AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
This amendment is to update the solicitation: delete the second bullet under section 2.5.1.1, regarding pricing of tool kits; delete the phrase under section 2.5.2.3 that says "and ceiling rates for assembly tools/equipment"; and to correct of the proposal submission date. Past performance attachments (Past Performance Overview Sheet, Project Summary Form, and Past Performance Questionnaire) that w ere omitted from the solicitation originally w ill be included as part of this amendment, as w ell as the updated specif ications (changes made to pages 1 and 21 to update the minimum insulation R values), and the proposal due date is extended to 25 May 2022 by 4:00 PM Eastern
Daylight Time (EDT).
1. CONTRACT ID CODE PAGE OF PAGES
1 37
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Apr-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ER22R0024
X 9B. DATED (SEE ITEM 11)
22-Mar-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-Apr-2022
CODE
W912ER DISTRICT (TAM), USACE
MIDDLE EAST DISTRICT (CETAM-CT)
PO BOX 2250
WINCHESTER VA 22604-1450
W912ER 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ER22R0024
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 06-May-2022 10:00 AM to 25-May-2022 04:00 PM.
The following have been modified:
PERFORMANCE WORK STATEMENT
Performance Work Statement (PWS)
Multiple Indefinite Delivery Indefinite Quantity (IDIQ) Contracts for the Supply, Delivery, and Assembly of Relocatable Buildings (RLBs)
U.S. Central Command (CENTCOM) Area of Responsibility (AOR)
1. OVERVIEW:
The U.S. Army Corps of Engineers (USACE), Transatlantic Middle East District (TAM), is seeking to award new, fully competed, multiple Indefinite Delivery/Indefinite Quantity (IDIQ) contracts to provide relocatable buildings
(RLBs) with energy efficient systems (R-20+ walls and R-40 roof envelope assemblies).
This contract shall support the manufacture, shipping, and delivery of RLB units to the locations within the
CENTCOM AOR designated in this PWS, as well as the capability to assemble the products on -site, if required to do so. The scope of each individual effort and delivery location will be identified in the PWS for the delivery orders supported by this IDIQ. In some cases, minor incidental construction may be required for some delivery orders. This incidental construction would primarily be to support site preparation activities and infrastructure, to include (but not limited to) minor demolition, clearing, grubbing, grading, compaction, foundation related work, and utility connections and/or installation of utility tanks or generators for projects that do not have acc ess to public utilities.
The ordering period for this contract will be one year, with four additional one-year optional periods, for a maximum total ordering period of up to five years and a total contract capacity of $250,000,000.00. The
Government intends to award five Firm-Fixed-Price (FFP) IDIQ contracts as part of this acquisition (although it reserves the right to award more or fewer contracts at its discretion). The delivery order limitations are described below in the clause FAR 52.216-19 and further explained in the below clause FAR 52.216-22.
2. REQUIREMENTS:
Product Development Requirements:
Per UFC 1-201-01, Paragraph 1-7, all products developed under this contract shall be stamped and sealed by licensed professional engineers with at least four years of experience in their relevant discipline (structural, electrical, mechanical, plumbing, fire protection, etc.) and knowledge and experience with the codes, standards, protocols, and procedures for RLB manufacture and assembly.
Qualifications and credentials shall be submitted for Government review in accordance with Section 12.a below.
All products must conform to the requirements of UFC 1-201-01 and attached Specification 13 34 12.10, and any persons working on the development of RLB product data must read and be familiar with the content of those codes and specifications. RLBs shall meet all applicable life safety and habitability relat ed requirements and be designed for a 15-year service life.
Facilities developed using RLB units procured under this contract shall be considered facility level “semi-permanent” structures as defined by UFC 1-201-01, Paragraph 1-4, and will meet or exceed all applicable requirements of the UFC.
There may be instances where the Government requests contractors to manufacture, deliver, and assemble a pre-approved RLB product. In those cases, the Government will provide that product design with the delivery order PWS. Any pre-approved product will be able to be manufactured using commonly available materials and hardware and assembled using commonly available tools. Of course, contractors will have the option to decline to offer on these types of delivery orders should they not possess the capability to produce them, and the core competency required for this contract involves the manufacture and delivery of semi-permanent
RLBs in accordance with the provisions of this PWS and attached technical specification.
Submittal Requirements:
The contracting officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the attached drawings and specifications.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings, and all submittals are to be in the English language using metric measurements.
