Amendment 0001 Channel Borrow Maps.pdf
PDF 4 MB Posted
- Solicitation number
- W912ES26BA009
About this file
This document contains channel survey maps and dredging volume data for four Habitat Restoration and Enhancement Project (HREP) sites along the Upper Mississippi River, prepared by the U.S. Army Engineer District, Corps of Engineers, St. Paul, Minnesota. The surveys were conducted in April 2024 and adjusted to specific Low Water Plane (LCP) elevations ranging from 609.7 to 610.4 feet.
The four project areas include: Catfish Slough (River Miles 625.9-627.0) with total dredging volumes of 57,765 cubic yards across three cuts; Hovie Island HREP with 23,899 cubic yards across four cuts; Upper Approach to L&D 10 HREP with 27,687 cubic yards across two cuts; and McMillan HREP (River Miles 617.5-619.5) with the largest volume of 166,865 cubic yards across five cuts. All volume quantities include 2:1 side slopes and are based on survey data current as of April 2024. The document notes that final quantities and cut priorities will be determined by the government at time of dredging, and identifies anticipated granular borrow channel dredging locations for four stages of work: Catfish Slough Stages 2 & 3, Hovie Island Stages 2 & 3, Upper Approach to LD10 Stage 1, and McMillan Island Stage 1. The maps display depth contours at 9' and 10.5' intervals with detailed planview layouts showing cut boundaries and excavation areas.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Abstract W912ES26BA009 Pool 10_Final .pdf | ||
| Amendment 0001 Full Spec Sections.pdf | ||
| Amendment 0001 W912ES26BA009 SF 30.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0 0
0 0 0 0 0 0
RR M e 90
3,814,000 + +
3,812,000 +
3,810,000 +
3,808,000
3,806,000 + +
3,804,000 + +
< 9.01 19 Apr, 2024 0 0
9.01 0 0 0 0
<i 00 � � >= 10.50 � � o usin Lower Lt. (627.2)
D
Island No. 177 a
42,48,4 1,38,35,34,31,28,25,22, 19, 14 42,49,43 37,36,34,33,28,24,21 1 8, 16, 1 2 40,45,46,40, 39,35,31,27,25 21, 1 8, 17, 18, 14, 35,42,45,43,37,32 29,27,29 25,24,21, 17, 14, 12, 40,42,40 35,31,28,29,26 23,22, 19, 17, 15 13, 1 36,40,38,35,31,28,26 23,23,22, 19, 16, 14, 11, 1 31,4 1,39, 35,32 28,25,27,26,22,21 18, 16 12 9, 21,38,43 42 38,34 31,28,24,21,19, 19 15, 12,1 , Island No. 178 a
36,39741135,33,31 27123,22,alO, 16, 161 13, 1 31,37,36,35,34,30,27,23,21"s, 16, 15, 12, 1 26,35,34,34,33,30,27,25,22 1 8, 16, 1 5, 12, 11, 21,31,33,35,36 34,32,28,24,20, 16, 13, 11, 11
28,30, 34,33,32 30,29,27 ,22,20, 19, 16, 14 25,29,30,30,31,30,29,26,24,22 19, 16, 13, 7, 7, 24 27,28,28,29,29,28,28,29,25,21, 16, 13, 12 8, 6,, 26,27,28,29,28,27,29,28,24,24,23, 19, 12, 7, 6, 6., 25,26,27 ,26,26,29,27,25,25,24,21, 19, 19, 1 5, 7, 5., 24,24,25,25,26,26,26,25,25,22,21,20, 17 15 1
22,23,24,25,25,25,28,24,23 24!1, 16, 14, 13, 12, 11 23,22,23,23,26,27 25,23,23121, 18;17 16 14, 13, 121 1
23,23,24,24,23,22,22,21,20, 1 8,21, 1 8, 1 5, 14, 12, 1 25 22,23,22,22,22 21,26,25,22, 19, 16, 1 5, 14, 13, 12 24,26,25,23,22,26,25,24 22,20g 1 8, 16, 17, 19 16, 13, 12
24,24,25,26,24,23 23,21,20 18, 17, 19,18, 16, 13, 13 1 23,23,25,23,22,22,21,20, 19, 18 22,20, 17, 15 1 5, 12, 12 24,24,23,22,21,22 20,20,25,22,21, 1 8, 1 5, 1 8, 16 14, 12 1
23,22 21,20,21,26,26,23,21, 19, 17, 19, 17, 15, 13, 13, 1 1
22,22,22,25,25,25 23,22,21 21 21,18 15, 15, 14,13, 13 24,25,24,23,24,22,20,20,21, 1 iji.7, 16, 17, 15 13, 12, 11 21,24 24,24,22,20,20,21 18, 17, 17 17, 15, 14, 14, 11, 12, 1 22,22,23,23,22,21,22,20, 1 8, 17, 19\ 16, 14, 1 5, 13, 13, 12, 11
21,21,21,22,23,24,26,23,21, 18, 18, 16, 16, 14, 12, 12, 12, 20, 19,20,21 21,21,22,21 19, 19, 17, 16, 14, 14, 13, 13, 12, 1
19,19,19,19,19,19,19,18,17,16,15,15,14,13 12 12,12, 18, 18, 19, 18, 18, 18 17, 17 16, 16, 17, 15, 14, 13 12 12, 12, 11
18, 19, 18, 18, 17, 16, 16, 18 17, 15, 15, 14, 14, 12, 13, 12, 12, 1 19, 18, 18, 17, 17, 16, 17, 17 16, 16, 15, 15, 13, 13, 12, 13, 13, 11.,• 17,18 17,18,20,19,17,15,17,16,1513,13,12,12,13 12,11,1\
17,18,19,18 17,18,17,16,18,11ji,.6,14,14,13,12,12 _)1, 20 18,17,18 1917,17,18,16,15,15,14 11,13 ,11, 16,16,16,17,15,18,15,15,15, ,13,13 11,13,12,12 1 ,11, 15,16,18,15,n�15,15,14,1 ,12,1 3 1 2,12 13,12,1 11, 18, 18, 16, 15, �1�15, 17, 16, 14 14\ 13, 12, 12, 12, 13, 11 2, 11, 16,18 17,18,17,17,15,14,14, 4,14,12,13 11,13,13 ,11, 151 15, 15, 15, 15, 15, 14, 14, 14 3, 131 13, 12, 11, 122 13, 1 , 12,w, 15,15,16,14,14,14,14 15,13 1 ,11,12,12,13,13,13,1 11,11, 17,15,15,16,16,15,13,15,1 13,13,12,13,11,11,12 13,11, "' SE
CUT-1
15 14, 14, 14, 14, 13, 13, 13 12, 13, 13 12, 13 13, 12 12, 3, 11, 11, 13,13 13,13,14,14212,13, 2,1�jl;:��5�5131 1,132 120
