B.04.09_Amendment_0001_.pdf

PDF 139 KB Posted

Attached to
Procure and Install Freezer and Combi Oven at Livorno ES-MS
Solicitation number
W912GB19Q0009
Issued by

About this file

Amendment 0001

View the file

Other files

File Type Posted
A.02.16_SOW_Revised.pdf PDF
Amendment_0002.pdf PDF
Solicitation_Conformed_Copy.pdf PDF
W912GB19Q0009.pdf PDF
A.02.16_SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to answ er requests for information, add optional items to the project, add Option clauses, and move the quote due date to 1200 PM on 4 September 2019. All other aspects of this solicitation remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 29-Aug-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912GB19Q0009

X 9B. DATED (SEE ITEM 11)

13-Aug-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

29-Aug-2019

CODE

CONTRACTING DIVISION

US ARMY CORPS OF ENGINEERS

KONRAD ADENAUER RING 39

D-65187 WIESBADEN GERMANY

WIESBADEN 65187

W912GB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912GB19Q0009

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 30-Aug-2019 12:00 PM to 04-Sep-2019 12:00 PM.

SUPPLIES OR SERVICES AND PRICES

CLIN 0002 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Job OPTION Two Year Warranty

FFP

Contractors are to provide pricing for a standard Two Year Warranty on the deliverables. Provide documentation as to why or why not this warranty is feasible in the quote as well as the terms and conditions. One of the two options will be exercised at award based upon what is most favorable to the government.

FOB: Destination

NET AMT

CLIN 0003 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0003 1 Job OPTION Ten Year Warranty

FFP

Contractors are to provide pricing for an extended Ten Year Warranty on the deliverables. Provide documentation as to why or why not this warranty is feasible in the quote as well as the terms and conditions. One of the two options will be exercised at award based upon what is most favorable to the government.

FOB: Destination

NET AMT

INSPECTION AND ACCEPTANCE

The following Acceptance/Inspection Schedule was added for CLIN 0002:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

N/A N/A N/A Government

The following Acceptance/Inspection Schedule was added for CLIN 0003:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

N/A N/A N/A Government

The following have been added by reference:

52.217-5

The following have been added by full text:

RFI

Q1. Reference W912GB19Q0009, page 8 of 41, 52.000-4090 S.O.A.s, it is stated: “the offerors must comply with D.P.R. n.34 of 25 January 2000…” and must furnish documentation within their proposal. In addition, “offerors must provide their S.O.A reflecting eligibility to bid on the work solicited, […] the prevailing work categories and classification are described in the pre-solicitation notice and in this solicitation”. There is no pre-solicitation notice regarding this opportunity and nowhere else in the solicitation there are specifications about S.O.A., please confirm that no S.O.A. qualification are required.

Government Answer:

Q2. Reference Scope of Work, Freezer and Oven requirements: “manufacturer’s warranty shall be a minimum of 10 years”. In the industrial and commercial European market, the warranty is of 1 year only (IAW legal requirements). Manufacturers do not extend the standard warranty up to 10 years. A revision of this requirement would allow all bidders to be in compliance with SOW based upon actual up to date standards. Could the Government revise this requirement accordingly?

Government Answer: With regard to warranty, there are different requirements depending on the region that the products are purchased from. Gewaehrleistung is required by law (Buergerliches Geseztbuch) to have a 24 month warranty period for new products. For Garantie, it is offered by the seller, normally for 12 to 24 months. The same appears true under Italian Law (Codice del Consumo). As such, two options have been added to the solicitation. Please submit a price for a normal warranty (2 years) and one which provides an extended guarantee (10 years). Please provide a statement of the conditions and terms for each warranty. If one or neither warranties are feasble, provide the documentation as to why with the proposal. Award to one of the options will be made at award based upon what is most favorable to the government.

Q3. Reference Scope of Work, Freezer requirements:

1. “injected high-density foam panel unit construction 120 mm plasticized galvanized steel”

2. “The freezer shall be rated for exterior use in the climate that it will be installed. It shall be weatherproof or provided with a secured protective covering to deflect weather from damaging the unit in accordance with the manufacturer’s installation instructions”.

Freezers equipped with high-density foam panels shall not be installed outdoors, actually the exterior use is not recommended, nor are they meant to be directly exposed to weather.

With the sentence “…provided with a secured protective covering…” is the Government expecting offerors to price the installation of a shelter on top of the freezer?

Government Answer: The primary intent of the scope of work is to provide an exterior walk-in freezer capable of achieving the specified temperature range identified. So long as the Offeror provides an exterior rated freezer, the Government does not anticipate a shelter. The intent of a protective covering would be limited to any weather sensitive components such as wiring connections, switches, etc. It is recommended that the Offeror submits his quote IAW the technical specifications clearly citing any variations in product requirements such as a different insulation type. This will be further reviewed during the submittal review process.

Q.4 If the answer to Q3 is Yes, please provide specific requirements for a protective cover in order to allow all bidder to quote the same item with their offer.

Government Answer: Not anticipated.

The following have been deleted:

52.000-4090

(End of Summary of Changes)