AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to include site visit meeting minutes and sign in documentation from the site visit on 30-Apr-2013 and 1-May-2013. This amendment also extends the proposal due date to 21-May-2013 at 2:00 PM.
1. CONTRACT ID CODE PAGE OF PAGES
1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 08-May-2013
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HN-13-R-0010
X 9B. DATED (SEE ITEM 11)
07-Feb-2013
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-May-2013
CODE
U.S. ARMY ENGINEER DISTRICT SAVANNAH
ATTN: CT/JENNIFER SLATE
100 W OGLETHORPE AVE
SAVANNAH GA 31401-3640
W912HN 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912HN-13-R-0010
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 16-May-2013 02:00 PM to 21-May-2013 02:00 PM.
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
The following have been added by full text:
SITE VISIT INFORMATION 30APR
Minutes of the Pre-proposal Conference for B125 Roof and Fire System Replacement, Robins AFB, GA, UHHZ110183, FY13, W912HN-13-R-0010 @ 0830
Hours 30 Apr 2013
1. A Pre-proposal Conference was held at 0830 hours on 30 Apr 2013 in the USACE conference room, Robins Air Force Base, GA to review the project solicitation with interested parties. A list of attendees has been attached as enclosure (1).
2. The meeting was opened with a review of contractual requirements of the solicitation. The following items were reviewed:
o Proposal due date.
o Project bid schedule.
o Project was identified as a design build.
o Project submission requirements.
o Project criteria, evaluation method and factor weights.
o Best value method of proposal evaluation.
o Contract may be awarded without discussions.
o Proposals development and format.
o Questions will be submitted Projnet Bidders Inquiry (DrChecks).
o Indicated that the project had Liquidated Damages at $2230.79 per calendar day IAW paragraph NOTE NO 4.
o Evaluation of Options clause 52.217- 5.
o Weather clause 52.249-4001.
o Timely submission of proposals o Conflicts in RFP specification 01 01 00 paragraph 7.1.
3. A site visit to the site was conducted after the conference and on 1 May 13.
Jimmy Jones
Senior Project Manager
(End of Summary of Changes)