It is the contractor’s responsibility to check and approve all items prior to submittal and stamp, sign, a nd date indicating action taken. Submittals requiring government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.
a . After award of their first delivery order under this contract, each contract ho lder shall provide submittals in compliance with UFC 1-202-01 Section 1-7 and Specification 13 34 23.12 10 Section 1.5.
b. All drawings submitted shall be complete and concise, drawn to scale, itemizing and clearly identifying each component comprising the RLB unit.
c. Simple reproduction of the drawings attached to this PWS is not acceptable.
d. Drawings shall bear the statement that the RLB units and the facilities that are assembled from those units conform to a “Semi-Permanent” facility level per UFC 1-202-01, and the respective Engineer’s stamp.
e. Drawings shall conform to USACE CADD Standards and the Middle East District Design Instruction
Manual.
f. Drawings must include product information for all RLB components including assembly instructions, installation directions and their size and weight.
g. Drawings shall include details on packing and shipping, including each component’s location within the shipping container.
All product submittals must be accepted and approved by the Government prior to the Contractor beginning work on any procurement related activities.
Submittal Types:
a . Post Award Submittals (SD-01): Submittals required following the award of a delivery order. The following submittals are examples of what will be required. Specific details on product submittals and required timeframes will be included in the PWS for the individual delivery orders.
1. Proof of DBA Insurance.
2. Health & Safety/Accident Prevention Plan: The Contractor is required to submit an Accident
Prevention Plan (APP) for all activities that could occur during performance of this contract (e.g., fabrication, shipment, installation, crane activities, etc.). This APP will be in accordance with the requirements of EM 385-1-1.
3. Quality Control Plan
4. Manufacturer’s Qualifications
5. List of Proposed Subcontractors
6. Submittal Register/List
7. Submittal, Procurement, Fabrication, and Delivery Schedule
8. Any other submittal designated as SD-01 in the attached specifications, as they apply to the scope of the individual delivery orders.
b. Shop Drawings (SD-02): Shop drawings include drawings, diagrams and schedules specifically prepared to illustrate some portion of the work, diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the contractor for integrating the product or system into the project, or drawings prepared by or for the contractor to show how multiple systems and interdisciplinary work will be coordinated.
c. Product Data (SD-03): Product data includes any catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work. This also includes submittal of any product warranties associated with each product and verification that the warranty complies with the general requirements of the contract.
Product data shall include information on the country of origin of each product procured under this contract so that it can be verified that it meets the requirements of the relevant contract clauses (i.e., DFARS 252.225-7021, Trade Agreements).
d. Samples (SD-04): Fabricated or un-fabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Contractors shall coordinate the number of samples required and the instructions for providing those samples with the Contracting Officer, with respect to the PWS of the individual delivery orders, as applicable.
e. Design Data (SD-05): Design calculations, analyses or other data pertaining to a part of work.
f. Test Reports (SD-06): Test reports include reports signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements.
g. Certificates (SD-07): This requirement includes statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. These certificates must be dated after award of project delivery order and clearly name the project.
This category also includes any document required of a contractor, or of a manufacturer, supplier, installer or subcontractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
h. Manufacturer’s Instructions (SD-08): Preprinted material describing installation of a product, system or material, including special notices and information concerning impedances, hazards and safety precautions.
Relocatable Building Unit - Use Groups Options:
RLB Type A: Single 160SF dry units that can be connected together for use as billeting or closed floor plan administrative space.
Figure 1: RLB Type A
RLB Type B: Two 160SF (total of 320 SF) wet units for use as latrine, shower, and shave (LSS) units.
Figure 2: RLB Type B (Latrine)
Figure 3: RLB Type B (Shower)
RLB Type C: Single 160 SF wet units for laundry uses.
Figure 4: RLB Type C
RLB Type D: Four connected 160SF wet unit pods capable of being connected together to create facilities of various sizes for Role 1 medical related uses including health and dental clinics.
RLB Type F: Four connected 160SF dry units capable of being connected together to create facilities of various sizes for general types of assembly uses, such as MWR, religious assembly, open space admin, fitness centers, seating areas for dining facilities, etc.
Figure 5: RLB Type D & F
All unit types are considered to be Risk Category –II.
Note that the Type E RLB unit listed in Specification 13 34 23.12 10 is not applicable to this contract.
3. DELIVERY:
a . Prior to delivery, the Contractor shall pre-assemble and confirm all components are included in its factory, including walls, floor, doors and roof, and ensure that they are all built square and plumb and fit together per the
Government’s intent. If the Government is unable to be present to inspect pre -assembly activities, the contractor shall provide a video of any of the pre-assembly activities listed in this paragraph as requested by the
Government. If a video is required, the Government will indicate which activities require video documentation prior to those activities beginning.
b. The Contractor is responsible for shipping the RLB units, and all associated parts and equipment to the location within the AOR as defined by the scope of each individual delivery order. Specific information related to the delivery location, as well as any requirements for installation and assembly (including local physical security requirements, etc.) will be specified in the scope of each individual delivery order.
c. For each shipment, the Contractor shall provide a packing list/inventory of all items in that shipment, including the items stored within each container, shall identify the total number of containers in the shipment, and shall number each individual container (e.g., 1 of 10, 2 of 20, etc.).
d. This contract includes delivery and assembly services for the countries of Kuwait, Qatar, Jordan, United Arab
Emirates, Saudi Arabia, Oman, Bahrain, Egypt, and Iraq. Other locations within the CENTCOM AOR may be requested and negotiated during the delivery order process.
