US Army Corps of Engineers Europe District
APO AE 09049
ar120
Statement of Work 34th Military Hospital Labor and Delivery Renovation
Freetown, Sierra Leone
Prepared by:
Design Section Engineering Branch
11 June 2018
01010 Statement of Work 34th Military Hospital Labor and Delivery Renovation
30MAY 2018 Page 2 of 43
SECTION 01010
STATEMENT OF WORK
SECTION TABLE OF CONTENTS;
1 GENERAL
2 CIVIL AND GEOTECHNICAL
3 ARCHITECTURAL
4 STRUCTURAL
5 ELECTRICAL
6 MECHANICAL
7 COMMUNICATIONS Not Applicable.
8 FIRE PROTECTION Covered by other sections.
ATTACHMENTS
Att. # 1 Location Map Att. # 2 Architectural Floor Plans –Existing and New Att. # 3 Structural Calculation Guideline Att. # 4 Dedication Plaque Att. # 5 Conceptual Site Plan Att. # 6 Rainwater Tank Example
1.0 GENERAL
1.1 PROJECT DESCRIPTION
The Request for Proposal (RFP) provides parameters for a design-build project for the renovation the Labor and Delivery Ward on the 34th Military hospital Complex in Freetown, Sierra Leone.
The work includes but is not limited to
- The complete replacement of the existing roof
- Partial renovation of the labor and delivery ward as described in the SOW
- Construction of the expansion of the existing ward as shown on the conceptual floor plan and described in this SOW Extensive coordination will be required between architectural, structural, electrical, mechanical and civil work.
The hospital is located in the vicinity of coordinates: Lat 08°27’48.78“N / Long 13°15’37.65“W.
Refer to Attachment #1 “Project Location Map” for the location of the site.
1.2 GENERAL REQUIREMENTS
The Contractor shall deliver fully functional, turnkey type facilities (without furniture) as described in this document. The work includes but is not limited to design, demolition, fabrication, delivery, installation, construction, and site work. The facility and the installed equipment shall be permanent construction.
The facility in this project shall be complete and usable to meet codes and technical and functional requirements per this Statement of Work (SOW). All design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, G&A and general conditions to complete this project as described in the SOW shall be included in the proposal price.
30MAY 2018 Page 3 of 43
These design and product requirements are minimum requisites. Compliance with the provisions of this section by subcontractors shall be the responsibility of the Contractor.
1.3 FUNCTIONAL AREAS AND FINISH REQUIREMENTS
The facility shall be designed and constructed as one-story building with masonry walls and sloped corrugated sheet metal roofs. Refer to Attachment #2 “Conceptual Architectural Floor Plan”.
The following areas shall be renovated:
1.3.1 Existing Building
- One (1) Surgical Suite app. 31 sm
- One (1) Washroom app. 4 sm
- One (1) Storage app. 4 sm
- Two (2) Labor/Delivery Rooms ea app. 12 sm
- One (1) Toilet app. 3 sm
- One (1) Electrical room
1.3.2 New Expansion Building
app. 4 sm
- One (1) NICU app. 35 sm
- One (1) Anesthesia / Nurse Preparatio app. 18 sm
- One (1) Nurse Breakroom app. 13 sm
- One (1) Toilet app. 3 sm
- One (1) Shower app. 3 sm
- One (1) Office app. 11 sm
- One (1) Battery room app. 6 sm
- Covered walkway app. 27 sm
New corridor connecting existing and new building app. 41 sm
Total net sm for the building 182 sm.
1.4 SUBMITTALS
Government approval is required for submittals with “G” designation; submittals not having a “G” are for Contractor Quality approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-05 Design Data
65% Pre-Final Design; G, DO
95% Final Design; G, DO
100% Corrected Final Design; G, D
1.4.1 DESIGN SUBMITTALS
Provide a complete design package at each milestone, as described in Specification Section 01 33 16 DESIGN AFTER AWARD. The milestones for this project are indicated above in Section 1.4 SUBMITTALS. The specific requirements of each milestone are described in each discipline-specific section of this Specification.
The Contractor shall submit all documents in electronic format (.pdf for text and calculations, .pdf and .dwg (AutoCAD, latest version) for drawings). See Specification 01 33 00 SUBMITTAL PROCEDURES for additional information.
1.5 MATERIALS AND EQUIPMENT
30MAY 2018 Page 4 of 43
Materials and products used, shall be durable, heavy duty industry standard. The equipment shall be the manufacturer’s standard quality and shall be compatible with all other equipment and materials within the system or assembly. Equipment and materials shall include all connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.
Each major piece of equipment shall have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number on a plate secured to the piece of equipment. The definition of a “major piece of equipment” shall be at the discretion of the COR.
1.5.1 LIFE-SPAN
Construction must have an expected life span of 25 years.
1.5.2 MAINTAINABILITY
Low maintenance materials and systems must be employed and shall be appropriate for the project climate and location.
1.5.3 OPERABILITY
Systems including but not limited to mechanical, electrical, communications, shall be simple to operate and easy to maintain.
1.5.4 STANDARDIZATION
The Contractor shall use standardized materials, products, equipment, and systems to minimize the requirements for replacement parts, storage facilities, and service requirements.
