About this file

Daopong SOW

View the file

Other files

File Type Posted
B.08.03_W912GB19R0040-0003_Amendment_Due_Date_Extension_Correction.pdf PDF
A.02.16.1_Tonte_School_SOW_ar148b_011010_09_AUG_2019_REVISED.pdf PDF
A.02.16.2_Papri_School_SOW_ar148c_011010_09_AUG_2019_REVISED.pdf PDF
A.02.16.3_Dapaong_SOW_ar_148d_011010_09_AUG_2019_REVISED.pdf PDF
B.08.03_W912GB19R0040-0002_Amendment_Revised_SOWs.pdf PDF
B.08.03_W912GB19R0040-0001_Amendment_Due_Date_Extension.pdf PDF
A.02.16.2_Papri_School_SOW_Rev_ar148c_011010_27_June_2019.pdf PDF
B.08.02.7_Att_7_-_BLG_Template_19R0040.docx DOCX document
B.08.02.10_Att_10_Specifications_Binder.pdf PDF
B.08.02.8_Att_8_ExpInfoSheet_19R0040.docx DOCX document
A.02.16.1.3_ar148b_Att._3_-_As-Built_Drawings.pdf PDF
B.08.02.9_Att_9_ExpOverviewSheet_19R0040.docx DOCX document
A.02.16.3.1_ar148d_Att._1_-_Project_Location_Map.pdf PDF
B.08.02.5_Att_5_-_Past_Performance_Questionnaire_-_19R0050.pdf PDF
A.02.16.2.4_ar148c_Att._4_-_Preparation_of_Structural_Calculations.pdf PDF
A.02.16.2.2_ar148c_Att._2_-_As-Built_Site_Layout.pdf PDF
B.08.02_W912GB19R0040_SOLICITATION.pdf PDF
A.02.16.3.3_ar148d_Att._3_-_As-Built_Drawings.pdf PDF
B.08.02.6_Att_6_-_BLA_Template_19R0040.docx DOCX document
A.02.16.3.2_ar148d_Att._2-_As-Built_Site_Layout.pdf PDF
A.02.16.2.1_ar148c_Att._1_-_Project_Location_Map.pdf PDF
A.02.16.3.4_ar148d_Att._4_-_Preparation_of_Structural_Calculations.pdf PDF
A.02.16.1_Tonte_School_SOW_ar148b_011010_27_June_2019.pdf PDF
A.02.16.1.2_ar148b_Att._2_-_As-Built_Site_Layout.pdf PDF
A.02.16.2.3_ar148c_Att._3_-_As-Built_Drawings.pdf PDF
B.08.02.4_Att_4_-_Price_and_Payment_Procedures.docx DOCX document
A.02.16.1.1_ar148b_Att._1_-_Project_Location_Map.pdf PDF
A.02.16.1.4_ar148b_Att._4_-_Preparation_of_Structural_Calculations.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Army Corps of Engineers Europe District

APO AE 09049

ar148d

Statement of Work Project Number:

OHASIS# 38915

Dapaong Regional Hospital Laboratory Dapaong, Tone, Togo

Prepared by:

Design Section

Engineering Branch 27 June 2019

01 10 10 Statement of Work Dapaong Regional Hospital Laboratory – Tone, Togo

27-Jun-19 Page 2 of 46

SECTION 01 10 10

STATEMENT OF WORK

SECTION TABLE OF CONTENTS:

1 GENERAL

2 CIVIL AND GEOTECHNICAL

3 ARCHITECTURAL

4 STRUCTURAL

5 ELECTRICAL & COMMUNICATIONS

6 MECHANICAL

ATTACHMENTS

Att. # 1 Project Location Map Att. # 2 As-Built Site Layout Att. # 3 As-Built Drawings Att. # 4 Preparation of Structural Calculations

1.0 GENERAL

1.1 PROJECT DESCRIPTION

The Request for Proposal (RFP) provides parameters for a design-build project for construction of a laboratory extension to the existing regional hospital in Dapaong, Tone, Togo. This project includes the design and construction of the following structures, detailed requirements are contained elsewhere in this Statement of Work (SOW):

a. One (1) laboratory facility; built as an extension to the existing hospital facility.

1.2 GENERAL REQUIREMENTS

The Contractor must deliver fully functional, turnkey type facilities (without furniture) as described in this document. The work includes - but is not limited to - design, demolition, fabrication, delivery, installation, construction, and site work. The facility and the installed equipment must be permanent construction.

The facility in this project must be complete and usable to meet codes and technical and functional requirements per this Statement of Work (SOW). The proposal price must include all design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, general and administrative expenses (G&A) and general conditions to complete this project as described in the SOW.

These design and product requirements are minimum requisites. Compliance with the provisions of this section by subcontractors is the responsibility of the Contractor.

1.2.1 BASE BID ITEMS AND OPTIONAL BID ITEMS

This Statement of Work addresses the technical requirements necessary to complete all work associated with this project. For information and requirements regarding the allocation of pricing between elements of the work, refer to the Bid Schedule included as a separate document. The Bid Schedule identifies the breakdown between the individual base bid and optional items for all work identified in this Statement of Work, associated drawings, and attachments. All work as described in these documents is included in either the Base Bid or Optional Items: consider all items not specifically identified in the Optional Items as part of the Base Bid Items.

27-Jun-19 Page 3 of 46

1.3 FUNCTIONAL AREAS

Provide the new, stand-alone structures described below. Detailed facility requirements are provided in the discipline-specific sections and attachments of this SOW.

