AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of Amendment 0001 to W912ES23Q0060 Sew er Pipeline and Septic Holding Tank Inspection at Mel Rieman Recreation Area, Valley City, ND, is to provide the follow ing:
1. Responses to Interested Contractor questions; and,
2. Revised SOW dated 24May23.
See Page 2 for full details.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 12
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 24-May-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912ES23Q0060
X 9B. DATED (SEE ITEM 11)
16-May-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
24-May-2023
CODE
CONTRACTING DIVISION
USACE, ST PAUL
332 MINNESOTA STREET
SUITE E1500
ST PAUL MN 55101-1323
W912ES 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ES23Q0060
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0001
Interested Contractor Questions and Answers (Q&A)
Q1: Is a Master Plumber license required?
A1: See Revised SOW, Paragraph 1.5 Submittals, Section SD-03 that deletes “Master Plumber Qualifications”.
Q2: If you do require a Master Plumber on this project, are we allowed to outsource that requirement?
A2: See A1 above. No Master Plumber is required.
Q3: Am I correct in understanding that the septic tank will be fully pumped 24-hours prior to our project start time thereby ensuring two project starting conditions: no sludge or grease will be in the tank and local permit filings for septic pumping will have been completed?
A3: See revised section 1.4.2 (highlighted) of the SOW.
Q4: Are there any specifications regarding the septic tank visual inspection?
A4: The Corps is unaware of standards for a septic tank inspection. The goal is to get enough pictures and video of as much of the tank interior as possible to determine the structural integrity of the tank;
pictures for cracks and deterioration, video for seepage/flow.
Q5: Is there a standing "waste disposal plan" or a pre-coordinated dump site?
A5: See revised (highlighted) SOW.
Q6: If the disposal plan is approved post-contract award, do you already have a relationship with a local dump site that we can leverage?
A6: The Corps does not have any relationships with a local dump site.
SECTION SF 1449 - CONTINUATION SHEET
SUPPLIES OR SERVICES AND PRICES
CLIN 0001
The CLIN extended description has changed from:
All labor, material, and equipment for condition assessments per SOW herein or as amended.
To:
All labor, material, and equipment for condition assessments per SOW herein or as amended.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent..
The following have been modified:
SCOPE OF WORK
PART 1 GENERAL
1.1 SCOPE OF WORK
The US Army Corps of Engineers, St. Paul District (Corps) requires a Contractor to provide all labor, material, and equipment necessary for condition assessments of the Mel Rieman Recreation Area (MRRA) Visitor Center sewer pipeline and septic holding tank that supports shower and restrooms only. The MRRA Visitor Center and Campground is a 70-acre facility on the shoreline of Lake Ashtabula, 114th Ave SE, Valley City, North Dakota.
The MRRA septic holding tank and much of the pipe are below the water level of the dam. The septic holding tank has a history of becoming full in decreasing time intervals. Significant Infiltration/Inflow (I/I) of groundwater is suspected. When the tank is pumped out, Corps staff can hear water immediately pouring in. In addition to I/I Inspection to determine the reason for the increasing rate of fill, the Contractor must determine the overall condition of the sewer pipeline and septic holding tank. The work includes remote televising and recording via closed-circuit television (CCTV).
1.2 SYSTEM DESCRIPTION
The sewer pipeline runs from the Mel Rieman Visitor Center to a septic holding tank. The pipeline consists of seven (7) straight segments with turns at six (6) manholes. The original pipe was 1021 ft of 8 in.
vitrified clay pipe installed in late 1971. In July 1995, the clay pipe was slip-lined with 6 in. SDR-35 PVC pipe, except for the 240 ft section between MH3 (manhole #3) and MH4.
The 10,000-gallon septic holding tank is a component of a decommissioned sewage treatment system.
1.3 DEFINITIONS
1.3.1 Cleaning
To remove soil or solid deposited materials from a pipe segment when the pipe is less than half-full to full of deposited materials.