1.6 DESIGN DIMENSIONS
The design shall be developed using the metric system.
1.7 DESIGN CRITERIA
Project design, site facilities, utility systems and material standards shall be in accordance with the latest editions of the Host Nation building codes and recommendations from the World Health Organization (WHO). In the absence of Host Nation building codes the Contractor shall use the International Building Code (IBC) , and codes, technical standards, and regulations referenced in this RFP.
While this RFP references various source standards and specifications, all design documents are to meet Host Nation codes and requirements. It is the designer's responsibility to demonstrate that the Host Nation standard is equal to the cited standard or specifications being supplanted. The more restrictive standards shall apply when conflicts arise between the requirements of this RFP and any referenced or other applicable codes, standards or regulations. If equivalency cannot be met, the more stringent requirement shall be used and both codes shall be quoted verbatim in the Contractor’s correspondence to the COR.
Where specific standards are not indicated, the designer shall determine the required material and execution standards.
Provide an electronic copy of the local host nation standards and building codes in its original language as related to facility design and construction.
1.8 DESIGN CONFERENCES AND MEETINGS
The Contractor and the entire design team are required to participate in a design review conference for each design submittal. [Review conferences will be held only if necessary to expedite the review process. The Contractor may request a review conference, but the Government is under no obligation to conduct or participate in a review conference unless specifically identified in the contract documents.] The Contractor shall bring the personnel that developed the design submittal to any review conference.
30MAY 2018 Page 5 of 43
All design review conferences shall be held via teleconference or be reviewed and comments resolved via email.
The Contractor is responsible for taking meeting minutes during each design review conference and submitting to the COR for information and approval.
The Contractor is responsible for evaluating all Government comments prior to each design review conference. The Contractor is responsible for resolving all Government comments from each design phase. The Contractor shall provide annotated responses to each design review comment with the subsequent design submittal packages. Construction may not begin until all Government comments from all design phases have been resolved.
1.9 SPECIAL CONSTRUCTION REQUIREMENTS
1.9.1 THIRD PARTY INSPECTION SERVICES
The Contractor shall furnish independent 3rd party inspection services to inspect the electrical and structural construction features of the project. The 3rd party shall not be the same company responsible for the electrical or structural installation. This is in addition to the Contractor Site Personnel Requirements contained in [01 45 05 CONTRACTOR SITE PERSONNEL REQUIREMENTS][01 46 00 SMALL PROJECT CONTRACTOR SITE PERSONNEL REQUIREMENTS]. All testing shall be at the expense of the Contractor. The Contractor shall submit a plan for third party services to the COR. The inspection plan must be approved by the COR prior to construction.
1.9.1.1 GENERAL REQUIREMENTS
3rd Party inspectors shall submit professional reports directly to the COR without coordination with the Contractor within 48 hours of the actual inspection. Report will contain the following at a minimum: names of all persons present for activity, listing and approval of all related materials, description of observed activity, and 10 photos (minimum resolution: 1504x1000) of the observed activity.
1.9.1.2 THIRD PARTY ELECTRICAL INSPECTOR REQUIREMENTS
The inspector shall be a certified Master electrician or licensed degreed Electrical Engineer and have a minimum of 10 years' experience, 5 years in the country where the project work is performed. The Contractor shall submit the inspector’s CV (Resume) for Government approval.
Minimum inspections to be conducted: all outlets, off-cover inspection of all panels, verify that GFCI is present on all panels, municipal power connections, lightning protection installations, and generator installations.
Contractor shall submit a plan and schedule to be part of the QC Plan or a separate submittal to be tracked via the submittal register, indicating the inspection plan and timing.
1.9.1.3 THIRD PARTY STRUCTURAL ENGINEER INSPECTOR REQUIREMENTS
Structural Engineer shall be a licensed graduate engineer with 10 years of experience, 5 years in the country where the project work is performed. Required experience includes, but is not limited to, inspecting concrete moment frame, concrete foundations, roof system and rebar and form work. Furnish CV for Government approval.
Contractor shall submit an inspection plan and schedule of inspections to be part of the QC Plan or a separate submittal to be tracked via the submittal register, indicating the inspection plan and timing.
30MAY 2018 Page 6 of 43
Minimum inspections to be conducted: Bearing capacity of foundation soils, formwork and rebar of foundations, concrete placement of foundations. Formwork, rebar and concrete pour of moment frame. No concrete may be placed in forms without a preceding rebar inspection report and verification of functioning vibration equipment.
Engineer shall review concrete test results and sign off on strength approvals.
1.9.2 PROTECTION OF WORK AREA
1.9.2.1 DUST AND DEBRIS CONTAINMNET
The Contractor is responsible for sealing the project area with construction barriers and dust partitions in order to contain construction dust and debris and maintain a clean environment outside of the work area. In addition to protections within the work area, the Contractor shall provide temporary protection for all finishes from the entrance of the facility to each area of work. The Contractor is responsible for patching and repairing any damage caused during construction.
Coordinate the locations of barriers with the COR prior to the start of work.
1.9.2.2 PROTECTION OF FURNITURE, FIXTURES, AND EQUIPMENT
The Contractor shall protect all existing furniture, fixtures, and equipment that remain within the work area. Coordinate with the COR and the User for any special protection measures required for sensitive equipment. The Contractor is responsible for repairing or replacing any damage caused during construction.