127 14114, 17, 15, 17 15 13, 1 , 12, 1Y,fr,YJ,'D, 13, 1 13, 1 l'i 16,16 15,14,14,14,13,1 14,15 14,13,12,13,12 13,14, 5 15,14,13,12,13,13 12,13 13,12,13,13,12,13,12, 2,1419, 13,13,13,12,12,12,12 12, 1,12,12,.13,12,12,13, ,11,17,15, 12,12,12 11,11,11,10, ,14,14,13,13,12,12,1 ,12,13,15 12, 12, 11, 12 14 14, 14, 1 12, 12,,1,, 13, 13, 12, 1 12, 14, 14 '
CATFISH SLOUGH
14, 13, 12, 12, 13, 13, 12 12, 12, 12, 13, 12, 11, 12, 11, 12 14, 1
� 12,12,11,12 13,12,12, 2 12112811,12111,12, 713,15,127
11, 11,11, 12 11, 11, 1 1 5 , 1 ,12, 13, 12, 1 , 10 1 11,1 , 3111_2,12 11,11,1,14,14,1311, ""''"'""' 12, 11, 11';'1-, 12, 12, 12, 1 12, 12, 12, 12 1�,1 1 1111,1110,11,1�,11,1;..11,11,1312,12,12,14, VOLUMES- PLANVIEW@ 12.3'
CUT-1
CUT-2
CUT-3
TOTAL
1,317 CU YDS
26,407 CU YDS
30,041 CU YDS
57, 765 CU YDS
1 ,f\.J.'1'�� 1,1:i,11,t1>,1'f,11,12,13, 3,13,13,1414, �,12, , 12 11,11,12,12, ,11,13,14,15
13, 11, 11 o, 11, 12, 12, 1 14, 13, 12, 12, CUT-2
'p'dr'l;'.'11 oe.�) "• n, 1,11,1:T,13� :it,1'1,1h ,11,11,12,12 12,13,1:iil, 'J
. �11,12,12 12,15,2 ...Plf2)fl"'5S "t-?, 1, 11, 12, 4 14,23, _12011,11, ,15,22,35, 1�12,12,1 ,14,17,29,34, , 'l,n'; -11,1 13,17,21,26,35, 10 1 1, 1 13, 16,22,22,25,26 1 12 13, 16,20,20 18, 18, ,13, 13,16,19,17,16 14,1
13, 4 15,18,17,14�13, ll, ,13, 3,14,16, 14,13,11 0 8, 1,12,13 15,15,14,13,11, Methodist Lake -----
CUT-3
, 12, 13, 13, 13, 14, 15, 16 , 15, 15, 15, 13, 14, 14, 19, 3 14,13,12,13,16 1721, o1Ql13, 14, 14, 17,19, 5,14 14,15,15,16,19
,1313 14,15,16,15,17,19,2, ,13,15 14,14,14,16,18,18,1 , 9, ,11,12, 3,13,14,14,15,16,19,22, 12,13, 5,14,14,16,19,17,18,22, ,12,12, 2,13,14,16,17,17,18,21, 1 11,12, ,14 14,15,15,1717,20,17, 12 1 ,12,12, 1 0,11,12,1 ,13,15,17,17,16,18,19,16, 12 1 ,11,11,�3 11,11,11,1 ,14,14,14,15,15,19,21,16, 7cs11,1 ,11,11,11 1112 _ ,13,14,13,13,17,20,20,16, , 12 11, 11, 12, 13, 12, 13, 13, 14, 15, 17, 19, 19, 18, 17, 17, 19, 17, 17,18 17, alusing Slough
" Clayton D c:J
) [j &625.5
+ + Island No. 181 a
Clayton, IA
Scale: 1 Inch = 40 00 Feet
500 1000 2000 3,00
"' "' � � � 0
0 0 0 0 0 0
Glass Lake
N w s
UM_SP _P10_20240409_CS_6259_6270
U.S. ARMY ENGINEER DISTRICT
CORPS OF ENGINEERS
ST. PAUL MINNESOTA
Catfish Slough - HREP
River Miles: 625.9 - 627.0
Depths Adjusted To L.C.P.
E
Vertical Control -NAVO 88 International Feet
Y381200
Y381000
3 808 00
WCM
Horizontal Control DGPS NAO 83 - State Plane - I A -North International Feet
DTF SCALE: 1" = 400'
CWA
LAUNCH: 22
CONTOURS: 9' & 10.5'
SURVEY DATE: 09 APRIL 2024
LCP: 610.4 WS: 611.7
b6coprm1 Text Box Notes about Channel Surveys:
1. Quantities noted only accurate as of date of surveys (APR 2024).
2. Quantities to include 2:1 side slopes.
3. Quantities and cut priorities to be determined by the Gov't at time of dredging.
4. Anticipate granular borrow channel dredging locations to be used as follows:
- Catfish Slough - Stages 2 & 3
- Hovie Island - Stages 2 & 3
- Upper Approach to LD10 - Stage 1
- McMillan Island - Stage 1 b6coprm1 Text Box Notes about Channel Surveys:
1. Quantities noted only accurate as of date of surveys (APR 2024).
2. Quantities to include 2:1 side slopes.
3. Quantities and cut priorities to be determined by the Gov't at time of dredging.
4. Anticipate granular borrow channel dredging locations to be used as follows:
- Catfish Slough - Stages 2 & 3
- Hovie Island - Stages 2 & 3 b6coprm1 Text Box Notes about Channel Surveys:
1. Quantities noted only accurate as of date of surveys (APR 2024).
2. Quantities to include 2:1 side slopes.
3. Quantities and cut priorities to be determined by the Gov't at time of dredging.
4. Anticipate granular borrow channel dredging locations to be used as follows:
- Catfish Slough - Stages 2 & 3
- Hovie Island - Stages 2 & 3
3,780,00 + +
Frenchtown Lake
3,778,00 + +
RR ile 81
3,776,00 +
3,774,00 + +
3,772,00 + +
R ·Ie 80
16 Apr, 2024 e
5,31,28,25,24,24,24,23,22,21,20,20, 18, 15, 12, 12, 12, 30,27,24,24,24,24,22,22,22, 19, 19, 1 8, 17, 14, 12, 27,26,26,28,29 28 27,26,24 24,21 21, 17, 15,13, 1f 24,24,27,26,25,25,24,24,E@rt:@!§19, 18, 16, 13, 1 , 24,26,26,23,23,23,22,22,21,20, 19, 18, 17, 16, 16 15 14, ,, ' \ A1�fri'3,23,22,22,21,20, 19,19 1 181 17, 16, 14, 14, 12, 11, 1
,v ��S,3,27,28,27 21,20, 19, 18, 17, 17 16, 13, 12, 12, 1), 1 22,22125,26,25124724,24,24,21, 185 177 157 15 12, 12, ffs1 25,23,24,23,22,22,22,21,21,21,21,21 20, 17, 13, 13, 13, 1 23,26,25,24 21,21,21,20,20,20,21,22 20, 19, 17, 15 14 1 21,24,,24,25,26,25,26,24,24,23,20, 1 8, 1 8, 18, 17, 16, 14, 12, 22,22,23,22,22,23,22,22,20, 18, 17, 17, 16, 15, 14, 14 13, 11.