4. QUALITY CONTROL:
In accordance with the terms of the clause in FAR 52.246-2, the Contractor shall provide and maintain an inspection system acceptable to the Government covering supplies under this contract that shall tender to the Government for acceptance only supplies that have been inspected in accordance with the inspection system and have been found by the Contractor to be in conformity with contract requirements. The Contractor shall submit its quality control plan to the Government for review and approval, in accordance with the Submittals Paragraph of this PWS. The
Government may perform reviews and evaluations as reasonably necessary to ascertain compliance with the clause in FAR 52.246-2. The Government has the right to inspect and test all supplies called for by each delivery order, at all places and times, including the period of manufacture, and in any event before acceptance.
The Quality Control (QC) plan shall include:
• QC organizational structure, and organizational chart.
• Names for key QC positions and their resumes. Include any certificates of completion for any coursework required by this contract.
• Duties, responsibilities, and authority of all QC personnel.
• Appointment letter for the QC Manager and Alternate QC Manager(s) from a senior Contractor official stating that they are responsible for managing and implementing the QC program as described in this PWS.
Include in this letter the QC Manager’s authority to direct the removal and replacement of non -conforming work.
• Information regarding any material testing or work to obtain certificates for proposed materials.
• Procedures to complete re-work as required.
• Procedures for performing all phases of quality control. Provide preparatory and initial checklists for installation activities. Include a breakdown of quality checks that will be used when performing QC functions, inspections, and tests required by the contract.
The Contractor shall notify the Contracting Officer, in writing, of any proposed changes to QC personnel or to the approved QC plan a minimum of 7 days prior to the proposed change. Any proposed change will be subject to acceptance by the Contracting Officer.
The Contractor shall identify an English-speaking QC Manager and Alternate QC Manager as part of this plan and provide instructions on how the Government will be able to communicate with the Contractor’s QC organization.
The QC Manager shall have a minimum of 5 years’ experience as a superintendent, inspector, QC manager, project manager, or construction manager on similar type projects (i.e., those involving some degree of steel fabrication).
The QC Manager must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance.
The QC Manager(s) must complete the USACE Construction Quality Management Course for Contractors within 30 days of issuance of delivery order NTP or must have an active completion certificate for this course which covers the full period of performance of that delivery order. If the proposed QC Man ager has not completed the training recently (i.e., they do not have an active training certificate) they shall coordinate a time and venue to receive the training through the Contracting Officer. The Government will make every reasonable effort to provide training to those that require it, but it is ultimately the responsibility of the Contractor to provide properly qualified and trained personnel under the terms of this contract.
The duties of the QC Manager shall include:
• Being on-site (at the place of manufacture and point of delivery/assembly) to observe manufacturing and installation activities (the QC manager may also perform the role of project superintendent for assembly activities).
• Preparing the reports described later in this paragraph.
• Review shop drawing, product, and other submittals for conformance with contract requirements prior to submittal to the Government.
• Attend all QC related coordination meetings with the Government, as requested by the Contracting Officer
(KO) or Contracting Officer’s Representative (COR).
• Manage all phases and activities related to QC.
• Provide certificates of conformance prior to invoicing.
The Alternate QC manager shall serve in the absence of the QC Manager or may act in the role of QC Manager if performance is occurring in multiple locations. The requirements for the Alternate QC Manager shall be the same as for the regular QC manager.
The location, frequency, and timing of inspections shall be agreed upon during the development of the project schedule for each delivery order. The Contractor shall assume that inspections may occur on -site at the point of delivery or at the place of manufacture. Additional locations of inspection may be identified if proposed by the
Contractor, and the Contracting Officer agrees inspection at that that location would be beneficial to the
Government.
All other terms and conditions related to inspections and quality control are outlined in the FAR clause listed previously in this paragraph.