1.3.1 LABORATORY BUILDING

Provide a one-story, solid masonry / concrete Laboratory Building to with a sloped metal roof. Provide the following functional areas for the Laboratory Building:

Room Name Function Approximate

Size (m2) Waiting Area Waiting area 28.5 Reception Area

Records and Processing 8.25

Doctor’s Office

Examination of patients 8.25

Hallway Access to reception area, doctor’s officer and blood draw area

7.1

Blood Draw Area

Blood sampling of patients 65.7

Toilet Room Unisex restroom 6 Storage Area Storage of medical equipment 7 Battery Room Ventilated battery room for photovoltaics *See Note 1

1.8

Staircase Covered stairway 5

Note 1: Battery Room is not shown on the attached as-built drawings. Battery Room may be integrated into the lab extension building as a separate room with an external access, occupying a portion of Storage Room.

The completed facility must have an enclosed net area of approximately 132.6 m2 and a gross footprint of approximately 156.0 m2.

1.4 SUBMITTALS

Government approval is required for submittals with “G” designation; submittals not having a “G” are for Contractor Quality approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Pre-construction Submittals

Inspection Plan; G

SD-05 Design Data

65% Pre-Final Design; G, DO

95% Final Design; G, DO

100% Corrected Final Design; G, DO

1.4.1 DESIGN SUBMITTALS

Provide a complete design package at each milestone, as described in Specification Section 01 33 16 DESIGN AFTER AWARD. The milestones for this project are indicated above in Section 1.4 SUBMITTALS. The specific requirements of each milestone are described in each discipline-specific section of this Specification.

27-Jun-19 Page 4 of 46

Submit all documents in electronic format (.pdf for text and calculations, .pdf and .dwg (AutoCAD, latest version) for drawings). See Specification 01 33 00 SUBMITTAL PROCEDURES for additional information.

1.5 MATERIALS AND EQUIPMENT

Materials and products used must be durable, heavy duty, industry standard. The equipment must be the manufacturer’s standard quality and must be compatible with all other equipment and materials within the system or assembly. Equipment and materials must include all connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.

Provide a nameplate secured to each major piece of equipment. Each nameplate must have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number. The definition of a “major piece of equipment” is at the discretion of the COR.

1.5.1 LIFE-SPAN

Construction must have an expected life span of 25 years.

1.5.2 MAINTAINABILITY

Provide low maintenance materials and systems appropriate for the project climate and location.

1.5.3 OPERABILITY

Systems (including but not limited to architectural, electrical, communications, and mechanical systems) must be simple to operate and easy to maintain.

1.5.4 STANDARDIZATION

Provide standardized materials, products, equipment, and systems to minimize the requirements for replacement parts, storage facilities, and service requirements.

1.5.5 SOURCING

Use materials, products, equipment, and systems that can be replaced, repaired, maintained, and/or serviced locally in Togo. All warranties must be valid in Togo and have local authorized service providers.

1.6 DESIGN DIMENSIONS

Develop the design using the metric system.

1.7 DESIGN CRITERIA

Project design, site facilities, utility systems and material standards must be in accordance with the latest editions of the Host Nation building codes. In the absence of Host Nation building codes, use the International Building Code (IBC) and codes, technical standards, and regulations referenced in this RFP.

While this RFP references various source standards and specifications, all design documents must meet Host Nation codes and requirements. It is the designer's responsibility to demonstrate that the Host Nation standard is equal to the cited standard or specifications being supplanted. Apply the more restrictive standards when conflicts arise between the requirements of this RFP and any referenced or other applicable codes, standards or regulations. If equivalency cannot be met, use the more stringent requirement and quote both codes verbatim in correspondence to the COR. The designer is responsible to determine the required material and execution standards where specific standards are not indicated.

Provide an electronic copy of the local Host Nation standards and building codes in their original language as related to facility design and construction.

1.8 DESIGN CONFERENCES AND MEETINGS

27-Jun-19 Page 5 of 46

The Contractor and the entire design team are required to participate in a design review conference for each design submittal. The Contractor must bring the personnel that developed the design submittal to any review conference.

All design review conferences must be held via teleconference or be reviewed and comments resolved via email.

The Contractor is responsible for taking meeting minutes during each design review conference and submitting to the COR for information and approval.

The Contractor is responsible for evaluating all Government comments prior to each design review conference. The Contractor is responsible for resolving all Government comments from each design phase. The Contractor must provide annotated responses to each design review comment with the subsequent design submittal packages. Construction may not begin until all Government comments from all design phases have been resolved.

1.9 SPECIAL CONSTRUCTION REQUIREMENTS

1.9.1 THIRD PARTY INSPECTION SERVICES

Furnish independent 3rd party inspection services to inspect the electrical and structural construction features of the project. The 3rd party must not be the same company responsible for the electrical or structural installation. This is in addition to the Contractor Site Personnel Requirements contained in 01 45 05 CONTRACTOR SITE PERSONNEL REQUIREMENTS. All testing is at the expense of the Contractor. Submit a plan for third party services to the COR. The inspection plan must be approved by the COR prior to construction.

1.9.1.1 GENERAL REQUIREMENTS

3rd Party inspectors must submit professional reports directly to the COR, without coordination with the Contractor, within 48 hours of the actual inspection. The report must contain the following at a minimum: names of all persons present for activity, listing and approval of all related materials, description of observed activity, and 10 photos (minimum resolution: 1504x1000) of the observed activity.

1.9.1.2 THIRD PARTY ELECTRICAL INSPECTOR REQUIREMENTS

The electrical inspector must be a certified Master electrician or licensed degreed Electrical Engineer and have a minimum of 10 years' experience, 5 years in the country where the project work is performed. Submit the inspector’s CV (Resume) to the COR for Government approval.

