amd1.pdf

PDF 37 KB Posted

Attached to
FY 16 Entrance Channel Dredging at Savannah and Brunswick Harbors
Solicitation number
W912HN-15-B-0004
Issued by

About this file

Amd 1

View the file

Other files

File Type Posted
Bid_Abstract_15-B-0004_Maint_Dredging_SAV_BRUNS.pdf PDF
15B04.pdf PDF
BrunEntChan--27July2015.xyz XYZ file
SavhEntChan-29oct2015.xyz XYZ file
SavhO M-00Bto60B_july_2015.xyz XYZ file
CedarHammock-24sept2015.xyz XYZ file
amd3.pdf PDF
15B04.pdf PDF
amd2.pdf PDF
W912HN-15-B-0004_AMD1.pdf PDF
15B04.pdf PDF
15B04.pdf PDF
W912HN-15-B-0004.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendement 1 to incorporate the follow ing changes:

A. CONTRACT CHANGES: Changes to estimated quantities and reaches in CLINs 0002, 0003, and 0005.

B. TECHNICAL SPECIFICATION CHANGES: There are no technical specification changes w ith this amendment.

C. CONTRACT DRAWINGS – File No. CWK0572:

Sheets VH103, VH104, VH105, VH106, VH107, VH108, and VH109, w ith Revision 1 dated 04 November 2015 are hereby added to and made a part of the Contract Draw ings.

All other conditions remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Nov-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HN-15-B-0004

X 9B. DATED (SEE ITEM 11)

28-Oct-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 2 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Nov-2015

CODE

US ARMY ENGINEER DISTRICT, SAVANNAH

100 WEST OGLETHORPE AVE.

SAVANNAH GA 31401-3640

W912HN 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912HN-15-B-0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SECTION 00 00 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

SUBCLIN 0002AB

The pricing detail quantity has increased by 139,000.00 from 225,000.00 to 364,000.00.

CLIN 0003

The CLIN extended description has changed from Cut/Jekyll Island - Maintenance Dredging -Station 21+835 to 12+000 (Bin limits are required for placement in the Savannah ODMDSDO NOT BID (SEE SUBCLINS 0003AA & 0003AB) to Cut/Jekyll Island - Maintenance Dredging -Station 25+000 to 12+000 (Bin limits are required for placement in the Savannah ODMDSDO NOT BID (SEE SUBCLINS 0003AA & 0003AB).

SUBCLIN 0003AA

The CLIN extended description has changed from Cut/Jekyll Island - First 10,000 Cubic Yards to Cut/Jekyll Island - First 25,000 Cubic Yards.

The pricing detail quantity has increased by 15,000.00 from 10,000.00 to 25,000.00.

SUBCLIN 0003AB

The CLIN extended description has changed from Cut/Jekyll Island - All over 10,000 Cubic Yards to Cut/Jekyll Island - All over 25,000 Cubic Yards.

The pricing detail quantity has increased by 42,000.00 from 10,000.00 to 52,000.00.

CLIN 0004

The CLIN extended description has changed from - Maintenance Dredging - Station 12+000 to -12+000B (Bin limits are required for placement in the Brunswick ODMDS)DO NOT BID (SEE SUBCLINS 0004AA & 0004AB) to - Maintenance Dredging - Station -12+000B to 12+000B (Bin limits are required for placement in the Brunswick ODMDS)DO NOT BID (SEE SUBCLINS 0004AA & 0004AB).

SUBCLIN 0005AA

The CLIN extended description has changed from First 447,000 cubic yards to First 500,000 cubic yards.

The pricing detail quantity has increased by 53,000.00 from 447,000.00 to 500,000.00.

SUBCLIN 0005AB

The CLIN extended description has changed from All over 447,000 cubic yards to All over 500,000 cubic yards.

The pricing detail quantity has decreased by 313,000.00 from 853,000.00 to 540,000.00.

