01 10 10 Statement of Work Kpangalam Kindergarten – Sokodé, Togo

US Army Corps of Engineers Europe District

APO AE 09049

ar148a

Statement of Work Project Number:

OHASIS# 31879

Kpangalam Kindergarten Sokodé, Togo

Prepared by:

Design Section Engineering Branch 13 May 2019 Revised 18 July 2019

SECTION 01 10 10

STATEMENT OF WORK

SECTION TABLE OF CONTENTS:

1 GENERAL

2 CIVIL AND GEOTECHNICAL

3 ARCHITECTURAL

4 STRUCTURAL

5 ELECTRICAL & COMMUNICATIONS

6 MECHANICAL

ATTACHMENTS

Att. # 1Project Location Map
Att. # 2Conceptual Site Plan
Att. # 3Conceptual Functional Layout
Att. # 4Ventilated Improved Pit Latrines
Att. # 5Preparation of Structural Calculations

1.0 GENERAL

1.1 PROJECT DESCRIPTION

The Request for Proposal (RFP) provides parameters for a design-build project for construction of a kindergarten school facility in Kpangalam, Sokodé, Togo. This project includes the design and construction of the following structures, detailed requirements are contained elsewhere in this Statement of Work (SOW):

a. One (1) four-classroom school building;

b. One (1) eight-toilet (four male/four female) ventilated improved pit (VIP) latrine;

c. One (1) rainwater harvesting system;

d. Battery room with optional photovoltaic (PV) system;

e. Site improvements.

1.2 GENERAL REQUIREMENTS

The Contractor must deliver fully functional, turnkey type facilities (without furniture) as described in this document. The work includes - but is not limited to - design, demolition, fabrication, delivery, installation, construction, and site work. The facility and the installed equipment must be permanent construction.

The facility in this project must be complete and usable to meet codes and technical and functional requirements per this Statement of Work (SOW). The proposal price must include all design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, general and administrative expenses (G&A) and general conditions to complete this project as described in the SOW.

These design and product requirements are minimum requisites. Compliance with the provisions of this section by subcontractors is the responsibility of the Contractor.

1.2.1 BASE BID ITEMS AND OPTIONAL BID ITEMS

This Statement of Work addresses the technical requirements necessary to complete all work associated with this project. For information and requirements regarding the allocation of pricing between elements of the work, refer to the Bid Schedule included as a separate document. The Bid Schedule identifies the breakdown between the individual base bid and optional items for all work identified in this Statement of Work, associated drawings, and attachments. All work as described in these documents is included in either the Base Bid or Optional Items: consider all items not specifically identified in the Optional Items as part of the Base Bid Items.

1.3 FUNCTIONAL AREAS

Provide the new, stand-alone structures described below. Detailed facility requirements are provided in the discipline-specific sections and attachments of this SOW.

1.3.1 KINDERGARTEN BUILDING

Provide a one-story, solid concrete / masonry Kindergarten Building with a sloped metal roof. Provide the following functional areas for the Kindergarten Building:

Room #
Room Name
Function
Approximate Size (m2)
101
Classroom
Teaching and instruction
63
102
Classroom
Teaching and instruction
63
103
Classroom
Teaching and instruction
63
104
Classroom
Teaching and instruction
63
105
Office
Administrative staff office
15.5
106
Storage Room
School storage
13.2
107
Terrace
Covered, open-air access to classrooms and office
73.2
108
Battery Room
Ventilated battery room for photovoltaics
1.8

The completed facility must have an enclosed net area of approximately 283 m2 and a gross footprint of approximately 376.0 m2.

1.3.2 8-TOILET LATRINE

Provide one (1), one-story, solid concrete / masonry Latrine building with concrete roof slabs containing 8 VIP latrines.

Provide the following functional areas for each Latrine:

Latrine #1
Latrine with one (1) hole
1.3
Latrine #2
Latrine with one (1) hole
1.3
Latrine #3
Latrine with one (1) hole
1.3
Latrine #4
Latrine with one (1) hole
1.3
Latrine #5
Latrine with one (1) hole
1.3
Latrine #6
Latrine with one (1) hole
1.3
Latrine #7
Latrine with one (1) hole
1.3
Latrine #8
Latrine with one (1) hole
1.3
Hallway Women
Access to female latrines
3.9
Hallway Men
Access to male latrines
3.9
Holding Tank Block
Vented waste pit
8.15

The completed facility shall have a net usable area of approximately 18.2 m2 and a gross footprint of approximately 32.2 m2.

Analyze the slope of the terrain and provide a cast-in-place concrete ramp for the latrine building to meet applicable Host Nation handicapped accessibility requirements.

1.4 SUBMITTALS

Government approval is required for submittals with “G” designation; submittals not having a “G” are for Contractor Quality approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Pre-construction Submittals Inspection Plan; G SD-05 Design Data

65% Pre-Final Design; G, DO
95% Final Design; G, DO
100% Corrected Final Design; G, DO

1.4.1 DESIGN SUBMITTALS

Provide a complete design package at each milestone, as described in Specification Section 01 33 16 DESIGN AFTER AWARD. The milestones for this project are indicated above in Section 1.4 SUBMITTALS. The specific requirements of each milestone are described in each discipline-specific section of this Specification.