The following inspections must be conducted at a minimum: all outlets, off-cover inspection of all panels, verify that GFCI is present on all panels, municipal power connections, lightning protection installations, and generator installations.

Submit a plan and schedule to be part of the QC Plan or a separate submittal to be tracked via the submittal register, indicating the inspection plan and timing.

1.9.1.3 THIRD PARTY STRUCTURAL ENGINEER INSPECTOR REQUIREMENTS

The structural inspector must be a licensed graduate engineer with 10 years of experience, 5 years in the country where the project work is performed. Required experience includes, but is not limited to, inspecting concrete moment frame, concrete foundations, roof system and rebar and form work. Submit the inspector’s CV (Resume) to the COR for Government approval.

Submit an inspection plan and schedule of inspections to be part of the QC Plan or a separate submittal to be tracked via the submittal register, indicating the inspection plan and timing.

27-Jun-19 Page 6 of 46

The following inspections must be conducted at a minimum: Bearing capacity of foundation soils, formwork and rebar of foundations, concrete placement of foundations. Formwork, rebar and concrete pour of moment frame. No concrete may be placed in forms without a preceding rebar inspection report and verification of functioning vibration equipment.

The inspector must review concrete test results and sign off on strength approvals.

END OF SECTION

27-Jun-19 Page 7 of 46

2. CIVIL AND GEOTECHNICAL DESIGN

2.1. GENERAL REQUIREMENTS

2.1.1. The Contractor shall provide and perform civil engineering design and construction services as required to provide a complete, accessible, functional, usable, and environmentally sustainable facility as described in this SOW. The services covered by this section include all civil engineering labor, material supplies, and incidental work required for the demolition, design, fabrication, delivery, installation, and construction that serve the project. The Contractor is required to extensively coordinate civil design and construction work with the scope of the other disciplines described in this SOW.

2.1.2. The civil design and construction, including demolition and mobilization, shall be coordinated with all other trades. The facility and equipment shall be permanent construction. All civil works shall be designed and constructed in accordance with the criteria provided herein, and with the minimum standards specified in the applicable referenced codes.

2.1.3. The contractor shall be responsible for obtaining all applicable permits for site clearing, digging, demolition, transport, and disposal of waste material generated by this work effort, and/or any other permits that may be required.

2.1.4. The Contractor shall coordinate the site layout of the new building and its associated exterior features with the local authorities.

2.1.5. Any damage to structures, drainage facilities, or other existing features on the site because of Contractor operations shall be repaired, or the damaged items replaced, at the Contractor's expense.

2.1.6. Contractor shall comply with all security/safety measures. In addition, no open fires or burning of trash will be allowed within the confines of the project site.

2.2. SCOPE SUMMARY

The civil works for this project include, but are not limited to, the following:

• Mobilization of all construction-related equipment.

• Site clearance of construction site of debris from the previous building, including any required demolition, foundation/slab removal, grubbing of shrubs, removal of trees, or removal of existing surface features at the site which are obstacles to locating the new building and its associated exterior features.

• Structural assessment/evaluation of the existing foundation slab/structure for reuse for new building.

• Mobilization of all construction-related equipment.

• Site earthwork and grading, including preparation of the subgrade beneath the new structures/foundations, and any necessary grading to achieve positive drainage away from structures.

2.3. EXISTING CONDITIONS

Site has previously been used for a laboratory extension to the existing Dapaong Regional Hospital. The laboratory extension building has been damaged beyond

27-Jun-19 Page 8 of 46 repair. Exterior site surface conditions have been impacted and will require repair/restoration.

The proposed project is located in the town of Dapaong, Togo (Latitude 10°51'58.26"N Longitude 0°12'3.16"E). See Attachment#1-Project Location Map.

The existing site contains buildings, utilities, fences, and vegetation as shown on Attachment#2-As-Built Layout. The site is a moderate slope away from the current treatment ward towards the low side in the parking area. Estimate 4 foot rise over 50 feet. There is no known topographic survey, as-built, or geotechnical information for the site. There are no known environmental protection areas or archeological preservation areas on the project site.

There is no subsurface storm system at the site.

2.3.1. HAZARDOUS MATERIALS AND CONTAMINATION

There is no prior knowledge of any hazardous materials at the site. However, it may be that there is a possibility of hazardous materials from previous use of the site, or that materials to be removed contain hazardous materials. The Contractor shall be responsible to survey the site and determine if hazardous materials exist.

If hazardous materials are found to exist, the Contractor shall immediately notify the COR. While awaiting further instructions from the COR, the Contractor shall cease work in, and close access to, the exact area where hazardous material has been discovered. The Contractor shall take precautions to protect the site from surface run-off and precipitation, and prevent leaching of any hazardous material in the surrounding area.

2.3.2. UNEXPLODED ORDNANCE (UXO) CLEARANCE

There is no knowledge of any UXO material on the available site. If any ordnance material is unexpectedly discovered though, the Contractor must immediately notify the COR, cease work and perform all measures he is required for as per applicable laws and regulations. Once notified of ordnance material, the COR will notify the appropriate authority which will then engage required measures for UXO clearance and unblock the concerned area for further construction work after clearance.

2.4. DESIGN SUBMITTALS

Provide civil design submittals in accordance with RFP Section 01 33 16, DESIGN AFTER AWARD and in compliance with SOW Section 1.0 – GENERAL.

65% Design Submittal:

a. Pre-Final Design Analysis of civil features.

b. Final Existing Conditions Plan.

c. Pre-Final Demolition Plan

d. Pre-Final Site Layout Plans - Indicate existing and proposed Civil features.

