Response to Questions _2_.pdf

PDF 8 KB Posted

Attached to
RECOVERY--J--PROJECT NUMBER 002640, Cape Fear River Above Wilmington.
Solicitation number
W912HN-09-R-0111
Issued by

View the file

Other files

File Type Posted
Revised_Technical_Requirements.pdf PDF
CFLD_1 3_Restroom_existing_facility.pdf PDF
W912HN-09-R-0111.pdf PDF
Technical_Requirements.pdf PDF
LD_2_comfort_station_existing.pdf PDF
ARRA_Sign.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number W912HN-09-R-0111 Response to Questions (Number 2)

Questions:

1. Interior privacy partitions at L&D #3 needs new handles. (3 are broken or missing)

2. Bug screen on louvers in men’s room at L&D #3 has since been torn out. Do you want them to replace?

3. Exterior privacy screens at L&D #2 are leaning and may require new uprights secured better.

4. After removing the 2nd water fountain at L&D #2 the electrical outlet will be exposed and may be required to be changed to a GFCI outlet.

5. Hand driers at L&D # 1 & #3 will require Wiremold or Conduit. Which is preferred?

Answers:

1. Corps of Engineers staff will replace.

2. Corps of Engineers staff will replace if additions can not be made.

3. Corps of Engineers staff will repair if additions can not be made.

4. It will not be used by the fountain and should be removed. Corps of Engineers staff will remove it.

5. Wiremold