W81G6740346704

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This Amendment is to 1.) Make changes to Section 01 57 20.00 13 ENVIRONMENTAL PROTECTION; and 2.) To update the Pricing Schedule (added CLIN 0024) and Section 01 22 00.00 13. (See SF30 Block 14 Continuation Page for details.)

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 25-Apr-2014

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ES-14-R-0003

X 9B. DATED (SEE ITEM 11)

17-Apr-2014

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

25-Apr-2014

CODE

CONTRACTING DIVISION

USACE - ST. PAUL

180 5TH STREET E SUITE 700

ST. PAUL MN 55101-1678

W912ES 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912ES-14-R-0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0001

1.) In Section 01 57 20.00 13 ENVIRONMENTAL PROTECTION, the Cover Letter dated

April 10, 2014 from the MNDNR addressed to Todd Peterson, includes a statement in regard to the “Erosion and Sediment Control Plan.” Please note that the 30 day submission requirement has been removed in the revised MNDNR permit attached to this amendment. The contractor is still required to conduct its operations in accordance with the permit requirements as modified. Please note that accomplishment of the “Fisheries Monitoring Plan” described in the MNDNR permit is not a requirement of this contract.

In Section 01 57 20.00 13 ENVIRONMENTAL PROTECTION, in the attachments at the end of the section, replace the MNDNR Protected Waters Permit No. 2010-0396 with the updated permit, issued 4/18/2014, included in this amendment.

2.) In Section 00 01 00 – Solicitation Contract Form, replace the Pricing Schedule with the included updated Pricing Schedule.

In Section 01 22 00.00 13, add the following paragraph 1.8.12:

1.8.12 Performance and Payment Bonds

Payment. Payment will be made for the costs associated with obtaining performance and payment bonds in accordance with the contract requirements. Bonds will be paid for on a Job basis.

Unit of Measure: Job

SECTION 00010 - SOLICITATION CONTRACT FORM

CLIN 0024 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0024 1 Job Performance & Payment Bonds

FFP

FOB: Destination

NET AMT

DELIVERIES AND PERFORMANCE

The following Delivery Schedule item has been added to CLIN 0024:

DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC

01-AUG-2015 1 N/A

FOB: Destination

INSPECTION AND ACCEPTANCE

The following Acceptance/Inspection Schedule was added for CLIN 0024:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

N/A N/A N/A Government

The following have been modified:

PRICING SCHEDULE

ROSEAU FLOOD RISK MANAGEMENT

PRICING SCHEDULE

ITEM

DESCRIPTION

QUANTITY

UNIT

UNIT

PRICE

AMOUNT

0001 Clearing and Grubbing 1 JB ______.__ _______.__

0002 Demolition 1 JB ______.__ _______.__

0003 Stripping

0003AA Up to 85,000 Cubic Yards 85,000 CY ______.__ _______.__

0003AB Over 85,000 Cubic Yards 15,292 CY ______.__ _______.__

0004 Diversion Channel Excavation

0004AA Up to 600,000 Cubic Yards 600,000 CY ______.__ _______.__

0004AB Over 600,000 Cubic Yards 105,000 CY ______.__ _______.__

0005 Impervious Fill

0005AA Up to 6,500 Cubic Yards 6,500 CY ______.__ _______.__

0005AB Over 6,500 Cubic Yards 1,215 CY ______.__ _______.__

0006 Topsoil 1 JB ______.__ _______.__

0007 Inspection Trench

0007AA Up to 850 Lineal Feet 850 LF ______.__ _______.__

0007AB Over 850 Lineal Feet 150 LF ______.__ _______.__

0008 Spoil Pile Grading

0008AA Up to 625,000 Cubic Yards 625,000 CY ______.__ _______.__

0008AB Over 625,000 Cubic Yards 110,500 CY ______.__ _______.__

0009 Diversion Channel Inlet 1 JB ______.__ _______.__

0010 Test Piling ‐ HP 10 x 57 65 LF ______.__ _______.__

0011 Test Piling ‐ HP 12 x 74 55 LF ______.__ _______.__

0012 Restriction Structure Piling ‐ HP 10 x 57

0012AA Up to 700 Lineal Feet 700 LF ______.__ _______.__

0012AB Over 700 Lineal Feet 110 LF ______.__ _______.__

0013 Restriction Structure Piling ‐ HP 12 x 74

0013AA Up to 2,000 Lineal Feet 2,000 LF ______.__ _______.__

0013AB Over 2,000 Lineal Feet 455 LF ______.__ _______.__

0014 Restriction Structure 1 JB ______.__ _______.__

0015 Multi‐Use Trail

0015AA Up to 7,000 Square Yards 7,000 SY ______.__ _______.__

0015AB Over 7,000 Square Yards 1,280 SY ______.__ _______.__

0016 Channel Slope Toe Protection

0016AA Up to 2,000 Lineal Feet 2,000 LF ______.__ _______.___

0016AB Over 2,000 Lineal Feet 6,000 LF ______.__ ______.__

0017 Trench Drain

0017AA Up to 8,500 Lineal Feet 8,500 LF ______.__ _______.__

0017AB Over 8,500 Lineal Feet 1,215 LF ______.__ _______.__

0018 Landscaping 1 JB ______.__ _______.__

0019 Site Furnishings 1 JB ______.__ _______.__

0020 Turf Establishment 1 JB ______.__ _______.__

0021 Trail Signage 1 JB ______.__ _______.__

0022 Storm Sewer at CSAH 24 1 JB ______.__ _______.__

Storm Sewer and Utility Modification for Multi‐Use Trail 1 JB ______.__ _______.__

0024 Performance & Payment Bonds 1 JB ______.__ _______.__

Total Amount for Reach 1

(End of Summary of Changes)