B.08.02 22R0021-001_released sf30.pdf
PDF 300 KB Posted
- Attached to
- Voru Kindergarten Renovation: Estonia
- Solicitation number
- W912GB22R0021
- Issued by
-
Department of the Army European Command
About this file
This document contains a solicitation for a design-build construction contract and related federal contract opportunity announcement. The U.S. Army Corps of Engineers, Europe District is seeking proposals to renovate the Kindergarten located in Voru, Estonia. Proposals are due by May 5, 2022 at 12:00 PM CEST. The project involves full renovation of electrical, ceilings, floors, walls, doors and optional renovations. The estimated construction cost is between $500,000 to $1,000,000. Award will be a firm-fixed-price contract determined by best value. The pre-award site visit is scheduled for April 20, 2022 and offerors must pre-register. Interested parties must submit both price and non-price proposals and be registered in the System for Award Management to be eligible for award. The federal contract opportunity provides location details and registration instructions.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this Amendment to W912GB22R0021 is to:
1. Extend the closing date of RFP from 5 May 2022 to 12 May 2022.
2. Provide the Government's answ ers to Contractor's Projnet Inquiries
3. Bid Schedule changed from Euros to US Dollars
4. Price Payment Procedures paragraph 1.3.2 changed from Ceilings to Walls
5. Building section draw ing provided for informational purposes
6. Roof Plan draw ing provided for informational purposes
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 05-May-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912GB22R0021
X 9B. DATED (SEE ITEM 11)
24-Mar-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
05-May-2022
CODE
CONTRACTING DIVISION
US ARMY CORPS OF ENGINEERS
KONRAD ADENAUER RING 39
D-65187 WIESBADEN GERMANY
WIESBADEN 65187
W912GB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
X 1
W912GB22R0021
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 01 10 - TABLE OF CONTENTS
The following have been modified:
TABLE OF CONTENTS
Section 00 10 00 – Price Schedule
Section 00 21 16 – Instructions to Offerors
Section 00 22 16 – Evaluation Factors for Award
Section 00 45 00 – Representations and Certifications
Section 00 70 00 – Conditions of the Contract
Section 00 72 00 – Contract Clauses
Section 00 73 00 – Supplementary Conditions
ATTACHMENTS (Incorporated herein by reference)
ATTACHMENT 1 – Project Location Map
ATTACHMENT 2 – Architecture As-Built Drawings
ATTACHMENT 3 – Interior Finishing Schedule
ATTACHMENT 4 – Specification of Sanitary Equipment
ATTACHMENT 5 – Dedication Plaque
ATTACHMENT 6 – Specifications Binder
ATTACHMENT 7 – Statement of Work (SOW)
ATTACHMENT 8 – Bank Letter of Assurance Sample
ATTACHMENT 9 – Bank Letter of Guarantee Sample
ATTACHMENT 10 – Past Performance Information Sheet
ATTACHMENT 11 – Past Performance Questionnaire
ATTACHMENT 12 - Site Visit Registration Spreadsheet
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 05-May-2022 12:00 PM to 12-May-2022 04:00 PM.
The required performance has changed from THE GOVERNMENT REQUIRES PERFORMANCE OF
THE WORK DESCRIBED IN THESE DOCUMENTS.THIS IS A REQUEST FOR PROPOSAL (RFP) FOR THE
DESIGN-BUILD PROJECT FOR RENOVATION OF A FACILITY IN VORU, ESTONIA;THE GOVERNMENT
CONTEMPLATES THAT THIS SOLICITATION WILL RESULT IN A SINGLE FIRM-FIXED PRICE
CONTRACT AWARD USING A BEST VALUE TRADE-OFF ACQUISITION METHOD.A. The estimated
Magnitude of Construction is betw een $500,000 and $1,000,000.B. This RFP is solicited under full and open competition (unrestricted).C. Award of this contract will be made in Euro. to THE GOVERNMENT REQUIRES
PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS.THIS IS A REQUEST FOR
PROPOSAL (RFP) FOR THE DESIGN-BUILD PROJECT FOR RENOVATION OF A FACILITY IN VORU, ESTONIA;THE GOVERNMENT CONTEMPLATES THAT THIS SOLICITATION WILL RESULT IN A
SINGLE FIRM-FIXED PRICE CONTRACT AWARD USING A BEST VALUE TRADE-OFF ACQUISITION
METHOD.A. The estimated Magnitude of Construction is betw een $500,000 and $1,000,000.B. This RFP is solicited under full and open competition (unrestricted).C. Award of this contract will be made in US Dollars $..