Submit all documents in electronic format (.pdf for text and calculations, .pdf and .dwg (AutoCAD, latest version) for drawings). See Specification 01 33 00 SUBMITTAL PROCEDURES for additional information.

1.5 MATERIALS AND EQUIPMENT

Materials and products used must be durable, heavy duty, industry standard. The equipment must be the manufacturer’s standard quality and must be compatible with all other equipment and materials within the system or assembly. Equipment and materials must include all connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.

Provide a nameplate secured to each major piece of equipment. Each nameplate must have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number. The definition of a “major piece of equipment” is at the discretion of the COR.

1.5.1 LIFE-SPAN

Construction must have an expected life span of 25 years.

1.5.2 MAINTAINABILITY

Provide low maintenance materials and systems appropriate for the project climate and location.

1.5.3 OPERABILITY

Systems (including but not limited to architectural, electrical, communications, and mechanical systems) must be simple to operate and easy to maintain.

1.5.4 STANDARDIZATION

Provide standardized materials, products, equipment, and systems to minimize the requirements for replacement parts, storage facilities, and service requirements.

1.5.5 SOURCING

Use materials, products, equipment, and systems that can be replaced, repaired, maintained, and/or serviced locally in Togo. All warranties must be valid in Togo and have local authorized service providers.

1.6 DESIGN DIMENSIONS

Develop the design using the metric system.

1.7 DESIGN CRITERIA

Project design, site facilities, utility systems and material standards must be in accordance with the latest editions of the Host Nation building codes. In the absence of Host Nation building codes, use the International Building Code (IBC) and codes, technical standards, and regulations referenced in this RFP.

While this RFP references various source standards and specifications, all design documents must meet Host Nation codes and requirements. It is the designer's responsibility to demonstrate that the Host Nation standard is equal to the cited standard or specifications being supplanted. Apply the more restrictive standards when conflicts arise between the requirements of this RFP and any referenced or other applicable codes, standards or regulations. If equivalency cannot be met, use the more stringent requirement and quote both codes verbatim in correspondence to the COR. The designer is responsible to determine the required material and execution standards where specific standards are not indicated.

Provide an electronic copy of the local Host Nation standards and building codes in their original language as related to facility design and construction.

1.8 DESIGN CONFERENCES AND MEETINGS

The Contractor and the entire design team are required to participate in a design review conference for each design submittal. The Contractor must bring the personnel that developed the design submittal to any review conference.

All design review conferences must be held via teleconference or be reviewed and comments resolved via email.

The Contractor is responsible for taking meeting minutes during each design review conference and submitting to the COR for information and approval.

The Contractor is responsible for evaluating all Government comments prior to each design review conference. The Contractor is responsible for resolving all Government comments from each design phase. The Contractor must provide annotated responses to each design review comment with the subsequent design submittal packages. Construction may not begin until all Government comments from all design phases have been resolved.

1.9 SPECIAL CONSTRUCTION REQUIREMENTS

1.9.1 THIRD PARTY INSPECTION SERVICES

Furnish independent 3rd party inspection services to inspect the electrical and structural construction features of the project. The 3rd party must not be the same company responsible for the electrical or structural installation. This is in addition to the Contractor Site Personnel Requirements contained in 01 45 05 CONTRACTOR SITE PERSONNEL REQUIREMENTS. All testing is at the expense of the Contractor. Submit a plan for third party services to the COR. The inspection plan must be approved by the COR prior to construction.

1.9.1.1 GENERAL REQUIREMENTS

3rd Party inspectors must submit professional reports directly to the COR, without coordination with the Contractor, within 48 hours of the actual inspection. The report must contain the following at a minimum: names of all persons present for activity, listing and approval of all related materials, description of observed activity, and 10 photos (minimum resolution: 1504x1000) of the observed activity.

1.9.1.2 THIRD PARTY ELECTRICAL INSPECTOR REQUIREMENTS

The electrical inspector must be a certified Master electrician or licensed degreed Electrical Engineer and have a minimum of 10 years' experience, 5 years in the country where the project work is performed. Submit the inspector’s CV (Resume) to the COR for Government approval.

The following inspections must be conducted at a minimum: all outlets, off-cover inspection of all panels, verify that GFCI is present on all panels, municipal power connections, lightning protection installations, and generator installations.

Submit a plan and schedule to be part of the QC Plan or a separate submittal to be tracked via the submittal register, indicating the inspection plan and timing.

1.9.1.3 THIRD PARTY STRUCTURAL ENGINEER INSPECTOR REQUIREMENTS

The structural inspector must be a licensed graduate engineer with 10 years of experience, 5 years in the country where the project work is performed. Required experience includes, but is not limited to, inspecting concrete moment frame, concrete foundations, roof system and rebar and form work. Submit the inspector’s CV (Resume) to the COR for Government approval.

Submit an inspection plan and schedule of inspections to be part of the QC Plan or a separate submittal to be tracked via the submittal register, indicating the inspection plan and timing.