Either the Contractor or the COR may request to conduct a preconstruction survey of furniture, fixtures, and equipment with both the Contractor and Government representative present.
1.9.2.3 NOISE AND VIBRATION CONTROL
The Contractor shall employ demolition and construction methods that minimize the production of sound and vibration. Coordinate the schedule of especially loud or disruptive activities with the COR prior to the start of work.
1.9.2.4 PROTECTION OF EGRESS AND LIFE SAFETY
The Contractor shall not take actions that hinder existing egress paths or disrupt operation of life safety systems without prior coordination with the COR and all applicable authorities having jurisdiction (AHJ). The Contractor is responsible for supplying signage or other protective measures as required by the COR or AHJ prior to impeding the egress path or life safety system.]
END OF SECTION
30MAY 2018 Page 7 of 43
2.0 CIVIL AND GEOTECHNICAL
Provide and perform civil engineering design and construction services as required to provide a complete, accessible, functional and usable project. The contractor is required to extensively coordinate civil design and construction work with the scope of the other disciplines described in this SOW.
2.1 SCOPE SUMMARY
Civil works for this project are comprised of, but are not limited to, site survey, geotechnical investigation, demolition, earthwork, storm system, septic system, and water. Refer to the bid schedule for which of these are base bid or optional.
2.2 EXISTING CONDITIONS
The property boundary for the site is not known. There are existing buildings on the southwest and southeast portion of the site, as well as a concrete slab and vegetation. The site is on top of a hill and slopes approximately 2% to the northwest.
There is no known existing topographic survey, as-built, or geotechnical information for the site.
There is a pressurized potable water connection on site. The reliability is poor and typically the city system runs out of water by 11am. The base has water storage units with pumps that fill the tanks in the morning to provide water for the day once the city system turns off. Rainfall and “Grey water” sanitary discharges collect in concrete gutters around the buildings and discharge offsite (discharge location unknown). “Black water” sanitary discharges to a septic tank/ leach field serving the hospital, which is assumed to have capacity for the building addition. The septic system is near the proposed addition. However, the exact location is unknown.
Prior to bid, investigate the general and local conditions which can affect the work and/or its cost, including but not limited to:
a. Location, size, material, and condition of existing structures, utilities, pavement, vegetation, and any other features. Site information provided to the Contractor by the Government is not to be considered accurate Site Survey information;
b. Weather, river stages, tides, or similar physical conditions at the site;
c. Surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site and due diligence research.
d. Mobilization and staging.
2.2.1 HAZARDOUS MATERIALS AND CONTAMINATION
There is no prior knowledge of any hazardous materials at the site. However, it is possible that hazardous material may be found from previous use of the site, or that materials to be removed contain hazardous materials. If hazardous materials are found to exist, immediately notify the COR, cease work in the area, and secure the site. Take precautions to protect the site from surface run-off and precipitation, and prevent leaching of any hazardous material in the surrounding area.
2.3 DESIGN SUBMITTALS
Provide civil design submittals in accordance with RFP Section 01 33 16, DESIGN AFTER AWARD and SOW Section 1.0 – GENERAL.
65% Design Submittal Preliminary Design Analysis of civil features.
Final Site Survey.
Final Geotechnical Report.
Preliminary Site Layout Plans - Indicate existing and proposed Civil features, structures, utilities, and demolition.
Preliminary Grading Plans, Profiles, Cross Sections, and Details, including contours, spot grades, finish floor elevation, and slopes. Include erosion control design.
30MAY 2018 Page 8 of 43
Preliminary Utility Plans, Profiles, Cross Sections, and Details.
Preliminary Pavement Plans, Cross Sections, and Details.
Preliminary Landscape Plan and Details.
Preliminary Civil Specifications.
95% Design Submittal
a. Update all items from the previous Design Submittal to 95% (Final) Design.
Incorporate all previous design comments.
100% Submittal The 100% Submittal provides a complete and final set of contract documents ready for construction. Update all Final submittals from 95% to a corrected Final submittal. Address all previous government review comments before submitting.
2.3.1 DESIGN ANALYSIS
Provide a Design Analysis for all Civil features that documents significant design choices and substantiates design compliance with contract requirements, applicable codes and standards. Documentation includes narrative, calculations, photographs, sketches, and catalog cut sheets. Reference all applicable regulations, standards, and criteria for the design. Reference sources are subject to Government approval.
Provide design assumptions. For design choices, discuss alternative systems considered, and provide rationale for the selected alternative.
The Design Analysis includes but is not limited to:
a. Discussion of Site Layout constraints and design decisions, including but not limited to, land use, vehicle and pedestrian access, orientation of features on-site, setbacks from site features, topography, sun angles, minimizing utility lengths, minimizing earthwork and tree removal, and future expansion.
b. Discussion of Demolition constraints and design decisions. Include phasing, discussion on how access will be provided during construction, and how each utility will be maintained and operated during construction.
c. Discussion of Earthwork and Site Grading constraints and design decisions.
