Pool 8 Islands Phase III Stage 3A Amendment 1
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid abstract and Cert.pdf | ||
| Pool 8 Bid Abstract.xls | XLS spreadsheet | |
| Pool 8 Amendment 3.pdf | ||
| Pool 8 Amendment 2.pdf | ||
| AC113_M-P8P3S3_STPLN_C-111328.pdf | ||
| AC302_M-P8P3S3_SECT_C-330230.pdf | ||
| AC111_M-P8P3S3_STPLN_C-111126.pdf | ||
| AC301_M-P8P3S3_SECT_C-330129.pdf | ||
| 08B0004_Full_Size_Part3.pdf | ||
| 08B0004_Full_Size_Part2.pdf | ||
| 08B0004_Full_Size_Part1.pdf | ||
| 08B0004.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 1
Pool 8 Islands Phase III - Stage 3A
Amendment 0001
1. Revisions to:
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 13
MEASUREMENT AND PAYMENT
1.8.2 Island Construction - Granular Fill
Granular fill for Island Construction will be measured for payment by the cubic yard (CY) in place, within the neat lines as shown on the drawings.
Granular fill material placed outside the required lines, grades and sections, including permitted tolerances, will not be measured for payment. Payment for granular fill for Island Construction will include the cost for dredging granular material, placing the granular material from the designated sand borrow areas and any surveys or testing. Random fill material from access dredging placed in a 6" layer below the fine material in the Islands will be paid for as Granular Fill.
1.9.1 Island C4 Construction - Granular Fill
Granular fill for Island C4 Construction will be measured for payment by the cubic yard (CY) in place, within the neat lines as shown on the drawings. Granular fill material placed outside the required lines, grades and sections, including permitted tolerances, will not be measured for payment. Payment for granular fill for Island C4 Construction will include the cost for dredging granular material, placing the granular material from the designated sand borrow areas and any surveys or testing. Random fill material from access dredging placed in a 6" layer below the fine material in the Islands will be paid for as Granular Fill.
1.9.2 Island C4 Construction - Random Fill
Random fill for Island C4 Construction will be measured for payment by the cubic yard (CY) in place, within the neat lines as shown on the drawings.
Random fill material placed outside the required lines, grades and sections, including permitted tolerances, will not be measured for payment. Payment for random fill for Island C4 Construction will include the cost for dredging random material, placing the random material and any surveys or testing. This does not include random fill material from access dredging placed in a 6" layer below the fine material in the Islands, which will be paid for under Granular Fill.
1.10.1 Island C5 Construction - Granular Fill
Granular fill for Island C5 Construction will be measured for payment by the cubic yard (CY) in place, within the neat lines as shown on the drawings. Granular fill material placed outside the required lines, grades and sections, including permitted tolerances, will not be measured for payment. Payment for granular fill for Island C5 Construction will include the cost for dredging granular material, placing the granular material from the designated sand borrow areas and any surveys or testing. Random fill material from access dredging placed in a 6" layer below the fine material in the Islands will be paid for as Granular Fill.
1.11.1 Island N2 Construction - Granular Fill
Granular fill for Island N2 Construction will be measured for payment by the cubic yard (CY) in place, within the neat lines as shown on the drawings. Granular fill material placed outside the required lines, grades and sections, including permitted tolerances, will not be measured for payment. Payment for granular fill for Island N2 Construction will include the cost for dredging granular material, placing the granular material from the designated sand borrow areas and any surveys or testing. Random fill material from access dredging placed in a 6" layer below the fine material in the Islands will be paid for as Granular Fill.
2. The following have been changed:
C-111: added Note 5 concerning possible government dredging.
C-113: revised Note 6.
C-301: revised sections to allow placement of random fill from access dredging.
C-302: added access dredging typical section.
See attachments.