Attachment Amendment 0003 01 91 00.15 10 Cx APS Zutendaal.pdf
PDF 118 KB Posted
- Solicitation number
- W912GB21R0027
- Issued by
-
Department of the Army European Command
About this file
This document includes specifications for the total building commissioning of an Army facility in Zutendaal, Belgium. The specifications require commissioning various building systems including HVAC, lighting, and plumbing. An independent Commissioning Firm must be hired to oversee and coordinate the commissioning process. The Commissioning Firm must employ a Lead Commissioning Specialist to develop commissioning plans, procedures, and checklists. Pre-functional checks and functional performance tests must be conducted for all equipment and systems. Training and a final Commissioning Report are also required deliverables. The specifications provide detailed requirements for the qualifications of the Commissioning Firm and Specialists, the commissioning process and procedures, testing and verification methods, documentation and reporting.
The related federal contract opportunity is for the renovation of Building 50039 at the APS-2 site in Zutendaal, Belgium. The U.S. Army Corps of Engineers Europe District intends to award a single construction contract for the renovation as described in the plans and specifications. Offerors must meet all requirements and terms in the solicitation to be eligible for award.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 91 00.15 10
TOTAL BUILDING COMMISSIONING
PART 1 GENERAL
Commission the building systems listed herein. Employ the services of an independent Commissioning Firm. The Commissioning Firm must be a 1st tier subcontractor of the General or Prime Contractor and must be financially and corporately independent of all other subcontractors. The Commissioning Firm must employ a Lead Commissioning Specialist that coordinates all aspects of the commissioning process. Conform to the commissioning procedures outlined in this specification.
1.1 SYSTEMS TO BE COMMISSIONED
Commission the following systems:
Heating, Ventilating, Air Conditioning, and Refrigeration Systems (HVAC) Building Automation System Utility Monitoring and Control System Lighting Systems Power Distribution Systems Power Generation Systems Plumbing Systems Natural Gas and Propane Systems Water Pumping and Mixing Systems Compressed Air and Vacuum Systems Energy and Water Utility Metering Systems and Sub-Meters Other required Systems
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 180 (2012) Standard Practice for Inspection and
Maintenance of Commercial Building HVAC Systems
ASHRAE 202 (2013; Addenda B 2018) Commissioning Process for Buildings and Systems
ASHRAE Guideline 0-2019 The Commissioning Process
ASHRAE Guideline 1.1-2007 HVAC&R Technical Requirements for the Commissioning Process
ASSOCIATED AIR BALANCE COUNCIL (AABC)
ACG Commissioning Guideline (2005) Commissioning Guideline
UNIFIED FACILITIES GUIDE SPECIFICATIONS (UFGS)
UFGS 01 92 00 Testing, Adjusting, and Balancing for HVAC
NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)
NEBB Commissioning Standard (2009) Procedural Standards for Whole Building Systems Commissioning of New Construction; 3rd Edition
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION (SMACNA)
ANSI/SMACNA 014 (2013) HVAC Systems Commissioning Manual, 2nd
Edition
U.S. ARMY CORPS OF ENGINEERS (USACE)
CEHNC 1110-1-1 (2013) Design Manual, Revision 8
ER 25-345-1 (2019) Systems Manual
1.3 COMMUNICATION WITH THE GOVERNMENT
The Lead Commissioning Specialist (CxC) must submit all commissioning plans, schedules, reports, and documentation directly to the Contracting Officer Representative concurrent with submission to the CQC System Manager. The Lead Commissioning Specialist must have direct communication with the Contracting Officer's Representative regarding all elements of the commissioning process;
however, the Government has no direct contract authority with the Lead Commissioning Specialist.
1.4 SEQUENCING AND SCHEDULING
1.4.1 Sequencing
Complete the following prior to starting Functional Performance Tests:
a. All equipment and systems have been completed, cleaned, flushed, disinfected, calibrated, tested, and operate in accordance with contract documents and construction plans and specifications.
b. Testing, Adjusting, and Balancing (TAB) has been completed and the TAB
Report, has been submitted and approved.
c. The building envelope is enclosed according to contract documents with final construction completed.
d. The Pre-Functional Checklists have been submitted and approved.
e. The Certificate of Readiness for the systems to be tested have been submitted and approved.
f. All electrical, power generation, and lighting equipment and systems have been completed, calibrated, tested, and operate in accordance with contract documents and construction plans.
g. Ceiling tiles, floor coverings, and window coverings are in place for commissioning of Lighting Systems.
