W912GB19F0026_0003_Amendment.pdf
PDF 525 KB Posted
- Attached to
- FY 19 Poland JOC Federal contract opportunity
- Solicitation number
- W912GB19R0026
About this file
This pre-solicitation announcement and related documents outline requirements for a firm-fixed-price indefinite-delivery, indefinite-quantity job order contract to provide sustainment, restoration, and modernization services in Poland. The U.S. Army Corps of Engineers Europe District will issue a solicitation on or around March 1, 2019 for a single-award IDIQ JOC with a one-year base period and four one-year options and a maximum value of $49.95 million to accomplish projects such as maintenance, repair, and facility upgrades. Offerors must monitor the website for solicitation details and amendments. The best value source selection will evaluate technical and price factors, with an anticipated award date of May 2019. The minimum task order value is $2,000 and maximum is $2.25 million.
W912GB19R0026 Amendment 0003
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JOCPOLAND1
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose if this amendment is to incorporate changes to Section 00 22 00 show n in RED. All other terms and conditions remain unchanged.
See continuation pages for details.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 01-Mar-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912GB19R0026
X 9B. DATED (SEE ITEM 11)
14-Feb-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
01-Mar-2019
CODE
CONTRACTING DIVISION
US ARMY CORPS OF ENGINEERS
KONRAD ADENAUER RING 39
D-65187 WIESBADEN GERMANY
WIESBADEN 65187
W912GB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912GB19R0026
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 22 00 - SUPPLEMENTARY INSTRUCTIONS
The following have been modified:
EVALUATION FACTORS
A. BASIS FOR AWARD
The Government will utilize the Best Value Tradeoff Process for Source Selection in accordance with FAR 15.101-1 to determine best value. This process permits tradeoffs among cost or price and non-cost factors. Award will be made to the Offeror proposing the combination most advantageous to the Government based upon an integrated assessment of the proposals received, including the evaluation factors described in paragraph B of this section. To receive consideration for award, a rating of no less than “Acceptable” must be achieved for all non-price factors. The Government considers it to be in its best interest to allow award to other than the lowest priced Offeror or other than the highest technically rated Offeror. The perceived benefits of the higher priced proposal shall merit the additional cost, and the rationale for tradeoffs must be documented in the file in accordance with FAR 15.406.
B. FACTORS TO BE EVALUATED
The Government Source Selection Team (SST) will evaluate proposals according to the factors listed below. Offerors are required to provide data addressing all stated factors in a clear and understandable format. If an Offeror does not have data relating to a specific factor, it shall be clearly stated in the proposal. Proposals that do not clearly address all factors may be considered unacceptable and may not receive further consideration. A detailed explanation of the criteria for the evaluation for each factor is set forth under the EVALUATION APPROACH paragraph below.
1. Non-Price Factors: The purpose of the non-price factors is to assess whether the Offeror’s proposal will satisfy the Government’s minimum requirements. A proposal receiving an unacceptable rating on one or more non-price factors will result in an overall unacceptable rating and be ineligible for award.
Factor 1 – Corporate Relevant Specialized Experience Factor 2 – Past Performance Factor 3 – Management Approach
2. Price Factor: The purpose of the price factor is to ensure a fair and reasonable price. The price factor will be evaluated differently than the non-price factors, and is subject to Contract Pricing policies as set forth in FAR Subpart 15.4.
Factor 4 – Unit Price Book (UPB) Coefficients
3. Relative Importance of the Evaluation Factors. In accordance with FAR 15.304(e), the non-priced factors, when combined, are significantly more important than approximately equal in importance to price.
In addition, of the non-price factors, Factor 1 Experience is more important than Factors 2 Management
Approach Past Performance and 3 Past Performance Management Approach, which are of equal importance to one another.
C. EVALUATION APPROACH
All proposals shall be evaluated by the Source Selection Team (SST).
1. DEFINITIONS. The following definitions are provided to assist evaluators in the evaluation process:
Strength. An aspect of an Offeror’s proposal that has merit or exceeds specified performance or capability requirements in a way that will be advantageous to the Government during contract performance.
Significant Strength. An aspect of an Offeror’s proposal that has appreciable merit or appreciably exceeds specified performance or capability requirements in a way that will be appreciably advantageous to the Government during contract performance.
Weakness. A flaw in the proposal that increases the risk of unsuccessful contract performance. See FAR 15.001.
Significant Weakness. A flaw in the proposal that appreciably increases the risk of unsuccessful contract performance. See FAR 15.001.
Deficiency. A material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. See FAR 15.001.
Clarification. Limited exchanges between the Government and Offerors that may occur when award without discussions is contemplated. See FAR 15.306.