20,20,20,21,21,21,21,20, 19, 1 8, 17, 16, 16, 14, 14, 13, 12, 11, 11, 20, 19, 19, 19,20,20,20, 19, 18 141,19, 17, 16, 15, 13, 13, 13, 12, 11, 22 20, 19122 21220, 19, 19,20,20, 191 18, 18, 17, 16, 141 12,;o, 12 e
22,24,23 20, 19,22 21,20 1 8, 17, 17, 16, 1 5, 15, 14, 13, 14, 13, 1 22 23 21,21,22,20, 19, 18, 18, 17, 16, 16, 15, 14, 13, 13 13 12, 11, 20,21,20,20,19,19,18,18,19,18 18 16,15,14,13,12,12,11,11 9, 20 19, 19,20, 19, 19,23,22,22, 17, 17, 17, 17 15, 13, 13, 11, 12, 11 20, 1 8, 1 8, 17,20,20,20, 19, 19, 19, 19, 19, 17, 16, 14, 14, 12, 11 e
20,22,22,20, 18, 18, 18, 18, 18, 18 17, 17, 17, 16, 15, 12, 11, 21,22,21,19 19, 19,18, 17, 17, 17,16, 17 16, 16,15, 14, 13, 13,1 , 21,21,20,21,21,21,20,21,21,21,20,20, 19, 19, 18, 17 15, 14, 13, 12,1
20,22 19,19,18,18,19,19 18,18�,17,17,16,15,14,14 13,12,11, 20, 19, 19, 19,20,20, 19, 18, 17, 17, 16, 17, 16, 16 15, 14, 13, 12, 12, 11
19, 18,21, 18, 17, 17, 16, 16, 16, 16 16, 16, 15, 14, 14, 13, 12, 12, 11, 21,21, 19 17, 16, 16, 15, 15, 15, 16 15, 15, 17, 15, 14, 14, 13, 12, 1 e
8, 6, 's, 20,20, 18, 17, 16, 15, 16 15, 19 18, 16, 16, 16, 15, 15, 14, 13, 13, 11, 13, 11, 19, 19, 18,17 19, 18, 17, 16, 16, 15, 15, 15, 14, 14, 13, 13, 12, 11, 11,11, 18, 17, 17 18 18, 17, 16, 15, 15, 15, 14, 14, 14, 14, 13, 12, 11, 11, 12 1
16,17,18,16,16,15,15,14,15,14,14,14,13,1313 12 1\1 16 19, 17, 16, 15, 15, 14, 14, 15, 14, 14, 14, 13, 12, 12, 11, 18,15,15 15,17,17,16,15,1514111_4,14,12,12,11, 16, 16, 18, 18 15, 14, 14, 14, 14, 1f,'T',t, 14, 13, 12, 12, 15,15,15,14,14,14,13,13,13,12,13,13,13,12,12,11,11,1113 11 9, 14, 15, 14, 13, 13, 13, 13, 14, 17, 16, 15, 15, 14, 14, 13, 13, 13, 12, 11, 12, 15, 14, 13, 13, 15, 16, 15, 15 16, 15, 15, 15, 14, 13, 13, 13, 12, 12, 13
12, 12, 15,14, 14, 15, 15, 13, 13, 13, 13, 14, 13, 13, 13, 12, 12 11, 15, 16, 16, 14, 15, 15, 13, 12, 13, 12, 12, 13, 13, 13, 12, 12, 13, 12
14, 14, 15, 15, 13, 12, 12, 12, 12 12, 11, 12, 12, 12, 12, 11, 11 13 15,14,13,13,14,13,13,14,12,12,12 11,11,12,12,1
14,13 13,12,11,12,12 12,12,13,12,13,13,12, 13 12, 12, 11, 11, 12, 13, 14, 14, 13Mi, 13, 13, 12
11, 11, 13, 13, 12, 12, 12, 12, 12, 12, 12, 1 'i3, 13, 12, 11,12, 15, 14, 14, 14, 13, 1 11, 11, 11, 12,11,12, 12, 12
12, 12, 12, 12, 12,, 12, 12 3, 13, 13, 13, 13, 2 , ,12 1313,1314,13
11,11,11,11,11,11,14 13,13,1 10 11 11,13,13,12,13,13,1
, 1 14, 13 12, 12, 13 i
0,13,12,12,1itlt::1f ,tli, 11, 11, 11,11, 11, 1r,'1}, ;'tj, 11, 1 -11, 13, 12, 11, 12, 11, 12, 12, 12, 12, 12, 12,12, 11, 12, 12, 11.,11, 11, 12,1�,11,11,1 12, 1 ,. � 11, 12, 11, 3 14 13,12,13,12, ,14,13,13,13,13 13, 12, 14, 13, 13, 12, 13 1 12,11,13 )3 12,1 1,J0, 12, 13 12, 1 :'ro, 11, 12.12, 1
, 13, 12, 12, , 11;a1,12, 12, 1 ,1�;12 11,12, ,13,13,13,13,12, 12,12,15,14,13, 12, 13 13
MCMILLAN HREP
VOLUMES- PLANVIEW@ 12.3'
CUT-1
CUT-2
CUT-3
CUT-4
CUT-5
TOTAL
37,016 CU YDS
25,306 CU YDS
11,825 CU YDS
67, 164 CU YDS
25,554 CU YDS
166,865 CU YDS
Millan Island
D
CUT-2
CUT-4
3, 14, 13, 12, 1 2,13 13,13,1
1,1111,11,12 12,12,12,11,12 12, 12, 12,11, 12i-;2,,2.1, °"o,-;c,,, s1, 11, '146,110;;Jl't
8, 8, 6, 7, 7, 3., 7, 6, 5 7, 5, 3,, 1 , 11, 12, 12, 12, 12, 12, 12, 12 12 12, 12, 12, 12, 12, 11, 12 12, 12, 12, 12, 12
7 6,6,5, 7, 5, 3,, , o, 11, 12, 12, 12112, 12, 12, 7, 6, 3,, ''" 11, 12, 12, 11, 12, 12, 12, 0,1 1 • ,s12,12,12,12,11,1 1 ,7, 6, 3, ,12 ,11,12,12,12 12,11,11
10 11,11,11,12,11,12,12,11, 7,5;3,3, , 12, 11, 1.i,.12, 12, 11, 12, 1 1,12, 11, 12, 12,12, 11, 11, 1
, 14, 15, 1 114, 15 ,M
12, 12, 12, 12, 11, 12, 12, 9, , 11, 11, 12, 12, 12, 12, 12, 12, 12, 12
2,12,13,13,14,1 ,17, :, ''""""''" • ,s , 1.::l-,Y4: 'rf,;"ft1� 2,13,14,16,1 ,\!1
12, 12,, 14 16, 17 o 1 Fl(2) 5s
5, 17, 15, 17, 1 19, 19,23,22 0
M Millan I land Lower Lt. ( 17.2)
,11, 12, 15, 18, 19, 16, 16, 16, 18,2� 1 , 12, 13, 15, 18,20, 19, 14, 16, 17, 19,;tr,'t
, 13 15, 16, 19,20, 19, 18, 16, 18, 17,20,20, 1 13, 15, 17, 19,20,20, 19, 18, 16, 18 18, 19, 18, 19, 16, 1, 13, 16, 18,20,21,20,21, 18,17, 16, 17, 17, 18, 17, 17, ,14,16,18,20,21,22,21,20 18,17 19 16,18,15,17,12
1 13, 16, 19,20,21,22,22, 19, 19, 17, 16, 17, 14, 16, 14, 1 6 2, 16, 19,21222 22,21,19, 19...18 18,14, 16, 15, 17 1
6, 1 16, 19,21,22,22,22,21,20, 1� 6, 17, 15, 15, 13, 1 7, 7, 1, 18,21,22,23,23,21, 19,20, 17, 16, 18,17, 15, 14, 7, 7 5,21,22,24 23,22,21, 19,17, 18 17, 17,15, 16, 7 ,21,22,23,24,22;,21,20 18,18, 15, 17, 15,13,, 13, 16,23,23,24,24,24 20, 19,20, 17, 16, 14, 13, 14 J2 5,22,23,24,23,24,22,22, 1 8, 1 8, 16, 1 5, 13, 12, 1 1:
7,22,23,23,24 24,2-�Jpv.8,tr.7, 17, 13, 14, 11 1 , 19,23,23,23,24,22,ffld, 1�, 17 ,'f6, 1 5, 13 11 4,22,23 23,23,,24,22,20,20, 17, 17, 14, 15 11
Scale: Inch = 400.00 Feet
1000 2000 3000 Feet
·°' Stateline Sloug
R
Chase reek
R Mi e 23
N w s
Lower Pool 10 HREP-MISC
U.S. ARMY ENGINEER DISTRICT
CORPS OF ENGINEERS
ST. PAUL MINNESOTA
Lower Pool 10 HREP
River Miles: 617.5- 619.5
Depths Adjusted To L.C.P.
