Solicitation W912ES18R0006 Lock & Dam 6 Traveling Mooring Bitt

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. W912ES-18-R-0006

MAINTENANCE

MISSISSIPPI RIVER

TREMPEALEAU COUNTY, WI

CONSTRUCTION

DOCUMENTS FOR

TRAVELING MOORING BITT

SYSTEM REHABILITATION

LOCK AND DAM NO. 6

UPPER GUIDE WALL

March 2018

US Army Corps of Engineers St. Paul District

W81G6771525178

Lock and Dam No. 6 Upper Guide Wall Traveling Mooring Bitt System Rehabilitation, Trempealeau County, WI

Work involves, but is not limited to, removal of the existing rail, rail clips, and traveling mooring bitts; proper onsite storage of existing rail and traveling mooring bitts; proper offsite disposal of rail clips and debris; concrete demolition and removal; crack repair; grouting abandoned conduits; placing concrete to restore top of guidew all and to f ill manholes; testing of the new traveling mooring bitt system; fabrication, and installation of the new traveling mooring bitts system, including rail anchors, bed plates, clips, rail, and traveling mooring bitts; and demonstration that the traveling mooring bitts are able to freely traverse the entire length of the rail w ithout binding. Work includes all parts, material, equipment, and labor as show n and specif ied.

The magnitude of this construction project is betw een $500,000 and $1,000,000. The North American Industry Classif ication (NAICS) for this acquisition is 237990 w ith a Small Business Size Standard of $36,500,000. This solicitation is issued as an Request for Proposal (RFP) w ith a

100% Small Business Set Aside.

JOHN P RIEDERER 651-290-5614

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

09-Mar-2018

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10 Alt1

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________10 Apr 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

CONTRACTING DIVISION

USACE - ST. PAUL

180 5TH STREET E SUITE 700

ST. PAUL MN 55101-1678

W912ES

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour) Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W912ES18R0006 203

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued)

(Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W912ES18R0006

Table of Contents

Table of Contents Table of Contents

Section 00 10 00 - Solicitation

INFORMATION TO OFFEROR

PRICE SCHEDULE

Section 00 21 16 - Instructions to Proposers

52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (JUL 2016)

52.204-22 ALTERNATIVE LINE ITEM PROPOSAL (JAN 2017)

52.211-5000 EVALUATION OF SUBDIVIDED ITEMS

52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991)

52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (APR 1991)

52.214-4002 ALL OR NONE QUALIFICATIONS (FEB 2011) FAR 14.404-5

52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2017)

52.216-1 TYPE OF CONTRACT (APR 1984)

52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY

2014)

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT--CONSTRUCTION MATERIALS (MAY 2014)

ALTERNATE I (MAY 2014)

52.233-2 SERVICE OF PROTEST (SEP 2006)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

Section 00 45 00 - Representations and Certifications

52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2016)

52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2017)

52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (JULY 2013)

252.203-7005 REPRESENTATION RELATING TO COMPENSATION OF FORMER DOD OFFICIALS

(NOV 2011)

252.204-7004 ALTERNATE A, SYSTEM FOR AWARD MANAGEMENT (FEB 2014)

252.204-7007 ALTERNATE A, ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2015)

Section 00 70 00 - Conditions of the Contract

52.202-1 Definitions (NOV 2013)

52.202-4001 DEFINITIONS (July 2014) UAI Part 2.101-100

52.203-3 GRATUITIES (APR 1984)

52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)

52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (SEP 2006)

52.203-7 ANTI-KICKBACK PROCEDURES. (MAY 2014)

52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER

ACTIVITY (MAY 2014)

52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)

52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS

(OCT 2010)

52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM

EMPLOYEES OF WHISTLEBLOWER RIGHTS (APR 2014)

52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS

OR STATEMENTS (JAN 2017)

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May 2011)

52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)

52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS

(OCT 2016)

52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2016)

52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (JUL 2016)

52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC

2014)

52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH

CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (OCT 2015)

52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY

MATTERS (JULY 2013)

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) -

ALTERNATE I (APR 1984)

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)

52.215-2 AUDIT AND RECORDS--NEGOTIATION (OCT 2010)

52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2011)

52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (NOV 2016)

52.219-14 LIMITATIONS ON SUBCONTRACTING (JAN 2017)

52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JULY 2013)

52.222-3 CONVICT LABOR (JUN 2003)

52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS - OVERTIME COMPENSATION.