1.4.2 Project Schedule
Include the following tasks in the project schedule. Ensure sufficient time is scheduled to accommodate the requirements of this specification section. The order of items listed below is not intended to imply a specified sequence:
a. Submission and approval of the Commissioning Firm and Commissioning Specialist.
b. Submission and approval of the TAB Firm and TAB Specialist.
c. Submission and approval of the Commissioning Plan.
d. Factory Acceptance Testing for each of the systems to be commissioned as required by technical specifications
e. Manufacturer's Equipment Start-Up for each of the systems to be commissioned.
f. Potable Water System Flushing and Disinfection
g. Submission and approval of the TAB Reports.
h. Pre-Functional Checklist Submittal
i. Functional Performance Testing for each system to be commissioned
j. Post-Test Deficiency Corrections
k. Re-Testing
l. Training for each of the systems to be commissioned
m. Submission and approval of the Commissioning Report, including completed Pre-
Functional Performance Test Checklists and completed Functional Performance Test results.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
SD-01 Preconstruction Submittals
Commissioning Firm; G Lead Commissioning Specialist; G Technical Commissioning Specialists; G Commissioning Firm's Contract; G
SD-06 Test Reports
Interim Commissioning Plan; G Final Commissioning Plan; G Pre-Functional Checklists; G Issues Log
SD-07 Certificates
Certificate of Readiness; G, DO
SD-10 Operation and Maintenance Data
Training Plan; G Training Attendance Rosters; G
SD-11 Closeout Submittals
Commissioning Report; G
1.6 COMMISSIONING FIRM
Provide a Commissioning Firm that is certified in commissioning by one of the following: the AABC Commissioning Group (ACG); the National Environmental Balancing Bureau (NEBB); the International Certification Board/Testing, Adjusting, and Balancing Bureau (ICB/TABB), the Building Commissioning Association (BCA); the Association of Energy Engineers (AEE).
The Commissioning Firm may employ a commissioning professional certified by the University of Wisconsin-Madison or the American Society of Heating, Refrigeration, and Air Conditioning Engineers (ASHRAE) as required in paragraph LEAD COMMISSIONING SPECIALIST as an alternative to certification of the Commissioning Firm.
The Commissioning Firm must be certified in all systems to be commissioned to the extent such certifications are available from the certifying body.
Describe any lapses in certification or disciplinary action taken by the certifying body against the proposed Commissioning Firm or Lead Commissioning Specialist in detail. Any firm or commissioning professional that has been the subject of disciplinary action by the certifying body within the five years preceding contract award is not eligible to perform any duties related to commissioning.
a. Submit the Commissioning Firm's certification of qualifications including the name of the firm and certifications no later than 30 calendar days after Notice to Proceed. Submit an electronic copy.
b. The Commissioning Firm's and Commissioning Specialists' certifications must be maintained for the entire duration of the duties specified herein. If, for any reason, the firm or a specialist loses a certification during this period, immediately notify the Contracting Officer's Representative and submit another Commissioning Firm or Commissioning Specialist for approval.
All work specified in this specification section performed by the Commissioning Firm or associated Commissioning Specialists is invalid if the Commissioning Firm or Commissioning Specialist loses its certification prior to contract completion and must be performed by an approved successor.
c. The Commissioning Firm must oversee and assist the General or Prime
Contractor with the work specified herein. Submit the Commissioning Firm's Contract including the Scope of Work to confirm compliance with the tasks identified in this Specification Section no later than 30 calendar days after approval of the Commissioning Firm. Submit an electronic copy.
1.6.1 Lead Commissioning Specialist
The Commissioning Firm must provide a Lead Commissioning Specialist (CxC) that has a minimum of five years of commissioning experience, including two projects of similar size and complexity, and that is one of the following: a NEBB qualified Systems Commissioning Administrator (SCA); ACG Certified Commissioning Authority (CxA); ICB/TABB Certified Commissioning Supervisor; BCA Certified Commissioning Professional (CCP); AEE Certified Building Commissioning Professional (CBCP); University of Wisconsin-Madison Qualified Commissioning Process Provider (QCxP); ASHRAE Commissioning Process Management Professional
(CPMP).
a. Submit the Lead Commissioning Specialist's certification of qualifications including the name of the specialist and firm; certifications; years of experience; and a listing of representative projects of similar size and complexity no later than 30 calendar days after Notice to Proceed. Submit an electronic copy.