E
Vertical Control -NAVO 88 International Feet
Y378000
Y377800
Y377600
Y377200
WCM
Horizontal Control DGPS NAO 83 - State Plane - I A -North International Feet
TF JR SCALE: 1" = 400'
WAWJ
LAUNCH: 22
CONTOURS: 9' & 10.5'
SURVEY DATE: 3-14, 4-8&9 2024
LCP: 609.7, 609.8, 609.9 WS: 609.9, 610.6, 610.8
b6coprm1 Text Box Notes about Channel Surveys:
1. Quantities noted only accurate as of date of surveys (APR 2024).
2. Quantities to include 2:1 side slopes.
3. Quantities and cut priorities to be determined by the Gov't at time of dredging.
4. Anticipate granular borrow channel dredging locations to be used as follows:
- Catfish Slough - Stages 2 & 3
- Hovie Island - Stages 2 & 3
| Solicitation - W912ES26BA009 Professional Appearance_FrontEnd |
| Solicitation/Contract Form |
| Contract Administration Data |
| LP10 Stage 3_TechnicalSpecs_RTA |
| 00 00 00.00 COVER |
| PROJECT TABLE OF CONTENTS |
| DIVISION 01 - GENERAL REQUIREMENTS |
| 01 00 00.00 13 - GENERAL |
| 01 00 00.00 13 - GENERAL |
| PART 1 GENERAL |
| 1.1 ORGANIZATION OF SPECIFICATIONS |
| 1.2 USE OF REFERENCES |
| PART 2 PRODUCTS |
| 2.1 RECYCLED/RECOVERED MATERIALS |
| PART 3 EXECUTION |
| 3.1 DISPOSAL OF DEBRIS AND WASTE |
| 3.1.1 Burning |
| 3.1.2 Disposal offsite for useful purposes |
| 3.1.3 Disposal in a locally operated sanitary landfill |
| 3.1.4 Disposal of Solid Construction Debris and Waste |
| 3.2 SCHEDULING |
| 3.2.1 General |
| 3.2.2 Notification |
| 3.2.3 Lock and Dam Operations |
| 3.3 OTHER CONTRACTS AND WORK |
| 3.3.1 List of other contracts |
3.4 Other Work
| 01 14 00.00 13 - WORK RESTRICTIONS |
| 01 14 00.00 13 - WORK RESTRICTIONS |
| PART 1 GENERAL |
| 1.1 GROUNDS AND ROADWAYS |
| 1.2 STAGING AREAS |
| 1.3 BLASTING |
| 1.4 TREE CLEARING RESTRICTIONS |
| 1.5 ACCESS ROUTES AND ACCESS CHANNELS |
| 1.6 SUBMITTALS |
| PART 2 PRODUCTS Not Used |
| PART 3 EXECUTION |
| 3.1 EXISTING UTILITIES |
| 3.2 CONSTRUCTION PADS |
| 3.3 REMNANT ISLAND LAND ACCESS |
| 3.4 MARINE STAGING AREA |
| 3.5 TREE SURVEY |
| 3.6 PROTECTION OF TREES |
| 3.6.1 Restoration of Damaged Trees |
| 3.7 CONTRACTOR PROPOSED BORROW AND DISPOSAL AREAS |
| 3.8 FLOATING PLANT |
| 3.8.1 Equipment and Personnel |
| 3.8.2 Navigable Waters |
| 3.8.3 Sewage and Bilge Water Disposal |
| 3.9 WILDLIFE |
| 3.9.1 Bats |
| 3.9.2 Eagles |
| 3.9.3 Bank Swallows |
| 3.9.4 Fall Waterfowl Migration |
| 3.9.5 Mussels |
| 3.10 EXCLUSION ZONES |
| 3.11 EXISTING ISLAND EXCAVATION |
| 3.12 DEMOBILIZATION |
| 01 22 00.00 10 - MEASUREMENT AND PAYMENT |
| 01 22 00.00 10 - MEASUREMENT AND PAYMENT |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 COMPENSATION |
| 1.3 APPROVAL OF MATERIALS OR ALTERNATES |
| 1.4 QUANTITY SURVEYS |
| 1.5 MEASUREMENT BY WEIGHT |
| 1.6 MEASUREMENT UNITS |
| 1.7 SUBMITTALS |
| 1.8 JOB PAYMENT ITEMS |
| 1.8.1 BONDS Performance and Payment |
| 1.8.1.1 Payment |
| 1.8.1.2 Unit of Measure |
| 1.9 UNIT PRICE PAYMENT ITEMS |
| 1.9.1 BERM AND ISLAND CONSTRUCTION - GRANULAR FILL |
| 1.9.1.1 Payment |
| 1.9.1.2 Measurement |
| 1.9.1.3 Unit of Measure |
| 1.9.2 BERM AND ISLAND CONSTRUCTION - FINE FILL |
| 1.9.2.1 Payment |
| 1.9.2.2 Measurement |
| 1.9.2.3 Unit of Measure |
| 1.9.3 RIPRAP |
| 1.9.3.1 Payment |
| 1.9.3.2 Measurement |
| 1.9.3.3 Unit of Measure |
| 1.9.4 MUDPUPPY/MUSSEL HABITAT |
| 1.9.4.1 Payment |
| 1.9.4.2 Measurement |
| 1.9.4.3 Unit of Measure |
| 1.9.5 TURF ESTABLISHMENT |
| 1.9.5.1 Payment |
| 1.9.5.2 Measurement |
| 1.9.5.3 Unit of Measure |
| 1.9.6 WILLOWS |
| 1.9.6.1 Payment |
| 1.9.6.2 Measurement |
| 1.9.6.3 Unit of Measure |
| PART 2 PRODUCTS NOT APPLICABLE |
| PART 3 EXECUTION NOT APPLICABLE |
| 01 32 01.00 10 - PROJECT SCHEDULE |
| 01 32 01.00 10 - PROJECT SCHEDULE |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.3 PROJECT SCHEDULER QUALIFICATIONS |
| PART 2 PRODUCTS |
| 2.1 SOFTWARE |
| 2.1.1 Government Default Software |
| 2.1.2 Contractor Software |
| 2.1.2.1 Primavera |
| 2.1.2.2 Other Than Primavera |
| PART 3 EXECUTION |
| 3.1 GENERAL REQUIREMENTS |
| 3.1.1 Scheduling Expectations Kickoff MeetingSEKO |
| 3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS |
| 3.2.1 Level of Detail Required |
| 3.2.2 Activity Durations |
| 3.2.3 Procurement Activities |
| 3.2.4 Mandatory Activities |
| 3.2.5 Government Activities |
| 3.2.6 Standard Activity Coding Dictionary |
| 3.2.6.1 Workers Per Day WRKP |
| 3.2.6.2 Responsibility Code RESP |
| 3.2.6.3 Work Area Coding AREA |
| 3.2.6.4 Modification of Claim Number MODF |
| 3.2.6.5 Bid Item Coding BIDI |
| 3.2.6.6 Phase of Work Coding PHAS |
| 3.2.6.7 Category of Work Coding CATW |
| 3.2.6.8 Feature of Work Coding FOW |
| 3.2.7 Contract Milestones and Constraints |
