Specifications: USACE Quality Control System

View the file

Other files

File Type Posted
A.07.24_Amendment_W912GB-17-R-0013-02_Att_Sign-in_Sheets_(26_Jan_2017).pdf PDF
A.07.24_Amendment_W912GB-17-R-0013-02.pdf PDF
A.07.24_Amendment_W912GB-17-R-0013-02_Att_PPC_slides_(26_Jan_2017).pdf PDF
A.07.24_Amendment_W912GB-17-R-0013-01.pdf PDF
01525_Safety_and_Occupational_Health_Requirements_for_Projects_in_Emerging_Countries_(05-15).pdf PDF
00_73_15.15_Time_Extensions_for_Unusually_Severe_Weather.pdf PDF
01_32_01.00_10_Project_Schedule.pdf PDF
EP_310-1-6b_Construction_Signs.pdf PDF
02_41_00_Demolition_and_Deconstruction.pdf PDF
01_00_15_Design_After_Award.pdf PDF
01_35_26_Safety_and_Occupational_Health_Requirements_(05-15).pdf PDF
A.07.23_Solicitation_Att_2_Experience_Info_Sheet_W912GB-17-R-0013oc.docx DOCX document
A.07.23_Solicitation_Att_4_Electronic_Pricing_Schedule_W912GB-17-R-0013.xlsx XLSX spreadsheet
A.07.23_Solicitation_Att_3_Past_Performance_Questionnaire_W912GB-17-R-0013.docx DOCX document
02_82_14.00_10_Asbestos_Hazard_Control_Activities.pdf PDF
A.07.23_Solicitation_17-R-0013_KO_Signed.pdf PDF
01_33_00_Submittal_Procedures.pdf PDF
A.07.23_Solicitation_Att_1_Experience_Overview_Sheet_W912GB-17-R-0013.docx DOCX document
01_45_01_USACE_Quality_Control.pdf PDF
00_73_15_General_Conditions_(05-15).pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 45 01.10

USACE QUALITY CONTROL SYSTEM (QCS*)

USACE RESIDENT MANAGEMENT SYSTEM (RMS) - CONTRACTOR-MODE

(05/16)

PART 1 GENERAL

1.1 Contract Administration

1.1.1 Correspondence and Electronic Communications

1.1.2 Other Factors

1.2 QCS/RMS CONTRACTOR-MODE SOFTWARE

1.3 SYSTEM REQUIREMENTS

1.3.1 Recommended Hardware Requirements

1.3.2 Minimum Software Requirements

1.4 RELATED INFORMATION

1.4.1 QCS/RMS Contractor-Mode User Guide

1.4.2 Contractor Quality Control (CQC) Training

1.5 CONTRACT DATABASE

1.6 DATABASE MAINTENANCE

1.6.1 Administration

1.6.2 Finances

1.6.3 Quality Control (QC)

1.6.4 Submittal Management

1.6.5 Schedule

1.7 IMPLEMENTATION

1.8 MONTHLY COORDINATION MEETING

1.9 NOTIFICATION OF NONCOMPLIANCE

PART 2 PRODUCTS [Not Used] PART 3 EXECUTION [Not Used]

SECTION 01 45 01.10 USACE QUALITY CONTROL SYSTEM (QCS*)

USACE RESIDENT MANAGEMENT SYSTEM (RMS) - CONTRACTOR MODE

(05/16)

PART 1 GENERAL

1.1 Contract Administration

The Government will use the Resident Management System (RMS)/RMS Government- Mode for Microsoft (MS) Windows® to assist in its monitoring and administration of this contract. The Contractor shall use the Government-furnished Construction Contractor Module of RMS, referred to as QCS*/RMS Contractor-Mode, to record, maintain, and submit various information throughout the contract period. The Contractor module, user manuals, updates, and training information can be downloaded from the Government’s RMS web site. All modules within QCS*/RMS Contractor-Mode shall be used.

This joint Government-Contractor use of RMS/RMS Government-Mode and QCS/RMS Contractor-Mode will facilitate electronic exchange of information and overall management of the contract.

*On Nov-2016 QCS will be updated and renamed “RMS Contractor-Mode”, and RMS will be renamed “RMS Government-Mode”. This update will be mandatory for all contracts awarded on or after Nov-2016 (date subject to change).

1.1.1 Correspondence and Electronic Communications

For ease and speed of communications, both Government and Contractor will, to the maximum extent feasible, exchange correspondence and other documents in electronic format. Correspondence, pay requests and other documents comprising the official contract record will also be provided in paper format, with signatures and dates where necessary. Paper documents will govern, in the event of discrepancy with the electronic version.