(MAY 2014)

52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (MAY 2014)

52.222-7 WITHHOLDING OF FUNDS (MAY 2014)

52.222-8 PAYROLLS AND BASIC RECORDS (MAY 2014)

52.222-9 APPRENTICES AND TRAINEES (JUL 2005)

52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)

52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)

52.222-12 CONTRACT TERMINATION--DEBARMENT (MAY 2014)

52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED

REGULATIONS (MAY 2014)

52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)

52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014)

52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015)

52.222-26 EQUAL OPPORTUNITY (SEPT 2016)

52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (APR

2015)

52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015)

52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUL 2014)

52.222-37 EMPLOYMENT REPORTS ON VETERANS (FEB 2016)

52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT

(DEC 2010)

52.222-50 COMBATING TRAFFICKING IN PERSONS (MAR 2015)

52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (OCT 2015)

52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 (DEC 2015)

52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 (JAN 2017)

52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND

CONSTRUCTION CONTRACTS (SEP 2013)

52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (JAN 1997) 98

52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)

52.223-6 DRUG-FREE WORKPLACE (MAY 2001)

52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-

DESIGNATED ITEMS (MAY 2008)

52.223-11 OZONE-DEPLETING SUBSTANCES AND HIGH GLOBAL WARMING POTENTIAL

HYDROFLUOROCARBONS (JUN 2016)

52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND

CONSTRUCTION CONTRACTS (MAY 2008)

52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING

(AUG 2011)

52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)

52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008)

52.227-1 AUTHORIZATION AND CONSENT (DEC 2007)

52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT

(DEC 2007)

52.227-4 PATENT INDEMNITY--CONSTRUCTION CONTRACTS (DEC 2007)

52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)

52.228-5 INSURANCE--WORK ON A GOVERNMENT INSTALLATION (JAN 1997)

52.228-11 PLEDGES OF ASSETS (JAN 2012)

52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS. (MAY 2014)

52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)

52.228-15 PERFORMANCE AND PAYMENT BONDS--CONSTRUCTION (OCT 2010)

52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013)

52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)

52.232-17 INTEREST (MAY 2014)

52.232-23 ASSIGNMENT OF CLAIMS (MAY 2-14) - ALTERNATE I (APR 1984)

52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)

52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER—SYSTEM FOR AWARD

MANAGEMENT (JULY 2013)

52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)

52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (DEC

2013)

52.233-1 DISPUTES. (MAY 2014)

52.233-3 PROTEST AFTER AWARD (AUG. 1996)

52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)

52.236-2 DIFFERING SITE CONDITIONS (APR 1984)

52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)

52.236-4 PHYSICAL DATA (APR 1984)

52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)

52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)

52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)

52.236-8 OTHER CONTRACTS (APR 1984)

52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS (APR 1984)

52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984)

52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)

52.236-12 CLEANING UP (APR 1984)

52.236-13 ACCIDENT PREVENTION (NOV 1991)

52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)

52.236-17 LAYOUT OF WORK (APR 1984)

52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)

52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)

52.242-13 BANKRUPTCY (JUL 1995)

52.242-14 SUSPENSION OF WORK (APR 1984)

52.243-4 CHANGES (JUN 2007)

52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS (JAN 2017)

52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)

52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)

52.248-3 VALUE ENGINEERING--CONSTRUCTION (OCT 2015)

52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012) -

ALTERNATE I (SEP 1996)

52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)

52.253-1 COMPUTER GENERATED FORMS (JAN 1991)

252.201-7000 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 1991)

252.203-7000 REQUIREMENTS RELATING TO COMPENSATION OF FORMER DOD OFFICIALS (SEP

2011)

252.203-7001 PROHIBITION ON PERSONS CONVICTED OF FRAUD OR OTHER DEFENSE-

CONTRACT-RELATED FELONIES (DEC 2008)

252.203-7002 REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS (SEP 2013)

252.204-7003 CONTROL OF GOVERNMENT PERSONNEL WORK PRODUCT (APR 1992)

252.204-7012 SAFEGUARDING COVERED DEFENSE INFORMATION AND CYBER INCIDENT

REPORTING (OCT 2016)

252.204-7015 NOTICE OF AUTHORIZED DISCLOSURE OF INFORMATION FOR LITIGATION

SUPPORT (MAY 2016)

252.209-7004 SUBCONTRACTING WITH FIRMS THAT ARE OWNED OR CONTROLLED BY THE

GOVERNMENT OF A COUNTRY THAT IS A STATE SPONSOR OF TERRORISM (OCT 2015)

252.223-7001 HAZARD WARNING LABELS (DEC 1991)

252.223-7004 DRUG-FREE WORK FORCE (SEP 1988)

252.223-7006 PROHIBITION ON STORAGE, TREATMENT, AND DISPOSAL OF TOXIC OR

HAZARDOUS MATERIALS (SEPT 2014) -- ALTERNATE I (SEPT 2014)

252.223-7008 Prohibition of Hexavalent Chromium (JUN 2013)

252.225-7008 RESTRICTION ON ACQUISITION OF SPECIALTY METALS (MAR 2013)