Adverse Past Performance. Past performance information that supports a less than satisfactory rating from sources where the information is from other than formal rating systems such as “Past Performance Information Retrieval System” (PPIRS) or “Federal Awardee Performance and Integrity Information System.” (FAPIIS).
2. TEAM ARRANGEMENTS. As described in FAR Subpart 9.6, it is the Government’s policy to recognize the integrity and validity of contractor team arrangements. For a teaming arrangement to be recognized for purposes of source selection evaluation and the application of non-price factors, there must be full disclosure of the teaming arrangement and company relationships in the team's proposal.
The proposal must include a narrative that explains the major or critical aspects of the work to be performed by each team member (to include identification of team members, a full delineation of roles and responsibilities of team members, and the duration of the agreement, etc.). The proposal must also include an agreement that has been executed between/among all team members. The proposal and agreement must be consistent; substantive inconsistencies between the proposal and agreement may be construed against the Offeror. The timely submission of the executed teaming agreement prior to award shall be a precondition to a finding of responsibility. NOTE: For the purposes of evaluation under this RFP, if one of the parties in a teaming arrangement possesses relevant experience and/or past performance, the experience and/or past performance of that firm will be considered as the experience and/or past performance of entire teaming arrangement.
a. Joint Ventures (JV). If the Offeror is a JV, the Offeror must provide evidence of a legally binding JV agreement, which creates legal responsibility on the part of all contractors in the JV. Further details surrounding requirements related to the JV agreement are provided in the section 00 21 00.
b. Other Teaming Arrangements. In the case of prime-sub teams (e.g., if an Offeror proposes to utilize a “key subcontractor”), the agreement must reflect that the prime contractor is vested with control and responsibility for the daily management of the work, and that it remains responsible for contract performance, including those items allocated to a subcontractor on the team. Offerors are reminded that the prime contractor remains fully responsible for contract performance, regardless of any team arrangement between the prime contractor and its subcontractors. However, consistent with FAR 9.104- 4, the Government may consider the responsibility of subcontractor team members when it may adversely affect the prospective prime contractor’s responsibility or when it is in the Government’s interest to do so.
Finally, any resulting subcontract(s) may not deviate from the substantive provisions of the teaming agreement. The failure of the Offeror to perform with one or more subcontractors on a recognized team may be grounds for termination for default. There can be no substitution of subcontractor team members except that, in the case of a prime-sub team arrangement, the Government may (in its sole discretion and without any obligation whatsoever), at the request of the prime, permit the substitution of a subcontractor with equivalent or greater capability for a subcontractor on the identified team. Note: Only a Contracting Officer can approve such a change after contract award.
3. Recent and Relevant Contracts. For Factor 1 evaluation purposes, the definition of a recent and relevant contract must meet the following conditions:
a. The contract was awarded to the Offeror as the prime contractor. In the case of an Offeror that is a JV, the contract must have been awarded to either member of the JV as the prime contractor. In the case of an Offeror that is a prime-sub team (see previous paragraph on teaming arrangements), the contract must have been awarded to the prime or the key sub-contractor.
b. The contract was completed no earlier than five calendar years before the closing date of the RFP or has been ongoing for at least one year before the closing date of this RFP.
c. The contract is fundamentally for building renovations that include floors, doors, walls, windows, external facades, repairs to roofs; repair/replacement of major building systems such as electrical, mechanical, HVAC; Civil work, that includes concrete/asphalt roads and pavements, earthwork, and drainage structures; and environmental work, such as hazardous material abatement and disposal.
d. Projects with a minimum cost of €50,000. to €2,500,000.
4. Non Price Factors:
Data provided in response to the non-price factors described below shall be included in Volume I, “Non-Price Proposal.”
a. Factor 1: Corporate Relevant Specialized Experience. The SST will evaluate Offerors under this factor to determine the depth and breadth of the Offeror’s experience that demonstrates the ability to accomplish the work specified under this solicitation. Offerors must submit no more than five projects meeting the criteria in Paragraph C.3.Recent and Relevant Contracts. The Experience Information Sheet shall not exceed 4 pages per contract.
For Offerors submitting as a Teaming Arrangement, each firm/contractor in the Teaming Arrangement, whether JV or prime/key sub, shall submit a minimum of one (1) project. If more than five projects are submitted by an Offeror, the Government will only review the first five (5) projects. The projects will be reviewed in the order in which they are received in Offeror’s submitted proposal.
For the purposes of evaluation under this factor, more consideration will be given to an Offeror that demonstrates greater depth and breadth of experience that involve the following (listed is in no order of importance).
i. Projects that demonstrate experience working in Poland.
ii. Projects that demonstrate experience working in European Union countries.
iii. Projects that demonstrate experience working with the United States Government.
iv. Projects demonstrating experience with multiple projects in multiple trades.
v. Projects demonstrating experience working with proposed Key Subcontractors and/or the proposed JV Partners.
