Technical_Requirements.pdf
PDF 41 KB Posted
- Solicitation number
- W912HN-09-R-0111
About this file
Technical Requirements
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Response to Questions _2_.pdf | ||
| Revised_Technical_Requirements.pdf | ||
| CFLD_1 3_Restroom_existing_facility.pdf | ||
| W912HN-09-R-0111.pdf | ||
| LD_2_comfort_station_existing.pdf | ||
| ARRA_Sign.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Requirements Lock #1 Specifications (all items as specified or approved equal) Staining/Painting/Sealing Reference facility plans for dimensions and layout
1. Exterior - Clean, prepare surface and apply 2 coats of stain on the exterior siding and trim
Siding and associated trim - Olympic exterior stain - match existing color - Fawn Other wood trim & louver panels - Olympic exterior stain - match existing color - Butternut
2. Exterior Doors - Clean, remove rust, prepare surface and apply 1 coat of primer and 2 coats of paint to 3 exterior doors and door frames
Pittsburg Paint Exterior Oil Base Semi-Gloss - match existing color - Tortoise
3. Interior - Clean, prepare surface and apply 2 coats of paint to interior walls, window frames, door and door frame of rest rooms (interior of pipe chase not included)
Olympic Semitransparent Stain Oil Base - match existing color - 917
4. Tile Floor - Clean, prepare surface, apply two coats of sealant TileLab Grout&Tile Sealer – TLPS1-2
Carpentry Reference facility plans for dimensions and layout
1. Gutters – install gutters on front and rear eaves, down spouts on each end
0.032 inch thickness, 6 inch diameter seamless aluminum gutters, 3x4 down spouts, leaf screens
Technical Requirements Lock #1 (continued) Specifications (all items as specified or approved equal) Plumbing Reference facility plans for waste and feed line details
1. Replace existing concealed flushing valve wall mounted button actuators with oscillating handle actuators for 1 water closet in Men’s room and 2 water closets in Women’s room.
Existing Flushing Valves – ZURN - change button flushing actuators to oscillating handle flushing actuators without changing out the concealed flush valves.
2. Remove damaged drinking fountain and replace with new drinking fountain in same location as existing. Reconfigure water supply lines and sanitary waste lines as required for new fountain. Patch and paint wall to match existing. Fountain is located on exterior wall between restroom access doors.
Metcraft 5691, or approved equal- stainless steel - handicap – Install according to ADA requirements. Install according to manufacturer’s instructions. Provide new plumbing connections from new fixture to existing water supply and sanitary waste lines.
Electrical Reference facility plans for existing layout & wiring
1. Install two (2) hand dryers; one for each restroom, install new wiring circuit and new breaker in existing box
Extremeair GXT6-C Satin Chrome, 18 gauge steal cover, chrome plated satin finish, tamper resistant, automatic sensor, 120 volt, 12.5 amp, 1500 watts 12/2 with ground, separate GFI circuits w/ 20 amp overcurrent protection
2. Interior light fixtures - remove existing fixtures and replace, ten (10) total = 2 ceiling and 3 wall mounted on each side, paint and patch ceiling, utilize existing wiring and breaker
Eclipse Lighting Interior - Vandal Resistant - Compact Fluorescent - 120 volt - 32 watt ceiling/wall mounted ceiling mount model 330, wall mount model 338
3. Exterior light fixtures - four (4) total - remove existing light fixtures and replace, utilize existing wiring and breaker
Lithonia -Wall Pack - TWAC 42 TRT compact fluorescent - 120 volt - 42 W
Technical Requirements Lock #2 Specifications (all items as specified or approved equal)
1. Exterior - Clean, prepare surface and apply 2 coats of stain on the exterior walls and trim of restroom building (including exterior of privacy partitions) and entire picnic shelter
Wood - Olympic Exterior Stain - match existing color Cement Board - Pittsburg Paint Exterior Oil Base Satin - match existing color
2. Exterior Doors - Clean, remove rust, prepare surface and apply 1 coat of primer and 2 coats of paint to 3 exterior doors and door frames
Pittsburg Paint Exterior Oil Base Semi-Gloss - match existing color
3. Interior - Clean, prepare surface and apply 2 coats of paint to interior walls, window frames, door and door frame of rest rooms (interior of pipe chase not included)
Concrete masonry walls - Epoxy paint - concrete masonry walls - match color Wood surfaces - Semi Transparent Stain Oil Base - match color
4. Tile Floor - Clean, prepare surface, apply two coats of sealant TileLab Grout&Tile Sealer – TLPS1-2
Carpentry Reference facility plans for dimensions and layout
1. Replace exterior siding on three exposed sides of restroom building and exterior privacy partitions.
19/32" reverse board & batten plywood siding
2. Restroom privacy partitions - Remove existing damaged privacy partitions, install stainless steal partitions with doors. Patch and repair floor & walls to match existing.
Men’s - one handicap stall (72" x 40"); one urinal screen (18”x24”) Women’s - one handicap and one standard (72" x 36")
Global Partitions - stainless steel #4 satin finish, floor anchored overhead braced
3. Replace insect screens on wall ventilation louvers - restroom building match existing
Technical Requirements Lock #2 (continued) Specifications (all items as specified or approved equal) Plumbing Reference original plumbing specifications for waste and feed line details
1. Remove two damaged drinking fountains and replace with a single new drinking fountain. One water supply line and one sanitary waste line serves both existing fountains. Reconfigure these lines for new fountain. Patch and paint wall to match existing. Located on exterior under picnic shelter.