Include pertinent geotechnical information that affects earthwork.
d. Discussion of Storm system constraints and design decisions.
e. Discussion of Sanitary system constraints and design decisions. For each section of pipe, include analyses indicating pipe size, friction factor, length, elevations at each end of pipe, slope, design flow (Q), maximum flow capacity, design depth of flow, design percentage full, and design flow velocity. Provide calculations for sizing of structures. Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10- Utilities. Include pertinent geotechnical information that affects the sanitary system. Confirm that the existing receiving system has adequate capacity to receive the additional sanitary flow generated by the project.
f. Discussion of Water system constraints, design decisions and source. Provide calculations to demonstrate water system meets project requirements, including demand, water pipe sizing, design water pressure and flow rates at buildings.
Provide field conducted flow tests from nearest hydrants (or other relevant water structures if hydrants unavailable). Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10- Utilities.
g. Discussion of Pavement constraints and design decisions. Provide calculations for the pavement section. Include pertinent geotechnical information that affects the pavement design.
30MAY 2018 Page 9 of 43
h. Site Survey as an appendix.
i. Geotechnical Investigation and Report as an appendix.
2.3.2 DESIGN DRAWINGS
Provide Civil design drawings of sufficient detail to address the requirements of each design submittal. Civil drawings include plans, profiles, cross sections, and details of Civil features for the project. Design drawings include all necessary information (labeling, dimensioning, legend, details, notes, etc.) to allow for complete understanding and constructability of all proposed features. Provide comprehensible differentiation between features that are proposed, existing, future, or proposed to be demolished by use of appropriate choice of line styles, line weights, and/or colors. In the absence of the Host Nation’s drafting requirements, reference USACE A/E/C Graphics Standard for graphic requirements.
2.3.3 SPECIFICATIONS
Provide Civil specifications of sufficient detail to address the requirements of each design submittal. Specifications, when combined with the design drawings, allow for complete understanding and constructability of all proposed Civil features.
2.4 DESIGN CRITERIA
Provide civil design in accordance with the design criteria outlined in the GENERAL section of this SOW. Reference codes used in the Design Analysis for each feature, and provide an electronic copy of the local Host Nation codes in its original language. In the absence of Host Nation Codes, use the latest release of the International Building Codes (IBC) and/or the following U.S. Codes and Technical Standards and regulations:
Uniform Facility Criteria (UFC) 3-201-01 - Civil Engineering UFC 3-230-01 Water Storage, Distribution, and Transmission UFC 3-240-01 Wastewater Collection UFC 3-220-01 Geotechnical Engineering USACE A/E/C Graphics Standard (ERDC/ITL TR-12-1) International Building Code (IBC) Architectural Barriers Act (ABA)
UFC documents are available on the internet at:
http://www.wbdg.org/ccb/browse_cat.php?c=4
2.5 SITE SURVEY
Provide a topographic survey from a licensed surveyor that includes all existing site information needed to design and construct the project. Include x, y, and z coordinates to the nearest 0.005 meters, dimensions, material, and basic characteristics of all features within the project site limits, as well as all features outside of the project site limits that will affect the design and construction of the project. Research record drawings to obtain utility and pavement information that is not visible from the surface. Provide notes indicating the sources and any limitations or assumptions of the data. Provide a copy of the survey in CAD, in addition to the paper/electronic requirements of the Design Analysis.
Locate and show on the topographic survey the following information:
a. Property boundary, public right of way, and easements. Include the address numbers, street names, and easement records.
b. Survey monuments and benchmarks. Include description.
c. Spot elevations covering the entire survey limits showing high points, low points, grade changes, and at sufficient intervals to represent the general character of the terrain.
d. Contours in intervals of 0.25 meters.
e. Buildings and other miscellaneous structures. Provide finish floor elevation.
30MAY 2018 Page 10 of 43
f. Pavements. Include pavement type, thicknesses, joint patterns, and pavement markings. Include top of curb and gutter elevations.
g. Surface Drainage Features. Indicate normal water level for water bodies.
h. Utility lines and structures. Include rim elevations and invert elevations for utility structures; identification of lines as underground or aboveground;
pipe sizes and materials.
i. Fences. Include height, material, direction of outrigger, gate locations and types.
j. Signs. Include sign text.
k. Trees/Woods. Locate trees over 150 millimeter diameter at chest height, and include tree species, diameter at chest height, and dripline diameter.
l. Geotechnical boring locations.
m. North arrow and scale of drawing.
n. Legend depicting the symbols and abbreviations used on the drawing.
o. Horizontal and vertical coordinate systems, date of survey, licensed surveyor name and license number.
Site information provided to the Contractor by the Government is not to be considered accurate Site Survey information. Utility field locates and as-built research are the responsibility of the Contractor.
Reference UFC 3-201-01, Civil Engineering, Section 2-2.2-SURVEYING for survey requirements. In the absence of the Host Nation’s horizontal and vertical coordinate system, use the Universal Transverse Mercator (UTM) coordinate system, and base vertical coordinates on sea level.
2.6 GEOTECHNICAL INVESTIGATION AND REPORT
Perform geotechnical investigations necessary for the design and construction of project features. Provide any geotechnical investigations and reports to the Government that are performed. Provide geotechnical information in the Design Analysis to support design decisions. Perform geotechnical work necessary for Construction (i.e. compaction tests, inspection of structure foundation excavations). In the absence of host nation standards, perform the geotechnical investigation and report per UFC 3-220-01 and IBC.