The following inspections must be conducted at a minimum: Bearing capacity of foundation soils, formwork and rebar of foundations, concrete placement of foundations. Formwork, rebar and concrete pour of moment frame. No concrete may be placed in forms without a preceding rebar inspection report and verification of functioning vibration equipment.

The inspector must review concrete test results and sign off on strength approvals.

END OF SECTION

2. CIVIL AND GEOTECHNICAL

2.1GENERAL REQUIREMENTS
2.1.1The Contractor shall provide and perform civil engineering design and construction services as required to provide a complete, accessible, functional, usable, and environmentally sustainable facility as described in this SOW. The services covered by this section include all civil engineering labor, material supplies, and incidental work required for the demolition, design, fabrication, delivery, installation, and construction that serve the project. The Contractor is required to extensively coordinate civil design and construction work with the scope of the other disciplines described in this SOW.
2.1.2The civil design and construction, including demolition and mobilization, shall be coordinated with all other trades. The facility and equipment shall be permanent construction. All civil works shall be designed and constructed in accordance with the criteria provided herein, and with the minimum standards specified in the applicable referenced codes.
2.1.3The contractor shall be responsible for obtaining all applicable permits for site clearing, digging, demolition, transport, and disposal of waste material generated by this work effort, and/or any other permits that may be required.
2.1.4The Contractor shall coordinate the site layout of the new building and its associated exterior features with the local authorities.
2.1.5No open fires or burning of trash will be allowed within the confines of the project site.
2.1.6Any damage to structures, drainage facilities, or other existing features on the site because of Contractor operations shall be repaired, or the damaged items replaced, at the Contractor's expense.
2.2SCOPE SUMMARY

The civil works for this project include, but are not limited to, the following:

• Site clearance in the area of the new building and access, including any required demolition, debris removal, grubbing of shrubs, removal of trees, or removal of existing surface features at the site which are obstacles to locating the new building and its associated exterior features.

• Performance of a site survey, including a topographical and drainage survey of the existing conditions.

• Performance of a geotechnical investigation of the site.

• Mobilization of all construction-related equipment.

• Site earthwork and grading, including preparation of the subgrade beneath the new structures/foundations, and any necessary grading to achieve positive drainage away from structures.

• VIP latrine cabin sanitary septic system

• If required by Host Nation, the planting of trees to replace in number any major trees, if any, that are removed in part to construct the new building and its associated exterior features.

2.3 EXISTING CONDITIONS

The proposed project is located in the town of Sokodé, Togo (Latitude 9°00'29.3"N Longitude 1°08'17.1"E). See Attachment#1-Project Location Map.

The existing site contains buildings, utilities, fences, and vegetation as shown on Attachment#2-Conceptual Site Plan. The site is flat. There is no known topographic survey, as-built, or geotechnical information for the site. There are no known environmental protection areas or archeological preservation areas on the project site.

An existing building is used for the kindergarten. The existing building is serviced by pit latrines. Building and latrines will be turned over to local authority for reuse or disposal.

There is no subsurface storm system at the site.

2.3.1 HAZARDOUS MATERIALS AND CONTAMINATION

There is no prior knowledge of any hazardous materials at the site. However, it may be that there is a possibility of hazardous materials from previous use of the site, or that materials to be removed contain hazardous materials. The Contractor shall be responsible to survey the site and determine if hazardous materials exist.

If hazardous materials are found to exist, the Contractor shall immediately notify the COR. While awaiting further instructions from the COR, the Contractor shall cease work in, and close access to, the exact area where hazardous material has been discovered. The Contractor shall take precautions to protect the site from surface run-off and precipitation, and prevent leaching of any hazardous material in the surrounding area.

2.3.2 UNEXPLODED ORDNANCE (UXO) CLEARANCE

There is no knowledge of any UXO material on the available site. If any ordnance material is unexpectedly discovered though, the Contractor must immediately notify the COR, cease work and perform all measures he is required for as per applicable laws and regulations. Once notified of ordnance material, the COR will notify the appropriate authority which will then engage required measures for UXO clearance and unblock the concerned area for further construction work after clearance.

2.4 DESIGN SUBMITTALS

2.4.1 Provide civil design submittals in accordance with RFP Section 01 33 16, DESIGN AFTER AWARD and in compliance with SOW Section 1.0 – GENERAL.

65% Design Submittal:

a. Pre-Final Design Analysis of civil features.

b. Final Site Survey (include in the Design Analysis).

c. Final Geotechnical Report (include in the Design Analysis).

d. Final Existing Conditions Plan.

e. Pre-Final Demolition Plan

f. Pre-Final Site Layout, Grading, and Utility (Storm, Sanitary, and Water) Plans – Indicate existing and proposed Civil features. Include other disciplines’ features (faded background) that effect the Civil Design (structures, wells, drainage, waste disposal vaults, latrines, etc.). Include contours, finish floor elevations, spot grades, and slopes in the Plans. Provide Profiles, Cross Sections, and Details. Include erosion control design.

g. Pre-Final Outdoor Furnishings Details

h. Pre-Final Civil Specifications

95% Design Submittal:

a. Update all items from the 65% Design Submittal to 95% (Final) Design. Incorporate all 65% design comments.

100% Submittal:

The 100% Submittal provides a complete and final set of contract documents ready for construction. Update all Final submittals from 95% to a corrected Final submittal. Address all previous government review comments before submitting.

