Pool 8 Amendment 1.doc

DOC document 41 KB Posted

Attached to
Pool 8 Islands Phase 3 Stage 3A, Habitat Rehabilitation and Enhancement Project (HREP)
Solicitation number
W912ES-08-B-0004
Issued by

About this file

Pool 8 Islands Phase III Stage 3A Amendment 1

View the file

Other files

File Type Posted
Bid abstract and Cert.pdf PDF
Pool 8 Bid Abstract.xls XLS spreadsheet
Pool 8 Amendment 3.pdf PDF
Pool 8 Amendment 2.pdf PDF
AC113_M-P8P3S3_STPLN_C-111328.pdf PDF
AC302_M-P8P3S3_SECT_C-330230.pdf PDF
AC111_M-P8P3S3_STPLN_C-111126.pdf PDF
AC301_M-P8P3S3_SECT_C-330129.pdf PDF
08B0004_Full_Size_Part3.pdf PDF
08B0004_Full_Size_Part2.pdf PDF
08B0004_Full_Size_Part1.pdf PDF
08B0004.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 1

Pool 8 Islands Phase III - Stage 3A

Amendment 0001

1. Revisions to:

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 13

MEASUREMENT AND PAYMENT

1.8.2 Island Construction - Granular Fill

Granular fill for Island Construction will be measured for payment by the cubic yard (CY) in place, within the neat lines as shown on the drawings.

Granular fill material placed outside the required lines, grades and sections, including permitted tolerances, will not be measured for payment. Payment for granular fill for Island Construction will include the cost for dredging granular material, placing the granular material from the designated sand borrow areas and any surveys or testing. Random fill material from access dredging placed in a 6" layer below the fine material in the Islands will be paid for as Granular Fill.

1.9.1 Island C4 Construction - Granular Fill

Granular fill for Island C4 Construction will be measured for payment by the cubic yard (CY) in place, within the neat lines as shown on the drawings. Granular fill material placed outside the required lines, grades and sections, including permitted tolerances, will not be measured for payment. Payment for granular fill for Island C4 Construction will include the cost for dredging granular material, placing the granular material from the designated sand borrow areas and any surveys or testing. Random fill material from access dredging placed in a 6" layer below the fine material in the Islands will be paid for as Granular Fill.

1.9.2 Island C4 Construction - Random Fill

Random fill for Island C4 Construction will be measured for payment by the cubic yard (CY) in place, within the neat lines as shown on the drawings.

Random fill material placed outside the required lines, grades and sections, including permitted tolerances, will not be measured for payment. Payment for random fill for Island C4 Construction will include the cost for dredging random material, placing the random material and any surveys or testing. This does not include random fill material from access dredging placed in a 6" layer below the fine material in the Islands, which will be paid for under Granular Fill.

1.10.1 Island C5 Construction - Granular Fill

Granular fill for Island C5 Construction will be measured for payment by the cubic yard (CY) in place, within the neat lines as shown on the drawings. Granular fill material placed outside the required lines, grades and sections, including permitted tolerances, will not be measured for payment. Payment for granular fill for Island C5 Construction will include the cost for dredging granular material, placing the granular material from the designated sand borrow areas and any surveys or testing. Random fill material from access dredging placed in a 6" layer below the fine material in the Islands will be paid for as Granular Fill.

1.11.1 Island N2 Construction - Granular Fill

Granular fill for Island N2 Construction will be measured for payment by the cubic yard (CY) in place, within the neat lines as shown on the drawings. Granular fill material placed outside the required lines, grades and sections, including permitted tolerances, will not be measured for payment. Payment for granular fill for Island N2 Construction will include the cost for dredging granular material, placing the granular material from the designated sand borrow areas and any surveys or testing. Random fill material from access dredging placed in a 6" layer below the fine material in the Islands will be paid for as Granular Fill.

2. The following have been changed:

C-111: added Note 5 concerning possible government dredging.

C-113: revised Note 6.

C-301: revised sections to allow placement of random fill from access dredging.

C-302: added access dredging typical section.

See attachments.