1.1.2 Other Factors

Particular attention is directed to Contract Clause, "Schedules for Construction Contracts", Contract Clause, "Payments", Section 01 32 01.00 10 PROJECT SCHEDULE, Section 01 33 00 SUBMITTAL PROCEDURES, and Section 01 45 01 USACE QUALITY CONTROL, which have a direct relationship to the reporting to be accomplished through QCS/RMS Contractor-Mode.

No separate payment for establishing and maintaining the QCS/RMS Contractor- Mode database shall be made; all costs associated therewith will be included in the contract pricing for the work.

1.2 QCS/RMS CONTRACTOR-MODE SOFTWARE

QCS/RMS Contractor-Mode is a Windows®-based program that can be run on a stand-alone personal computer or on a network. The Government will make available the QCS/RMS Contractor-Mode software to the Contractor after award of the construction contract through the Government’s RMS Internet Website.

Prior to the Pre-Construction Conference, the Contractor will be responsible to download, install and use the latest version of the QCS/RMS Contractor- Mode software from the Government’s RMS web site. Upon specific justification and request by the Contractor, the Government can provide QCS/RMS Contractor-Mode on electronic media. Any software updates of QCS/RMS Contractor-Mode will be made available to the Contractor via the Government RMS Website as they become available. The Contractor will be responsible to meet the system requirements to run QCS/RMS Contractor-Mode and any subsequent software updates.

1.3 SYSTEM REQUIREMENTS

The Contractor shall be responsible for providing a computer, printer, internet connection, and other peripherals (including, but not limited to, a mouse, monitor, and keyboard) for the use of QCS/RMS Contractor-Mode by their personnel. All software on the computer must be updated and legally licensed for use by the Contractor. The computer must meet the minimum system requirements necessary to operate all installed software, software updates, and hardware. It should be no more than six months old at the time of Notice to Proceed.

1.3.1 Recommended Hardware Requirements

MS Windows®-based PC Processor: 1.5 Ghz 2 Cores;

Memory: 8 GB RAM;

Storage: 500GB hard disk with 200GB free for QCS/RMS Contractor-Mode;

MS Windows® compatible peripherals;

Screen Resolution: 1366x768 24-bit color depth;

Connection to the Internet: Minimum 1 Mbps per user or higher (The slower the speed the longer the data transfers take).

1.3.2 Minimum Software Requirements

MS Windows® 7 (64 bits) or newer with Internet browser;

MS .Net® framework;

Anti-Virus protection software that is regularly upgraded with manufacturer-issued updates, and is able to detect “zero-day” viruses;

Electronic e-mail is required for communications with the Government and the RMS Helpdesk;

MS Office® Suite (or Viewer for MS Word® 2013, MS Excel® 2013), and Adobe® Reader® X or higher.

1.4 RELATED INFORMATION

1.4.1 QCS/RMS Contractor-Mode User Guide

After contract award, download instructions for the installation and use of QCS/RMS Contractor-Mode from the Government RMS Internet Website. In case of justifiable difficulties, the Government will provide the Contractor with a CD-ROM containing these instructions at the Contractor’s request.

1.4.2 Contractor Quality Control (CQC) Training

The use of QCS/RMS Contractor-Mode will be discussed with the Contractor's QC System Manager during the mandatory CQC Training class. The Contracting Officer may arrange for additional training in the use of the software if requested, however the Contractor is expected to understand the concepts and principles of Quality Control prior to requesting training on the use of the software.

1.5 CONTRACT DATABASE

Prior to the pre-construction conference, the Government will provide the Contractor with basic contract award data to use for QCS/RMS Contractor- Mode. The Government will provide data updates to the Contractor as needed, generally by using the Government's SFTP repository built into QCS import/export function or RMS Contractor-Mode “sync info” function. These updates will generally consist of submittal reviews, correspondence status, QA comments, and other administrative and QA data.

1.6 DATABASE MAINTENANCE

Establish, maintain, and update data in the QCS/RMS Contractor-Mode database relating to the contract and Contractor libraries throughout the duration of the contract to the maximum extent feasible. Submit data updates to the Government using the Government's SFTP repository built into QCS export function or RMS Contractor-Mode “sync info” function. If permitted in writing by the Contracting Officer, e-mail or other electronic transmission, such as CD-ROM or DVD-ROM may be used in lieu of the SFTP site.

The QCS/RMS Contractor-Mode database includes, but is not limited to, data on the following items:

1.6.1 Administration

1.6.1.1 Contractor Information

The Contractor's name, address, telephone numbers, management staff, and other required items.