As Built Drawing Submittal:

All requirements for the 100% submittal, updated to reflect actual project conditions as constructed. In addition to the as-built requirements discussed in RFP Section 00 78 00-CLOSEOUT SUBMITTALS, provide a topographical survey of the site per requirements of SOW Section 2.7-TOPOGRAPHIC SURVEY. Include existing utility lines or structures (both modified and unmodified) encountered in the construction footprint that were not located on the original Site Survey.

2.4.2 DESIGN ANALYSIS

Provide a Design Analysis for all Civil features that documents significant design choices and substantiates design compliance with contract requirements, applicable codes and standards. Documentation includes narrative, calculations, photographs, sketches, and catalog cut sheets. Reference all applicable regulations, standards, and criteria for the design. Reference sources are subject to Government approval. Provide design assumptions. For design choices, discuss alternative systems considered, and provide rationale for the selected alternative.

The Design Analysis includes but is not limited to:

a. Discussion of Site Layout constraints and design decisions, including but not limited to, land use, vehicle and pedestrian access, orientation of features on-site, setbacks from site features, minimizing utility lengths, minimizing earthwork and tree removal, and future expansion.

b. Discussion of demolition constraints and design decisions. Include discussion on how access will be provided during construction, and how each utility will be maintained and operated during construction.

c. Discussion of Earthwork and Site Grading constraints and design decisions. Provide cut and fill calculations. Include pertinent geotechnical information that affects earthwork.

d. Discussion of site drainage constraints and design decisions. Provide a hydrologic and hydraulic analysis of the site, including offsite areas that contribute to and influence the project’s site. Provide drainage basin map(s), rainfall data, and coefficients used. Provide calculations for designed finish floor elevations and sizing of infiltration features. Provide documentation for the 100 year flood elevation determination. Use the Rational Method or TR-55 for analysis and design. In the absence of Host Nation requirements, use a minimum 10-year storm frequency for analysis and design. Include pertinent geotechnical information that affects the site drainage.

e. Discussion of Sanitary system constraints, location, and design decisions. Include pertinent geotechnical information that effects the sanitary system.

f. Demonstrate the turning path of the largest anticipated vehicle(s) in the most constrained situations on the site plans.

g. Site Survey as an appendix.

h. Geotechnical Investigation and Report as an appendix.

2.4.3 DESIGN DRAWINGS

Provide Civil design drawings of sufficient detail to address the requirements of each design submittal. Civil drawings will include plans, profiles, cross sections, and details of Civil features for the project, as necessary, to provide clear direction for construction of this project. Civil drawings shall also include temporary construction plans/methods that affect the design and construction of the project. These temporary plans include mobilization, dewatering, shoring, construction sequence, etc. Design drawings include all necessary information (labeling, dimensioning, legend, details, notes, etc.) to allow for complete understanding and constructability of all proposed features. Provide comprehensible differentiation between features that are proposed, existing, future, or proposed to be demolished by use of appropriate choice of line styles, line weights, and/or colors. In the absence of the Host Nation CAD requirements, reference USACE A/E/C Graphics Standard for graphic requirements.

2.4.4 SPECIFICATIONS

Provide Civil specifications of sufficient detail to address the requirements of each design submittal. Specifications, when combined with the design drawings, allow for complete understanding and constructability of all proposed Civil features. Specifications may be notes on the Civil design drawings as an alternative to a separate specifications document.

2.5 DESIGN CRITERIA

Provide civil design in accordance with Host Nation codes. In the absence of Host Nation codes, use the latest release of the International Building Code (IBC) and the following codes and technical standards:

a. Uniform Facility Criteria (UFC) 3-201-01, Civil Engineering

b. UFC 3-220-01, Geotechnical Engineering

c. USACE A/E/C Graphics Standard (ERDC/ITL TR-12-1)

d. UFC 3-230-01, Water Storage, Distribution, and Transmission

e. UFC 3-240-01, Wastewater Collection

f. Host Nation Architectural Barriers regulations

g. WHO Fact Sheet 3.5 – VIP and ROEC latrines.

h. TB MED 577/NAVMED P-5010-10/AFMAN 48-138_IP, Sanitary Control and Surveillance of Field Water Supplies

i. USACE AED Design Requirements: Sanitary Sewer & Septic System

j. WHO Technical Notes on Drinking-Water, Sanitation and Hygiene in Emergencies

k. TAG – Technical Note No. 13 (TAG13) – The Design of Ventilated Improved Pit Latrines

2.6GEOTECHNICAL INVESTIGATION AND REPORT
2.6.1General

Perform a geotechnical investigation and assessment of the project site to determine the subsurface conditions and geotechnical parameters for foundation, grading, and utility design. The Geotechnical work must be performed under the supervision of a professional geotechnical engineer registered with the jurisdiction having authority, and the report must be signed by the Geotechnical Engineer.

Coordinate testing locations with the COR to avoid impact to existing utilities and facility operations. Utility locates, permits, pavement removal and vegetation clearing is the Contractor’s responsibility. Repair disturbed areas with compacted soil in non-paved areas. The repaired area must be flush with the adjacent surface. Following restoration, stake and flag each of the hole locations with boring identification numbers. Provide a map indicating the borehole and test pit locations.