1.3.2 Defects
Defects in the pipe, manholes, structures, and services include cracks, separation of joints, collapsed pipe, grade irregularities, leaks, roots, grease buildup, offset joints, reverse grades, obstructions, delamination, missing pipe, restrictions, fractures, and similar structural irregularities.
1.3.3 Entry Point
The leading edge of the access point or the manhole or structure wall where the pipe segment begins. Only the pipe is video inspected from manhole or structure wall to manhole or structure wall and does not include any portion of the manhole or structure.
1.3.4 Exit Point
The point where the downstream access manhole or structure wall is encountered. Only the pipe is video inspected from manhole or structure wall to manhole or structure wall and does not include any portion of the manhole or structure.
1.3.5 Hydraulically Propelled Cleaning Tools
Tools that depend upon water pressure to provide their cleaning force.
1.3.6 National Association of Sewer Service Companies (NASSCO)
National Association of Sewer Service Companies (NASSCO) identifies the generally accepted industry standards for CCTV inspection, observation coding, and certification.
1.3.7 Pipe Segment
The length of pipe from entry point to exit point along the main or service.
1.3.8 Pipeline Assessment and Certification Program (PACP)
A CCTV Inspection standardization certification and observation coding system sponsored by NASSCO.
1.3.9 Point Repair
The location of a failure where a repair has occurred.
1.3.10 Re-TV Inspection
Refers to rework for a CCTV inspection that has video interruptions, gaps, or is not continuous.
1.3.11 TV Inspection Log
Information collected and recorded by the CCTV operator for each CCTV inspection effort and includes pertinent information for the respective inspection section, such as; date of inspection, location of site, CCTV technician, direction of CCTV inspection with manhole or structure identifiers, weather conditions, pipe size(s), pipe materials, conditions found, locations where the conditions were found.
1.4 ADMINISTRATIVE
1.4.1 Pre-Quote Site Visit
Contractors are encouraged to visit the site prior to quoting. Visits must occur during normal business hours and must be scheduled in advance with:
Joel Zietz
Maintenance & Repair Coordinator Mel Rieman Recreation Area
(701) 845-2970 Ext. 5613 Joel.E.Zietz@usace.army.mil
Hours: 8:00 am – 3:00 pm, Monday – Friday, excluding weekends and Federal Holidays
1.4.2 Pre-Inspection Meeting
The Contractor will contact the Contracting Officer’s Representative (COR) and arrange a virtual pre-inspection meeting.
a. Scheduling of work. A Work Schedule must be submitted and approved by the Contracting Officer to allow the COR to arrange delivery of portable restrooms during Visitor Center closure. The Contractor will not be responsible for portable restrooms.
b. Timing of Visitor Center water shut-off. The Visitor Center is the only source of flow into the sewer pipeline, other than I/I. The outdoor shower near the beach percolates water into the ground and does not drain into the sewer pipeline.
c. Timing of emptying the septic holding tank. After Visitor Center water shut-off, the septic holding tank will be emptied. The Corps has a contract with a pump truck service and will schedule this service at Corps’ expense to be performed at the optimal time(s) agreed upon by the inspection Contractor and the Corps during this pre-inspection meeting. The timing of this action can be used to determine the existence and rate of I/I by checking water depth after a prescribed waiting period.
d. Access to electricity and water valves in the Visitor Center.
e. Reservation of vehicle and equipment parking areas.
1.4.3 Disposal Plan
Disposal of all waste materials shall be done in accordance with all applicable Federal, State, and local waste disposal requirements. Note that this sewer and septic system is for showers and restrooms only.
The Contractor’s Disposal Plan will be discussed and pre-approved during the Pre-Inspection Meeting.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following to the Contracting Officer (KO):
SD-01 Preconstruction Submittals
Work Schedule; G {KO}
SD-03 Product Data
Cleaning Products; G [KO] SD-07 Certificates CCTV Technician's Qualifications; G [KO] CCTV Inspection; G [KO] RE-TV Inspection; G [KO]
SD-11 Closeout Submittals Records of Disposals
1.6 QUALITY CONTROL & QUALIFICATIONS
The pipeline condition assessment must be performed by a CCTV Technician with a current Pipeline Assessment Certification Program (PACP) Operator certification for personnel performing closed circuit television inspection and pipeline assessments. The CCTV Technician’s PACP certificate must be provided with the Contractor’s quote.