252.225-7012 PREFERENCE FOR CERTAIN DOMESTIC COMMODITIES (DEC 2016)

252.225-7048 EXPORT-CONTROLLED ITEMS (JUNE 2013)

252.227-7033 RIGHTS IN SHOP DRAWINGS (APR 1966)

252.232-7010 LEVIES ON CONTRACT PAYMENTS (DEC 2006)

252.236-7000 MODIFICATION PROPOSALS - PRICE BREAKDOWN. (DEC 1991)

252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

252.236-7002 OBSTRUCTION OF NAVIGABLE WATERWAYS. (DEC 1991)

252.236-7008 CONTRACT PRICES - BIDDING SCHEDULES. (DEC 1991)

252.243-7001 PRICING OF CONTRACT MODIFICATIONS (DEC 1991)

252.243-7002 REQUESTS FOR EQUITABLE ADJUSTMENT (DEC 2012)

252.244-7000 SUBCONTRACTS FOR COMMERCIAL ITEMS (JUN 2013)

252.247-7023 TRANSPORTATION OF SUPPLIES BY SEA (APR 2014)

252.247-7024 Notification of Transportation of Supplies by Sea (MAR 2000)

Section 00 73 00 - Supplementary Conditions

AT/OPSEC 13: Will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas

AT/OPSEC 15: Pre‐screen candidates using E‐Verify Program

AT/OPSEC 2: Access and General Protection/Security Policy and Procedures

AT/OPSEC 2b: For contractors who do not require a CAC, but require access to a DoD facility or installation 172

Section 01 00 00 - General Requirements

General Requirements

PARTNERING

TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER - ER 415-1-15

INSURANCE

INVOICE PROCEDURES

UNAVAILABILITY OF UTILITY SERVICES

SAFETY AND HEALTH REQUIREMENTS MANUAL INTERIM CHANGES, EM 385-1-1

PURCHASE ORDERS

FLOATING PLANT EQUIPMENT

OBSTRUCTION OF CHANNEL

SIGNAL LIGHTS

RADIO

LABORATORY AND TESTING FACILITIES

52.211-5001 VARIATIONS IN ESTIMATED QUANTITIES, SUBDIVIDED ITEMS

52.249-5000 BASIS FOR SETTLEMENT OF PROPOSALS

MVP-0002 APPARENT CLERICAL MISTAKES

MVP-0003 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

WAGE DETERMINATION

General Decision Number: WI180015 01/05/2018 WI15

Section 00 10 00 - Solicitation

INFORMATION TO OFFEROR

INFORMATION TO OFFERORS

1. SAM REGISTRATION. All offerors must register and complete online representations and certifications in the System for Award Management (SAM) at www.sam.gov prior to the bid opening. Proposals from offerors that have not registered or completed their online representations and certifications may be rejected. Offerors are advised that the initial registration process in SAM may take several weeks. The Government will review completed Representations and Certifications in SAM following the initial evaluation of proposals. Submission of paper copies of completed representations and certifications is NOT required with proposals.

2. OFFEROR INQUIRIES. Any prospective offeror desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must submit their questions using the ProjNet system at https://www.projnet.org

All inquiries shall be submitted in writing. To submit a new inquiry or to view inquiries submitted by other prospective offerors, users must be registered and signed into the ProjNet system. Offerors may register online at https://www.projnet.org (click on “Register”). The following information will be needed to submit or view offeror inquiries:

Managing Agency: USACE The Solicitation Number is: W912ES-18-R-0006 The Bidder Inquiry “Key” Number is YX6I7X-IH5JS8

Offerors shall submit inquiries not later than 10 days prior to proposal submission date in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation if necessary. Those who submit an inquiry will receive a system-generated email acknowledgement. All answers to inquiries will be posted in ProjNet after they have been reviewed by the USACE technical team. Offerors are advised to review the solicitation in its entirety and to review all previously submitted questions and responses prior to submitting a new inquiry.

3. RESPONSIBILITY DETERMINATION. In accordance with Federal Acquisition Regulation (FAR) Subpart 9.1, the offeror with the apparent lowest price technically acceptable proposal will be requested to provide the following information:

a. A detailed description of the work to be self-performed and resources available to demonstrate the firm is capable of complying with: 52.219-14, Limitations on Subcontracting.

http://www.sam.gov/ http://www.projnet.org/ http://www.projnet.org/

b. Financial Statements, including balance sheets that identify major categories of assets, liabilities, and owner’s equity; and profit and loss statements for the past three (3) years.

c. A Bank Certification of Financial Capability (line of credit).

Offerors are advised to note ANTITERRORISM/OPERATIONS SECURITY special contract requirements (Section 00 73 00 Supplementary Conditions).

