09-B-0031 P00001 BEJ Rip Rap.pdf
PDF 199 KB Posted
- Solicitation number
- W912HN09-B-0031
About this file
SF 30 - summary of changes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Abstract.pdf | ||
| Bid Abstract.pdf | ||
| JrdnRipRapRpr_Plans.pdf | ||
| SPECIFICATIONS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W81LJ891697660
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
SOLICITATION NUMBER W912HN-09-B-0031, ENTITLED REPAIR RIPRAP AT B. EVERETT JORDAN DAM, NORTH CAROLINA IS AMENDED AS FOLLOWS:
1. THE TIME AND DATE SET FOR BID OPENING REMAINS UNCHANGED.
2. SEE SUMMARY OF CHANGES.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Nov-2009
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HN-09-B-0031
X 9B. DATED (SEE ITEM 11)
28-Oct-2009
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 2 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES T HE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. T HIS CHANGE ORDER IS ISSUED PURSUANT T O: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Nov-2009
CODE
U.S. ARMY ENGINEER DISTRICT SAVANNAH
ATTN: DANNY KISSAM
69 DARLINGTON AVENUE
910-251-4424 (FAX) 910-251-4454
WILMINGTON NC 28403
W912HN 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912HN-09-B-0031
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The following have been added by full text:
52.214-4006 52.214-4006 Solicitation/Technical Inquiries via ProjNet (Local Instruction - CECT-SAS Nov 2009)
1. Solicitation/Technical Inquiries.
a. Inquiries are to be submitted via Bidder Inquiry in ProjNet at www.projnet.org\projnet.
b. If you have problems submitting your inquires via ProjNet, contact Mr. Shane Jones at 910-251-4095 or Ms.
Oweita Freeman at 910-251-4741.
2. Read this paragraph in conjunction with contract provision FAR 52.214-6, “Explanation to Prospective Bidders”.
3. Any prospective bidder/offer desiring an explanation or interpretation of the solicitation, drawings specifications, etc., must request it in writing via Bidder Inquiry in ProjNet within no less than ten (10) calendar days prior to the date of bid opening or receipt of proposals. The Government reserves the right to decline addressing questions received less than ten (10) calendar days prior to receipt of bid opening or receipt of proposals.
4. ProjNet - Bidder Inquiry module.
a. To submit and review bid inquiry items, bidders/offerors will need to be a current registered user or self-register into system. To self-register go to the ProjNet web page, click BID tab, select Bidder inquiry, select agency USACE, enter Bidder Inquiry Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.
Please remember your Secret Question Answer for future access to this website.
b. From this page you may view all bidder/offeror inquiries under Reports or post a new inquiry under Submit.
c. Bidders/Offerors will receive an acknowledgement of their question via email, followed by another email notification that an answer to their question has been posted after it has been reviewed by our technical team and responded to by a Contracting Officer.
d. Bidders/Offerors are responsible for checking bid inquiry items.
e. Bidders/Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry. The name of the submitter or firm is not published for the public on the report of all Bidder Inquiries.
5. Solicitation Information:
IFB/RFP No: W912HN-09-B-0031
Bidder Inquiry Key: 6RTE24-Q1BUVK
(end)
W912HN-09-B-0031
The following have been deleted:
52.214-4006
Page 4 of 4 Pages
SECTION 01 35 26 – GOVERNMENTAL SAFETY REQUIREMENTS
(1) Delete existing Table of Contents Page 1 and Page 2 in their entirety and replace with enclosed revised Pages.
(2) Delete existing SECTION Page 7 thru Page 12 in their entirety and replace with enclosed revised Pages.
(3) ADD Attachment 3 – COVER and Enclosure in their entirety.
NOTE:
Text that is added or revised by this amendment is replaced in its entirety and underlined and/or printed in bold and/or stamped appropriately.
The text changes may have necessitated reformatting of subsequent text or pages. If this is the case, those pages have also been issued as amended pages but are not underlined or bold text.