| 3.2.7.1 Project Start Date Milestone and Constraint |
| 3.2.7.2 End Project Finish Milestone and Constraint |
| 3.2.7.3 Interim Completion Dates and Constraints |
| 3.2.7.3.1 Start Phase |
| 3.2.7.3.2 End Phase |
| 3.2.8 Adverse Weather |
| 3.2.9 Calendars |
| 3.2.10 Open Ended Logic |
| 3.2.11 Default Progress Data Disallowed |
| 3.2.12 Out-of-Sequence Progress |
| 3.2.13 Added and Deleted Activities |
| 3.2.14 Original Durations |
| 3.2.15 Leads, Lags, and Start to Finish Relationships |
| 3.2.16 Retained Logic |
| 3.2.17 Percent Complete |
| 3.2.18 Remaining Duration |
| 3.2.19 Early Completion Schedule and the Right to Finish Early |
| 3.3 PROJECT SCHEDULE SUBMISSIONS |
| 3.3.1 Initial Project Schedule Submission |
| 3.3.2 Periodic Schedule Updates |
| 3.4 SUBMISSION REQUIREMENTS |
| 3.4.1 Electronic Scheduling Data |
| 3.4.2 Narrative Report |
| 3.4.3 Schedule Reports |
| 3.4.3.1 Activity Report |
| 3.4.3.2 Logic Report |
| 3.4.3.3 Total Float Report |
| 3.4.3.4 Earnings Report by CLIN |
| 3.4.3.5 Scheduling and Leveling Report |
| 3.4.4 Network Diagram |
| 3.4.4.1 Continuous Flow |
| 3.4.4.2 Project Milestone Dates |
| 3.4.4.3 Critical Path |
| 3.4.4.4 Grouping and Sorting |
| 3.4.4.5 Cash Flow Schedule Variance Control SVC Diagram |
| 3.5 PERIODIC SCHEDULE UPDATE |
| 3.5.1 Periodic Schedule Update Meetings |
| 3.5.2 Update Submission Following Progress Meeting |
| 3.6 WEEKLY PROGRESS MEETINGS |
| 3.7 REQUESTS FOR TIME EXTENSIONS |
| 3.7.1 Justification of Delay |
| 3.7.2 Changes That Do Not Cause Delay |
| 3.7.3 Time Impact Analysis Prospective Analysis |
| 3.7.4 Forensic Schedule Analysis Retrospective Analysis |
| 3.7.5 Fragmentary Network Fragnet |
| 3.7.6 Time Extension |
| 3.7.7 Impact to Early Completion Schedule |
| 3.8 FAILURE TO ACHIEVE PROGRESS |
| 3.8.1 Artificially Improving Progress |
| 3.8.2 Failure to Perform |
| 3.8.3 Recovery Schedule |
| 3.9 OWNERSHIP OF FLOAT |
| 3.10 TRANSFER OF SCHEDULE DATA INTO RESIDENT MANAGEMENT SYSTEM |
| 3.11 PRIMAVERA P6 MANDATORY REQUIREMENTS |
| 01 33 00 - SUBMITTAL PROCEDURES |
| 01 33 00 - SUBMITTAL PROCEDURES |
| PART 1 GENERAL |
| 1.1 SUBMITTAL IDENTIFICATION |
| 1.2 SUBMITTAL CLASSIFICATION |
| 1.2.1 Government Approved |
| 1.2.2 Information Only |
| 1.3 APPROVED SUBMITTALS |
| 1.4 DISAPPROVED SUBMITTALS |
| 1.5 WITHHOLDING OF PAYMENT |
| PART 2 PRODUCTS Not Applicable |
| PART 3 EXECUTION |
| 3.1 GENERAL |
| 3.2 SUBMITTAL REGISTER |
| 3.3 TRANSMITTAL FORM ENG FORM 4025 |
| 3.4 GOVERNMENT REVIEW TIME |
| 3.5 SCHEDULING |
| 3.6 SUBMITTAL PROCEDURE |
| 3.7 DEVIATIONS |
| 3.8 CONTROL OF SUBMITTALS |
| 3.9 GOVERNMENT APPROVED SUBMITTALS |
| 3.10 INFORMATION ONLY SUBMITTALS |
| 3.11 STAMPS |
| 3.12 ATTACHMENTS |
| Form 4025 |
| Submittal Register |
| 01 35 26 - GOVERNMENTAL SAFETY REQUIREMENTS |
| 01 35 26 - GOVERNMENTAL SAFETY REQUIREMENTS |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 DEFINITIONS |
| 1.2.1 Site Safety and Health Officer SSHO |
| 1.2.1.1 Level One SSHO |
| 1.2.1.2 Level Two SSHO |
| 1.2.1.3 Level Three SSHO |
| 1.2.1.4 Alternate SSHO |
| 1.2.2 Competent Person CP |
| 1.2.3 Qualified Person QP |
| 1.3 SUBMITTALS |
| 1.4 PUBLIC HEALTH EMERGENCIES |
| 1.5 MONTHLY EXPOSURE REPORTS |
| 1.6 REGULATORY REQUIREMENTS |
| 1.7 SITE QUALIFICATIONS, DUTIES, AND MEETINGS |
| 1.7.1 Site Safety and Health Officer SSHO |
| 1.7.1.1 Qualifications of SSHO |
| 1.7.1.2 Duties of SSHO |
| 1.7.1.3 Safety Meetings |
| 1.7.2 Roles and Responsibilities of Prime Contractor and SSHO |
| 1.7.3 Contract Site Safety And Health OfficersSSHOs Minimum |
| 1.7.4 Dredging Contract Site Safety and Health OfficersSSHOs |
| 1.7.4.1 Dredging SSHO Personnel Requirements |
| 1.7.5 Crane Operators/Riggers |
| 1.7.6 Preconstruction Conference |
| 1.8 ACCIDENT PREVENTION PLAN APP |
| 1.8.1 Accident Prevention Plan APP |
| 1.8.2 Names and Qualifications |
| 1.9 ACTIVITY HAZARD ANALYSIS AHA |
| 1.9.1 AHA Management |
| 1.9.2 AHA Signature Log |
| 1.10 SITE SAFETY REFERENCE MATERIALS |
| 1.11 EMERGENCY MEDICAL TREATMENT |
| 1.12 NOTIFICATIONS AND REPORTS |
| 1.12.1 Accident Notification |
| 1.12.2 Accident Reports |
| 1.12.3 LHE Inspection Reports |
| 1.12.4 Certificate of Compliance and Pre-lift Plan/Checklist for LHE and |
1.13 SEVERE STORM PLAN
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 CONSTRUCTION AND OTHER WORK |
| 3.1.1 Worksite Communication |
| 3.1.2 Unforeseen Hazardous Material |
| 3.2 UTILITY OUTAGE REQUIREMENTS |
| 3.3 FALL PROTECTION PROGRAM |
| 3.3.1 Fall Protection Equipment and Systems |
| 3.3.1.1 Additional Personal Fall Protection Measures |
| 3.3.1.2 Personal Fall Protection Equipment |
| Attachments |
| Crane/Rigging Accident Form |
