Sample Task Order_West Basin Scour Phase 3.pdf
PDF 1 MB Posted
- Attached to
- FY20 Miscellaneous Repairs Federal contract opportunity
- Solicitation number
- W912EQ20R0002
About this file
This document provides details for a Multiple Award Task Order Contract (MATOC) solicitation for miscellaneous repairs throughout the Memphis District of the U.S. Army Corps of Engineers. Typical task orders under this contract may include levee embankment repairs, road gravel surfacing, channel bank riprap armoring, culvert installation and replacement, and maintenance of existing projects. The estimated total value of all task orders over the five-year contract period is $45 million. The solicitation number is W912EQ-20R0002 and proposals are due on March 3, 2020. The contract will be set aside for 8(a) small businesses with a size standard of $36.5 million. Evaluation criteria include past performance, technical and price factors. Site visits are available and the resulting awards will be firm-fixed-price IDIQ contracts to a maximum of four awardees.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 02_Miscellaneous Repairs.pdf | ||
| Amendment 01_ Miscellaneous Repairs 1.pdf | ||
| Miscellaeous Repairs Plates.pdf | ||
| Miscellaneous Repairs Solicitation.pdf | ||
| Miscellanesous Repairs Specifications .pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912EQ20R0002
OFFERORS SCHEDULE
MULTIPLE AWARD TASK ORDER CONTRACT (MATOC)
FOR MISCELLANEOUS REPAIRS AT
VARIOUS LOCATIONS WITHIN MEMPHIS DISTRICT
TASK ORDER_WEST BASIN SCOUR REPAIRS – PHASE 3
This Task Order will be awarded based on evaluation factors mentioned in the following announcement. The prices entered in the Offerors schedule will be used as one of the evaluation factors for the Task Order selection. These unit prices for
Miscellaneous Repairs will be used for all task orders awarded under this contract for the entire Memphis District as shown in Drawings Number 1 of the “Drawings &
Sketches”. A schedule of the unit price work is contained in Standard Form SF 1442, "Solicitation, Offer and Award."
ITEM DESCRIPTION Estimated
Quantity Unit
Unit
Price Amount
0001 Mobilization and Demobilization 1 JA XXX.XX $____.__
0002 Environmental Protection 1 JA XXX.XX $____.__
0003 Storm Water Pollution Prevention
0003A Write/Amend and Maintain SWPPP 1 JA XXX.XX $____.__
0003B Silt Fence 165 LF ______ $____.__
0003C Erosion Control Berm 22,800 LF ______ $____.__
0004 Clearing 40.5 AC ______ $____.__
0005 Grubbing 40.5 AC ______ $____.__
0006 Excavation 9,410 CY ______ $____.__
0007 Riprap, R-400 Procurement 161,095 TN ______ $____.__
0008 Riprap, R-400 Placement 161,095 TN ______ $____.__
0009 Riprap, R-400 Transport 161,095 TN ______ $____.__
0010 Embankment, Semi-Compacted 9,410 CY ______ $____.__
0011 Establishment of Turf 17 AC ______ $____.__
Grand Total Items 0001 thru 0011
TOTAL TASK ORDER AMOUNT $______
NOTE 1: Offerors shall furnish unit prices for all items listed on the schedule of offerors items, which require unit prices and have an estimated quantity. If the offeror fails to insert a unit price in the appropriate blank for required items, but does furnish an extended total or an estimated amount for such items, the Government will deem his unit price to be the quotient obtained by dividing the extended estimated amount for that line item by the quantity. IF THE OFFEROR OMITS BOTH THE
UNIT PRICE AND THE EXTENDED ESTIMATED AMOUNT FOR ANY ITEM, THIS OFFER WILL BE
DECLARED NONRESPONSIVE.
In the event there is a difference between a unit price and the extended total, the unit price will be held to be the intended offer. If the offeror shows only the total price but fails to enter a unit price, the total divided by the estimated quantity will be held to be the intended unit price.
Any offer price for items indicated above which are unbalanced as to price may be rejected as non-responsive. An unbalanced offer is one which is based on price significantly less than cost for some work and price which is significantly overstated for other work.
Each task order award will be made as a whole to one offeror.
AC = Acre CF = Cubic Feet CY = Cubic Yard
DH = Miles EA = Each FC = 1000 Cubic Feet
FT = Foot HF = 100 Feet HH = 100 Cubic Feet
HL = 100 Linear Ft HR = Hours HS = 100 Square Feet
HY = 100 Yards LB = Pound LF = Linear Foot
LH = Labor Hour JA = Job (lump sum) LY = Linear Yard
MI = Miles SB = Square Mile SF = Square Foot
SQ = Square SY = Square Yard TL = 1000 Linear Feet
TN = Net Ton UN = Unit YD = Yard
YL = 100 Linear Yards YM = Cubic Yards Per Mile
All quantities are estimated except where unit is given as "JA" or "EA".
NOTE 2: If an offer or modification to an offer based on unit prices is submitted and provides for a job adjustment to the total estimated cost, the application of the job adjustment to each unit price, including job units, in bid schedule must be stated, or, if it is not stated, the offeror agrees that the job adjustment shall be applied on a pro rata basis to every unit price in the bid schedule.
NOTE 3: Bidders are cautioned to read Contract Clause entitled "DFAR 252.204-7004, Alternate A, System for Award Management (FEB 2014) located in Section 00 70 00.00
MATOC TASK ORDER SCOPE OF WORK
PROJECT TITLE
St. Francis Basin Maintenance
West Basin Scour Repairs – Phase 3
Little River Drainage District
Bollinger County, MO
PROJECT LOCATION
The project is located along the West Basin Levee in Bollinger County, Missouri.