(End of Summary of Changes)
Encls As stated
Jordan Dam Riprap Repair, W912HN-09-B-0031 B.Everett Jordan Dam and Lake, Chatham County, NC
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DEFINITIONS
1.4 REGULATORY REQUIREMENTS
1.5 SITE QUALIFICATIONS, DUTIES AND MEETINGS
1.5.1 Personnel Qualifications
1.5.1.1 Site Safety and Health Officer (SSHO)
1.5.1.2 Crane Operators
1.5.2 Personnel Duties
1.5.2.1 Site Safety and Health Officer (SSHO)
1.5.3 Meetings
1.5.3.1 Preconstruction Conference
1.5.3.2 Safety Meetings
1.6 ACCIDENT PREVENTION PLAN (APP)
1.6.1 USACE EM 385-1-1 Contents
1.7 ACTIVITY HAZARD ANALYSIS (AHA)
1.8 DISPLAY OF SAFETY INFORMATION
1.9 SITE SAFETY REFERENCE MATERIALS
1.10 EMERGENCY MEDICAL TREATMENT
1.11 REPORTS
1.11.1 Accident Reports
1.11.2 Accident Notification
1.11.3 Monthly Exposure Reports
1.11.4 Crane Reports
1.11.5 Certificate of Compliance
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 CONSTRUCTION AND/OR OTHER WORK
3.1.1 Hazardous Material Use
3.1.2 Hazardous Material Exclusions
3.1.3 Unforeseen Hazardous Material
3.2 EQUIPMENT
3.2.1 Material Handling Equipment
3.2.2 Weight Handling Equipment
3.2.3 Equipment and Mechanized Equipment
3.3 EXCAVATIONS
3.3.1 Utility Locations
3.3.2 Utility Location Verification
3.3.3 Shoring Systems
3.3.4 Trenching Machinery
SECTION TABLE OF CONTENTS 01 35 26 Page 1 (Revised by Amendment No. 0001)
3.4 UTILITIES WITHIN CONCRETE SLABS
3.5 ELECTRICAL
3.5.1 Conduct of Electrical Work
3.5.2 Portable Extension Cords
ATTACHMENTS:
Attachment 1 - Minimum Basic Outline for Accident Prevention Plan
Attachment 2 - Safety Performance Sign
Attachment 3 - Work Sheet for Preliminary Accident Notification
-- End of Section Table of Contents --
SECTION TABLE OF CONTENTS 01 35 26 Page 2
EM 385-1-1. Submit the AHA for review at least 15 calendar days prior to the start of each phase. Format subsequent AHAs as amendments to the APP.
The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls.
The AHA list will be reviewed periodically (at least monthly) at the Contractor supervisory safety meeting and updated as necessary when procedures, scheduling, or hazards change.
Develop the activity hazard analyses using the project schedule as the basis for the activities performed. Any activities listed on the project schedule will require an AHA. The AHAs will be developed by the contractor, supplier or subcontractor and provided to the prime contractor for submittal to the Contracting Officer.
1.8 DISPLAY OF SAFETY INFORMATION
Within 5 calendar days after commencement of work, erect a safety bulletin board at the job site as shown on Attachment 2 - Safety Performance Sign.
Include and maintain information on safety bulletin board as required by USACE EM 385-1-1, section 01.A.06.
1.9 SITE SAFETY REFERENCE MATERIALS
Maintain safety-related references applicable to the project, including those listed in the article "References." Maintain applicable equipment manufacturer's manuals.
1.10 EMERGENCY MEDICAL TREATMENT
Contractors will arrange for their own emergency medical treatment.
Government has no responsibility to provide emergency medical treatment.
1.11 REPORTS
1.11.1 Accident Reports
a. Conduct an accident investigation for recordable injuries and illnesses, and property damage accidents resulting in at least $2,000 in damages, to establish the root cause(s) of the accident, complete the USACE Accident Report Form 3394 and provide the report to the Contracting Officer within 5 calendar days of the accident. The Contracting Officer will provide copies of any required or special forms.
b. Conduct an accident investigation for any weight handling equipment accident (including rigging gear accidents) to establish the root cause(s) of the accident, complete the WHE Accident Report (Crane and Rigging Gear) form and provide the report to the Contracting Officer within 30 calendar days of the accident. Do not proceed with crane operations until cause is determined and corrective actions have been implemented to the satisfaction of the contracting officer. The Contracting Officer will provide a blank copy of the accident report form.
1.11.2 Accident Notification
Notify the Contracting Officer of all accidents as soon as practical, but
SECTION 01 35 26 Page 7 not later than four hours after occurrence. The notification shall be done by completing the Work Sheet for Preliminary Accident Notification form (see Attachment 3 - Work Sheet for Preliminary Accident Notification) and providing it to the Contracting Officer. For major accidents, preserve the conditions and evidence on the accident site until the Government investigation team arrives on-site and the Government's investigation is complete. Major accidents are defined as accidents that result in fatalities, permanent total or permanent partial disabilities, three or more admitted to the hospital, and $200,000 or more in property damage.
1.11.3 Monthly Exposure Reports
Monthly exposure reporting to the Contracting Officer is required to be submitted by the 5th of the month for the previous month. This report is a compilation of employee-hours worked each month for all site workers, both prime and subcontractor. The Contracting Officer will provide copies of any special forms.