| 01 41 26.00 13 - IOWA NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM |
| 01 41 26.00 13 - IOWA NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM |
| PART 1 GENERAL |
| 1.1 GENERAL |
| 1.1.1 Definitions |
| 1.2 SUBMITTALS |
| 1.3 PERMIT COMPLIANCE AND REQUIREMENTS |
| 1.3.1 Schedule |
| 1.3.2 Application |
| 1.3.3 Stormwater Pollution Prevention Plan SWPPP |
| 1.3.3.1 The SWPPP Drawing |
| 1.3.3.2 The Surface Water Map |
| 1.3.3.3 The Site Map |
| 1.3.3.4 The Narrative |
| 1.3.3.5 Public Notification |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 IMPLEMENTATION |
| 3.2 MAINTENANCE |
| 3.3 RECORDS |
| 3.4 ATTACHMENTS |
| IPDES General Permit |
| IOWA NOI NPDES |
| 01 42 00 - SOURCES FOR REFERENCE PUBLICATIONS |
| 01 42 00 - SOURCES FOR REFERENCE PUBLICATIONS |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 ORDERING INFORMATION |
| PART 2 PRODUCTS Not Used |
| PART 3 EXECUTION Not Used |
| 01 45 00.15 10 - RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODERMS CM |
| 01 45 00.15 10 - RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODERMS CM |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 MEASUREMENT AND PAYMENT |
| 1.3 CONTRACT ADMINISTRATION |
| 1.3.1 Correspondence and Electronic Communications |
| 1.3.2 Other Factors |
| 1.4 RMS SOFTWARE |
| 1.5 SYSTEM REQUIREMENTS |
| 1.6 CONTRACT DATABASE - GOVERNMENT |
| 1.7 CONTRACT DATABASE - CONTRACTOR |
| 1.7.1 Administration |
| 1.7.1.1 Contractor Information |
| 1.7.1.2 Subcontractor Information |
| 1.7.1.3 Correspondence |
| 1.7.1.4 Equipment |
| 1.7.1.5 Reports |
| 1.7.1.6 Request For Information RFI |
| 1.7.2 Finances |
| 1.7.2.1 Pay Activity Data |
| 1.7.2.2 Payment Requests |
| 1.7.3 Quality Control QC |
| 1.7.3.1 Quality Control QC Reports |
| 1.7.3.2 Deficiency Tracking. |
| 1.7.3.3 Three-Phase Control Meetings |
| 1.7.3.4 Labor and Equipment Hours |
| 1.7.3.5 Accident/Safety Reporting |
| 1.7.3.6 Definable Features of Work |
| 1.7.3.7 Activity Hazard Analysis |
| 1.7.4 Submittal Management |
| 1.7.5 Schedule |
| 1.7.6 Closeout |
| 1.8 IMPLEMENTATION |
| 1.9 NOTIFICATION OF NONCOMPLIANCE |
| PART 2 PRODUCTS Not Used |
| PART 3 EXECUTION Not Used |
| 01 45 04.00 13 - CONTRACTOR QUALITY CONTROL |
| 01 45 04.00 13 - CONTRACTOR QUALITY CONTROL |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.3 QUALITY CONTROL ORGANIZATION |
| 1.3.1 Personnel Requirements |
| 1.3.2 CQC System Manager |
| 1.3.3 Additional Requirement |
| 1.3.4 Organizational Changes |
| PART 2 PRODUCTS Not Applicable |
| PART 3 EXECUTION |
| 3.1 GENERAL REQUIREMENTS |
| 3.2 CONTRACTOR QUALITY CONTROL CQC PLAN |
| 3.2.1 General |
| 3.2.2 Content of the CQC Plan |
| 3.2.3 Acceptance of Plan |
| 3.2.4 Notification of Changes |
| 3.3 COORDINATION MEETING |
| 3.4 SUBMITTALS AND DELIVERABLES |
| 3.5 CONTROL |
| 3.5.1 Preparatory Phase |
| 3.5.2 Initial Phase |
| 3.5.3 Follow-up Phase |
| 3.5.4 Additional Preparatory and Initial Phases |
| 3.6 TESTS |
| 3.6.1 Testing Procedure |
| 3.6.2 Testing Laboratories |
| 3.6.2.1 Compliance Check |
| 3.6.2.2 Compliance Recheck |
3.6.3 Furnishing or Transportation of Samples for Testing
| 3.7 COMPLETION INSPECTION |
| 3.7.1 Punch-Out Inspection |
| 3.7.2 Pre-Final Inspection |
| 3.7.3 Final Acceptance Inspection |
| 3.8 DOCUMENTATION |
| 3.9 NOTIFICATION OF NONCOMPLIANCE |
| 01 50 02.00 13 - TEMPORARY CONSTRUCTION FACILITIES |
| 01 50 02.00 13 - TEMPORARY CONSTRUCTION FACILITIES |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.3 GROUNDS AND ROADWAYS |
| 1.3.1 Availability of Grounds |
| 1.3.2 Drainage Facilities |
| 1.4 PAVEMENT REMOVAL AND REPLACEMENT |
| 1.5 AVAILABILITY AND USE OF UTILITY SERVICES |
| 1.5.1 Temporary Electrical Facilities |
| 1.5.2 Sanitation |
| 1.5.3 Telephone |
| 1.6 PROTECTION AND MAINTENANCE OF TRAFFIC |
| 1.6.1 Off-Site Haul Routes |
| 1.6.2 On-Site Haul Roads |
| 1.6.3 Barricades |
| 1.7 CONTRACTOR'S TEMPORARY FACILITIES |
| 1.7.1 Administrative Field Office |
| 1.7.2 Formaldehyde Emission Test Results Requirements |
| 1.7.3 Staging Area |
| 1.8 PLANT COMMUNICATION |
| 1.9 TEMPORARY PROJECT SAFETY FENCING |
| PART 2 PRODUCTS |
| 2.1 BULLETIN BOARD, PROJECT SIGN, AND PROJECT SAFETY SIGN |
| 2.1.1 Bulletin Board |
| 2.1.2 Project and Safety Signs |
2.2 GOVERNMENT FIELD OFFICE
| PART 3 EXECUTION |
| 3.1 MAINTENANCE OF GROUNDS |
| 3.2 CLEANUP |
| 3.3 RESTORATION |
| Attachements |
| Project Signs |
| 01 57 20.00 13 - ENVIRONMENTAL PROTECTION |
| 01 57 20.00 13 - ENVIRONMENTAL PROTECTION |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 DEFINITIONS |
| 1.2.1 Environmental Pollution and Damage |
| 1.2.2 Environmental Protection |
