Text version
FY18 LDPAV-AMEND2
SECTION TABLE OF CONTENTS
DIVISION 32 - EXTERIOR IMPROVEMENTS
SECTION 32 12 16.01
PLANT MIXED BITUMINOUS PAVEMENT
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 EQUIPMENT
PART 2 PRODUCTS
2.1 BITUMINOUS MIXTURES
2.2 BITUMINOUS MATERIAL
2.3 AGGREGATE
PART 3 EXECUTION
3.1 PREPARATION OF THE UNDERLYING SURFACE
3.2 PLACEMENT
3.3 COMPACTION OF MIXTURE
3.4 Tolerance
3.5 QUALITY CONTROL
3.6 TESTING
-- End of Section Table of Contents --
SECTION 32 12 16.01 Page 1 W912ES18B0015
SECTION 32 12 16.01
PLANT MIXED BITUMINOUS PAVEMENT
PART 1 GENERAL
This work consists of constructing a Wearing and a Non-Wearing bituminous pavement and bituminous curb as shown on the plans in accordance to MNDOT 2360, except as modified in this section.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
MINNESOTA DEPARTMENT OF TRANSPORTATION (MNDOT)
MNDOT (2018) Standard Specifications for Construction
ASTM INTERNATIONAL (ASTM)
ASTM C117 (2013) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing
ASTM C136/C136M (2014) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates
ASTM C136/C136M (2014) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates
ASTM D2172/D2172M (2011) Quantitative Extraction of Bitumen from Bituminous Paving Mixtures
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Bituminous Mixture Design; G
Equipment; FIO
SD-06 Test Reports
Testing; G
SD-07 Certificates
SECTION 32 12 16.01 Page 2 W912ES18B0015
Plant Certification; G
Delivered Material Certification; G
1.3 EQUIPMENT
Provide size, type, and manufacturer of paver and rollers to be used and a list of other equipment to be used for the seal coat operation.
PART 2 PRODUCTS
2.1 BITUMINOUS MIXTURES
1. SPWEA240E Wearing Course Mixture
2. SPNWB230E Non-Wearing Course Mixture
2.2 BITUMINOUS MATERIAL
Per the specified mix design.
2.3 AGGREGATE
Per the specified mix design.
PART 3 EXECUTION
3.1 PREPARATION OF THE UNDERLYING SURFACE
For aggregate surfaces; shape and grade to meet existing drainage grade.
Compact surface with a minimum of 2 passes using a roller weighing not less than 5 ton or a using a plate compactor whichever is appropriate for the size of paving.
For bituminous surfaces; immediately before placing the hot mix bituminous, clean the underlying course of dust and debris. Apply a tack coat in accordance with the contract specifications.
3.2 PLACEMENT
Place bituminous mixture in accordance to MNDOT 2360, except as modified below.
3.3 COMPACTION OF MIXTURE
After placing, the mixture shall be thoroughly and uniformly compacted by rolling. Compact the surface as soon as possible without causing displacement, cracking or shoving. The sequence of rolling operations and the type of rollers used shall be at the discretion of the Contractor. The speed of the roller shall, at all times, be sufficiently slow to avoid displacement of the hot mixture and be effective in compaction. Any displacement occurring as a result of reversing the direction of the roller, or from any other cause, shall be corrected at once. Furnish sufficient rollers to handle the output of the plant.
Continue rolling until the surface is of uniform texture, true to grade and cross section, and there is no further visual evidence of consolidation. A minimum of 3 passes are required.
SECTION 32 12 16.01 Page 3 W912ES18B0015
To prevent adhesion of the mixture to the roller, keep the wheels properly moistened but excessive water will not be permitted. In areas not accessible to the roller, the mixture shall be thoroughly compacted with hand tampers.
3.4 Tolerance
After compaction, the thickness of each lift shall be within a tolerance of 1/4 inch.
3.5 QUALITY CONTROL
Submit a Plant Certification stating that the plant producing the bituminous mixture is certified by a State Department of Transportation.
Submit a signed Delivered Material Certification stating that each type of material delivered to each site met the requirements found in this specification. This certification shall also include the dates of delivery and quantities delivered to each site.
Perform testing as indicated in paragraph TESTING.
3.6 TESTING
The following tests shall be performed by and at the expense of the Contractor. Copies of test results with verification that the results meet the mix design shall be submitted to the Contracting Officer.
Take one sample per day of paving and perform the following tests.
Bituminous Content by the extraction method in accordance with
ASTM D2172/D2172M.
Sieve Analysis in accordance with ASTM C117 and ASTM C136/C136M.
Take and record temperature of each load of mix once the truck is backed up to the paver. Loads not meeting the temperature required by the specified mix design shall not be placed.
-- End of Section --