- RECOVERY--47--Lake Marion Regional Water System Project, Holly Hill Reach Water Transmission Main Phase I
- Solicitation number
- W912HN-09-R-0076
About this file
Contract Drawing P23 has been revised to reflect a change in the horizontal alignment of the proposed pipeline to keep it within the existing easement. The existing well will be required to be demolished by the Contractor during construction. This modification eliminates two (2) 30-inch diameter fittings. Paragraph 1.8 of Specification Section 02300 has been revised to describe the use of unsatisfactory materials if encountered.