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following Delivery Schedule item for SUBCLIN 0002AB has been changed from:

DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC

POP 15-DEC-2015 TO

31-MAR-2016

N/A SEE SCHEDULE

GA

FOB: Destination

W912HN

To:

DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC

POP 15-DEC-2015 TO

31-MAR-2016

N/A SEE SCHEDULE

GA

The following Delivery Schedule item for SUBCLIN 0003AA has been changed from:

POP 15-DEC-2015 TO

31-MAR-2016

N/A SEE SCHEDULE

GA

POP 15-DEC-2015 TO

31-MAR-2016

N/A SEE SCHEDULE

GA

The following Delivery Schedule item for SUBCLIN 0003AB has been changed from:

POP 15-DEC-2015 TO

31-MAR-2016

N/A SEE SCHEDULE

GA

POP 15-DEC-2015 TO

31-MAR-2016

N/A SEE SCHEDULE

GA

The following Delivery Schedule item for SUBCLIN 0005AA has been changed from:

POP 15-DEC-2015 TO

31-MAR-2016

N/A SEE SCHEDULE

GA

POP 15-DEC-2015 TO

31-MAR-2016

N/A SEE SCHEDULE

GA

The following Delivery Schedule item for SUBCLIN 0005AB has been changed from:

POP 15-DEC-2015 TO

31-MAR-2016

N/A SEE SCHEDULE

GA

POP 15-DEC-2015 TO

31-MAR-2016

N/A SEE SCHEDULE

GA

SECTION 01 00 00 - GENERAL REQUIREMENTS

The following have been modified:

SOW

Statement of Work

FY 16 Savannah/Brunswick Entrance Maintenance Dredging Channels Contract

The Savannah District Corps of Engineers

Maintenance dredging of the Savannah and Brunswick Entrance Channels shall require dredging approximately 2 million cubic yards of maintenance material from the entrance channels of Savannah and Brunswick Harbors. The dredged material will be placed in the Savannah and Brunswick EPA approved ODMDS. The required dredging window will be 15 December 2015 through 31 March 2016.

Hopper dredge(s) will be required for the work. The dredge(s) must have the capability to dredge sands and silts to a depth of -46 MLLW and to transport the dredged sediment up to 15 miles to the dump location. QCS will be required and the dredge(s) will be required to have DQM installed and in operating condition. On board environmental monitoring will be required.

Dredged material shall be placed in the designate O&M box inside the limits of the approved ODMDS for both harbors, as noted in the plans and specifications. A depth of -30 feet is the warning threshold for monitoring and management purposes for dredge material placement in the ODMDS. If -30 feet MLLW is reached, then management decisions will be made on future sediment placement to avoid exceeding the -25 foot MLLW threshold. Furthermore, disposal shall be within a specific area within the ODMDS identified by the USACE in consultation with EPA, Region 4 in order for disposal monitoring to be effective.

There are bin size restrictions in Savannah and Brunswick Harbor. The Savannah bin restriction is 12,500 cu.yds.

The Brunswick bin size restrictions for the following navigation channel reaches are:

Stations +33+500 to 0+000 bin size restricted to 6,500 cu.yds.

Stations 0+000 to -19+000 bin size is unrestricted.

Stations -19+000 to -23+000 bin size is restricted to 8,000 cu.yds.

Stations -23+000 to -34+000 bin size is restricted to 5,000 cu.yds.

Stations 34+000 to deep water bin size is restricted to 9,500 cu.yds.

A concurrence, or permit, for disposal of dredged material in the ODMDS does not authorize excessive leakage, overflow, or spill out of barges, dump scows, or hopper dredges of water and excavated material while en route to the ODMDS release zone. Therefore, no overflow is allowed after the drag arms are raised and the dredge is on the way to the ODMDS.

An equipment list and capability of each piece of equipment to be used in the work is required. The dredge shall be available for work at the Notice to Proceed.

Environmental restrictions require all hopper dredging be performed between 15 December and 31 March.

Equipment specified must be capable of performing the work required within the time specified above.

Other contracted dredge(s) may be working for the Savannah District in the Savannah Harbor Entrance Channel. If such work occurs, the contractors shall coordinate activities under the direction of the Contracting Officer.

(End of Summary of Changes)