Reporting:
a . Prior to the start of manufacturing activities, the Contractor shall prepare and submit a weekly progress report to the COR/KO, which describes the current status of the project, to include the status of procurement activities, preparation and/or correction of submittals, status of installation access requests, etc.
b. Once manufacturing has begun, the Contractor shall prepare and submit a daily progress report (no later than 10:00 AM local time the day after the work was performed) to the COR/KO to include reports on su ch items as manufacturing status, current inventory, preparation for shipments to include date and time of next shipment/delivery, material delivery schedules, manufacturing quality control activities, etc. Daily reports may cease once materials have shipped and are in transit. When that occurs, weekly status of shipping reports shall be provided.
c. Once the shipments have begun to arrive and on-site assembly activities have begun, daily reporting shall commence to include all QC and inspection reports, delivery status, work performed during that day, any safety related issues, problems encountered, invoicing schedules, etc.
d. The contractor shall provide minutes from all meetings with Government personnel or other stakeholders.
Meetings and Conferences:
a . Pre-Fabrication Conference:
After submittals are received and approved (if required, see Section 12.a), but before RLB unit fabrication begins, the Contracting Officer may choose to hold a pre-fabrication conference to review the following after the award of each delivery order:
i. The detailed drawings, specifications, and manufacturer's descriptive and technical literature and test reports.
ii. Final end user RLB unit requirements.
iii. Fabrication schedule.
iv. Governing regulations and requirements for, certificates, insurance, tests and inspections if applicable.
b. Pre-Delivery
i. Prior to delivery, the Contractor shall perform all pre-assembly activities described in paragraph 3.a.
ii. The Contractor shall ensure all equipment, components and accessories are new and are in un-damaged condition.
iii. The Contractor shall notify Contracting Officer of the shipment date.
c. Pre-Assembly Conference (On-Site):
After delivery and acceptance of the RLB units, but before assembly, including any associated incidental construction work, is performed, the Contracting Officer may choose to hold a pre-assembly conference on-site
(or remotely if on-site is not possible) to perform the following actions:
i. Review temporary protection requirements for RLB components before, during, and after assembly.
ii. Ensure all equipment, components, and accessories have arrived on-site and are in an un-damaged condition.
iii. Review RLB assembly procedures, coordination, inspection and repair procedures, and final Government acceptance requirements.
iv. The Contractor shall inspect and accept as-built footings or foundation plans/details (if that work has been done or will be done by others) and/or discuss construction procedures if incidental construction is required by the delivery order.
Attendees shall include at a minimum, the Contractor’s Technical Representative, QC Manager, and the person on-site who will be overseeing the Contractor’s assembly efforts. The Contractor’s Technical Representative must have authorization from Contractor to discuss and approve potential contract changes and be thoroughly familiar with the products, and assembly of RLBs in the geographical area where assembly will take place.
d. Post Assembly Conference (On-Site):
A final inspection will occur once the RLBs and associated parts and equipment are delivered to the designated location, the components are assembled and are in move-in condition. This inspection will be coordinated through the USACE representatives listed below and will be conducted by local USACE representatives or their designates. Host Nation authorities may be involved as well. When the Government is satisfied that the
Contractor has fulfilled all of the terms and conditions of the subject delivery order, a Form DD250 Material
Inspection and Receiving Report will be signed thus indicating acceptance.
5. ASSEMBLY ACTIVITIES AND TRAINING:
a . The Contractor shall provide the capability to assemble the RLB units as directed by the scopes of the individual delivery orders. Some delivery orders may be manufacture and delivery-only; in those cases the
Contractor shall ensure that the components can be easily unpacked and assembled by able bodied U.S. Military members. When assembly is required, the Contractor shall ensure the entity that will be assembling the units on-site has sufficient experience working with the systems provided by the Contractor or similar systems.
b. The Contractor shall confirm the suitability of any foundation that is provided (as applicable) by the
Government under separate contract or arrangement. The Contractor shall inspect and accept the foundation prior to assembly activities beginning. Once the foundation is accepted by the Contractor, the condition and suitability of that foundation becomes the responsibility of the Contractor and the Government is not liable for necessary changes to that foundation after acceptance.
c. On-site startup and training will be accomplished on-site, when required by the delivery orders. Prior to start of any training, the Contractor shall complete all assembly and testing activities. Each delivered piece of equipment shall be started and tested per the procedures described in Specification 13 34 23.10. The Contractor shall ensure that all parts and systems are in working condition and are ready to be used for the on-site training.
d. The Contractor shall provide the standard manufacturer’s training in -country for U.S. Military members or other persons or entities as designated by the Contracting Officer, if required by the individual delivery orders.
Training shall cover all aspects of operations and maintenance and shall be conducted in English.
e. Incidental construction activities may be required as part of some individual delivery orders. The Contractor shall have the capability to perform minor construction tasks to support the assembly and installation of the
RLB units. Any required construction shall be described in the individual delivery order scope of work. The terms and conditions of any design work related to incidental construction shall be described in the scope of work of the individual delivery orders to include design requirements, submittal procedures, etc.