Metcraft 5691, or approved equal- stainless steel - handicap – Install according to ADA requirements. Install according to manufacturer’s instructions. Provide new plumbing connections from new fixture to existing water supply and sanitary waste lines.
1. Exterior - Clean, prepare surface and apply 2 coats of stain on the exterior siding and trim
Siding and associate trim - Olympic Exterior Stain - match existing color - Fawn Other wood trim (fascia, soffits, outlookers), louver panels - Olympic exterior stain - match existing color - Butternut
2. Exterior Doors - Clean, remove rust, prepare surface and apply 1 coat of primer and 2 coats of paint to 3 exterior doors and door frames
Pittsburg Paint Exterior Oil Base Semi-Gloss - match existing color - Tortoise
3. Interior - Clean, prepare surface and apply 2 coats of paint to interior walls, window frames, door and door frame of rest rooms (interior of pipe chase not included)
Olympic Semitransparent Stain Oil Base - match existing color - 917
4. Tile Floor - Clean, prepare surface, apply two coats of sealant TileLab Grout&Tile Sealer – TLPS1-2
Carpentry Reference facility plans for dimensions and layout
1. Gutters – install gutters on front and rear eaves, down spouts on each end
0.032 inch thickness, 6 inch diameter seamless aluminum gutters, 3x4 down spouts, leaf screens
2. Window - replace carbonate window - men’s room - per original specifications 1/4 inch polycarbonate - frosted - match existing
3. Sky Light - replace damaged skylight - per original specifications
2'-0" x 4'-0" Skylight with 4" integral curb flange, frosted glazing - match existing
Technical Requirements Lock #3 Specifications (all items as specified or approved equal)
1. Exterior - Clean, prepare surface and apply 2 coats of stain on the exterior siding and trim
Siding and associate trim - Olympic Exterior Stain - match existing color - Fawn Other wood trim (fascia, soffits, outlookers), louver panels - Olympic exterior stain - match existing color - Butternut
2. Exterior Doors - Clean, remove rust, prepare surface and apply 1 coat of primer and 2 coats of paint to 3 exterior doors and door frames
Pittsburg Paint Exterior Oil Base Semi-Gloss - match existing color - Tortoise
3. Interior - Clean, prepare surface and apply 2 coats of paint to interior walls, window frames, door and door frame of rest rooms (interior of pipe chase not included)
Olympic Semitransparent Stain Oil Base - match existing color - 917
4. Tile Floor - Clean, prepare surface, apply two coats of sealant TileLab Grout&Tile Sealer – TLPS1-2
Carpentry Reference facility plans for dimensions and layout
1. Gutters – install gutters on front and rear eaves, down spouts on each end
0.032 inch thickness, 6 inch diameter seamless aluminum gutters, 3x4 down spouts, leaf screens
2. Window - replace carbonate window - men’s room - per original specifications 1/4 inch polycarbonate - frosted - match existing
3. Sky Light - replace damaged skylight - per original specifications
2'-0" x 4'-0" Skylight with 4" integral curb flange, frosted glazing - match existing
Plumbing Reference facility plans for waste and feed line details.
1. Replace existing concealed flushing valve wall mounted button actuators with oscillating handle actuators for 1 water closet in Men’s room and 2 water closets in Women’s room.
Existing Flushing Valves – ZURN - change button flushing actuators to oscillating handle flushing actuators without changing out the concealed flush valves.
Technical Requirements Lock #3 (continued) Specifications (all items as specified or approved equal)
2. Remove damaged drinking fountain and replace with new drinking fountain in same location as existing. Reconfigure water supply lines and sanitary waste lines as required for new fountain.
Patch and paint wall to match existing. Fountain is located on exterior wall between restroom access doors.
Metcraft 5691, or approved equal- stainless steel - handicap – Install according to ADA requirements. Install according to manufacturer’s instructions. Provide new plumbing connections from new fixture to existing water supply and sanitary waste lines.
Electrical Reference facility plans for existing layout & wiring
1. Install two (2) hand dryers; one for each restroom, install new wiring circuit and new breaker in existing box
Extremeair GXT6-C Satin Chrome, 18 gauge steal cover, chrome plated satin finish, tamper resistant, automatic sensor, 120 volt, 12.5 amp, 1500 watts 12/2 with ground, separate GFI circuits w/ 20 amp overcurrent protection -
2. Interior light fixtures - remove existing fixtures and replace, ten
(10) total = 2 ceiling and 3 wall mounted on each side, paint and patch ceiling, use existing wiring and breaker
Eclipse Lighting Interior - Vandal Resistant - Compact Fluorescent - 120 volt - 32 watt ceiling/wall mounted ceiling mount model 330, wall mount model 338
3. Exterior light fixtures - four (4) total - remove existing light fixtures and replace, use existing wiring and breaker
Lithonia -Wall Pack - TWAC 42 TRT compact fluorescent - 120 volt - 42 W