4. FACSIMILE OF PROPOSALS AND MODIFICATIONS THERETO WILL NOT BE

ACCEPTED.

5. This solicitation and any forthcoming amendments will only be available on www.fbo.gov. Any forthcoming amendments will only be available on this web site. It is recommended that each registered firm check this website periodically for updates.

6. All Quantities are estimated except where unit is given as "EA" (each) or "JOB" (job).

All extensions of the unit prices shown will be subject to verification by the Government. In case of a discrepancy between the unit price and the extension, the unit price will govern.

For further information reference clause MVP-0002 entitled “Apparent Clerical Mistakes” in Section 01 00 00.

7. UNBALANCED OFFERS. The government may reject as non-responsive any proposal that is materially unbalanced between contract line item numbers or sub-items on the pricing schedule. A proposal is materially unbalanced when it is based on prices that are significantly less than cost for some work and significantly more than cost for other work. A materially unbalanced proposal may be rejected if the Contracting Officer has a reasonable doubt as to whether the proposal will result in the lowest overall cost to the government even though it may be the lowest evaluated offer found technically acceptable. Additionally, a proposal that is unbalanced so as to be tantamount to an advance payment will be rejected as non-responsive even if acceptance of the offer would result in the lowest overall cost to the government.

8. The addresses, phone numbers, and Internet address (if available) for references cited in these specifications are listed in the Unified Facilities Guide Specification (UFGS) 01 42 00 SOURCES FOR REFERENCE PUBLICATIONS. UFGS 01 42 00 is available under Publications on the TECHINFO page of the Corps of Engineers Huntsville District Internet site at: http://www.hnc.usace.army.mil/Missions/Engineering- Directorate/TECHINFO/.

9. PLEASE NOTE: Visitors that show up for the Organized Site Visit, In Person Discussions (or at any other time) may be required to show Real-ID compliant http://www.fbo.gov/ http://www.fbo.gov/ http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO identification cards, or have two forms of ID for those states that are not yet compliant (i.e. Minnesota standard Driver’s Licenses) A. Basis for Award:

Award will be made to the responsible offeror representing the best value based on the Lowest- Priced, Technically Acceptable (LPTA) proposal. Each technical evaluation factor and subfactor must be found to be “acceptable” in order for the proposal to be found technically acceptable.

Proposals will not be ranked using non-price factors. Award will be made to the lowest priced, technically acceptable proposal. Firms may only submit one proposal. Acceptable/Unacceptable Ratings are defined as follows:

Acceptable: Proposal clearly meets the minimum requirements of the solicitation.

Unacceptable: Proposal does not clearly meet the minimum requirements of the solicitation.

The successful offeror’s key personnel and subcontractors will be incorporated in any resulting contract. The identified key personnel and subcontractors must be used on the project. If any of the key personnel or subcontractors identified in the proposal are not available during construction, the prime contractor may propose a different subcontractor or employee by submitting the name and relevant experience to the Government in the form of a submittal prior to the start of work. The qualifications and experience of the key personnel and subcontractors incorporated into the contract will be considered the minimum acceptable qualifications for any proposed replacements during contract performance. In the event that the contractor cannot provide a listed key personnel or subcontractor, or one of comparable qualification, the contracting officer may reduce the contract price or take such other actions as are necessary to protect the interests of the Government, including the timely completion of the contract work.

B. Definitions:

Hydraulic machinery includes the following components: hydraulic pump and hydraulic motor.

Rated capacity for movable cranes is the stated maximum design load. Rated capacity for movable dam gates is the weight of the gate. Rated capacity for movable bridges is the weight of the bridge.

Movable structures include movable dam gates, movable cranes, or movable bridges with a rated capacity of 10 tons or more.

C. Proposal Submission Requirements

The offeror’s proposal shall be submitted in two volumes:

Volume I-Technical Proposal Volume II-Price Proposal

All pages containing text should be consecutively numbered, type-written on 8 ½ x 11 inch paper, with margins of at least one inch, using a standard font no smaller than 12. The Technical Proposal and Price Proposals should be stapled/bound separately.

Technical Proposal: Offerors shall submit one original and four (4) hard copies. The Technical Proposal shall include the following:

• Solicitation number (“W912ES-18-R-0006”)

• Offeror’s name, address, telephone and email address

• Names, titles, telephone and email addresses of persons authorized to negotiate on the

Offeror’s behalf with the Government in connection with this solicitation

• Name, title, and signature of person authorized to sign the proposal.

• Letter(s) of Commitment (if applicable).

• Responses to all technical evaluation factors. The format used for the Parts below should be strictly adhered to. All responses in the Offeror’s Technical Proposal must clearly indicate the areas to which they are applicable:

Part I: Recent and Relevant Experience Part II: Shop Fabrication Part III: Key Personnel Qualifications Part IV: Past Performance

• The Technical Proposal is limited to no more than 30 pages, not including supplementary documents (e.g. letters of commitment, joint venture agreements, etc.).