1.11.4 Crane Reports
Submit crane inspection reports required in accordance with USACE EM 385-1-1, Appendix H and as specified herein with Daily Reports of Inspections.
1.11.5 Certificate of Compliance
Provide a Certificate of Compliance for each crane entering an activity under this contract (see Contracting Officer for a blank certificate).
State within the certificate that the crane and rigging gear meet applicable OSHA regulations (with the Contractor citing which OSHA regulations are applicable, e.g., cranes used in construction, demolition, or maintenance comply with 29 CFR 1926 and USACE EM 385-1-1 section 16 and Appendix H. Certify on the Certificate of Compliance that the crane operator(s) is qualified and trained in the operation of the crane to be used. Post certifications on the crane.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 CONSTRUCTION AND/OR OTHER WORK
Comply with USACE EM 385-1-1, NFPA 241, the APP, the AHA, Federal and/or State OSHA regulations, and other related submittals and activity fire and safety regulations. The most stringent standard prevails.
3.1.1 Hazardous Material Use
Each hazardous material must receive approval prior to being brought onto the job site or prior to any other use in connection with this contract.
Allow a minimum of 10 working days for processing of the request for use of a hazardous material.
3.1.2 Hazardous Material Exclusions
Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation (with the exception of radioactive material
SECTION 01 35 26 Page 8 and devices used in accordance with USACE EM 385-1-1 such as nuclear density meters for compaction testing and laboratory equipment with radioactive sources) as well as materials which contain asbestos, mercury or polychlorinated biphenyls, di-isocynates, lead-based paint are prohibited. The Contracting Officer, upon written request by the Contractor, may consider exceptions to the use of any of the above excluded materials.
3.1.3 Unforeseen Hazardous Material
The design should have identified materials such as PCB, lead paint, and friable and non-friable asbestos. If material, not indicated, that may be hazardous to human health upon disturbance during construction operations is encountered, stop that portion of work and notify the Contracting Officer immediately. Within 14 calendar days the Government will determine if the material is hazardous. If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to "FAR 52.243-4, Changes" and "FAR 52.236-2, Differing Site Conditions."
3.2 EQUIPMENT
3.2.1 Material Handling Equipment
a. Material handling equipment such as forklifts shall not be modified with work platform attachments for supporting employees unless specifically delineated in the manufacturer's printed operating instructions.
b. The use of hooks on equipment for lifting of material must be in accordance with manufacturer's printed instructions.
c. Operators of forklifts or power industrial trucks shall be licensed in accordance with OSHA.
3.2.2 Weight Handling Equipment
a. Equip cranes and derricks as specified in USACE EM 385-1-1, section 16.
b. Notify the Contracting Officer 15 days in advance of any cranes entering the activity so that necessary quality assurance spot checks can be coordinated. Prior to cranes entering federal activities, a Crane Access Permit must be obtained from the Contracting Officer. A copy of the permitting process will be provided at the Preconstruction Conference. Contractor's operator shall remain with the crane during the spot check.
c. Comply with the crane manufacturer's specifications and limitations for erection and operation of cranes and hoists used in support of the work. Perform erection under the supervision of a designated person (as defined in ASME B30.5). Perform all testing in accordance with the manufacturer's recommended procedures.
d. Comply with ASME B30.5 for mobile and locomotive cranes, and ASME B30.22 for articulating boom cranes.
e. Under no circumstance shall a Contractor make a lift at or above
SECTION 01 35 26 Page 9
90% of the cranes rated capacity in any configuration.
f. When operating in the vicinity of overhead transmission lines, operators and riggers shall be alert to this special hazard and follow the requirements of USACE EM 385-1-1 section 11 and ASME B30.5 or ASME B30.22 as applicable.
g. Do not crane suspended personnel work platforms (baskets) unless the Contractor proves that using any other access to the work location would provide a greater hazard to the workers or is impossible. Do not lift personnel with a line hoist or friction crane.
h. Inspect, maintain, and recharge portable fire extinguishers as specified in NFPA 10, Standard for Portable Fire Extinguishers.
i. All employees must keep clear of loads about to be lifted and of suspended loads.
j. Use cribbing when performing lifts on outriggers.
k. The crane hook/block must be positioned directly over the load.