6. MANUALS and TOOLS: The Contractor is required to provide a minimum of two (2) complete (metric) tool kits required for the assembly and disassembly of each RLB unit type for each delivery order. The delivery order
PWS shall describe in more detail how many tool sets are required, which will likely be dependent on the size of that particular order.
The contractor shall provide one (1) hard copy and one electronic copy of any relevant manuals associated with each
RLB unit type selected as part of each delivery order at substantial completion phase prior to final payment. These include, but are not limited to operations manuals, instructions for assembly, disassembly & relocation, product manuals for building systems & equipment, maintenance/service manuals, storage manuals (which describe short -, medium-, and long-term storage requirements, including what efforts the user will need to bring the unit up to a transportable state), etc. A video shall be provided for each delivery order demonstrating assembly and disassembly procedures for each RLB type included in that order.
The electronic copy shall include both PDF and (editable) MS Word files, where available. All drawings shall be included as editable files, where available.
Delivery of the manuals and tool sets to the end user shall be coordinated through the Contracting Of ficer.
7. WARRANTY: In accordance with the clause in FAR 52.212-4, and per FAR 12.404 and FAR 46.709, offerors are to offer the Government at least the same warranty terms, including offers of extended warranties, offered to the general public in customary commercial practice. In addition to this clause and the FAR references, the Contractor shall provide a warranty in accordance with Specification 13 34 23.12 10, Paragraph 1.2. A point of contact (POC) for warranty implementation shall be identified by the Contractor. The Army Corps of Engineers representatives listed below (or their designee for each individual delivery order) shall be notified of all warranty complaints.
8. PERIOD OF PERFORMANCE: The period of performance of the base IDIQ contract is 36 5 days from contract award. Delivery orders can be issued at any time that the base IDIQ contract is active, and the period of performance of those delivery orders may extend beyond the period of performance of the base IDIQ. There will be four (4) optional years that may be exercised on a year-to-year basis at the discretion of the Contracting Officer.
9. U.S. ARMY CORPS OF ENGINEERS (USACE) POINTS OF CONTACT:
Contracting Officer:
Carlos S. Ramos
Phone: 540-665-6514
Email: Carlos.S.Ramos@usace.army.mil mailto:Holly.K.Watson@usace.army.mil
Contracting Specialist:
Peter S. Smith
Phone: 540-542-6620
Email: Peter.S.Smith@usace.army.mil
Project Manager:
Brian H. Ball
Phone: 540-678-1877
Email: Brian.H.Ball@usace.army.mil
Technical Manager:
Tricia L. Torok
Phone: 540-665-4067
Email: Tricia.L.Torok@usace.army.mil
10. DUTIES, TAXES, AND LICENSE FEES:
The Contractor should not assume that any work under this contract is exempt from taxes, duties, and/or license fees. It will be incumbent upon the Contractor to determine the individual tax and fee requirements for the pot ential points of delivery for this contract, as well as to determine what basis may exist for exemption from taxation and to do everything necessary to avail itself of all available exemptions. Taxes, duties, and fees may be reimbursable in some instances, and if so, that will be addressed in the scope of the individual delivery orders, but, in any event, the contractor will be obligated to preserve, and to ensure that its subcontractors and suppliers preserve, all documentation necessary to obtain any available reimbursement of taxes, duties, or government fees.
11. SUBMISSION OF INVOICES:
a . Invoices shall be prepared and submitted in accordance with FAR Clause 52.212 -4 Terms and Conditions
Commercial Items. One copy shall be marked "ORIGINAL".
b. Each invoice must be accompanied by the following:
i. Certificate of Conformance indicating Contractor conformance to the contract requirement.
ii. A copy of the DD Form 250 Material Inspection and Receiving Report signed by the Contracting
Officer's Representative (COR) or the Alternate COR.
c. The Project Manager must receive a copy of the signed Material Inspection and Receiving Report and the
Certificate of Conformance before payment will be authorized for services performed and supplies received. The Project Manager's copies must be sent to the address shown above in the previous paragraphs.
d. Final Pay Invoices must be accompanied by a release of claims in addition to the information requested above.
e. Failure to provide the required information will result in the rejection of the invoice and a request for a revised invoice that meets the contract requirements. Payment will not be authorized un til a proper invoice, meeting the requirements stated herein, is provided.