The Contractor is required to investigate subsoil conditions at the site location. The Contractor will perform sufficient borings necessary for the design and construction of project features. A minimum two (2) borings will be performed, and each boring shall extend to a minimum of 2 m below grade. The Contractor shall obtain soil samples for testing as required for the computation of bearing capacities, settlement calculations, etc. The Contractor shall perform groundwater recordings as basis of design for underground construction, drainage facilities, sewage disposal facilities, ventilated pit latrines (VIPs), etc.

2.6.2 APPLICABLE DESIGN CRITERIA FOR GEOTECHNICAL

All investigation work, laboratory testing of soils and aggregate materials, and identification and assessment of subsurface materials, shall be in accordance with the latest editions of the Host Nation Governmental Building Codes and Local Jurisdiction Governmental Codes (see section 2.5 DESIGN CRITERIA). In the absence of Host Nation Building Codes, the Contractor shall use the International Building Code (IBC). Additional information can be found in the Uniform Facility Criteria (UFC) document UFC 3-220-01, Geotechnical Engineering, which is available on the Internet at: http://www.wbdg.org/ccb/browse_cat.php?o=29&c=4

2.6.3 GEOTECHNICAL/HYDROLOGICAL REPORT

Unless otherwise approved by the COR, a licensed geotechnical engineer shall prepare the geotechnical/hydrological report. The geotechnical engineer shall be able to demonstrate that the engineer has at least 5 years of geotechnical engineering experience.

The investigation shall be performed and the report provided to the COR prior to finalizing the design of any features which are dependent on the condition and characteristics of the soil.

The results of the investigation and recommendations, specific to the geotechnical/hydrological design requirements at the site, shall be presented at the first design submittal in a geotechnical/hydrological report for review and approval by the COR. The Contractor shall use the data from this investigation to provide bearing capacity analyses and settlement calculations, assessment for infiltration capability, if necessary lateral earth pressure parameters; general soil condition, compaction requirements, and fill requirements.

As well as more general information, the geotechnical report shall specifically address the following:

Include, as a minimum, the following information:

a. Description of field work completed and equipment used; names, signatures and stamps of licensed professionals involved; name of drilling company.

b. It shall clearly describe the subsurface conditions and the regional geology and seismic conditions at the site. It shall also recommend any soil replacement or amendment/treatment requirements, general fill and backfill placement procedures, preparation, placement, and compaction of onsite soils, borrow material, soil, structural fill, topsoil, and trench backfill. Include dewatering and temporary retaining structure needs.

c. Site map of borehole and test pit locations.

d. High resolution color digital photographs of each borehole and test pit location.

e. Test pit logs with classification of all subsurface materials. The logs must distinguish fill materials from native materials, include all in‐situ test results, and include groundwater depth information, if groundwater is encountered. Distinguish between bedrock and rock boulders.

f. Reports of all the field and laboratory testing.

g. It shall recommend the type of foundation system to be used for the various structures, allowable bearing capacities, expected settlement, depths of placement and bearing elevations for footings, grade beams, or slabs, minimum footing and grade beam dimensions, lateral earth pressure parameters.

h. It shall provide specific information about earthwork procedures for any special features, such as Ventilated Pit Latrines (VIPs) or water catchment storage tanks.

i. Calculations to support conclusions and recommendations.

2.6.4 GEOTECHNICAL DESIGN DRAWINGS AND SPECIFICATIONS

On the design drawings and/or specifications, include geotechnical information that affect the design of the project, including but is not limited to, boring locations, boring logs, groundwater depths, and any details that convey requirements for site preparation.

Perform any additional geotechnical investigations necessary for the design and construction of project features. Provide any geotechnical investigations and reports to the Government that are performed. Provide geotechnical information and assumptions in the Design Analysis to support design decisions.

Perform geotechnical work required for construction (i.e. compaction tests, inspection of structure foundation excavations). In the absence of Host Nation standards, perform the geotechnical scope of work per the International Building Code (IBC) and UFC 3-220-01, Geotechnical Engineering.

2.7TOPOGRAPHIC SURVEY
2.7.1The Contractor is required to provide a topographic survey, by a licensed surveyor, of the site and all features that will be affected by construction as part of the contract work effort. The survey shall include all documentation in compliance with the applicable standards.
2.7.2Research record drawings to obtain utility and pavement information that is not visible from the surface. Provide notes indicating the sources and any limitations or assumptions of the data.
2.7.3The survey shall provide all data needed to design and construct the project. The survey shall also include sufficient documentation and analysis of the existing drainage to allow for new proper drainage design, including areas that will be affected by new drainage patterns and surfaces which new construction will abut or adjoin.
2.7.4Include x, y, and z coordinates to the nearest 0.005 meters, dimensions, material, and basic characteristics of all features within the project site limits, as well as all features outside of the project site limits that will affect the design and construction of the project. Provide a copy of the survey in CAD, in addition to the paper/electronic requirements of the Design Analysis.
2.7.5Locate and show on the topographic survey the following information:

a. Property boundary, public right of way, and easements. Include the address numbers, street names, and easement records.

