W912ES20B0006 Bid Abstract Montevideo 3B 20April21 SIGNED.pdf

PDF 274 KB Posted

Attached to
Montevideo Stage 3B Flood Risk Management Construction
Solicitation number
W912ES20B0005
Issued by

About this file

This document contains an abstract for bids received in response to a solicitation for construction of the Montevideo Stage 3B Flood Risk Management Project. The U.S. Army Corps of Engineers, St. Paul District is seeking to construct embankments, gatewells, clearing and grubbing, road raises, pump station modifications, drainage modifications including grading and piping, riprap, traffic control, topsoil, and seeding. Bids were received from AAECON General Contracting, LLC, Fed Serve LLC, and the government estimate. Bid amounts for the base scope of work ranged from $2,275,194.54 to $6,658,256.00. Optional items included submersible pumps and additional construction work. The total evaluated price including the base and both options ranged from $2,546,582.41 to $7,016,604.17. The solicitation is set aside 100% for Historically Underutilized Business (HUBZone) small businesses and closed on April 20, 2021.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Montevideo Stage 3B Flood Risk Management Construction Solicitation W912ES20B0005

US Army Corps of Engineers. 180 5th Street East, Suite 700, St. Paul, MN 55101-1678 Bid Opening: 20 April 2021 @ 2:00 p.m. Central

Contracting Officer: Gwendolyn K. Davis Contract Specialist: Toni W. Wasgatt

BASE

Item No. BASE - SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT

0001 Bonds (Performance & Payment) 1 JOB $33,623.56 $33,623.56 $232,813.00 $232,813.00 $23,100.00 $23,100.00 0002 Preconstruction Surveys 1 JOB $5,259.00 $5,259.00 $18,949.00 $18,949.00 $19,618.14 $19,618.14 0003 Traffic Control 1 JOB $3,091.00 $3,091.00 $4,691.00 $4,691.00 $8,547.91 $8,547.91 0004 Demolition 1 JOB $78,819.00 $78,819.00 $208,311.00 $208,311.00 $24,900.67 $24,900.67 0005 Clearing & Grubbing 1 JOB $64,813.00 $64,813.00 $112,515.00 $112,515.00 $39,930.01 $39,930.01 0006 Stripping 1 JOB $8,483.00 $8,483.00 $240,620.00 $240,620.00 $15,671.35 $15,671.35 0007 Topsoil & Seeding 1 JOB $41,455.00 $41,455.00 $923,146.00 $923,146.00 $175,800.65 $175,800.65 0008 Gatewell 2 Structure 1 JOB $144,757.00 $144,757.00 $250,360.00 $250,368.00 $198,526.95 $198,526.95 0009 Gatewell 2 Sluice Gate 1 JOB $42,264.00 $42,264.00 $65,434.00 $65,434.00 $33,917.30 $33,917.30 0010 Gatewell 2 Inlet/Outlet Piping 1 JOB $56,222.00 $56,222.00 $94,433.00 $94,433.00 $91,588.71 $91,588.71 0011 Gatewell 3 Structure 1 JOB $132,921.00 $132,921.00 $250,368.00 $250,368.00 $198,526.95 $198,526.95 0012 Gatewell 3 Sluice Gate 1 JOB $42,265.00 $42,265.00 $65,434.00 $65,434.00 $33,917.30 $33,917.30 0013 Gatewell 3 Inlet/Outlet Piping 1 JOB $133,512.00 $133,512.00 $155,354.00 $155,354.00 $160,168.13 $160,168.13 0014 Gravel Road Restoration 1 JOB $32,825.00 $32,825.00 $129,861.00 $129,861.00 $24,257.94 $24,257.94 0015 Highway 212 Drainage Modification 1 JOB $3,718.00 $3,718.00 $2,811.00 $2,811.00 $6,178.65 $6,178.65 0016 Excavation 7,556 CY $12.63 $95,432.28 $16.17 $122,151.00 $8.13 $61,430.28 0017 Inspection Trench 2,257 LF $13.94 $31,462.58 $34.45 $77,744.00 $16.26 $36,698.82 0018 Select Impervious Fill