NOTE: Offerors are cautioned that the SST may assess weaknesses against experience examples that are not verifiable, and/or where the Offeror or their proposed subcontractor were subcontractors and their role in the project was minor in comparison to the whole project.
For this factor, Offerors will be assigned a combined technical/risk rating from the following table, based on the evaluation of the Offeror’s proposal in accordance with the requirements of the solicitation:
NON-PRICE FACTOR COMBINED TECHNICAL/RISK RATINGS
Color Rating Description Blue Outstandin g Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is very low.
Purple Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.
Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Red Un-acceptable
Proposal does not meet requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.
Risk levels as described in the adjectival ratings in the combined technical/risk rating table will be assessed according to the following guidelines:
NON-PRICE FACTOR TECHNICAL RISK RATING
Adjectival
Rating Description
Low
Proposal may contain weakness(es) which have little potential to cause disruption of schedule, increased cost or degradation of performance. Normal contractor effort and normal Government monitoring will likely be able to overcome any difficulties.
Moderate Proposal contains a significant weakness or combination of weaknesses which may potentially cause disruption of schedule, increased cost or degradation of performance.
Special contractor emphasis and close Government monitoring will likely be able to overcome difficulties.
High Proposal contains a significant weakness or combination of weaknesses which is likely to cause significant disruption of schedule, increased cost or degradation of performance. Is unlikely to overcome any difficulties, even with special contractor emphasis and close Government monitoring.
Unacceptab le
Proposal contains a material failure or a combination of significant weaknesses that increases the risk of unsuccessful performance to an unacceptable level.
b. Factor 2: Past Performance. The SST will evaluate Offerors under this factor to determine how likely Offerors will be successful on the work under this solicitation. The Offeror's past performance will be evaluated based on performance on projects submitted under Factor 1 Experience, as well as other projects not submitted by the Offeror, to include the past performance of any Subcontractors or JV partners the Offeror may have submitted. The Government’s past performance evaluation will include an assessment of past performance on any and all relevant past performance (as defined below in paragraphs (c)(i) and (c)(ii). NOTE:
The evaluation for this factor uses a much broader definition of what is relevant as compared to Factor 1 Experience. This assessment will be based on consideration of all relevant facts and circumstances, including any trends in past performance. Key focus areas will include the following (see PPQ):
Quality Schedule/Timeliness of Performance Customer Satisfaction Management/Personnel/Labor Cost/Financial Management Safety/Security
Offerors shall provide a completed performance record for the same contracts submitted for consideration under Factor 1, Experience. If available, a completed record from the Contractor’s Performance Assessment Reporting System (CPARS) will be accepted for evaluation under this factor. An interim completed CPARs rating will be considered if a final record is not available. If a completed CPARS record is not available at all, Offerors shall complete and provide a Past Performance Questionnaire (PPQ). The completed PPQ shall not exceed 4 pages per contract.
PPQ Instructions: The Offeror shall complete Blocks 1-4 of the provided Past Performance Questionnaire and have the Contracting Activity and the Technical Representative responsible for the past/current contract complete the remainder of the contract. Offeror shall ensure correct phone numbers and email addresses are provided for the client point of contact. Completed Past Performance Questionnaires shall be submitted with the proposal. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact via email no later than the closing date of this RFP.
Also include performance recognition documents received for the Factor 1 projects such as awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition. Offerors shall provide a copy of any Cure Notices or Show Cause Letters received by the Offeror for each submitted project and a description of any corrective action implemented by the Offeror. The Offerors shall indicate if any of the contracts listed were terminated and the type and reasons for the termination.
The Government may verify information provided by the Offeror with any source available and has the right to contact points of contact other than those listed by the Offeror. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS), including Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror. In rating past performance, the Government may consider available past performance information on predecessor companies, or employment histories of key personnel, or committed subcontractors performing key elements of the project.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
Note: In the case of an Offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the Offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.304(a)(2)(iv)). If an Offeror has no relevant past performance history, the Offeror must affirmatively state that it possesses no relevant directly related or similar past performance.
For the Past Performance evaluation, the evaluation will include a relevancy rating and confidence assessment, as detailed below.
i. Past Performance Relevancy Rating. The first aspect of the past performance evaluation is to determine how relevant a recent effort accomplished by the Offeror is to the effort to be acquired through the source selection. Relevancy is not separately rated, however. Common aspects of relevancy include similarity of service/support, complexity, dollar value, contract type, and degree of subcontract/teaming:
Past Performance Relevancy Ratings:
Rating Definition
Very Relevant
Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant
Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant
Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
ii. Performance Confidence Assessment. The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts. In conducting the confidence assessment, each Offeror shall be assigned one of the ratings identified below:
Performance Confidence Assessments:
Rating Definition
Substantial Confidence
Based on the Offeror’s recent/relevant performance record, the Government has a high expectation that the Offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the Offeror’s recent/relevant performance record, the Government has a reasonable expectation that the Offeror will successfully perform the required effort.