1.7 SAFETY
The Contractor shall perform and complete all work in accordance with the U.S. Army Corps of Engineers, Safety Manual, USACE EM 385-1-1.
1.8 MEASUREMENT AND PAYMENT
Payment will be made upon completion and acceptance of the contracted work.
The Contractor must submit a completed ENG Form 93 for payment to the COR.
PART 2 PRODUCTS
2.1 SYSTEM DESCRIPTION
TV inspection of sewer pipelines encompasses cleaning, heavy cleaning, CCTV inspection and video recording of the existing sanitary mains included in the contract documents. This work includes inspection logs, video requirements, local permits, and the legal disposal of materials removed.
The Contractor shall provide the mechanical equipment used to clean and dispose of the materials found in sewer pipes and structures, CCTV cameras and recording devices used to record the internal conditions of sewer piping.
2.2 EQUIPMENT
2.2.1 Cleaning Equipment
Utilize mechanically powered equipment necessary for the proper rodding, bucketing, brushing, root cutting, and flushing of the sewers, rodding machine that is compatible with the cleaning to be performed.
2.2.1.1 Rodding
Provide rodding equipment capable of rodding distances of up to 350 feet in one (1) set-up and having the following capabilities:
a. The ability to spin the rod either clockwise or counterclockwise and be able to be pushed straight out or pulled back without rotating the machine.
b. The capability of pulling pipe-size swabs or brushes back through the pipeline for cleaning and flushing purposes.
2.2.1.2 Hydraulic Flusher
Provide hydraulic sewer cleaners used for sewer cleaning, specifically designed, and constructed for such cleaning, that have a minimum usable water capacity of 600 gallons and a pump capable of delivering at least 30 gallons per minute (gpm) at 100 psi and having the following capabilities:
a. Pressure regulator nozzle capable of adjustment from 1 psi to 1500 psi.
b. Constructed for ease of use and safety of operation with two (2) or more high-velocity nozzles capable of producing a scouring action from 15 to 45 degrees in lines designated to be cleaned.
c. Carry its own water tank, auxiliary engines, pumps, and hydraulically driven hose reel.
2.2.2 CCTV Equipment
Provide a video system capable of producing a sharply focused, well-lit and color balanced picture in accordance with the following requirements:
2.2.2.1 Pipe Inspection Camera and Associated Equipment
a. Provide a pipe inspection camera system that produces a video using a pan and tilt, radial viewing, that pans a minimum of 275 degrees and rotates 360 degrees. Illumination sensitivity of 3 Lux or less and a minimum of 460 lines of resolution is required.
b. Utilize video cameras specifically designed and constructed for CCTV inspection.
c. Provide a camera that is operative in 100 percent humidity conditions.
d. Provide a camera with an accurate footage counter that displays on the monitor the exact distance of the camera to the nearest 1/10 of a foot.
e. Provide a camera with a height adjustment so that the camera lens is typically centered in the pipe, or higher depending on water levels in the pipe.
f. Provide equipment that will produce digital color images and allows the CCTV technician to remotely balance the iris and color to produce a clear and true video of the pipeline.
g. Provide lighting for the camera that is suitable to provide a clear color picture of the entire periphery of the pipe.
h. Provide an accompanying computer and recording device capable of projecting and recording the facility location, project name, Contractor's name, date, line size, material type, line identification, manhole or structure ID numbers and ongoing footage counter onto the video screen.
2.3 MATERIALS
2.3.1 Cleaning Products
If used, select cleaning products that do not present a health and safety concern, are allowed for use in the sewer system according to Federal and State regulations, will not adversely affect the water quality of the water being conveyed in the sewer system, are suitable for the wastewater treatment plant and the climatic conditions at the project site. Submit manufacturer's label and SDS for the cleaning products to the Contracting Officer for approval prior to use.