• The Technical proposal shall not include pricing information.

Price Proposal: Offerors shall complete and submit the pricing schedule (schedule of items/bid schedule) with their proposal and include a price for each line item, including subtotals and totals. Failure to do so will result in the proposal being rejected without further consideration.

V. EVALUATION FACTORS

The evaluation factors and significant subfactors are listed below. It is intended that proposals be evaluated, and award made, without discussions with the offerors (other than for the purpose of minor clarification[s]), unless discussions are determined to be necessary. Failure to submit mandatory information for a factor or subfactor, indicated by the word shall, will result in a rating of “unacceptable” for that factor or subfactor, and the offer will be ineligible for award.

Requested information, indicated by the word should, is not mandatory, but missing, incomplete, or ambiguous information may result in a rating of “unacceptable” for that factor or subfactor. It is the offeror’s responsibility to ensure the completeness of its proposal. The Government intends to evaluate solely on the information provided in the initial proposal and not assume that an offeror possesses any capability that is not specifically identified in the proposal.

The technical evaluation factors—Recent and Relevant Experience, Shop Fabrication, Key Personnel Qualifications, and Past Performance, and their subfactors—will be evaluated first.

Price will be evaluated last.

The Government will evaluate the offeror’s and their major subcontractors’ experience and certifications only. If an offeror wishes to be credited with a subcontractor’s or supplier’s experience or certification, a letter of commitment signed by the subcontractor/supplier and the prime contractor (offeror) must be submitted with the proposal. The letter of commitment shall clearly state that the offeror and the subcontractor/supplier have committed to construct this project together if the offeror receives the contract award. In regard to Experience, if an offeror submits projects demonstrating experience in one of the factors, and that project was completed by a subcontractor, a subsidiary, or a supplier, as opposed to the offeror, the offeror MUST submit a signed letter of commitment from the subcontractor who performed and completed the work. If a letter of commitment is not submitted, the experience/certifications will not be considered.

A. Technical Proposal, Part I: Recent and Relevant Experience

Submission Requirements:

The offeror shall provide examples of recent and relevant projects. The technical proposal shall contain information documenting that the firm and its subcontractors (as applicable) have performed construction and field installation, alignment, and commissioning for movable structures. Provide information for a minimum of three (3) and a maximum of five (5) recent projects, with at least one (1) of these projects involving winter field construction in temperatures below freezing. Projects performed inside a shop environment do not qualify.

Project information will be evaluated sequentially. Information for work exceeding five (5) projects will not be considered and only the most recent projects will be evaluated.

Documentation for each project shall include, but not be limited to:

• Project Name

• Location

• Construction Dates

• Major Project Features Constructed

• Total Construction Cost

• Methods Employed to address construction issues related to work adjacent to or over water, as well as winter construction where applicable

• Names and Contact Information for the Project Owner

The offeror shall identify at least one recent project for each of the critical work elements identified below in which they have directly performed or supervised a subcontractor performing the required work. As described above, if an offeror wishes to be credited with a subcontractor’s experience, a letter of commitment signed by the subcontractor and the prime contractor (offeror) must be submitted with the proposal.

Recent is defined as work that was completed within the last ten (10) years from the proposal due date or work that is ongoing but not less than 50% physically complete. The definitions of relevant are included within each of the work element descriptions below (a.-c.)

Work Elements:

a. Precision welding in a field environment

• To be considered relevant, the project should include welding of rails, pipes, beams, plating or other large steel elements, one ton or greater, in a field environment. At least one project should demonstrate experience with welding outdoors in temperatures below freezing.

b. Concrete work in cold weather

• To be considered relevant, the project shall demonstrate experience with cast-in-place concrete in cold weather (below 32 degrees F).

c. Marine Construction

• To be considered relevant, the project must demonstrate the ability to safely work over or adjacent to a navigable body of water.

Each of the listed work elements must be addressed by at least one project. Multiple work elements may be addressed by the same project.

The Recent and Relevant Experience factor will receive a rating of “acceptable” or “unacceptable” based on its entirety. In order to receive an “acceptable” rating, Offerors must provide the requested information using the SSEB Technical Proposal Evaluation Form (Appendix B) and demonstrate to the evaluators that the Offeror and its personnel or subcontractors (as applicable) have sufficient recent and relevant experience, and the knowledge and capability to successfully perform the tasks described in this solicitation. Missing, incomplete, or ambiguous information could result in a rating of “unacceptable.” Missing mandatory information will result in a rating of “unacceptable.”