Include other disciplines’ features (faded background) that affect the Civil Design (buildings, mechanical structures, electrical utilities, etc.).

e. Pre-Final Grading Plan. Include spot grades and slopes in Grading Plan.

Include erosion control design.

f. Pre-Final Civil Specifications

95% Design Submittal:

27-Jun-19 Page 9 of 46

a. Update all items from the 65% Design Submittal to 95% (Final) Design.

Incorporate all 65% design comments.

100% Submittal:

The 100% Submittal provides a complete and final set of contract documents ready for construction. Update all Final submittals from 95% to a corrected Final submittal. Address all previous government review comments before submitting.

As Built Drawing Submittal:

All requirements for the 100% submittal, updated to reflect actual project conditions as constructed.

2.4.1. DESIGN ANALYSIS

Provide a Design Analysis for all Civil features that documents significant design choices and substantiates design compliance with contract requirements, applicable codes and standards. Documentation includes narrative, calculations, photographs, and sketches. Reference all applicable regulations, standards, and criteria for the design. Reference sources are subject to Government approval. Provide design assumptions. For design choices, discuss alternative systems considered, and provide rationale for the selected alternative.

The Design Analysis includes, but is not limited to:

a. Discussion of Site Layout constraints, including but not limited to, land use, vehicle and pedestrian access.

b. Discussion of Demolition constraints and design decisions. Include discussion on how access will be provided during construction, and how each utility will be maintained and operated during construction.

c. Discussion of Earthwork and Site Grading constraints and design decisions.

Discuss requirement and effort to restore grading to pre-demolition state.

Discuss changes to drainage that might be required or recommended.

d. Discussion of Storm system constraints and design decisions. Confirm that the existing receiving system has adequate capacity to receive the additional stormwater flow generated by the project.

2.5. FINAL DESIGN SITE PLANS

2.5.1. DESIGN CONDITIONS

It is the Contractor’s design responsibility to provide final design site plans based upon the RFP and coordination with the authorities. The required facilities will need to be site-adapted to existing conditions and to accommodate utility line connections and other features. Any modifications shall meet the intent of the RFP design and be approved by the COR before implementation.

The location of the Contractor’s staging area(s) shall be shown on a plan for approval by the COR. The Contractor shall develop the final site plan after coordination with the COR and End-User.

Finished Floor (FF) elevation will be such that a separation of 45cm will be established between FF and Finished Grade (FG) around building. See architectural plans for cross-section/building elevations.

Provide surface and drainage grading consistent with existing surface grading layout consistent with previous pre-demolition state. Slopes steeper than 2H:1V are not allowed.

27-Jun-19 Page 10 of 46

The Contractor is responsible for all aspects of the project.

2.5.2. REMOVE EXISTING FOUNDATION/PAD - BUILD LABORATORY IN ORIGINAL LOCATION

2.5.2.1. Remove existing foundation/pad. Site will be clear of debris and obstructions. Existing utilities to building site will remain and be protected.

2.5.2.2. Upon foundation/pad removal, a new building foundation/pad, capable of supporting the proposed building and consistent with geotechnical investigation, architectural and structural plans, will be provided.

2.5.2.3. Existing utilities to building site will remain and be protected.

Utilities required for new building shall be reconnected. Damage to existing utilities will be repaired or replaced to 2 meters beyond building footprint.

2.5.3. APPLICABLE DESIGN AND CONSTRUCTION DOCUMENTS FOR CIVIL

Civil design, construction, and material standards shall be in accordance with the latest editions of the Host Nation Governmental Building Codes and Local Jurisdiction Governmental.

2.6. CIVIL – SITE DEVELOPMENT

2.6.1. MOBILIZATION

The Contractor shall provide for approval the mobilization and demobilization of all vehicles, material, and construction equipment to the project area. The Contractor shall prepare the site and perform all necessary preparatory work for digging and excavation. A mobilization plan, including the location of the Contractor’s proposed staging area(s), shall be submitted to the COR for approval. Reference RFP Section 00 74 00-SPECIAL CONDITIONS for other mobilization, access, and permit requirements.

2.6.2. CLEARING, GRUBBING, DEMOLITION, AND REMOVAL

Any structure, feature, or landscaping to be demolished and removed shall be shown on the demolition site plan. The Contractor shall stake-out the limits of disturbance before starting work. Demolition and removal work includes, but is not limited to:

trench excavation, spoil materials, rubbish piles, spent construction related materials and material canisters, miscellaneous debris, and leftover materials, which have been abandoned.

2.6.2.1. Clearing and grubbing of vegetation includes, but is not limited to:

trees, stumps, roots larger than 75 mm in diameter, brush, shrubs and other landscaping obstacles that obtrude, encroach upon, or otherwise obstruct the work.

All debris generated during demolition, including excess soil/rock/topsoil, shall be removed from the project site, and properly disposed of by the Contractor in accordance with host nation requirements.

2.6.2.2. Tree cutting shall be limited to that necessary for construction of proposed facilities. A tree cutting plan shall be developed by the Contractor and provided to the COR for approval prior to any tree removal activities.

2.6.2.3. All debris generated during demolition, including excess soil/rock/topsoil, shall be removed from the project site, and properly disposed of by the Contractor in accordance with host nation requirements. The Contractor shall be responsible for all applicable permits for demolition, removal, 27-Jun-19 Page 11 of 46 transport, and disposal of waste material generated by this work effort. The dumps for uncontaminated demolition material shall be official disposal sites. The Contractor shall be responsible for meeting the requirements of the disposal site authorities regarding the material delivered there and for paying any dumping fees. The Contractor shall also provide the COR with documentation verifying the material has been properly disposed according to Host Nation laws and requirements.