12. CONTRACTOR’S DATA SUBMITTAL REQUIREMENTS:
(All submittals are due after a delivery order is awarded) mailto:Peter.S.Smith@usace.army.mil mailto:Brian.H.Ball@usace.army.mil mailto:Tricia.L.Torok@usace.army.mil
The Contractor is required to furnish the following data as specified :
a . PRODUCT DATA: Within 30 days of their first delivery order award under this contract, the Contractor shall provide product data for each type of RLB unit listed in Section 2 of this PWS. Each type of unit required will include all of the submittals listed in UFC 1-201-01, Paragraph 1-7 and under the provisions of Specification 13 34 23.12 10, Paragraph 1.5. Submittals will be sent to:
Middle East District
Center of Standardization for Non-Permanent Facilities
201 Prince Frederick Dr.
Winchester, VA 22602
Submittals will be sent to the attention of the Contracting Officer and the Project Manager listed in Section
9 of this PWS. The Contractor shall allow 15 business days for Government review (and subsequent re -review as required) and shall respond to any Government comments thoroughly and promptly. The
Contractor shall not begin work on the manufacture of any RLB units until they receive notice of product approval by the Contracting Officer.
b. WARRANTIES: Provide copies of warranty documents to the Contracting Officer, Contract Specialist, and Project Manager via electronic submission at the addresses listed in the previous paragraphs within 30 calendar days of contract award.
c. DEFENSE BASE ACT INSURANCE (DBA): Provide evidence of an active DBA insurance policy to the
Contracting Officer, Contracting Officers Representative, Contract Specialist, and Project Manager via electronic submission at the addresses listed in the previous paragraphs within 15 calendar days after each delivery order award.
d. MANUALS: Provided copies of all manuals to include data CDs to the Contracting Officer, Contract
Specialist, Technical Manager, and Project Manager (or their designees) via electronic submission (where possible) at the addresses listed in the previous paragraphs for each RLB unit type within 30 days of product approval. CDs or similar media shall be sent to the attention of the Contracting Officer by express shipment.
13. SECURITY REQUIREMENTS:
The Contractor is required to adhere to the most current versions of DFARS 252.204-7004: LEVEL I
ANTITERRORISM AWARENESS TRAINING FOR CONTRACTORS, and DFARS 252.225 -7043:
ANTITERRORISM/FORCE PROTECTION POLICY FOR DEFENSE CONTRACTORS OUTSIDE THE
UNITED STATES.
All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled-access areas shall complete AT Level I awareness training within 30 calendar days of requiring access to a U.S. military installation. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 3 calendar days after completion.
This contract will require contractor personnel to access U.S. Military Installations within the countries designated in this PWS. Contractor and all associated subcontractors’ employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal
Office or Director of Emergency Services or Security Office or other authorities as required by the installation where delivery and/or other performance is required. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. Policies, requirements, and procedures for access to installations and other sites where work is to be performed under this contract will not be under the control of the Corps of Engineers.
Those policies, procedures, and requirements may be onerous and may change at any time before or during performance. The Contractor will be required to comply with all such policies, procedures, and requirements, even as they change during performance, and to obtain and maintain installation and/or site access for all personnel, equipment, supplies, and materials necessary for performance of a delivery order. Installation or site access policies may include restrictions on personnel access based on nationality, which may be subject to change at any time, as well as requirements that all or certain Contractor personnel be escorted while on-base or on-site. When escort requirements apply, the Contractor will be required to work with installation or other authorities, as applicable, to comply with escort requirements and to schedule work so as to accommodate potentially limited escort availability.
It is the responsibility of the contractor to be familiar with the badging and access requirements of the installations it will be accessing, and to process access requests for its (or its designated subcontractor’s) personnel in a timely manner.
Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training.
New employees working on an active delivery order must be trained within 30 calendar days of their reporting for duty and annually thereafter.
52.212-2 EVALUATION--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)
(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:
ADDENDUM
1.0. BASIS OF AWARD
1.1 Proposals received in response to the solicitation will be evaluated in accordance with the DoD source selection procedures, as outlined in FAR part 15 and the Army Source Selection Supplement (November 2017), and will follow the evaluation procedures described below.
1.2 The Government will consider the following factors:
• Factor 1: Compliance with DFARS 252.225-7021, Trade Agreements
• Factor 2: Demonstration of UFC Compliance
1.3 Factors 1 and 2 are “Go/No-Go” factors and, thus, will receive a rating of either “Go” or “No -Go”. Offerors will be assigned a “Go” rating for each of these factors only if they meet all minimum requirements in the solicitation for that factor. Any offeror that receives a “No-Go” rating for either Factor 1 or 2 (under the evaluation procedures listed in the following paragraphs) will be considered ineligible for award.