PART 3 EXECUTION
3.1 PREPARATION
3.1.1 Coordination of Pre-Inspection Activities by USACE
Coordinate with the COR prior to beginning any work.
3.1.2 Sewer Line Cleaning
Immediately prior to conducting CCTV activities, thoroughly clean the segment of sewer pipe to be video inspected. Clean the segments using hydraulically propelled, high-velocity jet, or mechanically powered equipment.
a. During cleaning and preparation operations, undertake precautions to protect the sewer system and property from damage. Restore property damaged as a result of such cleaning and preparation operations to pre-existing conditions.
b. During the course of normal cleaning operations immediately report pre-existing damage such as broken or missing pipe to the Contracting Officer.
c. When hydraulically propelled cleaning tools or tools which retard the flow in the sewer line are utilized, take precautions to ensure that the water pressure created does not damage or cause flooding on the adjacent site.
d. If cleaning of an entire sewer section cannot be successfully performed from one manhole or structure, set up the equipment on the other entry or exit point and attempt cleaning again.
e. If successful cleaning cannot be performed from the opposite end or the equipment fails to traverse the entire pipeline section, cease cleaning those specific sewer sections, notify the Contracting Officer and CCTV inspect both sides of the pipeline section to determine the cause of the blockage.
3.1.3 Root Removal
Remove roots in the designated sewer sections. Ensure complete removal of roots to the joints. Use mechanical equipment that can be operated remotely, such as rodding machines, bucket machines, winches using root cutters and porcupines, and equipment such as high-velocity jet cleaners.
Capture and remove roots from the sewer pipeline at the downstream manhole or structure.
3.1.4 Material Removal and Disposal
Remove sludge, dirt, roots, grease, and other solid or semi-solid material resulting from cleaning operations at the downstream manhole or structure of the section being cleaned.
3.1.4.1 Dams or Weirs
When hydraulic cleaning equipment is used, place dam or weir in the downstream manhole or structure to trap such materials. Do not allow material to pass from pipeline section to pipeline section, which could cause stoppages, accumulations of sand in wet wells, or damage to pumping equipment.
3.1.4.2 Sludge and Debris Storage
Under no circumstances is sludge or other debris that is removed during these operations to be stored, dumped, or spilled into streets, ditches, storm drains, or other sanitary sewer systems.
a. Dispose of solids and semi-solids resulting from the cleaning operations no less often than the end of each workday in accordance with the approved Disposal Plan.
b. Continuously maintain the haul route and work areas neat, clean, and reasonably free of odor. Cleanup any spill which occurs during the transport of cleaning or surface preparation by-products. Perform the cleanup of any such material pursuant to this Contract and in accordance with applicable law and environmental regulations.
c. Immediately notify the Contracting Officer of any spill and begin cleanup any such spill or waste.
d. The Contractor is responsible for any costs incurred or penalties imposed upon the Government as a result of the spill, dump, or discard.
e. Under no circumstances is this material to be discharged into the waterways or any place other than where authorized to do so in accordance with the approved Disposal Plan.
3.1.4.3 Hauling of Waste Material
Provide vehicles hauling such waste material that meet the following requirements:
a. Provide transport vehicles of the type(s) approved for this application by the jurisdictions where those vehicles will be operated in the performance of activities associated with this Contract.
b. Provide transport vehicles with watertight bodies equipped and fitted with seals and covers to prohibit material spillage or drainage.
c. Clean vehicles to prevent deposits of material on roadways.
d. Load vehicles within legal weight limits and operate safely within traffic speed regulations.
e. The routes used for the conveyance of this material on a regular basis is subject to approval by the local governing bodies having jurisdiction over such routes.
3.2 APPLICATION
3.2.1 Inspection of Sewer Lines
Inspection of sewer lines applies to CCTV inspection and RE-TV inspection. Perform inspections of sewer lines in the presence of the Contracting Officer.