b. Survey monuments. Include description.

c. Spot elevations covering the entire survey limits showing high points, low points, grade changes, and at sufficient intervals to represent the general character of the terrain.

d. Contours in intervals of 0.10 meters.

e. Buildings and other miscellaneous structures. Provide finish floor elevation of existing finished floor.

f. Surface Drainage Features. Indicate normal water level for water bodies.

g. Utility lines and structures. Include rim elevations and invert elevations for utility structures; identification of lines as underground or aboveground; pipe sizes and materials.

h. Fences. Include height, material, and direction of outrigger, gate locations and types.

i. Trees/Woods: In wooded areas that trees are to be protected, locate outside drip line of wooded area, and include general density and type of trees. For wooded areas with proposed tree removal, identify trees per Host Nation permitting requirements. Where selective clearing will be proposed, locate trees over 150 millimeter diameter at chest height, and include tree species, diameter at chest height, and dripline diameter.

j. Geotechnical boring locations.

k. Locate environmentally sensitive areas (determined and marked by others).

l. North arrow and scale of drawing.

m. Legend depicting the symbols and abbreviations used on the drawing.

n. Horizontal and vertical coordinate systems, date of survey, licensed surveyor name and license number.

2.7.6 Upon completion of construction, the original survey shall be updated with an As-Built survey of the site as constructed. The As-built survey shall be submitted to the COR for approval.

Reference UFC 3-201-01, Civil Engineering, Section 2-2.2-SURVEYING for survey requirements. Use the Universal Transverse Mercator (UTM) coordinate system. The vertical coordinate system must be based on sea level.

2.8 SITE LAYOUT

2.8.1 MOBILIZATION & STAGING

The Contractor shall provide mobilization and demobilization of all vehicles, material, and construction equipment to the project area. The Contractor shall prepare the site and perform all necessary preparatory work for digging and excavation. A mobilization plan, including the location of the Contractor’s proposed staging area(s), shall be submitted to the COR for approval. Reference RFP Section 00 74 00-SPECIAL CONDITIONS for other mobilization, access, and permit requirements.

Reference RFP Section 00 74 00-SPECIAL CONDITIONS for other mobilization, access, and permit requirements.

Locate the proposed building and other improvements necessary for completion of this project on Attachment #2 – Conceptual Site Plan. Amend the site layout as determined by the site-specific constraints, the owner’s preferences, accessibility, future expansion, and opportunities that are identified and evaluated as part of the Contractor’s scope of work. Locate the proposed building a minimum of 3 meters away from existing buildings. Locate the latrine a minimum of 30m from the proposed school.

The Contractor is responsible for all aspects of the project whether they are shown on the concept layout plan or not.

2.8.2 PERMITTING

The contractor shall be responsible for obtaining all applicable permits for site clearing, digging, demolition, transport, and disposal of waste material generated by this work effort, and/or any other permits that may be required

2.9 DEMOLITION

Remove existing structures, utilities, pavement, vegetation, and any other features to construct the proposed improvements.

Any trees within the site construction areas and closer than 3 m to the new facilities shall be removed, including rootstocks, to a depth of 50 cm below final grade. Any dead trees within the site construction areas shall also be removed. The Contractor shall coordinate with the end-users and villagers prior to off-site disposal of any removed trees. Any trees, shrubs, rootstocks, and miscellaneous wood material that the villagers do not want to use, shall be disposed of off-site at the Contractor’s expense.

Any contaminated soils discovered will require special testing and disposal per Host Nation requirements.

2.9.1 CONSTRUCTION LIMITS

Do not disturb the project site beyond necessary for installation of proposed construction. Do not disturb any areas past the site’s property line. Show demolition work and limits of disturbance in the drawings. Stake-out the limits of disturbance on-site with temporary fencing before beginning construction.

2.9.2 ITEMS TO REMAIN IN PLACE WITHIN CONSTRUCTION LIMITS

Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the COR. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the COR prior to performing said work.

2.9.3 TREES

Protect trees larger than 150mm diameter at chest height within the project site which might be damaged during construction, with a 1.8 m high fence around the dripline of the tree(s), which is assumed to be the extent of the tree’s roots. Mitigate for tree removal per Host Nation Requirements.

2.9.4 UTILITIES

Any existing utilities encountered within the site boundary that are impacted by this project must be protected, or relocated if protection is not feasible. Relocate existing utility mains outside the structural zone of influence of proposed buildings and structures. Utilities impacted by this project that require decommissioning, or that are already out of service, must be removed up to the utility main and capped. Manholes or underground structures to be abandoned must be removed to a minimum depth of 50 centimeters below finish grade. Fill abandoned manhole or structure per Section 2.10 - EARTHWORK requirements.

2.9.5 DUST, DEBRIS, AND EROSION CONTROL

Prevent the spread of dust, debris, and erosion from the project site. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, flooding, erosion, or pollution. Remove dust, dirt, and debris from work areas daily. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.