2.7 SITE LAYOUT
Attachment #5 – Conceptual Site Plan of this SOW includes a site sketch that shows a feasible solution for the layout of the site which is to be considered as the preferred layout, but conceptual only. Amend the site layout as determined by the site-specific constraints, the owner’s preferences, accessibility, and opportunities that are identified and evaluated as part of the Contractor’s scope of work. The Contractor is responsible for all aspects of the project whether they are shown on the conceptual plan or not.
2.8 DEMOLITION
Remove existing structures, utilities, pavement, vegetation, and any other features to construct the proposed improvements. Provide straight, neat sawcuts at limits of pavement removal. Any contaminated soils discovered will require special testing and disposal per Host Nation requirements.
2.8.1 CONSTRUCTION LIMITS
Do not disturb the project site beyond necessary for installation of proposed construction. Do not disturb any areas past the site’s property line. Show demolition work and limits of disturbance in the drawings. Stake-out the limits of disturbance on-site with temporary fencing before beginning construction.
2.8.2 ITEMS TO REMAIN IN PLACE WITHIN CONSTRUCTION LIMITS
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged https://en.wikipedia.org/wiki/Universal_Transverse_Mercator_coordinate_system https://en.wikipedia.org/wiki/Universal_Transverse_Mercator_coordinate_system
30MAY 2018 Page 11 of 43 items as approved by the COR. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the COR prior to performing said work.
2.8.3 TREE DEMOLITION
Unless otherwise noted, protect trees larger than 150mm diameter at chest height within the project site which might be damaged during construction, with a 1.8 m high fence around the dripline of the tree(s), which is assumed to be the extent of the tree’s roots. Mitigate for tree removal per Host Nation requirements.
2.8.4 UTILITY DEMOLITION
Any existing utilities encountered within the site boundary that are impacted by this project must be protected, or relocated if protection is not feasible. Relocate existing utility mains outside the structural zone of influence of proposed buildings and structures. Utilities impacted by this project that require decommissioning, or that are already out of service, must be removed up to the utility main and capped. Manholes or underground structures to be abandoned must be removed to a minimum depth of 50 centimeters below finish grade. Fill abandoned manhole or structure per Section 2.9-EARTHWORK requirements.
2.8.5 DUST, DEBRIS, AND EROSION CONTROL
Prevent the spread of dust, debris, and erosion from the project site. Install erosion control measures before beginning construction. Sweep pavements as often as necessary to control the spread of debris. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, erosion, or pollution. Remove snow, dust, dirt, and debris from work areas daily.
Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply Host Nation regulations regarding hauling and disposal.
Reference RFP Section 00 74 00-SPECIAL CONDITIONS, and 01 30 00-GENERAL REQUIREMENTS for additional demolition, protection, and permitting requirements.
2.9 EARTHWORK
Perform all earth work necessary for the installation of the proposed improvements.
Define earthwork requirements in the plans and specifications. Include requirements for satisfactory material, borrow material, structural fill, topsoil, utility trenches, replacement and improvement of on-site soils, soil compaction (for subgrades of structures, paving, and landscaped areas), compaction for utility trenches, maximum lift depths, density testing frequency, maximum temporary and permanent slopes, dewatering, and engineered support systems.
Excavated material, if satisfactory for reuse, may be used on the project site where fill is required. Only gravelly and sandy non-cohesive materials shall be considered satisfactory for fill and backfill, with the provision that in any soil type the maximum particle size does not exceed 75 mm, the plasticity index is not greater than 30, the soil is not contaminated, and the soil does not contain trash, debris, or organic material. In case of a difference of opinion about the classification of soil type acceptability, an independent professional soils engineer shall be engaged at cost to the Contractor.
Unsatisfactory material, and surplus excavated material not required for fill, shall be disposed of offsite, and shall be the responsibility of the Contractor. Borrow material may be required for construction from sources off site. Borrow materials are to be free of hazardous materials and contaminants. Any soil brought in from off-site sources needs to be certified clean, or tested by the Contractor’s geotechnical engineer, for adverse contaminants above regulatory criteria, prior to use.
30MAY 2018 Page 12 of 43
Provide engineered support systems as required for the construction of temporary and permanent earth structures such as slopes, utility trenches, constructions pits and any other structure requiring earth support. The Contractor shall be responsible for all dewatering necessary for earthwork.
During construction, all structure foundation excavations shall be inspected and approved by the Contractor’s professional geotechnical engineer prior to placing concrete. In the absence of geotechnical recommendations, compact soil to 95% density in 20cm lifts in loose thickness, and provide density tests on all lifts at a frequency of 1 test per 40 square meters for foundations and parking, and 1 test per 30 meters of road and utility trench. Round up to nearest whole number (i.e. a 25 square meter foundation requires one test). The location of all tests shall be selected by the Contractor’s geotechnical engineer, and copies of all test results shall be furnished to the COR.