0018AA First 56,300 CY $14.22 $800,586.00 $47.96 $2,699,932.00 $15.69 $883,347.00 0018AA Over 11,000 CY $14.22 $156,420.00 $28.93 $318,218.00 $13.03 $143,330.00

0019 Impervious Fill 6,707 CY $14.22 $95,373.54 $25.98 $174,273.00 $13.03 $87,392.21 0020 Random Fill 7,693 CY $14.22 $109,394.46 $26.37 $202,842.00 $13.03 $100,239.79 0021 Aggregate Surface Course 797 CY $47.11 $37,546.67 $68.88 $54,899.00 $48.98 $39,037.06 0022 Riprap 245 TON $131.61 $32,244.45 $168.29 $41,232.00 $100.04 $24,509.80 0023 Trench Drain 1 JOB $92,707.00 $92,707.00 $211,857.00 $211,857.00 $60,534.53 $60,534.53

TOTAL OF BASE $2,275,194.54 $6,658,256.00 $2,491,170.15

AAECON General Contracting, LLC (d/b/a: AACON General Contractors)

1147 Logan Street Louisville, KY 40204

Fed Serve LLC 3950 25th St N

Fargo, ND 58102 Government Estimate

Item No. OPTION 1 1001 Submersible Pumps 2 EA $88,495.07 $176,990.14 $80,705.46 $161,411.00 $47,421.26 $94,842.52

TOTAL OPTION 1 $176,990.14 $161,411.00 $94,842.52

Item No. OPTION 2 2001 Bonds (Payment and Performance) 1 JOB $1,395.04 $1,395.04 $6,940.00 $6,940.00 $1,584.00 $1,584.00 2002 Demolition 1 JOB $6,505.00 $6,505.00 $4,848.00 $4,848.00 $4,430.28 $4,430.28 2003 Clearing & Grubbing 1 JOB $4,873.00 $4,873.00 $7,921.00 $7,921.00 $7,201.33 $7,201.33 2004 Stripping 1 JOB $1,455.00 $1,455.00 $7,400.00 $7,400.00 $784.83 $784.83 2005 Topsoil & Seeding 1 JOB $8,369.00 $8,369.00 $21,450.00 $21,450.00 $9,084.96 $9,084.96 2006 Inspection Trench 176 LF $13.94 $2,453.44 $29.13 $5,128.00 $16.26 $2,861.76 2007 Select Impervious Fill 3,048 CY $14.22 $43,342.56 $32.59 $99,347.00 $13.03 $39,715.44 2008 Impervious Fill 10 CY $14.22 $142.20 $21.51 $216.00 $13.03 $130.30 2009 Random Fill 508 CY $14.22 $7,223.76 $25.55 $12,982.00 $13.03 $6,619.24 2010 Aggregate Surface Course 24 CY $47.11 $1,130.64 $67.21 $1,613.00 $67.49 $1,619.76 2011 Gravel Road Restoration 1 JOB $16,965.00 $16,965.00 $28,313.00 $28,313.00 $7,074.62 $7,074.62 2012 Excavation 43 CY $12.63 $543.09 $12.62 $543.00 $22.65 $973.95

TOTAL OPTION 2 $94,397.73 $196,701.00 $82,080.47

TOTAL BASE PLUS OPTION 1 PLUS OPTION 2 $2,546,582.41 $7,016,368.00 $2,668,093.14

Clerical errors highlighted in the bid from AAECON. Total price using bid unit pricing is $7,016,604.17, not $7,016,368.00 as provided above.

I certify that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

Gwendolyn K. Davis Contracting Officer

2021-04-21T09:11:41-0500
DAVIS.GWENDOLYN.KAY.1145930800

File details come from the government source that posted it. Updated .