1.6.1.2 Subcontractor Information

Name, trade, address, phone numbers, and other required information for all subcontractors, including amount subcontracted. Assign each subcontractor/trade a unique Responsibility Code.

1.6.1.3 Correspondence

Identify all Contractor correspondence to the Government with a serial number. Prefix correspondence initiated by the Contractor's site office with “S”. Prefix letters initiated by the Contractor's home (main) office with "H". Letters must be numbered starting from 0001. (e.g., H-0001 orS- 0001). The Government's letters to the Contractor will be prefixed with "C".

1.6.1.4 Request For Information (RFI)

Exchange all Requests For Information (RFI) using the Built-in RFI generator and tracker.

1.6.1.5 Management Reporting

QCS/RMS Contractor-Mode includes a number of reports that Contractor management can use to track the status of the project. The value of these reports is reflective of the quality of the data input, and is maintained in the various sections of QCS/RMS Contractor-Mode. Among these reports are:

Progress Payment Request worksheet, QA/QC comments, Submittal Register Status, Three-Phase Inspection checklists.

1.6.2 Finances

1.6.2.1 Pay Activity Data

Include within the QCS/RMS Contractor-Mode database a list of pay activities that the Contractor must develop in conjunction with the construction schedule. All pay activities must be linked to the appropriate feature of work, and include scheduled start and finish dates, updated to the actual dates as they begin and end. Each pay activity may only be linked to a single feature of work.

The sum of all pay activities must be equal to the total contract amount, including modifications. Group pay activities Contract Line Item Number (CLIN); the sum of the activities must equal the amount of each CLIN. The total of all CLINs equals the Contract Amount.

Unless approved in writing by the Contracting Officer, the Pay Activities shall be identical to those identified on the project schedule.

1.6.2.2 Payment Requests

Prepare all progress payment requests using QCS/RMS Contractor-Mode.

Complete the payment request worksheet, prompt payment certification, and payment invoice in QCS/RMS Contractor-Mode. Update the work completed under the contract, measured as percent or as specific quantities.

A signed paper copy of the approved payment request is also required, which will govern in the event of discrepancy with the electronic version.

1.6.3 Quality Control (QC)

QCS/RMS Contractor-Mode provides a means to track implementation of the 3-phase QC Control System, prepare daily reports, identify and track deficiencies, document progress of work, and support other Contractor QC requirements. Maintain this data on a daily basis. Entered data will automatically output to the QCS/RMS Contractor-Mode generated daily report.

Provide the Government a Contractor Quality Control (CQC) Plan within the time required in Section 01 45 01 USACE QUALITY CONTROL. Within seven calendar days of Government acceptance, submit a QCS/RMS Contractor-Mode update reflecting the information contained in the accepted CQC Plan:

schedule, pay activities, features of work, submittal register, QC requirements, and equipment list.

1.6.3.1 Contractor Quality Control (CQC) Reports.

QCS/RMS Contractor-Mode includes the means to produce the CQC Report. The Contractor may use other formats to record basic QC data. However, the Daily CQC Report generated by QCS/RMS Contractor-Mode must be the Contractor's official report. Summarize data from any supplemental reports by the Contractor and consolidate onto the QCS/RMS Contractor-Mode-generated Daily

CQC Report. Also provide the Government a signed, printed copy of the daily CQC report.

1.6.3.2 Deficiency Tracking.

Use QCS/RMS Contractor-Mode to track deficiencies. Deficiencies identified by the Contractor will be numerically tracked using QC punch list items.

Maintain a current log of punch list items in the QCS/RMS Contractor-Mode database. The Government will log the deficiencies it has identified using its QA punch list items. The Government's QA punch list items will be included in its export file to the Contractor. Regularly update the correction status of both QC and QA punchlist items.

1.6.3.3 QC Requirements

Develop and maintain a complete list of QC testing, transferred and installed property, and user training requirements.

1.6.3.4 Three-Phase Control Meetings

Maintain scheduled and actual dates and times of preparatory and initial control meetings in QCS/RMS Contractor-Mode.

1.6.3.5 Labor and Equipment Hours

Log labor and equipment exposure hours on a daily basis and complete the monthly reports for exposure hours using QCS/RMS Contractor-Mode.

1.6.3.6 Accident/Safety Reporting

The Government will issue safety comments, directions, or guidance whenever safety deficiencies are observed. The Government's safety comments will be included in its export file to the Contractor. Regularly update the correction status of the safety comments. In addition, utilize QCS/RMS Contractor-Mode to advise the Government of any accidents occurring on the jobsite. This brief supplemental entry is not to be considered as a substitute for completion of mandatory reports, e.g., ENG Form 3394 and OSHA Form 300.