| 1.2.3 Contractor Generated Hazardous Waste |
| 1.2.4 Land Application for Discharge Water |
| 1.2.5 Pesticide |
| 1.2.6 Pests |
| 1.2.7 Surface Discharge |
| 1.2.8 Waters of the United States |
| 1.2.9 Wetlands |
| 1.3 GENERAL REQUIREMENTS |
| 1.4 SUBCONTRACTORS |
| 1.5 PAYMENT |
| 1.6 SUBMITTALS |
| 1.7 ENVIRONMENTAL PROTECTION PLAN |
| 1.7.1 Compliance |
| 1.7.2 Contents |
| 1.8 PROTECTION FEATURES |
| 1.9 ENVIRONMENTAL ASSESSMENT OF CONTRACT DEVIATIONS |
| 1.10 NOTIFICATION |
| PART 2 PRODUCTS NOT USED |
| PART 3 EXECUTION |
| 3.1 PERMITS |
| 3.2 LAND RESOURCES |
| 3.2.1 Work Area Limits, Exclusion Zones, Access Dredging |
| 3.2.1.1 Eagle Nesting Exclusion Zones |
| 3.2.2 Mussel Exclusion Zones |
| 3.2.3 Landscape |
| 3.2.4 Erosion and Sediment Controls |
| 3.2.5 Contractor Facilities and Work Areas |
| 3.3 WATER RESOURCES |
| 3.3.1 Cofferdams, Diversions, and Dewatering Operations |
| 3.3.2 Stream Crossings |
| 3.3.3 Wetlands and Work Exclusion Zones |
| 3.3.4 Access Routes and Access Channels |
| 3.4 AIR RESOURCES |
| 3.4.1 Particulates |
| 3.4.2 Odors |
| 3.4.3 Sound Intrusions |
| 3.5 CHEMICAL MATERIALS MANAGEMENT AND WASTE DISPOSAL |
| 3.5.1 Solid Wastes |
| 3.5.2 Chemicals and Chemical Wastes |
| 3.5.3 Contractor Generated Hazardous Wastes/Excess Hazardous Materials |
| 3.5.4 Fuel and Lubricants |
| 3.5.5 Waste Water |
| 3.6 RECYCLING AND WASTE MINIMIZATION |
| 3.7 HISTORICAL, ARCHAEOLOGICAL, AND CULTURAL RESOURCES |
| 3.8 BIOLOGICAL RESOURCES |
| 3.9 PESTICIDES |
| 3.9.1 Pesticide Delivery and Storage |
| 3.9.2 Qualifications |
| 3.9.3 Pesticide Handling Requirements |
| 3.9.4 Application |
| 3.10 INVASIVE SPECIES PREVENTION |
| 3.11 MAINTENANCE OF POLLUTION CONTROL FACILITIES AND DEVICES |
| 3.12 TRAINING OF CONTRACTOR PERSONNEL |
| 3.13 POST CONSTRUCTION CLEANUP |
| 3.14 Attachments |
| Nationwide General Permit |
| Iowa Sect 401 Water Quality Permit |
| US Fish and Wildlife Special Use Permit |
| 01 71 23.05 13 - CONTRACTOR SURVEYS |
| 01 71 23.05 13 - CONTRACTOR SURVEYS |
| PART 1 GENERAL |
| 1.1 DEFINITIONS |
| 1.2 REFERENCES |
| 1.3 AVAILABLE DATA FROM THE GOVERNMENT |
| 1.4 SUBMITTALS |
| 1.5 GEOSPATIAL DATA |
| 1.5.1 Metadata |
| 1.5.2 Geospatial Information |
| 1.5.2.1 GNSS/GPS Data |
| 1.5.2.2 Field Notes/Books |
| 1.6 DATUMS AND UNITS OF MEASURE |
| 1.7 MEASUREMENT AND PAYMENT |
| 1.8 QUALITY CONTROL |
| 1.8.1 Quality Control Plan |
| 1.8.2 Layouts and Surveys |
| 1.9 PROFESSIONAL SURVEYOR |
| 1.9.1 Professional Certification and Work Experience |
| 1.10 GEOSPATIAL DATA COLLECTION EQUIPMENT |
| 1.10.1 Positioning Equipment |
| 1.10.2 Hydrographic Survey Equipment |
| PART 2 PRODUCTS NOT APPLICABLE |
| PART 3 EXECUTION |
| 3.1 COMMENCEMENT, PERFORMANCE, AND COMPLETION |
| 3.1.1 General |
| 3.1.2 Alignment Changes |
| 3.1.3 Geospatial Data Collection |
| 3.1.3.1 Preliminary Surveys |
| 3.1.3.2 Layout Surveys |
| 3.1.3.3 As-Built Surveys |
| 3.1.3.3.1 Project Elements and Features |
| 3.1.3.3.2 Utilities |
| 3.1.3.4 Quantity Surveys for Measurement and Payment |
| 3.1.3.5 Surveys for Verification of Design Section |
| 3.1.3.6 Granular Borrow Dredging Surveys |
| 3.1.3.6.1 Contractor Granular Borrow Surveys |
| 3.1.3.6.2 Government Pre-Dredge Surveys |
| 3.1.3.6.3 Government Post-Dredge Surveys |
| 3.1.3.6.4 Returning to Previous Cuts |
| 3.1.3.7 Survey Deliverables |
| 3.1.3.7.1 Surveying Timeframe |
| 01 78 02.00 10 - CLOSEOUT SUBMITTALS |
| 01 78 02.00 10 - CLOSEOUT SUBMITTALS |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| 1.2 NPDES Closeout Submittals and Records |
| 1.3 AS-BUILT DRAWINGS |
| 1.3.1 Working Drawings |
| 1.3.2 Final Drawings |
| 1.3.3 Changes and Corrections |
| 1.3.4 Drawing Standards |
1.4 APPROVAL
| PART 2 PRODUCTS NOT USED |
| PART 3 EXECUTION NOT USED |
| DIVISION 32 - EXTERIOR IMPROVEMENTS |
| 32 92 19.00 13 - SEEDING |
| 32 92 19.00 13 - SEEDING |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.3 DELIVERY, INSPECTION, STORAGE, AND HANDLING |
| 1.3.1 Inspection |
| 1.3.2 Storage |
| 1.3.3 Handling |
| PART 2 PRODUCTS |
| 2.1 SEED |
| 2.1.1 Seed Classification |
| 2.1.2 Permanent Seed Species and Mixtures |
| 2.1.3 Temporary Seed Species |
| 2.1.4 Quality |
| 2.2 MULCH |
| 2.2.1 Straw Mulch |
| 2.3 WATER |
| 2.4 SPECIAL SEEDING AND MULCHING EQUIPMENT |
| 2.4.1 Equipment |
| 2.4.2 Seeding |
| PART 3 EXECUTION |
| 3.1 INSTALLING SEED TIME AND CONDITIONS |
| 3.1.1 Notification |
| 3.1.2 Seeding Time |
| 3.1.3 Seeding Conditions |
| 3.2 SITE PREPARATION AND TILLAGE |
| 3.3 SEEDING |
| 3.3.1 Equipment |
| 3.3.2 Broadcast Seeding |
| 3.3.3 Drill Seeding |
| 3.3.4 Applying and Anchoring Mulch |
| 3.4 RESTORATION AND CLEAN UP |
