A22 W912ES20B0021 0002 - Solicitation Amendment 0002.pdf
PDF 224 KB Posted
- Attached to
- Harper's Slough Flood Damage Repair
- Solicitation number
- W912ES20B0021
About this file
This solicitation amendment provides answers to vendor questions on solicitation number W912ES20B0021 for repair of damage to Harpers Slough Islands in Allamakee County, Iowa. The U.S. Army Corps of Engineers, St. Paul District seeks a contractor to complete repairs between $5-10 million. The work includes restoring islands damaged by flooding in recent years using dredged material. The amendment clarifies that excess dredged material may be used for backfilling and that material paid as construction pads can also be paid if used for island fill or disposal.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A22 W912ES20B0021 0001 - Solicitation Amendment 0001.pdf | ||
| P9HSIR_CONTROL_TABLES.xlsx | XLSX spreadsheet | |
| Bathymetry Data Islands W1 and W2.xlsx | XLSX spreadsheet | |
| HARPER W2 W3aa.xlsx | XLSX spreadsheet | |
| A2_B1_B2_ALIGNMENT.xls | XLS spreadsheet | |
| Harper_Slough_Control_Points.xlsx | XLSX spreadsheet | |
| Harpers Slough W1 and W2 Merged.xlsx | XLSX spreadsheet | |
| A22 W912ES20B0021_PLANS.pdf | ||
| A22 W912ES20B0021-SPECS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this solicitation amendment is to answ er Vendor submitted questions.
All other solicitation terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 13-Apr-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ES20B0021
X 9B. DATED (SEE ITEM 11)
18-Mar-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
13-Apr-2021
CODE
CONTRACTING DIVISION
USACE - ST PAUL
180 FIFTH STREET EAST
SUITE 700
SAINT PAUL MN 55101-1678
W912ES 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ES20B0021
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The following have been added by full text:
AMENDMENT 0002
Vendor Questions and Answers:
Q - Can Material designated as excess material disposal be placed at the big slough beneficial use site?
A - Excess material may be used to backfill dredged areas as noted in the Plans (see Sheet C-103, Note 13).
Placement of material is not allowed at Corps’ dredged material placement sites, including the Lansing Highway Bridge location (Big Slough).
Q - Due to mailing issues with the pandemic, is it possible to change the bid submissions to a type of electronic upload, instead of mailing a hard copy?
A - This office has conducted several bid openings since the beginning of the pandemic. So far, I have not been informed of any issues with submitting bids in hard copy form. Bids shall be submitted in accordance with the Bid Submission instructions within the solicitation.
Q - If additional access dredging is required (surpassing island fill), will additional access dredging quantity be paid as excess material disposal?
A - Yes. The contractor may dispose of excess access dredging on M2 see Specifications Section is 35 20 23 DREDGING, paragraph 3.2. However, a quantity balance will have to be submitted following preconstruction surveys. These surveys also have to show that this additional access dredging is required to complete the work.
Q - Can excess material removed from construction pads be used as access channel backfill?
A - Yes, but only in the locations specified in the planset (C-103 Note 13 and C-104 Note 7). Required construction pad removal is specified on planset sheet C-302.
Q - If material is paid as construction pad material, will it be paid for again if used for excess material or island fill?
A - Yes - See Specifications Section 01 22 00.00 10 MEASUREMENT AND PAYMENT, paragraph 1.9.4 Construction Pads, subparagraph 1.9.4.2 Measurement and planset sheet C-103 Note 13 and sheet C-104 Note 7.
Q - If construction pad material is subsequently used as dredge backfill, will it be paid as excess material disposal?
A - Yes. Material meeting granular specifications (Specifications Section 35 20 23.40 13 PLACEMENT OF FILL, paragraph 2.2.3 Granular Fill) may be placed in hatched areas as shown in the planset (C-103 Note 13 and C-104 Note 7).
Q - Do existing willows need to be removed from islands?
W912ES20B0021
A - No. The contractor may remove willows as necessary to reach the work areas. Removal should be minimized to the extent possible (see planset sheet C-102 Note 7).
Q - In reference to 01 22 00.00 10 para 1.9.4; "Granular fill removed from construction pads designated to be removed is measured either as granular fill, if placed on an island, or measured as excess material disposal." Will the same cubic yards be paid for twice? - First as construction pad material and second as island fill/excess material disposal.
A - Yes - See Specifications Section 01 22 00.00 10 MEASUREMENT AND PAYMENT, paragraph 1.9.4 Construction Pads, subparagraph 1.9.4.2 Measurement and planset sheet C-103 Note 13 and sheet C-104 Note 7.
(End of Summary of Changes)