Design and Construction Schedule Specification

View the file

Other files

File Type Posted
W912GB-16-R-0001-0003.pdf PDF
W912GB-16-R-0001-A0002.pdf PDF
W912GB-16-R-0001-A0001.pdf PDF
Site_Visit_Information.pdf PDF
0790003_E800.pdf PDF
0790003_E801.pdf PDF
FIO-_Future_Utility_Project_by_Others.pdf PDF
Solicitation_A2_ExperInfoSheet.docx DOCX document
Solicitation_A1_ExperienceOverviewSheet.docx DOCX document
Solicitation_A3_PastPerformanceClientForm.docx DOCX document
CAD_Files.7z 7Z file
W912GB-16-R-0001.pdf PDF
DB_RFP_Dec_2015.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 01 00 00.00 44 Page 1

SECTION 01 00 00.00 44

DESIGN AND CONSTRUCTION SCHEDULE

10/2015

PART 1 GENERAL

1.1 SCHEDULE

Commence, prosecute, and complete the work under this contract in accordance with the following schedule and Section CONTRACT CLAUSES COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK and LIQUIDATED DAMAGES:

Item of Work Commencement of

Work (calendar days) Completion of Work (calendar days)

Liquidated Damages per calendar day*

1.

Construct Northern 20 MVA (18 MW) Substation and associated Transformer Building, complete with all associated work.

Upon notice of receipt of NTP

720 1880 Euros

2. Construct Upgrades to existing Southern substation located in Landstuhl in order to provide 20 MVA (18MW) of power to the new transformer station located south of hospital project site, Complete with all associated work.

Upon award and issuance of NTP

540 1880 Euros

3. Design Services, Complete with all associated work.

Upon notice of receipt of NTP

180 None

5. Operation and Maintenance Manuals

See Note ** See Note ** None

6. Record Drawings See Note *** See Note *** None

a. All work on this project shall be completed within the number of calendar days stated above, inclusive of all review periods and Government phasing requirements specified. If the Government accepts a proposal for a completion period of lesser duration, and such proposal alters the time periods for review and phasing, the Contract shall be read to include the original periods for review and phasing. If a completion period of lesser duration is proposed and accepted by the Government, the accepted completion period will replace the original construction schedule listed above in the Schedule. If an alternate completion period is proposed, the Bid Schedule must reflect pricing information for the alternate proposed completion period. The liquidated damages stated above will be applied for each calendar day the Contractor exceeds the Contract scheduled duration.

Section 01 00 00.00 44 Page 2

b. Liquidated damages for individual items of work will not be combined.

Only the rate of the affected item of work will be assessed. The Liquidated damages noted above are for the entire project and are not by Contract Line item.

** Operation and Maintenance Manuals: 3 copies of approved O&M Manuals for each building shall be turned in to the Government 60 days before completion of the respective Item of Work. See Section CLOSEOUT SUBMITTALS, paragraph

OPERATION AND MAINTENANCE MANUALS.

*** Record Drawings: See Section CLOSEOUT SUBMITTALS, paragraph titled

RECORD DRAWINGS.

1.2 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (OCT 1989)

(ER 415-1-15)(52.0001-4038 1/96)

a. This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause FAR 52.249-10 entitled "DEFAULT: (FIXED PRICE CONSTRUCTION)." In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.

b. The following schedule of monthly anticipated adverse weather delays due to precipitation and temperature is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities. Wind is not considered in the Monthly Anticipated Adverse Weather Calendar Day Schedule.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

_4_ _4_ _4_ _4_ _6_ _4_ _3_ _3_ _4_ _4_ _3_ _4_

c. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day.

The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each

Section 01 00 00.00 44 Page 3 month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph "b", above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "Default (Fixed Price Construction)."

1.3 CONSTRUCTION PHASING

1.3.1 Phasing Requirements

Not Used

1.3.2 Superintendence of Subcontractors

a. The Contractor shall be required to furnish the following, in addition to the superintendence required by the Contract Clause entitled "SUPERINTENDENCE BY CONTRACTOR As a minimum, 2 superintendants shall be provided.

1.4 WORK RESTRICTIONS

Not used

1.4.2 Working Hours

Normal working hours are Monday through Friday, 0700 to 1700 hours.

Requests to work at times other than the stated working hours, including scheduled utility outages discussed below, shall be submitted to the Contracting Officer for approval. Contractor shall not work outside of the above stated working hours without prior written approval of the Contracting Officer.

