W912ES19T0109_Amendment_0002_Leech_Lake_Well.pdf
PDF 1 MB Posted
- Attached to
- Leech Lake Well Drilling
- Solicitation number
- W912ES19T0109
About this file
Modification to scope of work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912ES19T0109_Amendment_1.pdf | ||
| W912ES19T0109_Leech_Lake_Well_Drilling.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W81G6792066499
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to change the pump size, add language to the fire hydrant paragragh, and extend the closing to 10 Sept
2019 @ 10AM
1. CONTRACT ID CODE PAGE OF PAGES
J 1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Aug-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ES19T0109
X 9B. DATED (SEE ITEM 11)
09-Aug-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
30-Aug-2019
CODE
CONTRACTING DIVISION
USACE - ST. PAUL
180 5TH STREET E SUITE 700
ST. PAUL MN 55101-1678
W912ES 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ES19T0109
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 05-Sep-2019 10:00 AM to 10-Sep-2019 10:00 AM.
The following have been modified:
SCOPE OF WORK
DESCRIPTION/SPECS/PERFORMANCE WORK STATEMENT
REPLACE AND ABANDON
WELL AT LEECH LAKE RECREATION AREA
C-1. GENERAL.
C-1.1. Scope of Work. The work to be performed under this contract consists of furnishing all plant, materials, equipment, supplies, labor and transportation and performing all work as required in strict accordance with the specifications and in accordance with federal, state and local laws and regulations. All work materials and services not expressly called for in the specifications or shown on the drawings but which are necessary for completion of the contract requirements shall be performed and furnished by the Contractor at no increase in cost to the Government.
C-1.2. Payment. Payment will be made upon completion and acceptance of all contract work. The contractor must submit a detailed invoice to the Section Supervisor for payment at the following address: US Army Corps of Engineers, Mississippi Headwaters Office, PO Box 625, 34385 US Highway 2 West, Grand Rapids, Minnesota 55744or email Antonia.v.huber@usace.army.mil
C-1.3. Description and Location. Leech Lake Recreation Area is a Corps of Engineers managed recreation area that includes heavily utilized facilities including a dam, campground, boat ramp, picnic areas, playground, etc. It is located on the Leech River near Federal Dam, Minnesota in Cass County.
C-1.4. Contract Period. All contract work must be completed by 1 November 2019.
C-1.5. Safety. All work shall be performed in accordance with all state, federal and local laws and regulations and the Corps of Engineers Safety and Health Manual, EM-385-1-1. A copy of this manual can be found on line at http://140.194.76.129/publications/eng-manuals/em385-1- 1/2008_English/toc.html
C-1.6. Orientation. Prior to the start of work, the Government will provide an orientation to the Contractor and their personnel which will include discussion of contract requirements, facility inventory, safety considerations, quality control, security and administration.
C-1.7. Site Visit. A site visit is recommended by all bidders. The specifications only have approximate measurements. To schedule a site visit contact Timm Rennecke at 651-290-5470 or email timm.v.rennecke@usace.army.mil
C-2 SPECIFICATIONS
C-2.1. Contact: The Contractor shall contact the Section Supervisor (Jeff Steere 651-290-5808) to coordinate the work at the Leech Lake Recreation Area.
C-2.2. Utilities: The Contractor is responsible for locating all utilities prior to beginning work.
C-2.2. New Well: The Contractor shall drill a new 6 inch PVC well within 15 feet of the old well on the west northwest side of the pump house in the lawn. The pump house has 3-phase electricity available. The contractor will be required to add a main electrical panel, breakers, wiring, conduit, parts, Etc. to power the new well and components with 3-phase electricity. The well pump for the new well shall be variable speed, 3-phase, minimum 7.5HP at 75GPM or larger depending on well capacity after the well is drilled and sized appropriately to be compatible with the new fire hydrant as specified in paragraph C-2.4, plus supply the demand for the Leech Lake Recreation Area that may utilize up to 4,000 thousand gallons of water per day during the months of May thru October and as little as only about 1000 gallons per month during November thru April.