2.9.1 SITE GRADING
Provide site grading that directs storm water runoff away from buildings and structures either by drainage systems or by grading as follows:
Finished grades of earth/grass/gravel surfaces adjacent to buildings and structures must slope away from all exterior edges with a gradient of min. 5% for the first 3 meters.
a. Finished grades of paved surfaces adjacent to buildings and structures must slope away from all exterior walls with a gradient of min. 2% for the first 3 meters.
b. Finished grades must not create stagnating water or ponding anywhere on the project site, nor create ponding on adjacent properties.
c. Set building finish floor elevations at a minimum of 30cm above the local 100 year flood level, if the proposed finish floor is different than the existing building it is connecting to. In the Design Analysis, provide flood maps and/or hydrologic calculations and/or other engineering analysis to determine this elevation.
d. Site grading around the building must meet local accessibility guidelines. In the absence of local codes for handicapped accessibility, Architectural Barrier Act requirements apply. The Contractor must limit proposed landscape slopes to a maximum 2H:1V, or as recommended by the Contractor’s geotechnical engineer.
2.10 UTILITIES
Provide utility line depths, bedding, and backfill as required by applicable standards and geotechnical recommendations. Minimum cover over pipes is 2 feet (0.61 m); greater than frost penetration; or sufficient to support imposed dead and live loads for the pipe materials used; whichever is more stringent. Place plastic warning tape along the route of the buried lines after pipe installation at a height of 30 cm above the line.
Any existing utilities encountered within the site boundary that are impacted by this project must be protected, or relocated if protection is not feasible. Utilities impacted by this project that require decommissioning, or that are already out of service, must be removed up to the property line. Cap utilities at property line per applicable codes. Manholes or underground structures to be abandoned must be removed to a minimum depth of 50 cm below finish grade. Fill abandoned manhole or structure per Section 2.9-EARTHWORK requirements.
Coordinate all required installation, relocation, improvement and protection of utilities held by third party (e.g. public or private utility). This includes coordination of any work to be performed by the utility owner. Choice of materials and products for utility installation must be coordinated with the utility owner
30MAY 2018 Page 13 of 43
(customer or third party) to ensure proper integration and compliance with existing systems and allow for easy maintenance and repair of the utilities in the future.
2.10.1 STORM SYSTEM
Provide a storm drainage system to direct runoff away from improvements and eliminate ponding. Connect building roof gutters and downspouts to two rainwater tanks (5000 liter each) as shown on Attachment#2-Conceptual Site Plan and Attachment#6-Rainwater Tank Example. Locate tanks out of pathways and windows. For each rainwater tank, provide a spigot at the bottom of each tank. Below the spigot, provide a splash block that will drain water away from building foundations a minimum of 3 meters per site grading requirements. Provide an overflow system from the tanks to the “Grey Water” gutter system or splash blocks that drain away from foundations a minimum of 3 meters per site grading requirements. Reroute existing “Grey Water” system as necessary. Provide insect screens to all open orifices to the tank system. Provide UV resistant tanks. Provide concrete support as described in the Pavement Section.
Provide structural tie downs for when the tank is empty. Provide an opening for cleaning and allow access into the tanks. Provide system in order to divert first flush from the roofs that may be contaminated with dust, animal droppings and dirt so that it does enter the tank. Provide sign next to tap that shows a pictogram “not for drinking”. Sign shall be firmly fastened aluminum or other durable weather resistive material (no adhesive sticker allowed).
The storm system must function by gravity. A pump system is not allowed. In the absence of host nation standards, design the storm drainage system per UFC 3-201- 01, Chapter 3-Storm Drainage Systems.
2.10.2 SANITARY SYSTEM
Connect the remodeled existing building and proposed addition “Black Water” sanitary discharges to the on-site septic system. Connect the remodeled existing building and proposed addition “Grey Water” sanitary discharges to the existing “Grey Water” system. Reroute existing sanitary system as necessary. The “Gray Water” gutters must not connect to the “Black Water” septic system. In the absence of Host Nation standards, design the sanitary system per UFC 3-240-01.
2.10.3 WATER SYSTEM
Connect the remodeled existing building and proposed addition to the site’s water system as described in Section 06 - MECHANICAL. Reroute existing water lines as necessary to connect to the water system. In the absence of Host Nation standards, design any exterior water system per UFC 3-230-01.
2.11 PAVEMENT
Provide foundations for rainwater collection tanks per Structural Section requirements. Install the bottom of the tank a minimum of 45cm above finish grade.
2.12 MOBILIZATION / STAGING
The site has staging room north of the proposed building addition.
30MAY 2018 Page 14 of 43
3.0 ARCHITECTURAL
3.1 PROJECT DESCRIPTION
Design and construction work for the renovation and expansion of the 34th Hospital, Labor and Delivery Ward in Freetown, Sierra Leone.
The Buildings shall be renovated in accordance with the design drawings provided as Attachment #2 and as stated in this document, regarding room finishes, dimensions and layout. Where reference is made to the Architect, the contractor shall coordinate with the Contracting Officer Representative (COR).
Extensive coordination will be required between the architectural work and the civil, structural, mechanical, and electrical requirements of this project.
3.1.1 DRAWINGS
The Contractor shall develop a design based on the functional adjacencies, conceptual floor plans, and space allocations given in the RFP. The design shall incorporate all referenced codes and regulations. The Contractor shall provide a design and construction package that uses the design details and features given or referenced in this RFP. Additional details shall be created by the Contractor as required, but shall conform to the requirements of this RFP and are subject to the approval of the
COR.