b. The Lead Commissioning Specialists certifications must be maintained for the entire duration of the duties specified herein. If, for any reason, the specialist loses a certification during this period, immediately notify the Contracting Officer's Representative and submit another Lead Commissioning Specialist for approval. All work specified in this specification section to be performed by the Lead Commissioning Specialist is invalid if the Lead Commissioning Specialist loses its certification prior to contract completion and must be performed by an approved successor.
c. The Lead Commissioning Specialist must lead and oversee the commissioning work specified herein and be the primary point of contact for the Government regarding the commissioning work. One of the Technical Commissioning Specialists may be the Lead Commissioning Specialist provided that all of the qualification requirements are met.
1.6.2 Technical Commissioning Specialists
Technical Commissioning Specialists, employed by the Commissioning Firm and that have the following qualifications, must perform the technical work specified herein associated with each system to be commissioned:
a. Mechanical Technical Commissioning Specialist: The technical work associated with mechanical systems must be performed by a Commissioning Specialist certified by NEBB, ACG, ICB/TABB, or BCA in the commissioning of HVAC systems with five years of experience in the commissioning of HVAC systems.
b. Electrical Technical Commissioning Specialist: The technical work associated with electrical systems including must be performed by an engineering technician certified by the International Electrical Testing Association (NETA) with five years of experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices.
c. Submit the Technical Commissioning Specialist's certification of qualifications including the name of the specialist and firm; certifications;
years of experience; and a listing of representative projects of similar size and complexity no later than 30 calendar days after Notice to Proceed. Submit an electronic copy.
1.7 Commissioning Standard
Comply with the requirements of the commissioning standard under which the Commissioning Firm and Specialists qualifications are approved.
a. Implement all recommendations and suggested practices contained in the
Commissioning Standard and electrical test standards.
b. Use the Commissioning Standard for all aspects of Commissioning, including calibration of instruments.
c. Where the instrument manufacturer calibration recommendations are more stringent than those listed in the Commissioning Standard, adhere to the manufacturer calibration recommendations.
d. All quality assurance provisions of the Commissioning Standard such as performance guarantees are part of this contract.
e. The Commissioning Specialists must develop commissioning procedures for any systems or system components not covered in the Commissioning Standard.
f. Use any new requirements, recommendations, and procedures published or adopted prior to contract solicitation by the body responsible for the Commissioning Standard.
1.8 ISSUES LOG
The Lead Commissioning Specialist must develop and maintain an Issues Log for tracking and resolution of all deficiencies discovered through submittal reviews, inspection, and testing. Include the date of final resolution of issues as confirmed by the Commissioning Specialist. Submit the Issues Log on a monthly basis at a minimum. At any point during construction, any commissioning team member finding deficiencies may communicate those deficiencies in writing to the Commissioning Specialist for inclusion into the Issues Log.
1.9 CERTIFICATE OF READINESS
Prior to scheduling Functional Performance Tests for each system, issue a Certificate of Readiness for the system certifying that the system is ready for Functional Performance Testing. The Certificate of Readiness must include, for each system to be commissioned, all equipment and system start-up reports;
completed Pre-Functional Checklists; Testing, Adjusting, and Balancing (TAB) Report; HVAC Controls Start-Up Reports to the extent applicable to the system.
The Contractor; the Lead Commissioning Specialist; the Contractor's Quality Control Representative; the Mechanical, Electrical, Controls, and TAB subcontractor representatives must sign and date the Certificate of Readiness.
Submit the Certificate of Readiness for each system no later than 14 calendar days prior to Functional Performance Tests of that system. Submit an electronic copy. Do not schedule Functional Performance Tests for a system until the Certificate of Readiness for that system receives approval by the Government.
PART 2 PRODUCTS
Not used
PART 3 EXECUTION
3.1 Commissioning Coordination Meeting
The Lead Commissioning Specialist must lead a Commissioning Coordination Meeting no later than 30 days after approval of the Commissioning Firm and Commissioning Specialists to discuss the commissioning process including contract requirements, lines of communication, roles and responsibilities, schedules, documentation requirements, inspection and test procedures, and logistics as specified in this specification section. The Contractor's Superintendent or Project Manager, the Contractor's Quality Control Representative, and the Government must attend this meeting. Invite the User and a Directorate of Public Works Representative to attend this meeting.