2.10 EARTHWORK

The Contractor shall perform all earth work necessary for the installation of the proposed improvements

2.10.1 PLANS AND SPECIFICATIONS

The Contractor is responsible for defining earthwork requirements in the plans and specifications. Include requirements for satisfactory material, borrow material, structural fill, topsoil, utility trenches, replacement and improvement of on-site soils, soil compaction (for subgrades of structures and latrine areas), compaction for utility trenches, maximum lift depths, density testing frequency, maximum temporary and permanent slopes, and engineered support systems. The earthwork requirements must not conflict with the recommendations in the Contractor-provided geotechnical report.

2.10.2 CONTAMINATED SOIL

Inspect and test all soil according to Host Nation requirements. If hazardous materials are discovered, cease excavation, secure the area, and notify the COR for further guidance.

2.10.3 CULTURAL RESOURCES

Cultural resources, such as archaeological remains are not expected but may be uncovered during excavation operations. If suspected cultural remains are found, cease excavation, secure the area, and notify the COR for further guidance.

2.10.4 SATISFACTORY MATERIAL

Remove and save topsoil (approximately first 15 centimeters of excavation). When restoring the site to finish grade, place topsoil back in excavated areas that do not include proposed structures. Excavated material (below topsoil), if satisfactory for reuse per the geotechnical report, may be used on the project site where fill is required. Unsatisfactory material, and surplus excavated material not required for fill, must be disposed of offsite, and is the responsibility of the Contractor. Borrow material may be required for construction from sources off site. Borrow materials are to be free of hazardous materials and contaminants. Any soil brought in from off-site sources must be certified clean.

2.10.5 FILL AND BACKFILL COMPACTION

In the absence of Host Nation standards and geotechnical recommendations, fill and backfill must be placed in layers of 20 centimeters loose thickness and compacted to a minimum 95% of the maximum dry density as determined by Host Nation test method equivalent to ASTM D-1557 (Modified Proctor test). Provide density tests on all lifts at a frequency of 1 test per 40 square meters for foundations, and 1 test per 30 meters utility trench. Round up to nearest whole number (i.e. a 25 square meter foundation requires one test). The location of all tests must be selected by the Contractor’s geotechnical engineer, and copies of all test results must be furnished to the COR. All structure foundation excavations must be inspected and approved by the Contractor’s geotechnical engineer prior to placing concrete. Repair earthwork areas as recommended by the Contractor’s geotechnical engineer, and approved by the COR.

2.10.6 Provide engineered soil support systems (i.e. shoring) as required for the construction of the proposed improvements. The Contractor is responsible for all dewatering necessary for earthwork.

2.10.7 SITE GRADING

Provide site grading that directs storm water runoff away from buildings and structures either by drainage systems or by grading as follows:

a. Finished grades of earth/grass/gravel surfaces adjacent to buildings and structures must slope away from all exterior edges with a minimum slope of 5% for the first 2 meters.

b. Ditches, swales and open channels will be provided as required, and have a minimum longitudinal gradient of 0.5%.

c. Finished grades of concrete surfaces adjacent to buildings and structures must slope away from all exterior edges with a minimum slope of 2% for the first 2 meters.

d. Finished grades must not create stagnating water or ponding anywhere on the project site, nor create ponding on adjacent properties. Provide storm improvements if ponding is unavoidable.

e. Set finished floor elevations a minimum of 45 centimeters above finished grade at the perimeter of the building, with the exception of finished grade at entry points.

f. Set building finish floor elevations at a minimum of 30 centimeters above the local 100 year flood level.

Site grading around the building must meet local accessibility guidelines.

2.11 UTILITIES

This section applies to all project underground utilities located outside the building, including but not limited to, sanitary sewer, water supply, storm drainage, electrical, communications, gas, liquid fuel, and heat.

In the absence of Host Nation requirements, design utilities per IBC and UFC 3-201-01, Civil Engineering. Provide utility line depths, bedding, and backfill as required by applicable standards and geotechnical recommendations. Minimum cover over pipes is 0.6 meters or sufficient to support imposed dead and live loads for the pipe materials used, whichever is more stringent. Place plastic warning tape along the route of the buried pipe after installation at a height of 0.3 meters above the pipe.

2.11.1 STORM SYSTEM

The Contractor shall provide the most appropriate drainage system for the site, in accordance with host nation and local government regulations. The Contractor will take into account the information gathered from the site survey, local climate and rainfall data, 10 year return storm frequency, and any geotechnical/hydrological investigation.

Provide drainage ditches, swales, or other gravity-driven drainage features to divert surface runoff away from structures. Design drainage features to eliminate ponding and to be protected against erosion. Provide 2 meters of gravel erosion protection around the perimeter of the proposed school building.

The Contractor shall take special care to avoid poor site drainage, stagnant water, and ponding anywhere on the project site in order to minimize the likelihood of water-borne diseases, which are prominent in this region.

