W912GB19SXX2X_A-29_Program_Beddown_at_Kainji_Airbase,_Kainji,_Nigeria,_Africa_DRAFT_SYNOPSIS.pdf

PDF 125 KB Posted

Attached to
INDUSTRY DAY: A-29 Program Beddown at Kainji Airbase, Kainji, Nigeria, Africa
Solicitation number
W912GB19SXX2X
Issued by

About this file

W912GB19SXX2X A-29 Program Beddown at Kainji Airbase, Kainji, Nigeria, Africa DRAFT SYNOPSIS

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A-29 Program Beddown Kainji Airbase, Nigeria

The proposed construction consists of infrastructure and facilities to support the A-29 aircraft beddown and munitions at Kainji Air Base. The construction of these required facilities includes three (3) separate packages of deliverables which in sequence will fulfill the needs and requirements of the program.

(1) Critical Facilities Package: The primary construction features consist of temporary infrastructure which will support operations during the construction of permanent facilities. This package include, but are not limited to:

i. The conversion of an existing runway hammerhead into a temporary arm/de-arm location.

ii. A complete retrofitting of an auxiliary parking apron to a tie-down and grounding area.

iii. Providing a temporary structure to house aircraft.

iv. Provide temporary structure for secure storage.

(2) Security Package: Primary construction features include, but are not limited to:

i. Construction of a new chain link perimeter fence with a minimum length of approximately 12-km.

ii. Construction of a munitions storage area (MSA) consisting of earth cover magazines, security (fencing, lighting and locks), observation tower, and power.

iii. Construction of a permanent arm/de-arm pad.

iv. Improvements to the two base entry control points.

(3) Operations Package: Primary construction features include, but are not limited to:

i. Renovation of the existing aircraft hangar including, roof replacement, mobile fire suppression systems.

ii. Renovation of existing air traffic control tower including, configuration of a new simulator training room, new secure storage space, renovation of a security control and processing center, and new power distribution requirements.

iii. Renovation of existing aircraft parking apron including.

iv. Parking apron improvements to include patching and repair of damaged areas for lightning protection and grounding and new paint striping for taxi and parking.