• Factor 3: Delivery, Logistics, and Offeror’s Capability Plan
• Factor 4: Past Performance
• Factor 5: Price
1.4 Adjectival ratings will be assigned to Factors 3 and 4. For Factor 3, non-pricing features of each proposal will be evaluated against the RFP requirements, assessing the strengths and significant strengths, weaknesses, and significant weaknesses, as well as associated risks, and deficiencies of each proposal in light of the non -pricing evaluation criteria that are also described herein. For Factor 4, non-pricing features of each proposal will be evaluated against the RFP requirements, assessing the quality of the offeror’s past performance, making note of any deficiencies and uncertainties. Non-pricing features of Factors 3 and 4 shall be evaluated in such a manner as to assess the value of those features as compared to the proposed prices or costs to the Government. The Best Value
Tradeoff process permits tradeoffs among cost or price and non-cost or price evaluation factors and allows the
Government to accept other than the lowest priced proposal or other than the highest technically rated proposal.
Pricing will be evaluated for completeness and reasonableness.
1.5 The ratings for Factors 3 and 4 and the pricing report for the Price Factor (Factor 5) will be used in selecting the awardees using the Best Value Tradeoff process. As stated above, any offeror who receives a “No -Go” rating for either Factor 1 or 2 will be considered ineligible for award.
1.6 Subject to the provisions herein, award will be made to a target of five offerors that are deemed responsible according to the FAR, whose offer(s) conform to the RFP, whose proposal(s), judged by an overall assessment of the evaluation criteria, receive “Go” ratings for Fa ctors 1 and 2, and whose combination of technical capabilities (as demonstrated by the ratings of Factors 3 and 4) and prices represent the best value to the Government in accordance with FAR 15.101-1. However, the Government reserves the right to award to more or fewer offerors.
1.7 In evaluating proposals and in making the contract award, the Government is as concerned with obtaining the best non-pricing features as it is in doing so at a competitively reasonable price. The Government will not make a contract award to an offeror whose superior non-pricing features would cause the total cost of the procurement to become unreasonably high, nor is the Government willing to make a contract award to an offeror submitting the lowest set of prices if the non-pricing features of its proposal indicate a reasonable likelihood that successful contract execution will not occur. For this evaluation, all evaluation factors other than cost or price, when combined, are significantly more important than price.
1.8 The Government intends to award a contract without discussions, although the Government reserves the right to conduct discussions if it is determined to be in the Government's best interests. Therefore, an offeror that desires consideration for the contract award is advised to comply with all mandatory requirements of this solicitation for submission of price and non-price factors and to include its best terms in its proposal.
2.0. FACTORS TO BE EVALUATED
2.1 FACTOR 1: COMPLIANCE WITH DFARS 252.225-7021, TRADE AGREEMENTS:
2.1.1 SUBMISSION REQUIREMENTS:
For this factor, offerors must demonstrate how they intend to comply with the requirements in DFARS 252.225 -
7021, Trade Agreements. Offerors must provide the locations where they intend to manufacture the RLB units under this contract. Each offeror must also provide an affirmative statement indicating it will comply with all aspects of
DFARS 252.225-7021 with regard to sourcing of materials in order to provide products of the United States or designated and/or qualifying countries. In determining and demonstrating their compliance, offerors should take into account that there are several different categories of designated and/or qualifying countries under DFARS 252.22 5-
7021, and that different origin determination rules apply to end products of different categories of countries.
2.1.2 EVALUATION PROCEDURES
The Government will review the information provided by the offeror against the requirements of DFARS 252.225 -
7021 to determine whether the RLBs manufactured with the components presented and as described in the offeror’s plan will meet the requirements of that clause. The Government will review the intended place of manufacture to determine whether it is in the United States or a designated and/or qualifying country. Offerors whose places of manufacture meet the requirements of DFARS 252.225-7021 will be given “Go” ratings. Offerors whose places of manufacture do not meet the requirements of DFARS 252.225-7021 will be given “No-Go” ratings and will not be eligible for award. Failure to provide the affirmative statement of compliance will also result in a “No -Go” rating.
2.1.3 FACTOR 1: ADJECTIVAL RATINGS AND DEFINITIONS
Offerors must submit proof of their ability to conform to the Trade Agreements requirements to receive “Go” ratings. Offerors that receive “No-Go” ratings will be eliminated from consideration for award.
Compliance with Trade Agreements Ratings
Rating Definition
Go Offeror provided proof that its manufacturing plan is in conformance with the
Trade Agreements requirements in the solicitation.
No-Go Offeror did not provide proof that its manufacturing plan is in conformance with the Trade Agreements requirements in the solicitation.