3.1.2 DESIGN SUBMITTALS
The contractor shall make the architectural submittals after contract award in accordance with Section 01 33 16, DESIGN AFTER AWARD.
3.1.2.1 65% DESIGN SUBMISSION
65% Submission: Include the following drawings and reports as applicable to the project:
• Floor Plans – Provide all floor plans, indicating room names and basic dimensions.
• Ceiling Plans – Provide reflected ceiling plans for all rooms, indicating ceiling materials and fixtures.
• Building Elevations – Provide all building elevations indicating all exterior materials.
• Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.
• Building Section – Indicate heights of critical building elements.
• Wall Sections – Provide a typical interior and exterior wall section describing wall materials.
• Room Finish Schedule – Provide intended wall, floor, and ceiling finishes for all rooms in the project.
• Furniture/Equipment Plan – Provide plans showing all intended furniture/equipment (both in this project and to be provided by the local authorities / school administration) and dimension clearances between furniture/equipment and the structure.
• Outline Specifications – Provide outline specifications for all work and materials.
• Design Analysis – Provide a narrative indicating how the design meets the code requirements of this SOW
3.1.2.2 95% DESIGN SUBMISSION
The 95% Submittal provides a complete and final set of contract documents essentially ready for construction by the Design Built (D/B) Contractor. All previous government review comments must have been addressed. Include the following drawings and reports:
• All required documents from the 35% Submission updated to incorporate all comments from the 35% Review.
30MAY 2018 Page 15 of 43
• Section and Plan Details – Provide enlarged details of critical intersections indicating all materials
• Interior Elevations – Provide enlarged interior elevations indicating all materials, finishes, and coordination with other building systems.
• Interior Details – Provide details for casework, equipment mounting, ceilings, floor finishes, etc.
• Window, Door, and Hardware Schedule – Provide size, function, and material for all windows and doors in the project.
• Window and Door Details – Provide enlarged details of door and window head, jamb, and sills
• Color Board – Provide a material and color board
• Detailed Specifications – Provide detailed specifications with line items for all work and materials.
3.1.2.3 100% (CORRECTED FINAL) DESIGN SUBMISSION
The 100% Submittal provides a corrected final set of contract documents ready for construction by the D/B Contractor. All government review comments from all submittal phases must have been addressed and incorporated. Include all of the required drawings and documents from previous submittals.
3.2 TECHNICAL CRITERIA AND STANDARDS
Project design shall be in accordance with the requirements outlined in section 1.7
3.2.1 LIFE SAFETY REQUIREMENTS
The Contractor shall meet all Host Nation and local Fire codes / Suppression System codes and requirements.
All structures to be provided shall have exits and means of egress that comply with current Host Nation codes and standards, or in accordance with US codes and standards.
In the absence of Host Nation codes and standards, for individual concerns of Life Safety the Contractor shall follow the NFPA 101 Life Safety Code.
3.2.2 HANDICAPPED ACCESSIBILITY REQUIREMENTS
Handicapped Accessibility Requirements shall apply for this project. Local codes for handicapped accessibility must be followed. In the absence of local codes for handicapped accessibility, Architectural Barrier Act requirements shall apply:
https://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-the-aba-standards/aba-standards
3.3 GENERAL SCOPE OF WORK
The architectural elements of this facility shall be designed to withstand all site-specific environmental conditions such as wide seasonal temperature swings, local wind, rain snow and earthquake conditions. All architectural features shall be appropriately braced for anticipated seismic activity. The Contractor shall have flexibility to propose alternate building materials to meet the facility’s requirements, but final selection of materials shall be subject to the approval of the COR. Materials and building systems shall be selected with consideration given to economics not only in the initial acquisition, but also in the future maintenance of the materials when incorporated into the work.
3.4 DETAILED SCOPE OF WORK
The contractor shall be responsible for the following specific tasks required for the construction of this facility.
3.4.1 DEMOLITION
The Contractor shall be responsible for all required demolition as indicated in this scope and shown on att#2 “Conceptual Architectural Floor Plan” to achieve the https://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-the-aba-standards/aba-standards https://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-the-aba-standards/aba-standards
30MAY 2018 Page 16 of 43 specified layout. The existing roof on the renovated part of the building shall be replaced with a new sloped roof.
3.4.2 BUILDING SYSTEM AND MATERIALS
The intent of this RFP is to allow the contractor the maximum flexibility to design and construct this facility in an economical manner without sacrificing good engineering practices, quality materials and systems. The Government would like low or no maintenance finish materials to the greatest extent possible. Building materials as described herein for roofing, walls, ceilings, doors, windows and floors are minimum requirements and may require revision based on code compliance and criteria.
3.4.2.1 FIRE PROTECTION RATINGS OF INTERIOR FINISHES
All interior finishes shall conform to Host Nation fire protection standards / requirements or equivalent US standards / requirements.
3.4.2.2 ACOUSTICAL DESIGN
Doors and walls shall meet the minimum sound protection per Host Nation requirements.