B. Technical Proposal, Part II: Shop Fabrication

Submission Requirements:

The offeror shall provide documentation that the firm and/or its subcontractors, as applicable, have performed fabrication of machinery for moveable structures. Hydraulic machinery does not qualify. Provide information for a minimum of two (2) and a maximum of five (5) recent projects. The fabricator shall be an American Institute of Steel Construction (AISC) Certified Fabrication Plant, Category BU, SBR, IBR, ABR, CBR, or HYD. Documentation for each project shall include, but not be limited to:

• Construction Dates

• Major Project Features Constructed

• Total Construction Cost

• Names and Contact Information for the Project Owner (telephone and/or email address for valid contact)

• Letter of Commitment if the fabrication will be performed by a subcontractor

Each of the following work elements shall be included in the cited projects:

Work Elements:

• Bearings (rolling element or plain)

• Fabrication of machined steel weldments

The shop fabrication work shall have been completed within the last ten (10) years from the proposal due date or work that is ongoing but not less than 50% physically complete.

The Shop Fabrication factor will receive a rating of “acceptable” or “unacceptable” based on its entirety. In order to receive an “acceptable” rating, Offerors must provide the requested information using the SSEB Technical Proposal Evaluation Form (Appendix B) and demonstrate to the evaluators that the Offeror and its personnel or subcontractors (as applicable) have performed the fabrication work required by the factor. Missing, incomplete, or ambiguous information could result in a rating of “unacceptable.” Missing mandatory information will result in a rating of “unacceptable.”

C. Technical Proposal, Part III: Key Personnel Qualifications

Offerors shall identify the Erecting Engineer assigned to this project. The Erecting Engineering shall be a licensed mechanical engineer. If the individual is not an employee of the offeror’s firm, a signed Letter of Commitment must be included. If the personnel presented in the offer need to be replaced, replacement personnel must have equal or better qualifications as those proposed and shall be approved by the contracting officer. Key personnel shall speak English fluently. Note that the data requested here are not elements that will be separately evaluated; the Key Personnel Qualifications factor will receive a rating of “acceptable” or “unacceptable” based on its entirety. The offeror shall include the following information:

• Name of the person

• Title of position

• Technical background

• Educational level of person (university degree, technical school, high school, etc.)

• Professional License(s) held

• Number of years of relevant experience

• The person’s level of English language proficiency

Qualifications shall include at least two (2) projects performed in the last ten (10) years, in which the individual has performed field alignment for movable structures with a rated capacity of 10 tons or more to a precision of +/- 1/16 inch or less. Projects performed inside a shop environment do not qualify. The documentation shall include:

• Construction Dates

• Names and Contact Information of Project Owners (telephone and/or email address for valid contact)

• Major project features constructed

• Total construction cost

D. Technical Proposal, Part IV: Past Performance

Offerors’ past performance is a measure of the degree to which an offeror was successful on projects of similar scope, size, and complexity, as measured by the level of past customer satisfaction. It is also a measure of the degree to which an offeror has complied with Federal, state, and local laws and regulations. The Government’s assessment of past performance will be subjective and based mainly on offeror reputations with customers and other sources. The Government will evaluate the reference information/performance data provided by offerors and obtained from other sources, such as Government databases. Note that the data requested below are not subfactors that will be separately evaluated; past performance will receive a consensus evaluation based on its entirety.

Submission Requirements:

(1) Offerors should submit a list of at least three, but no more than five, past performance references for work performed since 2008 that should meet the following conditions. If more than five past performance references are submitted, only the first five will be considered. If less than three past performance references are submitted, they will be evaluated, and the lack of the requested number of projects will not be evaluated favorably or unfavorably for this factor (see subparagraph (4) below).

(a) The past performance reference must have been a client, or client representative, with whom the offeror had a contract, or subcontract (if applicable) for one or more projects.

(b) The past performance reference must hold, or held at the time, a senior position in the client organization with responsibilities for either contract administration, quality control, engineering or technical supervision, or was otherwise in a position to evaluate the offeror’s performance in executing the contract or subcontract. The past performance reference must have first-hand knowledge of the offeror’s performance.

(c) The past performance reference must have a current, valid phone number they can be reached at during normal business hours, a fax number, and must be able to speak, read, and write in the English language.

(2) For each of the past performance references described in (a) above, offerors shall submit the following information.

• The name, title, company or government agency, and address of the past performance reference

• A current, valid phone number and fax number at which the past performance reference can be reached during normal business hours. If available, include an e-mail address as well

• A brief description of the qualifying project or projects, including name, location, and year completed, for which the past performance reference will be able to provide valid past performance information

• Offerors may include information on problems encountered on the identified contracts and the offeror’s corrective actions

(3) The government may contact any or all of the past performance references provided by the offerors to collect and evaluate past performance information. This information may be written or oral. The government shall consider this information, as well as information obtained from any other sources, when evaluating an offeror’s past performance. The evaluation will take into account past performance information regarding predecessor companies, key personnel who have relevant experience, or subcontractors that will perform major or critical aspects of the requirement when such information is available and relevant to the instant acquisition.

