQCR briefly describes the day’s work, lists the personnel on site, visitors, weather, equipment on site, and other information. They are provided to the TM, at minimum, by the end of each week.

Identification of Responsible Personnel Each submittal shall identify the specific members and title of the Contractor's and Subcontractor’s staff that had significant input into the report’s preparation or review. All submittals shall be signed by a registered Professional-In-Charge.

Review Comments Various reviewers will have the opportunity to review submittals made by the Contractor under this contract. The Contractor shall review all comments received through the Project Delivery Team/ Contracting Officer and evaluate their appropriateness based upon their merit and the requirements of the PWS. The Contractor shall issue to the Project Manager a formal, annotated response to each. The Contractor shall not non-concur with a comment without discussing with the PM and/or comment maker. Where comments refer to a specific paragraph of a document and the paragraph number has changed since the comment was made, the Contractor shall note the new paragraph number in the annotated response to the comment.

Meeting Minutes The Contractor shall be responsible for recording and preparing the notes for each meeting. Meeting notes shall be prepared and submitted via email or fax, signed by the Contractor PM, and distributed to all meeting attendees within ten working days after the meeting date. The notes shall include the date, place, and a list of attendees, including organization and telephone number. Comments made during the meeting or decisions affecting criteria changes shall be recorded. Written comments presented by attendees shall be attached to all copies of the meeting notes with the conference action noted.

Confirmation Notices The Contractor shall be required to provide a record of all discussions, verbal directions, and telephone conversations participated in by the Contractor or his representative on matters relative to this project. These records, titled “Confirmation Notices”, shall be numbered sequentially and shall fully identify participating personnel, subject discussed, and any conclusions reached. A copy of all notices shall be provided to the USACE PM and to the USACE TM within 1 week of the discussion.

Project Records At the completion of the project, the Contractor shall provide to the USACE a complete set of project records including all correspondence, memorandums, trip reports, confirmation notices, maps, photographs, and any other records or documents generated as a result of the project.

Electronic Format Requirements All reports generated by the Contractor under this task order shall be submitted in .pdf format in accordance with Technical Appendix 1, which is included at the end of the PWS text. In addition, all final text and spreadsheet files shall be furnished to the USACE in MS Office 2007 compatible format.