2.6.3. CONSTRUCTION LIMITS

Do not disturb the project site beyond necessary for installation of proposed construction. Do not disturb any areas past the site’s property line. Show demolition work and limits of disturbance in the drawings. Stake-out the limits of disturbance on-site with temporary fencing before beginning construction.

2.6.4. DUST, DEBRIS, AND EROSION CONTROL

Prevent the spread of dust, debris, and erosion from the project site. Install erosion control measures before beginning construction. Sweep pavements as often as necessary to control the spread of debris. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, erosion, or pollution. Remove dust, dirt, and debris from work areas daily. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.

2.6.5. EARTHWORK

The Contractor shall perform all earthworks necessary to provide a uniform and even grade in the immediate vicinity of the project.

Compaction under building foundations shall be at least 95% of maximum density.

Erosion control measures using rock, geotextiles, or other materials shall be included as required to stabilize the soil where necessary.

Control Tests shall be performed on all prepared subgrades in accordance with host nation and local government codes and standards. Copies of all test results shall be furnished to the COR.

Trench backfill shall be with appropriate compactable soil materials and shall be compacted in layers of about 20cm each to at least 95% maximum density. Density tests shall be conducted by the Contractor in accordance with the technical specifications. The backfilling of pits and trenches shall only be performed after approval by the COR.

All excavated material, if satisfactory for reuse, should be used on the project site where fill is required. Only gravelly and sandy non-cohesive materials shall be considered satisfactory for fill and backfill, with the provision that in any soil type the maximum particle size does not exceed 75 mm, the plasticity index is not greater than 30, the soil is not frozen or contaminated, and the soil does not contain trash, debris, or organic material. In case of a difference of opinion about the classification of soil type acceptability, an independent professional soils engineer shall be engaged at cost to the Contractor.

The COR has the right to require that trench shoring be improved if the trench shoring measures provided by the Contractor are deemed insufficient in terms of safety. This improvement shall be at the Contractor's cost if the original Contractor's measures did not meet the requirements of applicable safety criteria.

The removal of trench shoring after construction pit work or trenching shall only be performed after approval by the COR.

27-Jun-19 Page 12 of 46

2.6.6. SITE GRADING

The proposed site grading will be developed to minimize the amount of earthwork required.

Finished grades adjacent to structures on grass surfaces will be selected which direct runoff away from structures at 5% for the first 2 m. Ditches, swales and open channels will be provided as required, and have a minimum longitudinal gradient of 0.5%.

The Contractor shall also similarly grade the soil subgrade before pavements, foundations, or concrete pads are installed, in order to keep the subgrade sufficiently dry until pavement or foundation work is complete.

All depressions and low areas within the project site shall be filled and brought to grade. The final site shall be graded to provide a uniform surface over the entire site with no abrupt changes in grade due to depressions or embankments. The Contractor shall take into account the annual wet and rainy periods and shall perform site grading such that there is no erosion or undermining of the fill areas for the new building and its associated exterior features.

2.6.7. STORM DRAINAGE

The Contractor shall provide the most appropriate drainage system for the site, in accordance with host nation and local government regulations. The Contractor will take into account the information gathered from the previous site design, local climate and rainfall data, 10 year return storm frequency, and any other relevant information/data.

Storm drainage systems shall be designed to carry storm water away from structures and pavements by channel, piping, or sheet flow. The storm drainage system will be designed for a 10-year return storm frequency so that the likelihood of ponding around the building, or elsewhere on the project site, is minimized. Below each downspout outlet provide a splash block that will drain water away from building foundations a minimum of 3 meters per site grading requirements.

2.6.8. UTILITY LINES - GENERAL

The intention of this scope is that the project will reuse existing connection points for all utilities. The Contractor shall verify the condition and capacity of any existing exterior utilities which will be affected by this project. It is the Contractor's responsibility to confirm the specific location, depth, capacity and condition of the existing utilities and to construct and install any new required utility services for the project facility.

The COR shall be notified of any utility lines found to be missing from or incorrectly shown on any existing plans showing existing conditions and made available to the Contractor. Any indication of existing utility lines on such plans shall not mean the existence, location, depth and/or alignment of the lines is accurately represented. The Contractor is responsible for the protection of those lines that are to be kept in operation.

2.6.8.1. WATER SUPPLY

The Dapaong Hospital has an existing water supply to which the new laboratory addition will reconnect.

After installation, the waterlines shall be tested according to local codes for leakage under pressure. Before the waterline is put into final operation, it shall

27-Jun-19 Page 13 of 46 be disinfected in accordance with local standards and then flushed through to remove traces of the sterilization agent. The line shall not be put into operation until absence of coli form organisms is proven by a bacterial examination of the treated line by a local medical service. The results of both tests shall be provided to the COR and, if the test results are unsatisfactory, necessary remedial work shall be at the Contractor’s expense.

2.6.8.2. WASTEWATER SYSTEM

The Dapaong Hospital has an existing waste water septic system to which the new laboratory replacement will connect. The Contractor will reuse connections utilized by previous laboratory structure.

2.6.8.3. BURIED ELECTRICAL CABLES

Where proposed electrical utilities cross existing or proposed ditches, the cables shall be buried to a minimum depth of 30 cm below the ditch/swale bottom. Where cables are required to cross concrete walls, cables shall be installed in a steel conduit below the wall foundation. If a wall foundation extends 1 m or more deep, the foundation may be cored and fitted with a PVC sleeve to allow passage of cables through it. The PVC sleeve size shall be coordinated with the COR.