| 3.4.1 Land Access Restoration |
| 3.5 TURF ESTABLISHMENT PERIOD |
| 3.6 MAINTENANCE |
| 3.6.1 General Maintenance |
| 3.6.1.1 Repair or Reinstall |
| 3.6.2 Maintenance Record |
| 3.6.3 Maintenance During Establishment Period |
| 3.6.4 Erosion Control |
| 3.6.4.1 Repair |
| 3.7 QUALITY CONTROL |
| 3.8 FINAL ACCEPTANCE |
| 3.8.1 Preliminary Inspection |
| 3.8.2 Final Inspection |
3.9 SEEDING AS-BUILT DRAWINGS
| 32 93 00.00 13 - PLANTING |
| 32 93 00.00 13 - PLANTING |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| 1.2 WILLOW SOURCES |
| 1.3 DELIVERY, STORAGE, AND HANDLING |
| 1.3.1 Delivery |
| 1.3.1.1 Protection During Delivery |
| 1.3.2 Storage |
| 1.3.3 Handling |
| 1.4 SCHEDULE |
| 1.5 INSPECTION |
| PART 2 PRODUCTS |
| 2.1 PLANT MATERIAL |
| 2.1.1 Agency Coordination and Requirements |
| 2.1.2 Willow Plant Cuttings |
| PART 3 EXECUTION |
| 3.1 SITE PREPARATION |
| 3.1.1 Layout |
| 3.2 INSTALLATION |
| 3.2.1 Willow Plantings |
| 3.3 PROTECTION OF PLANTINGS |
| 3.4 RESTORATION AND CLEAN UP |
| 3.5 MAINTENANCE |
| 3.6 PLANT ESTABLISHMENT PERIOD |
| 3.7 FINAL ACCEPTANCE |
| 3.7.1 Preliminary Inspection |
| 3.7.2 Final Inspection |
| 3.8 WILLOW PLANTING AS-BUILT DRAWINGS |
| 3.9 ATTACHMENTS |
| Willow Sources |
| DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION |
| 35 20 23 - DREDGING |
| 35 20 23 - DREDGING |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 THE PLANT |
| 1.3 SUBMITTALS |
| 1.4 EFFLUENT WATER QUALITY |
| 1.5 MATERIAL BALANCE PLAN |
| 1.6 CLASSIFICATION OF SOIL MATERIALS |
| 1.7 HISTORIC BORINGS |
| PART 2 PRODUCTS |
| 2.1 MATERIALS |
| 2.1.1 Satisfactory Materials |
| 2.1.2 Unsatisfactory Materials |
| 2.1.3 Fine Material and Granular Material |
| 2.1.4 Construction Pads |
| 2.1.5 Woody Material |
| 2.1.6 Aquatic Vegetation |
| 2.2 CHARACTERISTICS OF DREDGED MATERIAL |
| 2.2.1 Fine Fill |
| 2.2.2 Granular Fill |
| 2.2.3 Random Fill |
| 2.3 COMMUNICATION |
| 2.3.1 Plant Communication |
| 2.3.2 Marine Traffic Communication |
2.4 INSPECTION BOAT
| PART 3 EXECUTION |
| 3.1 GENERAL REQUIREMENTS |
| 3.2 DISPOSAL OF WOODY MATERIAL ONSITE |
| 3.3 CONFINED DISPOSAL FACILITY CDF BERMS |
| 3.4 CONSTRUCTION PADS |
| 3.4.1 Construction Pad for SP-H4 |
| 3.5 SLIDES |
| 3.6 TOLERANCES |
| 3.7 PIPELINES |
| 3.8 NAVIGATION |
| 3.9 PROTECTION OF STRUCTURES, UTILITIES AND DREDGED AREAS |
| 3.10 PLANT REMOVAL |
| 3.11 ATTACHMENTS |
| Attachments |
| Historical Boring Logs |
| Historical Borrow Sources |
| 35 20 23.40 13 - PLACEMENT OF DREDGED AND STOCKPILED FILL MATERIAL |
| 35 20 23.40 13 - PLACEMENT OF DREDGED AND STOCKPILED FILL MATERIAL |
| PART 1 GENERAL |
| 1.1 THE PLANT |
| 1.2 SUBMITTALS |
| 1.3 EFFLUENT WATER QUALITY |
| PART 2 PRODUCTS |
| 2.1 DEFINITIONS |
| 2.2 MATERIALS |
| 2.2.1 Fine Fill Topsoil |
| 2.2.2 Granular Fill |
| 2.2.3 Random Fill |
| PART 3 EXECUTION |
| 3.1 GENERAL |
| 3.2 FOUNDATION SETTLEMENT AND DISPLACEMENT |
| 3.3 FOUNDATION PREPARATION |
| 3.4 PLACEMENT |
| 3.4.1 Direction of Work |
| 3.4.2 Construction Pads |
| 3.4.3 Material Transport |
| 3.5 RANDOM FILL |
| 3.6 COMPACTION |
| 3.6.1 Granular Fill |
| 3.6.2 Fine Fill |
| 3.7 TOLERANCES |
| 3.7.1 Excess Material Outside Tolerances |
| 3.7.2 Construction Pad Removal Tolerances |
| 3.8 FINISHING |
| 3.9 MUD WAVE |
| 3.10 SLIDES |
| 3.11 PROTECTION |
| ATTACHMENTS |
| Tree Piling Loafing Structure Typical |
| Habitat Dredge Loafing Structure Locations |
| 35 31 19.00 13 - STONE PROTECTION RIPRAP |
| 35 31 19.00 13 - STONE PROTECTION RIPRAP |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| PART 2 PRODUCTS |
| 2.1 STONE SOURCES AND EVALUATION |
| 2.1.1 Alternate Sources |
| 2.1.2 Acceptance of Materials |
| 2.2 RIPRAP |
| 2.2.1 General |
| 2.3 MUDPUPPY/MUSSEL HABITAT FEATURES |
| 2.3.1 General |
| 2.3.2 Production |
| 2.4 SOURCE QUALITY CONTROL |
| 2.4.1 Sampling Requirements |
| 2.4.2 Riprap Gradation Testing |
| 2.4.2.1 Riprap Test Method A |
| 2.4.2.2 Riprap Test Method B |
| 2.5 MUDPUPPY/MUSSEL HABITAT STONE GRADATION TESTING |
| 2.6 STOCKPILES |
| PART 3 EXECUTION |
| 3.1 CONSTRUCTION TOLERANCES |
| 3.2 FOUNDATION PREPARATION |
| 3.3 PLACEMENT OF RIPRAP |
| 3.3.1 Layer Requirements |
| 3.3.2 Riprap Construction Methods |
| 3.3.3 Riprap Placement in Water |
| 3.3.4 Material Transport |
| 3.4 PLACEMENT OF MUDPUPPY/MUSSEL HABITAT FEATURES |
| 3.4.1 Layer Requirements |
| 3.5 MAINTENANCE |
| 3.6 CONTRACTOR QUALITY CONTROL |
| 3.7 SURVEY PLAN AND SURVEY SECTION FOR VERIFICATION OF RIPRAP SECTION AND |
| 3.8 ATTACHMENTS |
| Approved Material Source List |
| ENG Form 4055 |
| Gradation Analysis Riprap Method A&B |
File details come from the government source that posted it. Updated .