About this file

This is the original Attachment 3 - Priority of Work for this solicitation.

View the file

Other files

File Type Posted
W912ES-09-T-0101 Abstract.pdf PDF
HaulRoutes.pdf PDF
sf30 W912ES-09-T-0101-0001.pdf PDF
W912ES-09-T-0101-0001.pdf PDF
VCLevee DisposalSiteMapRevised.pdf PDF
VCLevee DisposalSitePicsRevised.pdf PDF
Answers-to-questions01.doc DOC document
VCLevee DisposalSitePics.pdf PDF
W912ES-09-T-0101.pdf PDF
HaulRoutes.pdf PDF
VCLevee DisposalSiteMap.pdf PDF
HaulRoutes.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment #3 Priorities for Emergency Levee Removal

Priority No. 1 Areas – These levee segments are to be worked first and in the order listed.

Levee Segment No. Approximate Location

2 1440 Chautauqua Boulevard to 12th St. NE (Adjacent to the city park)

19 Across from 220 5th Avenue SW to 2nd Street SW

Note – Two ring levees (included in Bid Item No.

30) and one clay pile (included as Bid Item No. 29) are included in this priority work.

20 Viking Drive North side to 4th Street SW (Bridge)

Note – A clay pile (included in Bid Item No. 29) is also to be removed along with this priority item.

21 Viking Drive South side to 436 Riverview Drive

22 Viking Drive and 6th Avenue SW to East side of sewage lift station

23 West side of sewage lift station to 8th Avenue SW, East side

Priority #2 Areas – These levee segments are to be worked second, after or concurrent with those listed above, in the order listed.

Levee Segment No. Approximate Location

13 5th Avenue SE (Bridge) to 641 3rd Street SE

11 5th Ave SE to 3rd Street SE

14 464 3rd Street SE to 360 6th Avenue SE

10 Main Street E to 5th Ave SE

15 Intersection of 4th Avenue SE and 4th Street SE to 328 4th Street SE

Levee segments not listed as priority sites are considered Priority 3.