(4) In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available, the offeror may not be evaluated favorably or unfavorably. If the government is unable to reach an individual past performance reference within a reasonable time, this will be treated as “past performance information not available,” and will not be evaluated favorably or unfavorably.

(5) The Past Performance factor will receive a rating of "acceptable" or "unacceptable" based on its entirety. Collected past performance information will be rated "acceptable" if it reflects performance that met contractual requirements. The Past Performance factor will be rated “acceptable” even if contractual performance of a particular element or sub-element may contain some minor problems for which corrective actions taken by the offeror appear or were satisfactory.

E. Price Proposal

Submission Requirements:

The Price Proposal shall be submitted as a single-sided original, and shall include the following:

1. Completed Standard Form (SF) 1442, including acknowledgement of all Amendments

2. Completed Pricing Schedule with a price for each line item including subtotals and totals

3. Proof of current System for Award Management (SAM) registration including the applicable NAICS code for this acquisition (237990)

4. Representations and Certifications (completed clause 52.204-8, if Offeror’s SAM profile does not contain current FAR and DFARS Reps & Certs)

VI. EVALUATION PROCESS

After receipt of proposals, the SSEB will convene and the voting members will independently evaluate all submitted proposals according to the evaluation factors set forth in the solicitation, beginning with the Technical proposals. Once the Technical evaluations are completed, the SSEB chairperson will lead the SSEB in discussion of each proposal, and they will come to a consensus decision as to the acceptability of each factor for each offeror. A consensus is not a majority opinion, but rather a collective opinion on the acceptability of each factor or significant subfactor. In the event that a consensus cannot be reached, the opposing views will be presented to the Contracting Officer for resolution. After concluding the evaluations, the chairperson will provide an oral briefing of the consensus evaluation results to the SSA and submit a written consensus evaluation report for the record.

The written consensus report will detail the reasons for acceptability or unacceptability of proposals noted during the SSEB evaluation. The SSEB will make no recommendation as to who shall receive the award and additionally shall not establish a rank order or order of merit list pertaining to the offers being evaluated. Upon completion of the Technical proposal report for the record, the SSA will evaluate the Price proposals price in terms of unbalancing and for potential performance risks.

The SSA, or the SSA’s designee, will evaluate each offeror’s price to determine price reasonableness.

In this context, reasonableness will be determined by comparing offered prices to one another, to the government estimate, and to pricing for previous work of a similar nature.

After receiving the SSEB chairperson’s written consensus evaluation report and briefing for the Technical proposals, the SSA, independently exercising prudent business judgment, will make a source selection decision on the basis of the lowest priced proposal meeting the acceptability standard for the technical factors and subfactors. While the SSA may use reports and analyses prepared by others, the source selection decision shall represent the SSA's independent judgment. The source selection decision shall be documented, and the documentation shall include the rationale for any business judgments made or relied on by the SSA.

If, during the evaluation process, any offerors are eliminated from the competition, the offerors excluded from the competition shall be promptly notified in writing. The notice shall state the basis for the determination and that a proposal revision will not be considered. The Procuring Contracting Officer shall award a contract to the successful offeror by furnishing the executed contract or other notice of the award to that offeror. Each offeror whose proposal was not selected for award, will be notified in writing within three days after the date of the contract award. Debriefings will be provided to unsuccessful offerors who submit timely requests.

PRICE SCHEDULE

LOCK AND DAM NO. 6 UPPER GUIDE WALL

TRAVELING MOORING BITT SYSTEM REHABILITATION

Item Description Quantity Unit Unit Price Amount

0001 PERFORMANCE AND PAYMENT BONDS 1 JOB ___________ ____________

0002 REMOVALS 1 JOB ___________ ____________

0003 CONCRETE REHABILITATION 1 JOB ___________ ____________

0004 SHOP LOAD TESTING 1 JOB ___________ ____________

0005 GROUTING ABANDONED CONDUITS

0005AA FIRST 30 GALLONS 30 GAL ___________ ____________

0005AB OVER 30 GALLONS 15 GAL ___________ ____________

0006 CRACK REPAIR

0006AA FIRST 40 GALLONS 40 GAL ___________ _____________

0006AB OVER 40 GALLONS 15 GAL ___________ _____________

0007 RAIL SUPPORT ASSEMBLY FABRICATION 270 EA ___________ _____________

0008 RAIL SUPPORT ASSEMBLY INSTALLATION 235 EA ___________ _____________

0009 TOW HAUL RAIL 712 LF ___________ _____________

0010 BEGIN AND END STOPS 2 EA ___________ _____________

0011 TRAVELING MOORING BITTS 2 EA ___________ _____________

TOTAL AMOUNT (CLINS 0001 - 0011) ___________________________

http://www.sam.gov/ https://cage.dla.mil/ https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx http://www.nato.int/structur/AC/135/main/links/contacts.htm https://cage.dla.mil/

