W81G6741139818

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See the "Summary of Changes" for the amendment details.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 26-Aug-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ES-15-B-0001

X 9B. DATED (SEE ITEM 11)

29-Jun-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

26-Aug-2015

CODE

CONTRACTING DIVISION

USACE - ST. PAUL

180 5TH STREET E SUITE 700

ST. PAUL MN 55101-1678

W912ES 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912ES-15-B-0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0005

The purpose of the amendment is to address the addition of a bid item to wash riprap/bedding, add more approved bedding sources, provide the 401 water quality certification, incorporate FAR provision 52.217-5 (Evaluation of Options), and local clause 52.217-4000 (Option for Additional Work (Construction)).

The IFB closing due date and time have been extended.

I. WASH RIPRAP/BEDDING

a. Bid Schedule: The current bid schedule is hereby replaced in its entirety-see attached final bid schedule which includes an optional bid item to wash riprap/ bedding material.

b. Specification Section 01 22 00.00 10 MEASUREMENT AND PAYMENT: The following paragraph along with its subparagraphs have been added to describe the measurement and payment requirements for the Riprap/ Bedding Wash bid item:

1.8.4 Riprap/Bedding Wash

1.8.4.1 Payment

Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for washing riprap/bedding as specified.

1.8.4.2 Measurement

Riprap/Bedding Wash shall be measured for payment by the ton (2,000 pounds avoirdupois) of riprap and bedding washed and used in the work in accordance with paragraph MEASUREMENT BY WEIGHT. Weighing of trucks shall be in the dry prior to washing of the riprap/bedding. Quantities shall be computed to the nearest whole ton.

1.8.4.3 Unit of Measure

Unit of measure: ton.

c. Specification Section 35 31 19.00 13 STONE PROTECTION (RIPRAP): The following paragraph has been added to this section to specify washing requirements for riprap and bedding:

3.6.1 Washing Riprap and Bedding

The Contracting Officer may require that the riprap/bedding materials be washed prior to placement in the river. Riprap/bedding material requiring washing shall be washed on all surfaces with a commercial grade pressure washer with a minimum pressure of 2,500 psi. When handling and storing the washed riprap and bedding (whether at the quarry, in transit, at the washing location, during unloading, during placement or otherwise), the Contractor shall ensure that the washed riprap/bedding is not contaminated by foreign materials or re-contaminated with dust, silt, debris, or chemicals from the washing process. No wash water effluent shall be allowed to enter the river.

II. ADDITIONAL BEDDING MATERIAL SOURCES: In the attachments at the end of Section 35 31 19.00 13 STONE PROTECTION ATTACHMENTS, Replace the page titled - “APPROVED MATERIAL SOURCES FOR BEDDING” with the attached revised bedding material sources page. The new source list for bedding materials adds five additional sources for bedding material.

III. 401 WATER QUALITY CERTIFICATION: Add the revised 401 water quality certification.

IV. Section 01 00 00.00 13 GENERAL, Paragraph 3.3 Permits: This paragraph has been reworded to reflect the fact that both the Section 401 Water Quality Certification and the Minnesota DNR Public Waters Work Permit are now included in the attachments at the end of Section 01 00 00.00 13 GENERAL. The revised paragraph is as follows:

3.3 PERMITS

The Contractor's attention is directed to contract clause 52.236-7, Permits and Responsibilities.

Under that clause, the Contractor is responsible for obtaining any necessary licenses and permits and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of this contract.

The following permits are provided by the Government as attachments at the end of this section.

a. Section 401 Water Quality Certification

b. Minnesota DNR Public Waters Work Permit

IV. Add provision 52.217-5, Evaluation of Options.

V. Add local clause 52.217-4000, Option for Additional Work (Construction).

All other terms and conditions remain unchanged.

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 28-Aug-2015 02:00 PM to 04-Sep-

2015 02:00 PM.

CLIN 0009 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0009 4,000 Net Ton

(2,000 LB)

OPTION Optional Item-Riprap/bedding wash

FFP

FOB: Destination

NET AMT

INSPECTION AND ACCEPTANCE

The Acceptance/Inspection Schedule for SUBCLIN 0008AB has been changed from:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

N/A N/A N/A Government

To:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

Destination Government Destination Government

The following Acceptance/Inspection Schedule was added for CLIN 0009:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

N/A N/A N/A Government

SECTION 00700 - CONTRACT CLAUSES

The following have been added by full text:

52.217-5 EVALUATION OF OPTIONS (JUL 1990)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

(End of provision)

52.217-4000 OPTION FOR ADDITIONAL WORK (Construction) (AUG 2000)

The Government may require the Contractor to perform the work identified as optional item(s) (CLIN(s) 0009 at the price stated in the Schedule. The Contracting Officer may exercise the option(s) by written notice to the Contractor at any time prior to the stated quantity of riprap and/or bedding being placed at the site.

(End of Summary of Changes)