3.2 Commissioning Plan
3.2.1 Interim Commissioning Plan
The Lead Commissioning Specialist (CxC) must prepare the Interim Commissioning Plan. Submit the Interim Commissioning Plan no later than 30 calendar days after the Commissioning Coordination Meeting. Submit an electronic copy.
Identify the commissioning and testing standards and outline the overall commissioning process, the commissioning schedule, the commissioning team members and responsibilities, lines of communication, documentation requirements in the Interim Commissioning Plan.
3.2.1.1 Checklists
Download example Pre-Functional Checklists and Functional Performance Test Checklists at the following location:
https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/ ufgs-01-91-00-15-10
The checklists submitted in the Interim and Final Commissioning Plans must contain the same level of detail shown in the examples. The submitted checklists are not required to match the format of the examples.
3.2.1.2 Final Commissioning Plan
The Lead Commissioning Specialist (CxC) must prepare the Final Commissioning Plan. Submit the Final Commissioning Plan no later than 30 calendar days prior to the start of Pre-Functional Checks. Submit one hard copy and an electronic copy.
Include the information provided in the Interim Commissioning Plan. In addition, the Technical Commissioning Specialist(s) must develop the Pre-Functional Checklists and Functional Performance Test Checklists for each building, for each system required to be commissioned, and for each component for inclusion in the Final Commissioning Plan.
3.2.1.2.1 Pre-Functional Checklists
The Pre-Functional Checklists must include items for physical inspection or testing that demonstrate that installation and start-up of equipment and systems is complete. Refer to paragraph Pre-Functional Checks for more information.
3.2.1.2.2 Functional Performance Test Checklists
Functional Performance Test Checklists must include procedures that explain, step-by-step, the actions and expected results that will demonstrate that the system performs in accordance with the contract. Refer to paragraph Functional Performance Tests for more information.
Include the following sections and details appropriate to the systems being tested in the Functional Performance Test Checklists:
a. Notable system features including information about controls to facilitate understanding of system operation
b. Conclusions and recommendations. Conclusions must clearly indicate if system does or does not perform in accordance with contract requirements.
Recommendation must clearly indicate that the system should or should not be accepted by the Government.
c. Test conditions including date, beginning and ending time, and beginning and ending outdoor air conditions.
d. Attendees
e. Identification of the equipment involved in the test http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/ http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/
f. Control system feature identification
g. Point-to-point observations including demonstrating system flow meters and sensors have been calibrated and are correctly displayed on the Operator work station
h. Actuator operation observations demonstrating actuator responses to commands from the control system
i. As-found condition of the system operation
j. List of test items with step numbers along with the corresponding feature or control operation, intended test procedure, expected system response, and pass/fail indication.
k. Space for comments for each test item.
3.3 Inspection and Testing
Demonstrate that all system components have been installed and started per manufacturer’s recommendations, industry accepted minimum standards and the Contract Documents. Demonstrate that each control device and item of equipment operates, and that the systems operate and perform, including interactive operation between systems, in accordance with contract documents. Requirements in related specification sections are independent from the requirements of this section and do not satisfy any of the requirements specified in this specification section.
Provide all materials, services, and labor required to perform the Pre- Functional Checks and Functional Performance Tests.
3.3.1 Commissioning Team
Provide a commissioning representative for each sub-contractor associated with the systems to be commissioned. Each commissioning representative is responsible for coordination of their respective sub-contractor's execution of the commissioning activities and participation in the inspection and testing required by this specification section.
In addition to the sub-contractors associated with the systems to be commissioned, provide the Lead Commissioning Specialist, Technical Commissioning Specialist(s), Contracting Officer’s Quality Assurance Representative (QAR), and Contractor’s Quality Control Personal (CQC).
3.3.2 Pre-Functional Checks
Pre-Functional Checklists from the approved Final Construction Phase Commissioning Plan must be completed by the commissioning team.
Complete one Pre-Functional Checklist for each individual item of equipment or system for each system required to be commissioned including, but not limited to, ductwork, piping, equipment, fixtures (lighting and plumbing), and controls.
Indicate commissioning team member inspection and acceptance of each Pre- Functional Checklist item by initials. Acceptance of each Pre-Functional Checklist item by each team member indicates that item conforms to the construction contract and design requirements.
Technical Commissioning Specialist acceptance of each Pre-Functional Checklist item indicates that each item has been installed correctly and in accordance with contract documents.
Submit the completed and initialed Pre-Functional Checklists no later than 7 calendar days after completion of inspection of all checklists items for each system. Submit one hard copy and an electronic copy. Include manufacturer start-up checklists associated with equipment with the submission of the Pre- Functional Checklists.