3.2.1.1 Camera Operation
Set counter to 0.00 feet at the entry point, which is the beginning manhole or structure wall. Move the camera through the line in either direction at a moderate speed, stopping to permit proper documentation of the sewer's condition or service connection locations. In no case will the camera be operated at a speed greater than 30 feet per minute.
Slowly pan and tilt the camera at the beginning and ending manhole, structure connections, service connections, joints, visible defects, and pipe arterial transitions. Provide a full 360-degree view of the pipe, joints, and service connections.
Utilize manual winches, power winches, cable, powered rewinds, or other devices that do not obstruct the camera view or interfere with camera operation or CCTV inspection of the pipe conditions as the camera is moved through the sewer line.
3.2.1.1.1 Recording Defects
During CCTV inspection, temporarily stop the camera at each defect or feature along the line.
3.2.1.2 Documentation of CCTV Inspection
Documentation applies to CCTV inspection and RE-TV inspection.
Utilize a data logger and reporting system that is Pipeline Assessment and Certification Program (PACP) compliant to make a video and audio recording of the CCTV inspections. Submit video recordings, inspection logs, and digital photographs as indicated in the following sub-paragraphs.
3.2.1.2.1 Video Recordings
Provide a color video showing the completed work and document the inspection on a digital recorder. Capture inspection video in either MPEG-4 or Windows Media Video (WMV) format with a minimum resolution of 352 x 240 pixels and an interlaced frame rate at a minimum of 24 frames per second. The CCTV inspection video of a segment must be wholly contained on one continuous MPEG-4 or WMV file. The video recording must meet the following requirements:
a. Provide a continuous and uninterrupted recorded video for the pipe segment being examined. Include the official project title, Contractor's name, manhole ID numbers, direction of video and flow, date and time video was recorded, continuous counter text, pipe size and material, material changes in the pipe segment, audio and text call outs of laterals, fixtures, and problem areas in the recorded video.
b. Include an audio track recorded by the CCTV technician during the actual inspection work with a description of the parameters of the line being inspected on the video recordings. The audio may be from the voice of the CCTV technician, or it may be computer generated.
c. Include the location, pipe diameter, pipe material, defects, service lateral locations and any unusual conditions found in PACP format.
d. Submit MPEG-4 or WMV files of the video inspections to the Contracting
Officer. Submission shall be done via a transmission method approved by the Contracting Officer.
e. Without exception, CCTV inspections must be continuous without video interruption or gaps for pipe segments.
f. Clean, flush, and RE-TV pipe segments with video interruptions or gaps.
3.2.1.2.2 TV Inspection Logs
Submit computer-generated records that clearly show the location and orientation in relation to an adjacent manhole or structure of each infiltration point observed during the inspection.
Record other points of significance such as locations and orientations of service connections, missing or broken pipe, roots, the presence of grease, scale or corrosion, bellies, fractures, cracks, and other discernible features using PACP designations.
3.2.1.2.3 Digital Photographs
Submit images in .jpeg file format at a minimum resolution of 640 x 480 pixels. Save digital photographs in .jpeg file. Document noted defects and lateral connections as color digital files and hard copy printouts. Photo logs are to accompany each photo submitted.
3.2.2 CCTV Inspection
Immediately after cleaning has been performed, complete a CCTV inspection, in accordance with paragraph INSPECTION OF SEWER LINES.
Submit CCTV inspection documentation in accordance with paragraph
DOCUMENTATION OF CCTV INSPECTION.
3.2.3 RE-TV Inspection
After a CCTV inspection that has video interruptions, gaps, or is not continuous, complete RE-TV inspection accordance with paragraph INSPECTION OF SEWER LINES and DOCUMENTATION OF CCTV INSPECTION.
3.3 CLOSEOUT ACTIVITIES
3.3.1 Sewer Cleaning
Submit copies of Records of Disposals indicating the disposal site, date, amount, and a brief description of the materials disposed.
3.4 Appendix A – Sewer and Water General Plans. See separately attached.
(End of Summary of Changes)