Side loading of the crane is prohibited.
l. A physical barricade must be positioned to prevent personnel from entering the counterweight swing (tail swing) area of the crane.
m. Certification records which include the date of inspection, signature of the person performing the inspection, and the serial number or other identifier of the crane that was inspected shall always be available for review by Contracting Officer personnel.
n. Written reports listing the load test procedures used along with any repairs or alterations performed on the crane shall be available for review by Contracting Officer personnel.
o. Certify that all crane operators have been trained in proper use of all safety devices (e.g. anti-two block devices).
p. Take steps to ensure that wind speed does not contribute to loss of control of the load during lifting operations. Prior to conducting lifting operations set a maximum wind speed at which a crane can be safely operated based on the equipment being used, the load being lifted, experience of operators and riggers, and hazards on the work site. This maximum wind speed determination shall be included as part of the activity hazard analysis plan for that operation.
3.2.3 Equipment and Mechanized Equipment
a. Proof of qualifications for operator shall be kept on the project site for review.
b. Manufacture specifications or owner's manual for the equipment shall be on-site and reviewed for additional safety precautions or requirements that are sometimes not identified by OSHA or USACE EM 385-1-1. Incorporate such additional safety precautions or requirements into the AHAs.
SECTION 01 35 26 Page 10
3.3 EXCAVATIONS
Perform soil classification by a competent person in accordance with
29 CFR 1926.
3.3.1 Utility Locations
Prior to digging, the appropriate digging permit must be obtained. All underground utilities in the work area must be positively identified by a private utility locating service in addition to any station locating service and coordinated with the station utility department. Any markings made during the utility investigation must be maintained throughout the contract.
3.3.2 Utility Location Verification
The Contractor must physically verify underground utility locations by hand digging using wood or fiberglass handled tools when any adjacent construction work is expected to come within three feet of the underground system. Digging within 2 feet of a known utility must not be performed by means of mechanical equipment; hand digging shall be used. If construction is parallel to an existing utility expose the utility by hand digging every 100 feet if parallel within 5 feet of the excavation.
3.3.3 Shoring Systems
Trench and shoring systems must be identified in the accepted safety plan and AHA. Manufacture tabulated data and specifications or registered engineer tabulated data for shoring or benching systems shall be readily available on-site for review. Job-made shoring or shielding must have the registered professional engineer stamp, specifications, and tabulated data. Extreme care must be used when excavating near direct burial electric underground cables.
3.3.4 Trenching Machinery
Operate trenching machines with digging chain drives only when the spotters/laborers are in plain view of the operator. Provide operator and spotters/laborers training on the hazards of the digging chain drives with emphasis on the distance that needs to be maintained when the digging chain is operating. Keep documentation of the training on file at the project site.
3.4 UTILITIES WITHIN CONCRETE SLABS
Utilities located within concrete slabs or pier structures, bridges, and the like, are extremely difficult to identify due to the reinforcing steel used in the construction of these structures. Whenever contract work involves concrete chipping, saw cutting, or core drilling, the existing utility location must be coordinated with station utility departments in addition to a private locating service. Outages to isolate utility systems must be used in circumstances where utilities are unable to be positively identified. The use of historical drawings does not alleviate the contractor from meeting this requirement.
SECTION 01 35 26 Page 11
3.5 ELECTRICAL
3.5.1 Conduct of Electrical Work
Underground electrical spaces must be certified safe for entry before entering to conduct work. Cables that will be cut must be positively identified and de-energized prior to performing each cut. Positive cable identification must be made prior to submitting any outage request for electrical systems. Arrangements are to be coordinated with the Contracting Officer and Station Utilities for identification. The Contracting Officer will not accept an outage request until the Contractor satisfactorily documents that the circuits have been clearly identified.
Perform all high voltage cable cutting remotely using hydraulic cutting tool. When racking in or live switching of circuit breakers, no additional person other than the switch operator will be allowed in the space during the actual operation. Plan so that work near energized parts is minimized to the fullest extent possible. Use of electrical outages clear of any energized electrical sources is the preferred method. When working in energized substations, only qualified electrical workers will be permitted to enter. When work requires Contractor to work near energized circuits as defined by the NFPA 70, high voltage personnel must use personal protective equipment that includes, as a minimum, electrical hard hat, safety shoes, insulating gloves with leather protective sleeves, fire retarding shirts, coveralls, face shields, and safety glasses. In addition, provide electrical arc flash protection for personnel as required by NFPA 70E.
Insulating blankets, hearing protection, and switching suits may also be required, depending on the specific job and as delineated in the Contractor's AHA.
3.5.2 Portable Extension Cords
Size portable extension cords in accordance with manufacturer ratings for the tool to be powered and protected from damage. Immediately removed from service all damaged extension cords. Portable extension cords shall meet the requirements of NFPA 70.
-- End of Section --
SECTION 01 35 26 Page 12