3.3.3 Testing, Adjusting, and Balancing (TAB) Report and Field Acceptance Testing
The Mechanical System Technical Commissioning Specialist must review the TAB Report. Identify any deficiencies to the Contracting Officer's Representative and the Contractor's Quality Control Personnel. Resolve all deficiencies prior to TAB Field Acceptance Testing.
The Mechanical System Technical Commissioning Specialist must witness the TAB Field Acceptance Testing specified by UFGS Specification Section 01 92 00 TESTING, ADJUSTING, AND BALANCING FOR HVAC. Include a certification by the Mechanical Technical Specialist that no outstanding deficiencies exist in the systems relative to Testing, Adjusting, and Balancing with the final TAB Report submittal.
3.3.4 Functional Performance Tests
Schedule Functional Performance Tests for each system only after the Certificate of Readiness has been approved by the Government for the system. Correct all deficiencies identified through any prior review, inspection, or test activity before the start of Functional Performance Tests.
Functional Performance Tests must be performed with the Contracting Officer's Quality Assurance Representative present.
Abort Functional Performance Tests when any system deficiency prevents the successful completion of the test.
Technical Commissioning Specialists must lead and document all Functional Performance Tests for the systems to be commissioned with the Contractor and appropriate sub-contractors performing the Functional Performance Tests. The representatives listed in the paragraph Commissioning Team must attend the tests. Abort Functional Performance Tests when any required commissioning team member is not present for the test.
3.3.4.1 Checklists
Use the Functional Performance Test Checklists from the approved Final Commissioning Plan to guide the Functional Performance Tests.
Functional Performance Tests must be performed for each item of equipment and each system required to be commissioned and verify all sensor calibrations, control responses, safeties, interlocks, operating modes, sequences of operation, capacities, lighting levels, and all other performance requirements comply with construction contract regardless of the specific items listed within the Functional Performance Test Checklists. Testing must progress from equipment or components to subsystems to systems to interlocks and connections between systems. The order of components and systems to be tested must be determined by the Technical Commissioning Specialists.
3.3.4.2 Prior to Testing
Prior to testing operating modes, sequences of operation, interlocks, and safeties, complete control point-to-point observations, test sensor calibrations, and test actuator commands.
3.3.4.3 Sample Strategy
Prepare and complete a Functional Performance Test Checklist for each item of equipment or system to be tested.
For sample sizes less than 100 percent for all similar equipment, the Government will select the specific equipment or system to be tested during testing.
Equipment Identifier Sample Size (Percent) Building Automation System 100 Air Handling Units (RLT) 100 Fans (Exhaust) 20 Variable and Constant Air Volume Terminals (LAA / LAZ)
Heat Exchangers 100 Pumps 100 Radiators 20 Water Heater (Instantaneous) 20
Hygiene Flushing Valves 20 Emergency Power Systems 100 Lighting Controls 100 Energy and Water Meters 100
3.3.4.4 Tests
Perform Functional Performance Tests.
Provide all necessary materials and system modifications to produce the necessary flows, pressures, temperatures, and other conditions necessary to execute the test according to the specified conditions. At completion of the test, return the affected building equipment and systems to their pre-test condition.
Perform each test under conditions that simulate actual conditions as close as is practically possible.
Develop and implement means of artificial loading to demonstrate, to a reasonable level of confidence, the ability of the HVAC systems to handle peak seasonal loads.
3.3.4.4.1 Simulating Conditions
Over-writing control input values through the controls system is not acceptable, unless approved by the Contracting Officer's Representative.
Identify proposed exceptions in a protocol submitted to the Contracting Officer's Representative for approval. Before simulating conditions, overwriting values (if approved), or changing set-points, calibrate all sensors, transducers and devices. Below are examples of exceptions that would be considered acceptable:
a. When varying static pressures inside ductwork cannot be simulated, and where a sensor signals the controls system to initiate sequences at various duct static pressures, it is acceptable to simulate the various pressures with a Pneumatic Squeeze-Bulb Type Signaling Device with gauge temporarily attached to the sensing tube leading to the transmitter. It is not acceptable to reset the various set-points, nor to simulate an electric analog signal (unless approved as noted above).
b. Dirty filter pressure drops can be simulated using sheets of cardboard at filter face.
c. Freeze-stat safeties can be simulated by packing portion of sensor with ice.