Connect building roof gutters and downspouts to a rainwater tank (5000 liter). Locate tank out of pathways and windows. Provide a spigot at the bottom of each rainwater tank. Below the spigot, provide a splash block that will drain water away from building foundation a minimum of 3 meters per site grading requirements. Provide an overflow system from the tank to splash blocks that drain away from foundation a minimum of 3 meters per site grading requirements. Provide insect screens to all open orifices to the tank system. Provide UV resistant tanks. Provide concrete foundation to support rainwater collection tank, and install the bottom of the tank a minimum of 60 centimeters above finish grade. Provide structural tie downs for the tank. Provide an opening for cleaning and allow access into the tank. Provide system in order to divert first flush from the roofs that may be contaminated with dust, animal droppings and dirt so that it does enter the tank. Provide sign next to tap that shows a pictogram “not for drinking”. Sign must be firmly fastened aluminum or other durable weather resistive material (no adhesive sticker allowed).

2.11.2 SANITARY SYSTEM

The project utilizes VIP latrine cabin sanitary septic system as discussed in SOW Section 3.0 – ARCHITECTURE. If the Geotechnical Investigation determines that groundwater is less than 1 meter deep, raise the latrine per WHO Fact Sheet 3.5. In the absence of Host Nation standards, design the latrine disposal system per WHO Fact Sheet 3.5.

2.12 LANDSCAPING

Existing trees within the site construction areas that are to remain in place shall be properly protected during construction work. Any trees or shrubs that are to remain in place and are damaged by the Contractor shall be, irrespective of the degree of damage, replaced in kind and number.

The Contractor shall provide a landscaping plan showing, at a minimum, the exact existing landscaping to be removed and the location and limits of areas to be restored and/or repaired which were damaged by contractor’s work effort, if any. Restoration plan will include, at a minimum, a plan for re-establishment of ground cover consistent with the surrounding area. These items shall be indicated on the new site plan.

3.0 ARCHITECTURAL

3.1 PROJECT DESCRIPTION

Design and construction work of Kpangalam Kindergarten in Sokodé, Togo, Africa.

Design and then perform the construction work of one-story, solid masonry / concrete building that will serve as a kindergarten. The kindergarten building will contain one (1) new building with 4-classrooms, one (1) office, one (1) storage room, one (1) battery room, and one (1) exterior terrace; two (2) one (1) new 8-stall Ventilated Improved Pit (VIP) latrine building (4 stalls for girls/ 4 stalls for boys total), and elevated water tank with eight (8) taps for handwashing outside new kindergarten building.

Extensive coordination is required between the architectural work and the civil, geotechnical, structural, fire protection, mechanical, and electrical requirements of this project.

3.1.1 DESIGN

Provide a design and construction package that uses the space allocations, functional adjacencies, design details, and features given or referenced in this RFP. The design must incorporate all referenced codes and regulations. The Contractor is responsible for creating additional details as required to complete a full design. All details must conform to the requirements of this RFP and are subject to the approval of the COR. A schematic design has been attached for reference. The schematic plans are provided for diagrammatic purposes only and do not necessarily represent an approved floor plan or design. The Contractor is responsible for providing a design that meets all requirements of the User and the codes and criteria referenced in this Statement or Work.

3.1.2 DESIGN SUBMITTALS

Provide all architectural submittals after contract award in accordance with Section 01 33 16 DESIGN AFTER AWARD and Section 01 33 00 SUBMITTAL PROCEDURES. Prepare and submit the documents listed below at the submittals indicated.

3.1.2.2 65% DESIGN SUBMISSION

Include the following drawings and reports as applicable to the project:

a. Code Summary – Provide a tabular code compliance summary [per UFC 3-600-01].

b. Life Safety Plans – Provide plans depicting smoke/fire resistance ratings, egress routes, dead-end corridors, exits, and other aspects of life safety pertaining to the design.

c. Floor Plans – Provide all floor plans, indicating room names, areas, and basic dimensions, scale 1:50.

d. Ceiling Plans – Provide reflected ceiling plans for all rooms, indicating ceiling materials and fixtures, scale 1:50.

e. Building Elevations – Provide all building elevations indicating all exterior materials.

f. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.

g. Building Section – Indicate heights of critical building elements.

h. Wall Section - Provide a typical interior and exterior wall section for each building – describe wall materials.

i. Interior Elevations – Provide interior elevations of all Latrines, indicate critical heights of surfaces and plumbing fixtures and describe all materials and finishes.

j. Pre-Final Design Analysis – Provide a narrative explaining the design and indicating how the design and materials meet the requirements of this SOW.

k. Pre-Final Specifications – Provide detailed explanations of requirements for all performed work or provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.

3.1.2.3 95% DESIGN SUBMISSION

The 95% Submittal provides a complete and final set of contract documents essentially ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include the following drawings and reports as applicable to the project:

a. All documents from the 65% submittal updated to incorporate 65% review comments.

b. Floor Plans – Provide all floor plans, indicating room names, areas, and dimensions, scale 1:50.

c. Building Elevations – Provide all building elevations indicating all exterior materials.

d. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.

e. Building Section – Indicate heights.

f. Wall Sections – Provide sufficient wall section(s) to indicate all materials and different conditions.

g. Section and Plan Details – Provide details of critical building intersections.

h. Window and Door Schedule – Provide a schedule of all windows and doors, indicating sizes, hardware, and operation.

i. Stair Section and Details.

j. Finish Schedule – Indicate all proposed finishes.

k. Final Design Analysis – Provide a finalized narrative describing all work to be performed on the project and how it meets the functional and code requirements of the project. Provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.

l. Final…