The currency type for this contract has changed from Euro to US Dollars.
The following have been added by full text:
PRICE SCHEDULE
PRICE SCHEDULE
Renovate Kindergarten “Päkapikk”, Võru, Estonia
Offerors shall provide pricing for all base and option items.
The following items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Scope of Work (SOW), Solicitation/Request for Proposal. It also includes preparation of all documents, submittals, and schedules;
inspections; and compliance with all technical, quality control, administrative, and safety requirements. All work shall be performed in accordance with these documents. Refer to Specification Section 01 22 00 Price and Payment Procedures for additional description of the work associated with each of the items.
Period of Performance: Refer to clause COMMENCEMENT PROSECUTION AND EXECUTION OF
WORK (52.211-10) in the Solicitation/Request for Proposal for the period of performance for all base and option items.
Liquidated Damages: Refer to clause LIQUIDATED DAMAGES-CONSTRUCTION (52.211-12) in the
Solicitation/Request for Proposal for the liquidated damages for all base and option items.
Option Items: The Government reserves the right to award the options up to 90 calendar days after contract award.
Item
No.
Description Qty Unit Unit Price Amount
BASE ITEMS
0001 Full Electrical Renovation 1 Job $ $
0002 Renovate Ceilings 1 Job $ $
Renovate Floors
(except rooms 136, 139, 143, 144, 145, 146, 150, 151, 218, 221, 221A, 224, 228)
1 Job $ $
0004 Install new doors 1 Job $ $
Renovate walls
(except rooms 136, 139, 143, 144, 145, 146, 150, 151, 218, 221, 221A, 224, 228)
1 Job $ $
Total of Base Items 0001-0005 $
OPTION ITEMS
Renovate Floors
(only rooms 136, 139, 143, 144, 145, 146, 150, 151, 218, 221, 221A, 224, 228)
1 Job $ $
Renovate Walls
(only rooms 136, 139, 143, 144, 145, 146, 150, 151, 218, 221, 221A, 224, 228)
1 Job $ $
0008 Replace Sanitary Equipment in the Bathrooms 1 Job $ $
Item
No.
Description Qty Unit Unit Price Amount
Total of Option Item 0006-0008 $
Total of all Base and Option Items $
EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.
-- END OF PROPOSAL SCHEDULE –
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
PAYMENT TYPES
SINGLE JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the PRICE SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved.
The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
If there is any work required of this contract that is not associated with a base bid item description or bid option description, then the costs for that work shall be included proportionally spread across the base bid items.
SCHEDULE OF ITEMS: BASE ITEMS
Base Item 0001: Full Electrical Renovation
Unit of Measure: Job.
Payment will be made for costs associated with the design and construction of the full electrical renovation for the Renovate Kindergarten “Päkapikk” Võru, Estonia as indicated in the SECTION 01 10 10, and shown on the Architecture As-Built Drawings and Interior Finishing Schedule attachments, with the exception of option items listed below. This work shall include all applicable demolition and removals work to support the work elements contained in this item.
Base Item 0002: Renovate Ceilings
Payment will be made for costs associated with the design and construction of renovating ceilings for the
Renovate Kindergarten “Päkapikk” Võru, Estonia as indicated in the SECTION 01 10 10, and shown on the
Architecture As-Built Drawings and Interior Finishing Schedule attachments, with the exception of option items listed below. This work shall include all applicable demolition and removals work to support the work elements contained in this item.