1.4.3 Security Requirements

1.4.3.1 Installation Entrance Requirements

For the duration of this Contract, access to the hospital construction site will be coordinated with the USACE Project Engineer assigned to this contract.

1.4.4 Identification of Employees

The Contractor shall be responsible for furnishing to each employee, and for requiring each employee engaged on the work to display, identification as approved and directed by the Contracting Officer. Contractor and subcontractor personnel shall wear identifying markings on hard hats clearly identifying the company for whom the employee works.

Contractor personnel shall wear visible Contractor-furnished employee identification badges while physically on the Installation. Each badge shall include, as a minimum, the company name, employee name, photograph, Contract Title, Contract Number, and the expiration date of the badge.

Section 01 00 00.00 44 Page 4

1.5 UTILITIES

1.5.1 Payment for Utility Services

In accordance with Contract Clause 52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES, gas, and electricity are available from Government-owned and operated systems and will be furnished with a charge to the Contractor.

a) Use of Government services:

(1) Contractors must reimburse Government for utilities usage (electricity, gas, water, sewer, and refuse) for admin trailer and construction sites.

(2) A utilities sales agreement must be signed by Contractor prior to connection/use of utilities services.

(3) Contractor must provide all metering devices for trailer and construction project.

(4) Current utilities rates can be obtained from 254-287-7671.

b) Meters and Temporary Connections

The Contractor, at its expense and in a manner satisfactory to the Contracting Officer, shall provide and maintain necessary temporary connections, distribution lines, meters, and meter bases required measuring the amount of each utility used for the purpose of determining charges. The Contractor shall notify the Contracting Officer, in writing, 5 working days before utility (gas, water, sewer, electricity) connection is desired so that a utilities contract can be established. The Contractor will provide a meter and make the final hot connection after inspection and approval of the Contractor's temporary wiring installation. Sewage usage is based on water usage and does not require a meter.

c) Advance Deposit

Not Used

d) Final Meter Reading

Before completion of the work and final acceptance of the work by the Government, the Contractor shall notify the Contracting Officer, in writing, 5 working days before termination is desired. The Government will take a final meter reading; and thereafter, the Contractor shall disconnect service, and remove the meters. The Contractor shall also remove all the temporary distribution lines, meter bases, and associated paraphernalia. The Contractor shall pay all outstanding utility bills before final acceptance of the work by the Government.

Section 01 00 00.00 44 Page 5

1.5.3 Outages

The Contractor shall coordinate all requests for utility outages with the Contracting Officer and local utility provider (where applicable) in writing 14 days prior to date of requested outage:

a. Water, gas, steam, and sewer outages shall be held to a maximum duration of 4 hours unless otherwise approved in writing.

b. Electrical outages shall have a maximum duration of 4 hours.

c. All utility outages shall be scheduled only on Saturdays, Sundays, or holidays unless specific approval is otherwise received.

1.6 STREET CLOSINGS

The Contractor shall coordinate all requests for street closings with the Contracting Officer in writing 14 days prior to date of requested outage:

a. One lane traffic shall be maintained at all times (except that a total closing may be allowed for specific 8-hour periods).

b. No open cut will be allowed for street crossings. All street crossings shall be by jack and borings.

1.10 SEQUENCE OF DESIGN/CONSTRUCTION (FAST TRACK)

(a) After receipt of the Contract Notice to Proceed (NTP) the Contractor shall initiate design, comply with all design submission requirements as covered under Division 01 General Requirements, and obtain Government review of each submission. The Contractor may begin construction on portions of the work for which the Government has reviewed the final design submission and has determined satisfactory for purposes of beginning construction. The Contracting Officer will notify the Contractor when the design is cleared for construction. The Government will not grant any time extension for any design resubmittal required when, in the opinion of the Contracting Officer, the initial submission failed to meet the minimum quality requirements as set forth in the Contract.

(b) If the Government allows the Contractor to proceed with limited construction based on pending minor revisions to the reviewed Final Design submission, no payment will be made for any in-place construction related to the pending revisions until they are completed, resubmitted and are satisfactory to the Government.

(c) No payment will be made for any in-place construction until all required submittals have been made, reviewed and are satisfactory to the Government.

1.11 Contractor Design Team

The Contractor shall have their design team established in the field during construction. This includes designers that have the authority to make changes to omissions and errors made during the design phase of the project. A representative of each discipline shall be stationed in the field during the complete construction phase of the project.

Section 01 00 00.00 44 Page 6

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)