2.6.9. LANDSCAPING

The Contractor shall provide a plan indicating the location and limits of areas to be restored and/or repaired which were damaged by the contractor’s work effort.

Restoration plan will include, at a minimum, a plan for re-establishment of ground cover consistent with the surrounding area. These items shall be indicated on the new site plan.

End of Section

27-Jun-19 Page 14 of 46

3.0 ARCHITECTURAL

3.1 PROJECT DESCRIPTION

Design, demolition and construction work of Laboratory Extension to Dapaong Regional Hospital in Dapaong, Togo. The existing facility is a one-story light metal stud – cement panel construction containing Waiting Area, Reception Area, Doctor’s Office, Blood Draw Area, Storage Area, Battery Room, Toilet Room, and an integrated Rain Water Collection System. The project construction was completed in 2014. Storm caused severe structural damage in spring 2017.

Design and then perform the demolition and rebuilding work of one-story, solid masonry / concrete building that will serve as a laboratory extension to the existing Dapaong Regional Hospital. Demolish the entire existing laboratory extension building and build the laboratory extension facility anew.

The rebuilt laboratory extension building will contain Waiting Area, Reception Area, Doctor’s Office, Blood Draw Area, Storage Area, Battery Room, Toilet Room, and an integrated Rain Water Collection System. The Main functional requirements are as follows:

a) Provide maximum use of natural ambient light (without glare = no direct sunlight);

b) Provide maximum use of natural ventilation and passive cooling for a cool climate inside the lab extension building;

c) Provide minimum room dimensions as shown on as-built drawings (unless required to be larger by local building code);

d) Provide minimum wall height of 3m (unless required to be higher by local building code).

Extensive coordination is required between the architectural work and the civil, geotechnical, structural, fire protection, mechanical, and electrical requirements of this project.

3.1.1 DESIGN

Provide a design and construction package that uses the space allocations, functional adjacencies, design details, and features given or referenced in this RFP. The design must incorporate all referenced codes and regulations. The Contractor is responsible for creating additional details as required to complete a full design. All details must conform to the requirements of this RFP and are subject to the approval of the COR.

The rebuilt laboratory extension facility must be designed and constructed on the basis of the existing functional layout. As-built drawings have been attached and provided for reference only. They do not necessarily represent an approved floor plan or design. The Contractor is responsible for providing a design that meets all requirements of the User and the codes and criteria referenced in this Statement or Work.

3.1.2 DESIGN SUBMITTALS

Provide all architectural submittals after contract award in accordance with Section 01 33 16 DESIGN AFTER AWARD and Section 01 33 00 SUBMITTAL PROCEDURES.

Prepare and submit the documents listed below at the submittals indicated.

3.1.2.2 65% DESIGN SUBMISSION

Include the following drawings and reports as applicable to the project:

a. Code Summary – Provide a tabular code compliance summary.

b. Life Safety Plans – Provide plans depicting smoke/fire resistance ratings, egress routes, dead-end corridors, exits, and other aspects of life safety pertaining to the design.

c. Demolition Plans – Provide existing floor plans, indicating all demolition required.

27-Jun-19 Page 15 of 46

d. Floor Plans – Provide all floor plans, indicating room names, areas, and basic dimensions, scale 1:50.

e. Ceiling Plans – Provide reflected ceiling plans for all rooms, indicating ceiling materials and fixtures, scale 1:50.

f. Building Elevations – Provide all building elevations indicating all exterior materials.

g. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.

h. Building Section – Indicate heights of critical building elements.

i. Wall Section - Provide a typical interior and exterior wall section for each building – describe wall materials.

j. Interior Elevations – Provide interior elevations of all bathrooms, indicate critical heights of surfaces and plumbing fixtures and describe all materials and finishes.

k. Pre-Final Design Analysis – Provide a narrative explaining the design and indicating how the design and materials meet the requirements of this SOW.

l. Pre-Final Specifications – Provide detailed explanations of requirements for all performed work or provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.

3.1.2.3 95% DESIGN SUBMISSION

The 95% Submittal provides a complete and final set of contract documents essentially ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include the following drawings and reports as applicable to the project:

a. All documents from the 65% submittal updated to incorporate 65% review comments.

b. Floor Plans – Provide all floor plans, indicating room names, areas, and dimensions, scale 1:50.

c. Building Elevations – Provide all building elevations indicating all exterior materials.

d. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.

e. Building Section – Indicate heights.

f. Wall Sections – Provide sufficient wall section(s) to indicate all materials and different conditions.

g. Section and Plan Details – Provide details of critical building intersections.

h. Window and Door Schedule – Provide a schedule of all windows and doors, indicating sizes, hardware, and operation.

i. Stair Section and Details.

j. Finish Schedule – Indicate all proposed finishes.

k. Final Design Analysis – Provide a finalized narrative describing all work to be performed on the project and how it meets the functional and code requirements of the project. Provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.

l. Final Specifications – Provide line items and detailed descriptions of all work to be performed.

3.1.2.4 100% DESIGN SUBMISSION

The 100% Submittal provides a complete and final set of contract documents ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include all drawings, specifications and calculations from the 95% Submittal updated to incorporate all previous review comments.

3.2 TECHNICAL CRITERIA AND STANDARDS

27-Jun-19 Page 16 of 46

Design and construct the project in accordance with the requirements outlined in Section 1.7 DESIGN CRITERIA.

3.2.1 LIFE SAFETY REQUIREMENTS

The Design must meet all Host Nation and local Life Safety codes and requirements.

All structures to be provided must have exits and means of egress that comply with current Host Nation codes and standards, or in accordance with US codes and standards.