Base Item 0003: Renovate Floors (except rooms 136, 139, 143, 144, 145, 146, 150, 151, 218, 221, 221A, 224, 228)
Payment will be made for costs associated with the design and construction of renovating the floors for the
Renovate Kindergarten “Päkapikk” Võru, Estonia as indicated in the SECTION 01 10 10, and shown on the
Architecture As-Built Drawings and Interior Finishing Schedule attachments, with the exception of option items listed below. This work shall include all applicable demolition and removals work to support the work
Base Item 0004: Install New Interior Doors
Payment will be made for costs associated with the design and construction of installing new interior doors for the Renovate Kindergarten “Päkapikk” Võru, Estonia as indicated in the SECTION 01 10 10, and shown on the Architecture As-Built Drawings and Interior Finishing Schedule attachments, with the exception of option items listed below. This work shall include all applicable demolition and removals work to support the work elements contained in this item.
Base Item 0005: Renovate Walls (except rooms 136, 139, 143, 144, 145, 146, 150, 151, 218, 221, 221A, 224, Payment will be made for costs associated with the design and construction of renovating the walls for the
Renovate Kindergarten “Päkapikk” Võru, Estonia as indicated in the SECTION 01 10 10, and shown on the
Architecture As-Built Drawings and Interior Finishing Schedule attachments, with the exception of option items listed below. This work shall include all applicable demolition and removals work to support the work
SCHEDULE OF ITEMS: OPTION ITEMS
Option Item 0006: Renovate Floors (only rooms 136, 139, 143, 144, 145, 146, 150, 151, 218, 221, 221A, 224, Payment will be made for costs associated with the design and construction of renovating the floors, in rooms
136, 139, 143, 144, 145, 146, 150, 151, 218, 221, 221A, 224, 228 only, for the Renovate Kindergarten
“Päkapikk” Võru, Estonia as indicated in the SECTION 01 10 10, and shown on the Architecture As-Built
Drawings and Interior Finishing Schedule attachments, This work shall include all applicable demolition and removals work to support the work elements contained in this item.
Option Item 0007: Renovate Walls (only rooms 136, 139, 143, 144, 145, 146, 150, 151, 218, 221, 221A, 224, Payment will be made for costs associated with the design and construction of renovating the ceilings, in rooms 136, 139, 143, 144, 145, 146, 150, 151, 218, 221, 221A, 224, 228 only, for the Renovate Kindergarten
“Päkapikk” Võru, Estonia as indicated in the SECTION 01 10 10, and shown on the Architecture As-Built
Drawings and Interior Finishing Schedule attachments, This work shall include all applicable demolition and
Option Item 0008: Replace Sanitary Equipment in the Bathrooms
Payment will be made for costs associated with the design and construction of replacing the sanitary equipment in the bathrooms for the Renovate Kindergarten “Päkapikk” Võru, Estonia as indicated in the
SECTION 01 10 10, and shown on the Architecture As-Built Drawings, Interior Finishing Schedule, and
Specification of Sanitary Equipment attachments, This work shall include all applicable demolition and
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section –
Renovate Kindergarten “Päkapikk”, Võru, Estonia
COMMENCEMENT PROSECUTION AND EXECUTION OF WORK (52.211-10)
The Contractor shall be required to (a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use no later than 455 calendar days after the contractor receives the Notice to Proceed.
Any options, if awarded, shall be completed concurrently with all other work.
The time stated for completion shall include final cleanup of the premises. The Government intends to issue a single Notice to Proceed for all work.
LIQUIDATED DAMAGES-CONSTRUCTION (52.211-12)
If the Contractor fails to complete the work associated with the this contract within the time specified in under 52.211-10, the Contractor shall pay liquidated damages to the Government in the amount of $583 for each calendar day of delay until the work is completed or accepted.
(End of Summary of Changes)