Section 00 21 16 - Instructions to Proposers

52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (JUL 2016)

(a) Definition. As used in this provision--

Commercial and Government Entity (CAGE) code means—

(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics Agency (DLA) Commercial and Government Entity (CAGE) Branch to identify a commercial or government entity;

or

(2) An identifier assigned by a member of the North Atlantic Treaty Organization (NATO) or by the NATO Support and Procurement Agency (NSPA) to entities located outside the United States and its outlying areas that the DLA Commercial and Government Entity (CAGE) Branch records and maintains in the CAGE master file. This type of code is known as a NATO CAGE (NCAGE) code.

(b) The Offeror shall enter its CAGE code in its offer with its name and address or otherwise include it prominently in its proposal. The CAGE code entered must be for that name and address. Enter ``CAGE'' before the number. The CAGE code is required prior to award.

(c) CAGE codes may be obtained via--

(1) Registration in the System for Award Management (SAM) at www.sam.gov. If the Offeror is located in the United States or its outlying areas and does not already have a CAGE code assigned, the DLA Commercial and Government Entity (CAGE) Branch will assign a CAGE code as a part of the SAM registration process. SAM registrants located outside the United States and its outlying areas shall obtain a NCAGE code prior to registration in SAM (see paragraph (c)(3) of this provision).

(2) The DLA Commercial and Government Entity (CAGE) Branch. If registration in SAM is not required for the subject procurement, and the offeror does not otherwise register in SAM, an offeror located in the United States or its outlying areas may request that a CAGE code be assigned by submitting a request at https://cage.dla.mil.

(3) The appropriate country codification bureau. Entities located outside the United States and its outlying areas may obtain an NCAGE code by contacting the Codification Bureau in the foreign entity's country if that country is a member of NATO or a sponsored nation. NCAGE codes may be obtained from the NSPA at https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx if the foreign entity's country is not a member of NATO or a sponsored nation. Points of contact for codification bureaus, as well as additional information on obtaining NCAGE codes, are available at http://www.nato.int/structur/AC/135/main/links/contacts.htm.

(d) Additional guidance for establishing and maintaining CAGE codes is available at https://cage.dla.mil.

(e) When a CAGE Code is required for the immediate owner and/or the highest-level owner by 52.204-17 or 52.212-3(p), the Offeror shall obtain the respective CAGE Code from that entity to supply the CAGE Code to the Government.

(f) Do not delay submission of the offer pending receipt of a CAGE code.

(End of Provision)

52.204-22 ALTERNATIVE LINE ITEM PROPOSAL (JAN 2017)

(a) The Government recognizes that the line items established in this solicitation may not conform to the Offeror's practices. Failure to correct these issues can result in difficulties in acceptance of deliverables and processing payments. Therefore, the Offeror is invited to propose alternative line items for which bids, proposals, or quotes are requested in this solicitation to ensure that the resulting contract is economically and administratively advantageous to the Government and the Offeror.

(b) The Offeror may submit one or more additional proposals with alternative line items, provided that alternative line items are consistent with subpart 4.10 of the Federal Acquisition Regulation. However, acceptance of an alternative proposal is a unilateral decision made solely at the discretion of the Government. Offers that do not comply with the line items specified in this solicitation may be determined to be nonresponsive or unacceptable.

(End of provision)

52.211-5000 EVALUATION OF SUBDIVIDED ITEMS

Item Nos. 0005 and 0006 are subdivided into two or more estimated quantities and are to be separately priced. The Government will evaluate each of these items on the basis of total price of its sub-items.

(End of provision)

52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991)

Offers submitted in response to this solicitation shall be in the English language. Offers received in other than English shall be rejected.

(End of provision)

52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (APR 1991)

Offers submitted in response to this solicitation shall be in terms of U.S. dollars. Offers received in other than U.S.

dollars shall be rejected.

(End of provision)

52.214-4002 ALL OR NONE QUALIFICATIONS (FEB 2011) FAR 14.404-5

A vendor must provide a price on all items in this solicitation to be eligible for award. The Government will award on an “All or None” basis. Evaluation of bids/offers will be based upon only the total price included on the pricing schedule for all items. If options are included in the pricing schedule the evaluation will be conducted in accordance with the applicable option clause in the solicitation.

52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2017)

(a) Definitions. As used in this provision--

“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer's discretion, result in the offeror being allowed to revise its proposal.

“In writing or written” means any worded or numbered expression which can be read, reproduced, and…