Contractors are to bid this work to comply with minimum 7.5 HP at 75 GPM. Once the new well is drilled, the new well capacity will be determined by the contractor and that data must be provided to the US Army Corps of Engineers along with actual HP and GPM recommendations along with pricing information for appropriately sized equipment that matches the new well capacity for consideration by the Contracting Officer or Representative to modify the pump, piping sizes, from the above specified 7.5HP at 75 GPM, etc. Then the contractor shall provide and install an appropriate well regulator/control box and pressure switch, appropriately sized rigid water line down the well, appropriately sized poly water line from the new well into the pump house, appropriately sized stainless steel well screen, new wiring from the well to the new regulator/controls inside the pump house, and a replacement pressure tank to accommodate the new variable speed pump system. The Contractor is responsible to add appropriately sized water line for the fire hydrant and for connecting to the existing 2 inch copper water line inside the pump house that currently supplies water to the Leech Lake Recreation Area. The new waterline from the well shall enter through the floor of the pump house. The existing well water supply system is about 200 feet in depth and utilizes a Standard Pressure System.
C-2.3. Abandon Old Well: The Contractor shall abandon the old 8 inch steel well according to state codes and the following specifications. The existing well is located in the southwest corner inside the pump house. There is a skylight in the roof for access directly above the well. The contractor shall remove the discharge spool and well pump and cut off the steel well casing flush with the concrete floor. The well shall be filled with bentonite or another approved material used for sealing abandoned wells according to the state well abandonment code. The electrical controls and wiring on the inside of the pump house that were used with the old well shall also be removed so that the new electrical controls and wiring can be installed in the same general location.
C-2.4. New Fire Hydrant & Installation: The Contractor shall provide and install a new Dry Barrel Hydrant with Drain Valve, water supply pipe, fittings, shut off valve, with all necessary components, parts, and provide all locates, equipment, digging, trenching, labor, etc. to install a New, Year-Round, Red, Frost Proof, Fire Hydrant with 3-Outlets (of which one must be 4-1/2” and two must be 2-1/2”), that is designed with the new well specified in this contract in the following location: East approximately 25 feet from Pump House, and West approximately 35 feet from the Main Boat Ramp Parking Lot (see attachments for map of Parking Lot that’s located East of the Pump House). This location is on the West side of the row of Red Pine Trees located adjacent to the above described Parking Lot so not to kill the trees. The contractor is required to locate buried utilities and then the exact location will be determined and approved by the US Army Corps of Engineers. Water for the new fire hydrant will be supplied from the same Pump House that the new well is being piped into. The water supply to the hydrant will be constructed to meet the new well output capacity that will be determined after the new well is drilled and tested. The contractor will be required to perform a flow rate test witnessed by US Army Corps of Engineers to satisfy this requirement. The contractor is responsible for changes to or additional piping inside the pump house including pipes, fittings, valves, shut offs, back flow preventer, Etc. and drilling or cutting through concrete floor, Etc. The new Fire Hydrant and all components and water supply will comply with standards for year-round use for filling tanks.
The MN Department of Health requires there to be a back flow preventer installed into the water line that supplies the fire hydrant. The contractor shall provide and install a back flow preventer into the fire hydrant water supply pipe inside the pump house that meets the MN Department of Health codes and guidelines.
Two photos are attached at the end of this document to illustrate an example of a Fire Hydrant in use at an off-site location.
C-2.5. Disposal. All construction debris shall be removed and disposed of off-site according to the local and state disposal codes.
C - 2.6. Work Area: The contractor is responsible for leaving the work area in the same condition as before the start of contract work. Holes, trenches, etc. must be compacted while backfilling to prevent any future settling. Surfaces must be returned to grade upon completion.
Top soil should be stock piled separately from other soils while digging and reutilized for top-soil on surfaces when final leveling/grading/landscaping is done at the end of the job. Contractor is responsible for all additional sand, gravel, etc. that may be needed to complete the job correctly. Any damages shall be repaired at the contractor’s expense. All construction debris shall be removed and disposed of off-site in accordance with local and state regulations.
C-2.7. Existing Well Specifications.
Well Depth: 200’ Well Casing Depth: 190’ Well Casing: 8” Steel Stainless Steel Well Screen: 8” x 10’ Static Water Level: 6’ Well Pump: 3 HP Volts: 230 Well Capacity: 41 GPM Date Drilled: 1967
C-2.7 Submittals: The contractor shall submit a drawing with his quote of the new system including the well location, well pump manufacturer/model, pump electric controls, pressure tank, location of the new waterline entering the pump house, manufacturer/model of fire hydrant and the plumbing to existing waterline.
C-3.0. Site Map
3.1. Areal Photo
W ell
3.2 Photo of Pump House Exterior.
3.3 Well Regulator/Controls
3.4 Well
Plumbing
Fire Hydrant Example
(End of Summary of Changes)