Neutral Confidence
No recent/relevant performance record is available or the Offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The offeror may not be evaluated favorably or unfavorably on the factor of past performance.
Limited Confidence
Based on the Offeror’s recent/relevant performance record, the Government has a low expectation that the Offeror will successfully perform the required effort.
No Confidence
Based on the Offeror’s recent/relevant performance record, the Government has no expectation that the Offeror will be able to ‘successfully perform the required effort.
c. Factor 3: Management Approach. Evaluators will determine whether the Offeror’s management approach is logical, feasible, and demonstrates a comprehensive understanding of the complexity of managing the contract. The information shall provide charts, tables, sketches and maps as needed to make the work approach understandable. The narrative shall not exceed 10 pages. In performing the evaluation, the Government will evaluate the following:
i. Whether the proposal clearly delineates lines of authority, and communication with the Government, on the organizational chart organized in a precise and logical manner, including all offices involved with the management of the contract, including Key Subcontractors and JV partners.
ii. The extent to which the proposal describes a reasonable and logical plan for the performance of five (5) simultaneous task orders that illustrates a detailed understanding of multiple task order requirements, proposes personnel that meet the specification requirements, and provides subcontracting and staffing plan.
For this factor, Offerors will be assigned a combined technical/risk rating from the following table, based on the evaluation of the Offeror’s proposal in accordance with the requirements of the solicitation:
NON-PRICE FACTOR COMBINED TECHNICAL/RISK RATINGS
Color Rating Description Blue Outstanding Proposal meets requirements and indicates an exceptional approach and understanding of the requirements. Strengths far outweigh any weakness. Risk of unsuccessful performance is very low.
Purple Good Proposal meets requirements and indicates a thorough approach and understanding of the requirements. Proposal contains strengths which outweigh any weaknesses. Risk of unsuccessful performance is low.
Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance. Risk of unsuccessful performance is no worse than moderate.
Yellow Marginal Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weaknesses which are not offset by strengths. Risk of unsuccessful performance is high.
Red Un-acceptable
Proposal does not meet requirements and contains one or more deficiencies.
Proposal is unawardable.
Risk levels as described in the adjectival ratings in the combined technical/risk rating table will be assessed according to the following guidelines:
NON-PRICE FACTOR TECHNICAL RISK RATING
Adjectival Rating
Description
Low
Proposal may contain weakness(es) which have little potential to cause disruption of schedule, increased cost or degradation of performance. Normal contractor effort and normal Government monitoring will likely be able to overcome any difficulties.
Moderate Proposal contains a significant weakness or combination of weaknesses which may potentially cause disruption of schedule, increased cost or degradation of performance.
Special contractor emphasis and close Government monitoring will likely be able to overcome difficulties.
High Proposal contains a significant weakness or combination of weaknesses which is likely to cause significant disruption of schedule, increased cost or degradation of performance. Is unlikely to overcome any difficulties, even with special contractor emphasis and close Government monitoring.
Unacceptab le
Proposal contains a material failure or a combination of significant weaknesses that increases the risk of unsuccessful performance to an unacceptable level.
5. Price Factor: Data provided in response to the non-price factors described below shall be included in Volume II, “Price Proposal and Administrative Matters.” Price will not be rated, but will be considered in establishing the competitive range prior to discussions (if held) and in making the final determination of best value. The Government will perform price analysis on all proposals received in accordance with FAR 15.404-1 to determine completeness, balanced pricing, reasonableness, and understanding of the work.
a. Factor 4, Unit Price Book (UPB) Coefficients. Offerors are required to price for all items for the base and all option ordering periods. See the RFP Section 01 11 00 for a definition of UPB Coefficients. See also the attached sample Task Order Proposal for an explanation of how the coefficients will be applied per Task Order. Prices proposed will be analyzed to determine if the prices are unbalanced. If the price analysis indicates that an offer is unbalanced the contracting officer shall consider the risks to the Government associated with the unbalanced pricing. An offer will be rejected if the lack of balance poses an unacceptable risk to the Government. From a price perspective, an offer’s overall value will be assigned as being the sum of all the CLINs added together.
b. The Government intends to evaluate all options and has included the provision FAR 52.217-5, Evaluation of Options (JUL 1990) in the Solicitation. In accordance with FAR 52.217-5, evaluation of options will not obligate the Government to exercise the option(s). Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
(i) Comparison of proposed prices received in response to the Solicitation.
(ii) Comparison of proposed prices with the independent Government cost estimate.
(iii) Comparison of proposed prices with available historical information.