d. High outside air temperatures can be simulated with a hair blower.
e. High entering cooling coil temperatures can be used to simulate entering cooling coil conditions.
f. Do not use signal generators to simulate sensor signals unless approved by the Contracting Officer's Representative, as noted above, for special cases.
g. Control set points can be altered. For example, to see the air conditioning compressor lockout work at an outside air temperature below 13 degrees C, when the outside air temperature is above 13 degrees C, temporarily change the lockout set point to be minus 18 degrees C above the current outside air temperature. Caution: Set points are not to be raised or lowered to a point such that damage to the components, systems, or the building structure and/or contents will occur.
h. Test duct mounted smoke detectors in accordance with the manufacturer's recommendations. Perform the tests with air system at minimum airflow condition in ductwork.
i. Test current sensing relays used for fan and pump status signals to control system to indicate unit failure and run status by resetting the set point on the relay to simulate a lost belt or unit failure while the unit is running.
Confirm that the failure alarm was generated and received at the control system. After the test is conducted, return the set point to its original set-point or a set-point as indicated by the Contracting Officer's Representative.
3.3.4.4.2 Aborted Tests and Re-Testing
Abort Functional Performance Tests if any deficiency prevents successful completion of the test or if any required commissioning team member is not present for the test.
Reimburse the Government for all costs associated with effort lost due to re-testing due to test failures and aborted tests. These costs must include salary, travel costs, and per diem for Government team members.
Re-test only after all deficiencies identified during the original tests have been corrected.
3.3.4.4.2.1 100 Percent Sample
Systems or equipment for which 100 percent sample size are tested fail if one or more of the test procedures results in discovery of a deficiency and the deficiency cannot be resolved within 5 minutes during the test.
Re-test to the extent necessary to confirm that the deficiencies have been corrected without negatively impacting the performance of the rest of the system.
3.3.4.4.2.2 Less than 100 Percent Sample
For systems tests with a sample size less than 100 percent, if one or more of the test procedures for an item of equipment or a system results in discovery of a deficiency, regardless of whether the deficiency is corrected during the sample tests, the item of equipment or system fails the test.
a. If the system failure rate is 5 percent or less, meaning that 5 percent or less of the equipment or systems had at least one deficiency, re-test only on the items which experienced the initial failures.
b. If the system failure rate is higher than 5 percent, meaning that more than 5 percent of equipment or systems tested had at least one deficiency, re-test the items which experienced the initial failures to the extent necessary to confirm that the deficiencies have been corrected. In addition, test another random sample of the same size as the initial sample for the first time. If the second random sample set has any failures, re-test those failed items and all remaining equipment and systems to complete 100 percent testing of that system type.
3.4 Acceptance
All Functional Performance Test procedures must be completed prior to full systems acceptance.
Indicate acceptance of each item of equipment and systems tested by signature of each commissioning team member for each Functional Performance Test on the Functional Performance Test Checklists.
The Contractor's Quality Control Representative and the Technical Commissioning Specialists must indicate acceptance after the equipment and systems are free of deficiencies.
3.5 Training Plan
Develop a training plan which identifies all training required by specification sections associated with commissioned systems. Include a matrix listing each training requirement, content of the training, the trainer name, trainer contact information, and schedule and location of training. Submit an electronic copy of the Training Plan to the Commissioning Specialists and the Government no later than 30 calendar days prior to the associated training.
Document training attendance using training attendance rosters and provide completed attendance rosters to the Commissioning Specialists and the Government no later than 7 calendar days following the completion of training for each system to be commissioned. Submit an electronic copy.
3.6 COMMISSIONING REPORT
Following the completion of Functional Performance Tests, the Lead Commissioning Specialist must prepare a Commissioning Report.
a. Include an executive summary describing the overall commissioning process, the results of the commissioning process, any outstanding deficiencies and recommended resolutions, and any seasonal testing that must be scheduled for a later date. Indicate, in the executive summary, whether the systems meet the requirements of the construction contract.
b. Detail any deficiencies discovered during the commissioning process and the corrective actions taken in the report. Include the completed Pre-Functional Checklists, Functional Performance Test Checklists, Commissioning Plans, the Issues Log, Performance Verification Test Reports, Training Attendance Rosters, and the final TAB Report.
c. Submit the Commissioning Report no later than 14 calendar days following commissioning team acceptance of all Functional Performance Tests. Submit one hard copy and an electronic copy.
- End of Section --