3.4.3 EXTERIOR CONSTRUCTION WORK
3.4.3.1 EXTERIOR WALLS / COVERED WALKWAY
Provide new exterior masonry and/or concrete walls and columns for the expansion of the Labor and Delivery Ward and the covered walkway in accordance with functional requirements and structural requirements as described in Section 4.0 STRUCTURAL DESIGN. Provide penetration openings (for example for ventilation, piping and cables) as required by other sections and drawings of this RFP
3.4.3.2 EXTERIOR WALL FINISH - STUCCO
Install new exterior wall finish stucco and paint the whole facade. The work shall include all necessary expansion joints, base - and corner rails. Use products from a single system, by a single manufacturer, which are certified by the manufacturer to be suitable for the purpose. This also applies to the paint.
Apply products in accordance with the manufacturer's instructions.
The work shall include all necessary sealing e.g. at windowsills. Submit a sample of the exterior wall finish along with the manufacturer's catalog data including installation instructions, typical details and product data for COR's acceptance
3.4.3.3 EXTERIOR DOORS
3.4.3.3.1 DOOR FRAMES AND PANELS
Provide new exterior single and double doors and frames to include new emergency exit doors as required by the conceptual floor plan. Steel frames and panels shall be painted with zinc chromate primer, one coat of universal undercoat and two coats of enamel paint. The Contractor shall provide all necessary hardware for all doors including panic hardware locking mechanisms. All door frames shall be mounted flush with surrounding walls and seams shall be sealed. Exterior doors shall include a commercially manufactured threshold with a vinyl or silicone rubber weather stripping insert in the face of the stop. Weather stripping shall be held in an extruded non-ferrous metal housing. All doors shall have heavy-duty closers. The Contractor shall size closers in accordance with the specific door application and size, and with manufacturer's recommendations. All exterior doors shall have key lock.
3.4.3.3.2 DOOR HARDWARE
Provide all hardware necessary for the operation of the door. All hardware shall be heavy duty and fabricated from corrosion resistant metals. All hardware shall be compliant with applicable Accessibility and Life Safety codes. Provide 3 keys
30MAY 2018 Page 17 of 43 for each door. Label all keys. At a minimum provide the following hardware for each exterior door:
• Three metal butt hinges (provide with tamper proof hinge pins);
• One floor or wall mounted doorstopper, as appropriate;
• Lever latch handles;
All doors shall have a mortise lockset. All locksets shall be keyed to existing key system, coordinate requirements with COR. Panic hardware and smoke/fire rated doors in egress routes shall be provided as required by the Host Nation Life Safety Code.
3.4.3.4 EXTERIOR WINDOWS
3.4.3.4.1 EXTERIOR WINDOW FRAMES AND GLAZING
Provide new windows and frames for the new building expansion as required. New aluminum windows and frames shall be provided. Windows shall be non-operable factory finished commercial grade with surround frame. Window installation must allow installation of security bars on the exterior of the window Accessories and hardware includes drip sills, hinges, lever handles and latch lock. Anchor and secure window frames on masonry walls as recommended by the manufacturer to meet the wind and seismic loads. Caulk all joints between window frames and building with sealant to provide a watertight installation and proper finish.
All windows shall have double glazing. Windows shall have R-value IAW Host Nation Codes and Requirements.
3.4.3.4.2 EXTERIOR WINDOW SILLS
Provide new pre-fabricated concrete window sills. Exterior window sills shall be set in continuous bed of mortar and sloped to drain to exterior of building.
Paint exterior window sills to match adjacent walls.
3.4.3.4.3 SECURITY BARS
Provide security bars matching bars on existing buildings made from minimum 10 mm flat steel bars welded to form a grid. The grid shall have a maximum spacing of 250 mm x 250 mm. The design shall allow maintenance and installation access to the perimeter of the window frame and insect screens. Security bars must not hinder operation of the windows. Security bars shall be painted with zinc chromate primer, one coat of universal undercoat, and two coats of enamel paint.
Color to be approved by COR. Security bars shall be anchored to exterior walls, on the exterior of the windows. Security bars shall have a minimum of four anchor points to the structure, one at each corner of the windows. The anchor points shall be designed to prevent removal of the security bars from the outside. Bolts used to secure security bars to building must be ground round if accessible from the exterior.
3.4.3.4.4 INSECT SCREENS
All operable louver windows at the existing building and ventilation openings shall be provided with industry standard, exterior grade insect screens on the outside of the opening. Insect screen frames shall be fastened securely according to manufacturer’s guidelines. Insect screen fabric shall be resistive to aging caused by ultra-violet light. Insect screens (frames) shall be installed to allow storm water run-off and yet don’t allow insects to enter through the screens. Insect screens shall be colored black.
3.4.3.5 ROOF WORK
3.4.3.5.1 ROOF CONSTRUCTION AND ROOF COVERING
Provide new roof structure (see Section 4.0 Structural), roof lathing and new insulated metal roofing, thermal conductivity group IAW Host Nation Energy Codes
30MAY 2018 Page 18 of 43 and Requirements over the renovated part of the building and the new expansion including the covered walkway. The sheathing/planking shall be supported by a steel frame/truss system with purlins. Fastening and overlapping of roof covering material shall be in accordance with manufacturer guidelines and structural requirements. Fastening through corrugated roofing shall always be at the high point (“ridge”) of the profile. New roof to match existing roof slope and geometry. Steel or aluminum roofing shall be factory finished and shall have minimum thickness of 0.60 mm.