In the absence of Host Nation codes and standards, for individual concerns of Life Safety the Contractor must follow the International Building Code (IBC).

3.2.2 HANDICAPPED ACCESSIBILITY REQUIREMENTS

All facilities must meet applicable Host Nation handicapped accessibility requirements.

3.3 GENERAL SCOPE OF WORK

Design the architectural elements of this facility to withstand all site-specific environmental conditions such as wide seasonal temperature swings, local wind, rain and earthquake conditions. All architectural features must be appropriately braced for anticipated seismic activity. The Contractor may propose alternate building materials to meet the facility’s requirements, but final selection of materials is subject to the approval of the COR. Consider economics not only in the initial acquisition, but also in the future maintenance of the materials, when selecting materials and building systems to be incorporated into the project. When requested, the Contractor must provide documentation demonstrating that a chosen alternative material is life cycle cost effective.

3.4 DETAILED SCOPE OF WORK

The Contractor is responsible for the following specific tasks required for the construction of this facility.

3.4.1 DEMOLITION

The Contractor is responsible for all required demolition as indicated in this scope.

Demolition work includes, but is not limited to, the following items:

a. Demolish and remove existing roof structure and covering;

b. Demolish and remove existing exterior and interior walls;

c. Demolish and remove existing exterior and interior doors;

d. Demolish and remove existing exterior windows;

e. Demolish and remove existing floor, wall, and ceiling finishes;

f. Demolish and remove existing floor slab;

g. Demolish and remove existing foundations.

After the demolition, any protruding objects, bolts, rebar, holes or sharp edges, which might cause a hazard for the users, must not remain.

3.4.1.1 DEMOLITION AND DISPOSAL

All demolished materials must be abated and disposed of in accordance with local laws, codes and regulations. The Contractor is responsible for all required testing before, during and after demolitions as well as for all required compliance with safety standards. No burning of disposals and garbage, packaging, etc. on project site allowed.

Submit a Demolition Plan to be part of the QC Plan or a separate submittal to be tracked via the submittal register, indicating the demolition, abatement, and disposal methods. Cost must be included in the total bid price.

27-Jun-19 Page 17 of 46

DO NOT reuse any demolished materials.

3.4.1.2 DEMOLITION AND DISPOSAL OF HAZARDOUS MATERIAL

The Contractor is responsible to survey the site and determine if hazardous materials exist. If hazardous materials are found to exist, immediately notify the COR, and provide the COR with the results of the relevant sampling and testing.

Provide the hazardous material report to the COR no later than 30 days after Notice to Proceed (NTP) for information and approval.

3.4.2 BUILDING SYSTEM AND MATERIALS

The intent of this RFP is to allow the Contractor the maximum flexibility to design and construct this facility in an economical manner without sacrificing good engineering practices, quality materials and systems. The Government requires low or no maintenance finish materials to the greatest extent possible. Regarding the use of wood, special attention must be paid to termites and other harmful influence to wood in the local region and conditions. Provisions must be taken and documented in the contractor’s submittal / design. Contractor must use locally available material and construction to the maximum extent possible to support the local industry and to allow for easy maintenance and replacement. Building materials as described herein for roofing, walls, ceilings, doors, windows and floors are minimum requirements and may require revision based on code compliance and criteria.

3.4.2.1 FIRE PROTECTION RATINGS OF INTERIOR FINISHES

All interior finishes must conform to Host Nation fire protection standards/requirements or equivalent US standards/requirements.

3.4.2.2 ACOUSTICAL DESIGN

Doors, walls, floors, and ceilings must meet the minimum sound protection per Host Nation requirements.

3.4.2.3 THERMAL INSULATION

Provide thermal insulation in accordance with Host Nation and local requirements.

Minimum R-values and maximum U-factors required by this SOW are minimally acceptable levels of thermal insulation.

3.4.3 EXTERIOR CONSTRUCTION WORK

Provide the following exterior architectural systems.

3.4.3.1 EXTERIOR WALLS

Design and construct new solid CMU (Concrete Masonry Units) exterior walls in accordance with (IAW) the requirements of this SOW. Refer to Section 4.0 STRUCTURAL. Exterior walls must have smoke/fire resistance ratings as required by Host Nation, and local fire and life safety codes.

Metal or wooden stud wall construction is not acceptable for this SOW.

Provide exterior wall finishes appropriate for the wall structure as required below.

3.4.3.1.1 EXTERIOR WALL PLASTER AND PAINT

Provide new exterior cementitious plaster and paint on all concrete and masonry surfaces. Apply brown/rough coat and then top coat plaster. Steel trowel to a smooth surface. Cure plastered surfaces, neutralize acid/apply primer, then paint.

Exterior walls must be painted to protect wall material from weather effects.

Paint must be washable, abrasion resistive and suitable for wall material. Apply primer and coatings as per paint manufacturer’s guidelines. Color must be light

27-Jun-19 Page 18 of 46 for maximum light (heat) reflection. Submit a color sample of the paint along with the manufacturer's catalog data including application instructions and product data for COR's acceptance.

3.4.3.2 EXTERIOR DOORS

Provide new exterior doors as indicated on attached as-built drawings. Doors must be minimum 1 m wide and 2.1m high (clear opening), unless required to be wider and higher per local building code.

3.4.3.2.1 EXTERIOR PERSONNEL DOORS

Provide new factory finished, local industry, heavy duty standard doors and frames to include new exit / escape doors. Metal doors must include reinforcing or corrugation of metal sheet to prevent oil-canning. All metal must be covered with a suitable rust-inhibitive primer and then be painted with a glossy protective coating. Wooden doors must be suitable for a high humidity climate and resistant to potential damage from insects. Paint surfaces of doors as per paint manufacturer’s guidelines. Color of paint must be approved by COR. Door frames must be galvanized and painted / coated steel or other local type heavy duty standard.