2.2 FACTOR 2: DEMONSTRATION OF UFC COMPLIANCE:
2.2.1 SUBMISSION REQUIREMENTS:
2.2.1.1 For this factor, offerors shall submit technical drawings and narratives to demonstrate that they can develop a shippable RLB unit that can be assembled into usable facilities that meet all technical requirements for a
“semi-permanent” construction level in UFC 1-201-01, as well as the DoD’s definition of a relocatable building
(DoDI 4165.56). These drawings may be of an existing RLB unit previously manufactured by the offeror which is similar in size and nature to the RLB units required by this solicitation (see Section 2 of the attached PWS and attached “Relocatable Building Unit” specification), or the offeror may submit technical drawings and narratives that it has developed for an RLB unit that meets the requirements for one of the types of RLB containers required under the scope of work of this contract (even if it has not been previously manufactured). The offeror’s proposal package shall include all elements required under the noted UFC.
2.2.1.2 For the purposes of this evaluation, an RLB product which is “similar in size and nature” to the RLB units required by this solicitation means a pre-fabricated structure that is developed and newly manufactured to be readily moved (transportable over public roads) and is capable of being erected, disassembled, stored, and re-used, not including tension fabric structures assembled from modular components, air supported domes, mobile military equipment, tents, modular sheds, or temporary contractor/construction trailers. This product must be capable of being shipped in standard-sized shipping containers (8’ x 8’ x 20’) and assembled in such a way to allow for the creation of a structure suitable for human use and occupation. Submittal of RLB products which are made of combustible materials, or for products which the U.S. Government holds the patent, will also not be acceptable for this factor.
2.2.2 EVALUATION PROCEDURES:
2.2.2.1 Proposals will be evaluated to determine if the product technical drawings and narratives for the RLB product submitted for review adhere to the minimum standards of UFC 1-201-01 for Relocatable Buildings. The information provided will be compared against the requirements listed in UFC 1-201-01. Offerors that do not provide all submittals required by UFC 1-201-01 and this factor will be assigned a “No-Go” rating. The proposal will be evaluated using the following checklist:
2.2.2.2 SEMI-PERMANENT CONSTRUCTION LEVEL CHECKLIST
STRUCTURAL
Drawings YES NO Comment
General Notes
Inspection Requirements
Foundation Plans
Framing Plans, all levels
Roof Framing Plans
Details
Schedules as required (footings, columns, beams, shear walls)
Calculations
Basis of Design; summary of applicable codes, live loading, snow loading, wind and seismic loads, dead load assumptions.
Gravity design; design of floor and roof framing members – i.e. beams, slabs, joists, decks, and composite slabs.
Column and bearing wall design
Foundation design
Lateral design; i.e. design of diaphragms and collectors, distribution of loads to lateral forces resisting elements (frames, walls), design of shear walls, moment frames, and braced frames, design of foundations at lateral force resisting elements, and design of hold downs, and straps.
Design for Anti-Terrorism (AT)/Force
Protection (FP); confirm setbacks, wall construction types, and progressive collapse mitigation design requirements, check window designs, jambs and sills for AT/FP window loading requirements
Load combinations used
Materials used with properties and section properties.
Connection design and details – bolted and welded
Wind load analysis applied to structure
Seismic load analysis
Serviceability check (deflections and overturning)
Wall panel design (building envelope) and connection to superstructure
Stated structure life-span
Erection plan(s)
ELECTRICAL
Drawings YES NO Comment
Comply with the requirements of UFC
3-501-01, Electrical Engineering, Section 3-3, “Drawing Requirements”, and the following subsections:
Section 3-3.1, “Legends and
Abbreviations.
Section 3-3.2.2, “Transformer Details.
Section 3-3.2.3, “Underground
Distribution”.
Section 3-3.4, “Lighting Plans and
Details”.
Section 3-3.5, “Power Plans”.
Section 3-3.12, “Telecommunications
Riser Diagram”.
Section 3-3.13, “Intercommunication/Paging Riser
Diagram”.
Section 3-3.14, “Fire Alarm Riser
Diagram”.
Section 3-3.16, “Schedules and
Elevations”.
Calculations YES NO Comment
Comply with the requirements of UFC 3-
501-01, Electrical Engineering, for the following calculations:
Section 3-2.4, “Short Circuit Analysis”
Section 3-2.6, “Arc Flash Analyses”
Section 3-2.15, “Lightning Protection
Calculations”
PLUMBING AND MECHANICAL
Drawings YES NO Comment
Natural ventilation - Floor plans showing the layout of the ventilation system, dimensions of openings and associated equipment, and the means of controlling the system.
Mechanical ventilation - Floor plans showing the layout of the ventilation system, equipment schedules and details, schematic diagrams, and control sequences and diagrams.
Specific Systems, provide Mechanical
System documentation in accordance with UFC-3-410-01, Chapter 5-2, “Drawings”.
with UFC-3-420-01, Chapter 5-2, “Drawings”.
Calculations…