1.6.3.7 Features of Work

Identify all features of work and develop the proposed schedule (dates for conducting the preparatory and initial inspections). Identify all critical inspection checks using the “3-Phase Inspections” screens, and utilize the preparatory and initial meeting minutes generated by QCS/RMS Contractor-Mode to conduct these meetings.

1.6.3.8 Hazard Analysis

Use QCS/RMS Contractor-Mode to develop a hazard analysis for each feature of work included in the CQC Plan. Address any hazards, or potential hazards, that may be associated with the work.

1.6.3.9 Equipment

Contain within the Contractor's QCS/RMS Contractor-Mode database a current list of equipment planned for use or being used on the jobsite, including the most recent and planned equipment inspection dates.

1.6.4 Submittal Management

Maintain a complete list of all submittals, including completion of all data columns. Dates on which submittals are received and returned by the Government will be included in its export file to the Contractor. Use QCS/RMS Contractor-Mode to track and transmit all submittals. ENG Form 4025, submittal transmittal form, and the submittal register update must be produced using QCS/RMS Contractor-Mode. QCS/RMS Contractor-Mode and RMS/RMS Government-Mode will be used to update, store and exchange submittal registers and transmittals. QCS will not be used for storage of actual submittals. RMS Contractor/Government-Mode will be used for storage of actual submittals.

1.6.5 Schedule

Input and maintain in the QCS/RMS Contractor-Mode database the construction schedule either manually or by using the Standard Data Exchange Format (SDEF) (see Section 01 32 01.00 10 PROJECT SCHEDULE). Include with each pay request the updated schedule.

1.7 IMPLEMENTATION

Contractor use of QCS*/RMS Contractor-Mode as described in the preceding paragraphs is mandatory. Ensure that sufficient resources are available to maintain the QCS/RMS Contractor-Mode database, and to provide the Government with regular database updates. QCS/RMS Contractor-Mode shall be an integral part of the Contractor's management of quality control.

1.8 MONTHLY COORDINATION MEETING

Update the QCS/RMS Contractor-Mode database each workday. At least bi-weekly (every two weeks), generate and submit an export file to the Government with schedule update and progress payment request. As required in Contract Clause "Payments", at least one week prior to submittal, meet with the Government representative to review the planned progress payment data submission for errors and omissions.

Make all required corrections prior to Government acceptance of the export file and progress payment request. Payment requests accompanied by incomplete or incorrect data submittals will be returned. The Government will not process progress payments until an acceptable QCS/RMS Contractor- Mode export file is received.

1.9 NOTIFICATION OF NONCOMPLIANCE

The Contracting Officer will notify the Contractor of any detected noncompliance with the requirements of this specification. Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, will be deemed sufficient for the purpose of notification.

PART 2 PRODUCTS [Not Used]

PART 3 EXECUTION [Not Used]

-- End of Section --

PART 1 GENERAL
1.1 Contract Administration
1.1.1 Correspondence and Electronic Communications
1.1.2 Other Factors
1.2 QCS/RMS CONTRACTOR-MODE SOFTWARE
1.3 SYSTEM REQUIREMENTS
1.3.1 Recommended Hardware Requirements
1.3.2 Minimum Software Requirements
1.4 RELATED INFORMATION
1.4.1 QCS/RMS Contractor-Mode User Guide
1.4.2 Contractor Quality Control (CQC) Training
1.5 CONTRACT DATABASE
1.6 DATABASE MAINTENANCE
1.6.1 Administration
1.6.1.1 Contractor Information
1.6.1.2 Subcontractor Information
1.6.1.3 Correspondence
1.6.1.4 Request For Information (RFI)
1.6.1.5 Management Reporting
1.6.2 Finances
1.6.2.1 Pay Activity Data
1.6.2.2 Payment Requests
1.6.3 Quality Control (QC)
1.6.3.1 Contractor Quality Control (CQC) Reports.
1.6.3.2 Deficiency Tracking.
1.6.3.3 QC Requirements
1.6.3.4 Three-Phase Control Meetings
1.6.3.5 Labor and Equipment Hours
1.6.3.6 Accident/Safety Reporting
1.6.3.7 Features of Work
1.6.3.8 Hazard Analysis
1.6.3.9 Equipment
1.6.4 Submittal Management
1.6.5 Schedule
1.7 IMPLEMENTATION
1.8 MONTHLY COORDINATION MEETING
1.9 NOTIFICATION OF NONCOMPLIANCE
PART 2 PRODUCTS [Not Used]
PART 3 EXECUTION [Not Used]