Attachment 5 - Price schedule - Serbian MOI 22May17 final.pdf

PDF 233 KB Posted

Attached to
Laboratory Training Classroom Federal contract opportunity
Solicitation number
W912GB-17-R-0047
Issued by
Department of the Army Corps of Engineers Engineering District Europe

About this file

Attachment 5

View the file

Other files for this federal contract opportunity

Other files attached to Laboratory Training Classroom, newest first.
File Type Posted
PreProposal_Slides_Classroom_Construction,_Serbia,_27_June_2017.ppt PPT presentation
Attendance_Roster.pdf PDF
SOW Attachment 6 - GiftSign.pdf PDF
Attachment 2 - Experience Info Sheet.docx DOCX document
SOW Attachment 5 - Site Photo.pdf PDF
Attachment 3 - PastPerformanceClientForm.docx DOCX document
SOW sr13_01010.pdf PDF
SOW Attachment 7 - Structural Calculations Guideline.pdf PDF
SOW Attachment 4 - Conceptual Site Plan.pdf PDF
Attachment 4 - KeyPersResume.docx DOCX document
SOW Attachment 1 - Location Map.pdf PDF
Attachment 8 - Letter of Commitment Sample.docx DOCX document
W912GB-17-R-0047.pdf PDF
Attachment 6 - BankLetterAssuranceSample.docx DOCX document
SOW Attachment 2 - FuncLayout.pdf PDF
Specifications Combined.pdf PDF
Attachment 7 - BankLetterGuaranteeSample.docx DOCX document
Attachment 1 - Overview Experience.docx DOCX document
SOW Attachment 3 - AsBuilt.pdf PDF
Pre-Solicitation_Notice_W912GB-17-R-0047_MOI_Lab_Classroom,_Serbia.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICE SCHEDULE

Request for Proposal (RFP)

Serbian Ministry of the Interior Renovation and New Construction

Mitrovo Polje, Serbia

The Offeror shall bid on all base bid and option items. Provide completion of all design and construction of award items from the Notice to Proceed as described in the contract FAR Clause 52.211-10 “ COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK” according to the following schedule. Each CLIN duration is as per the price schedule and the calendar days are from issuance of the Notice to Proceed (NTP). The contractor shall have the project fully functional and available for normal, regular use no later than the end date of the period of performance.

See FAR Clause 52.211-12 for Liquidated Damages. Liquidated damages apply to any completion date specified in the contract or Price Schedule including interim completion dates for individual facilities.

Base Bid Period of Performance: The base period of performance is 365 calendar days from issuance of the notice to proceed (NTP). The contractor shall have the project fully functional and available for normal, regular use no later than the end date of the period of performance to ensure the patients can utilize the space.

Award of Options and Period of Performance: The Government reserves the right to award any or all options up to 90 calendar days following issuance of NTP for the base bid work. Any optional work awarded shall be completed as noted within a particular CLIN, as described in contract FAR Clause 52.211-10

“COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK”. If an option is exercised, they must be completed within the base period of performance of 365 calendar days.

This project is a Design-Build and the contractor shall be required to prepare a detailed design as well as provide for construction of the project.

Allowable Work Hours: The allowable working hours are from 0800-1900 Local Time, Monday through Saturday.

Work on US and Serbian holidays and outside of these hours shall not be performed without prior approval from the

Contracting Officer. Office hours for coordination with Government representatives are from 0730-1600 hours CET, except U.S. holidays.

Prices: All prices are to be proposed in U.S. Dollars.

BASE ITEMS:

CLIN

Construct New Classroom Facility

Design: All work associated with the design of a new classroom facility in

Serbia. The facility shall consist of a masonry / concrete building with sloped roof and utility / heating mechanical room. The facility shall accommodate

120 trainees. All work shall be built as described in the statement of work and specifications.

Construction: All work associated with the Construction of a new classroom facility in Serbia. The facility shall consist of a masonry / concrete building with sloped roof and utility / heating mechanical room. The facility shall accommodate 120 trainees.

First Floor Renovation of Barracks and All Exterior Renovations

Design: All work associated with the design of a renovation of a barracks in

Serbia. The facility shall accommodate 33 trainees as well as all exterior renovation work on the building. All work shall be built as described in the statement of work and specifications.

Construction: All work associated with the construction of a renovation of a barracks in Serbia. The facility shall accommodate 33 trainees as well as all exterior renovation work on the building. All work shall be built as described in the statement of work and specifications.

BASE ITEMS TOTAL: $____________

OPTIONAL ITEMS:

Option Item 1 – Pavements

Design: All work associated with the design of a sidewalk that connects the new building to existing adjacent building entrances. All work shall be built as described in the statement of work and specifications.

Construction: All work associated with the construction of a sidewalk that connects the new building to existing adjacent building entrances. All work shall be built as described in the statement of work and specifications.

Option Item 2 – Second Floor Renovation of Barracks

Design: All work associated with the design of a renovation of a second floor barracks in Serbia. The facility shall accommodate 33 trainees. All work shall be built as described in the statement of work and specifications.

Construction: All work associated with the construction of a renovation of a second floor barracks in Serbia. The facility shall accommodate 33 trainees.

All work shall be built as described in the statement of work and specifications.

Option Item 3 – Landscaping

Design: All work associated with the design of landscaping in areas that do not have pavement or a building. Provide grass seed and 20cm of topsil on the site with the limits of disturbance. All work shall be built as described in the statement of work and specifications.

Construction: All work associated with the application of landscaping in areas that do not have pavement or a building. Provide grass seed and 20cm of topsil on the site with the limits of disturbance. All work shall be built as described in the statement of work and specifications.

OPTION ITEMS TOTAL:

TOTAL PRICE – ALL BASE AND OPTION ITEMS: $____________