All screws and fastening materials must be stainless steel or brass. Mount all door frames flush with surrounding walls and seal all seams.

All doors must be keyed separately. Provide 3 keys with each lock. Locking system must prevent un-authorized copying of keys. Product certificates must be provided to the COR.

Provide all necessary hardware for all doors including panic hardware locking mechanisms. All hardware must be heavy duty industry standard. Each door must have the following hardware as a minimum:

a. Three hinges on each leaf;

b. One floor or wall mounted doorstopper, as appropriate;

c. Lever latch handles;

d. Cylinder type door locks.

e. Panic push bar in compliance with Host Nation criteria on each leaf, as required;

f. Door threshold and door bottom in compliance with Host Nation criteria.

3.4.3.2.2 EXTERIOR BATTERY ROOM DOORS

Provide doors on the battery room similar to the exterior personnel doors except all battery room doors must be fully louvered to allow natural ventilation of the battery room even when the doors are closed and locked. Louvres must be waterproof.

Provide insect screens on louvres.

3.4.3.3 EXTERIOR WINDOWS

Provide exterior windows as indicated on attached as-built drawings.

3.4.3.3.1 EXTERIOR WINDOW FRAMES AND GLAZING

Provide new operable framed windows. Frames must be primed and painted as per paint manufacturer’s guidelines. Anchor and secure window frames to structure as recommended by the manufacturer to meet the wind and seismic loads. Provide all accessories and hardware including drip sills, hinges, lever handles and latch lock. All windows must be 100% operable and meet life safety requirements.

Install windows in wall openings to allow for installation of outside mounted insect screens. Windows must be installed to include all required caulking sealing and proofing, with materials to be weather resistive and environmentally friendly.

Caulk all joints between window frames and building with sealant to provide a watertight installation and proper finish. Glazing must be transparent except in bathrooms. Provide translucent glazing or obscured or matt foil for all bathroom windows.

27-Jun-19 Page 19 of 46

3.4.3.3.2 EXTERIOR WINDOW SILLS

Provide plastered exterior window sills at all new windows. Window sills must slope away from the window. Caulk all joints between window frames and building with sealant to provide a watertight installation and proper finish.

3.4.3.3.3 INSECT SCREENS

All windows must be provided with steel insect screens mounted on the interior sides of window openings. Fastened insect screen frames to the wall securely and mount insect screen netting onto the frames. Insect screen netting must be resistive to aging caused by ultra-violet light.

3.4.3.3.4 EXTERIOR WINDOW BARS

Install exterior window bars outside all operable windows. Window bars must be steel rod or flat steel profiles. All metal parts must be painted and primed to prevent corrosion. Fastening must be done with steel anchor into wall or other method that will assure similar intrusion resistance as the surrounding wall.

Window bar fasteners must not be accessible from the exterior.

3.4.3.4 ROOFING

Roof design and materials must comply with Host Nation requirements. Provide sloped roof. Roof must be designed not to gather hot air but allow for maximum air movement.

3.4.3.4.1 ROOF CONSTRUCTION AND ROOF COVERING

Provide new roof structure, roof lathing and new corrugated insulated metal sandwich panel roofing. Insulated metal sandwich panel roofing must have interlocking trapezoidal profile. All roofing must have a slope greater than 30%.

Steel or aluminum face layers must be factory finished and have minimum thickness of 0.70 mm. Sandwich panels must have a maximum U-factor of U-0.220 (USI 1.249).

Sandwich panels must have concealed fasteners that limit thermal bridging. Provide all required flashings, fasteners, and sealing materials. Install as required by the manufacturer. Metal roofing must be anodized or coated with protective film / foil. Roof color must be light color to maximize reflection of heat. Submit material and color samples to COR for approval. Roof must be ventilated. Install galvanized steel mesh over the openings to prevent insects and bird nesting on the interior of the building.

3.4.3.4.2 EAVES, OVERHANGS, AND SOFFITS

Provide roof overhangs a minimum of 600 mm from the face of exterior walls. Leave roof soffits open for ventilation.

3.4.3.4.4 ROOF GUTTERS, DOWNSPOUTS AND FLASHING

Provide new pre-finished galvanized steel roof gutters, downspouts and flashing.

Size gutters and downspouts for roof drainage area and maximum expected rainfall intensity. Submit gutter and downspout sizing calculations in the Design Analysis.

Coordinate storm drainage connections with the requirements of Section 2.0 CIVIL AND GEOTECHNICAL. Submit material and color to COR for review and approval.

3.4.3.4.5 ENTRANCE CANOPIES

Provide exterior canopies over personnel doors serving as building entrances. Roof slope and material at canopies must match building roof material.

3.4.3.5 STAIRS

Provide cast-in-place concrete stairs as indicated on the attached as-built drawings. Stair and stair components must comply with Host Nation Life Safety Codes and accessibility requirements. Provide new metal handrails on both sides of stair. Handrails must extend a minimum of 300 mm beyond each end of the stair.

Handrail extensions at the top of the stair must be level, handrail extensions at

27-Jun-19 Page 20 of 46 the bottom of the stair must be sloped. Stairs and all stair components must conform to the requirements of Section 4.0 STRUCTURAL.

3.4.3.6 EXTERIOR METAL

All new exterior metal must be painted. Clean and paint all new metal elements that have not received a factory applied finish in the field.