SCOPE OF WORK
The work consists of furnishing all plant, labor, and materials and any incidental related work according to the plans and specifications for repairing 3 scour site locations that have occurred along the right bank of the West
Basin Levee - Headwater Diversion Channel.
AREA OFFICE
Caruthersville Area Office
AREA ENGINEER INFORMATION
Mr. Daimon McNew, P.E.
Caruthersville Area Office
706 Harry S. Truman Blvd.
Caruthersville, Missouri, 63830-1268
573-333-1043
If other, give contact information:
N/A
TRANSPORTATION FACILITIES (DIRECTIONS TO THE PROJECT)
From Advance, MO, take Hwy 91 (Oak Street) north 3.0 miles. Levee can be accessed on both sides immediately south of the bridge.
LENGTH OF PROJECT
This is a project consists of a three separate sites totaling 138 acres. The total length is approx. 4.3 miles.
STATION RANGE
Repairs begin at Levee Baseline Station 334+00 (Scour Site 1) and end at Levee Baseline Station 567+72 (Scour
Site 3). See sheet G-002 for site limits.
PERFORMANCE PERIOD (# of calendar days)
220 days.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
*Based on a 6 day work week
January – 17 days
February –15 days
March – 9 days
April – 8 days
May – 8 days
June – 5 days
July – 5 days
August – 3 days
September – 5 days
October – 7 days
November – 8 days
December – 14 days
AMOUNT OF LIQUIDATED DAMAGES
$1390.00 per calendar day
LOCAL POINT OF CONTACT
Contact Contracting Officer
AUTHORITY
The work provided for herein is authorized by the Flood Control Act of 1936, as amended.
APPROPRIATION
96X3123 - Operations & Maintenance
ALLOTMENT
St. Francis Basin - Maintenance
ESTIMATED PROJECT VALUE
The estimated value of the proposed work is between $5,000,000 and $10,000,000.
TOTAL PROJECT SITE AREA
138 acres
TOTAL DISTURBED AREA
41 acres
PROJECT RECEIVING WATERS
The project receiving water is the Headwater Diversion Channel. The ultimate receiving water is the Mississippi River.
PROJECT WITHIN THE JURISDICTION OF AN MS4
No
STORMWATER ENTER A WATERBODY ON THE 303(d) LIST OR WITH AN APPROVED TMDL
No
OTHER INFORMATION
1. Access to the project site is gated. Contact Contracting Officer for access.
2. Section 32 92 32.01 11 ESTABLISHMENT OF TURF shall not be used for this task order. Instead, Section
32 92 35.00 13 SEEDING AND MULCHING – SOUTHEAST MO (LRDD) shall be used in its place.
References to 32 92 32.01 11 shall instead refer to 32 92 35.00 13 throughout.
3. Although there is no non-work period, Contractor is advised that the seasonal variation in water levels may make the project inaccessible at times. See Sheet X-001.
West Basin Scour Repairs Phase 3
SECTION TABLE OF CONTENTS
DIVISION 32 - EXTERIOR IMPROVEMENTS
SECTION 32 92 35.00 13
SEEDING AND MULCHING - SOUTHEAST MO (LRDD)
06/12/06
PART 1 GENERAL
1.1 SCOPE
1.2 REFERENCES
1.3 SUBMITTALS
1.4 QUALITY CONTROL
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Seed
2.1.2 Mulch
2.1.3 Soil for Repairs
2.2 SAMPLING, TESTING, AND CERTIFICATES
2.2.1 Seed
PART 3 EXECUTION
3.1 AREAS TO RECEIVE SEEDING AND MULCHING
3.2 COMMENCEMENT, PROSECUTION, AND COMPLETION
3.3 PREPARATION OF GROUND SURFACE
3.3.1 Clearing
3.3.2 Dressing
3.4 SEEDING
3.4.1 General
3.4.2 Methods for Seeding
3.4.3 Compacting
3.4.4 Damage to Seeding
3.5 APPLICATION OF MULCH
3.6 INSPECTION AND ACCEPTANCE
-- End of Section Table of Contents --
SECTION 32 92 35.00 13 Page 1
FOR SOLICITATION
SECTION 32 92 35.00 13
SEEDING AND MULCHING - SOUTHEAST MO (LRDD)
06/12/06
PART 1 GENERAL
1.1 SCOPE
The work covered by this section consists of furnishing all plant, labor, equipment, and materials, and performing all necessary operations for establishment and maintenance of turf as specified herein and as indicated on the drawings. Seeding shall be accomplished using ground equipment.
1.2 REFERENCES
The publications listed below form a part of this section to the extent referenced:
U.S. DEPARTMENT OF AGRICULTURE (USDA)
AMS Seed Act (1940; R 1988; R 1998) Federal Seed Act
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Seed Invoices
Native Grass Seeding Equipment; G, CAO
SD-04 Samples
Mulch Material
Alternate Seeding Mixture; G, CAO
SD-07 Certificates
AMS Seed Act Certification
Mulch Supplier Certification
1.4 QUALITY CONTROL
The Contractor shall establish and maintain quality control for seeding and mulching operations to assure compliance with the contract requirements and shall maintain records of his quality control for all construction operations, including, but not limited to the following:
SECTION 32 92 35.00 13 Page 2
a. Pre-construction survey of sites
Contractor shall survey the project sites prior to the start of construction and document all areas that have been denuded of grass from prior construction operations.
b. Preparation of Ground Surface
Indicate the location and quality of finish dressing, including necessary clearing, filling, or dressing-out of washes, smoothness and uniformity of surfaces, and time of year.
c. Seeding
Indicate the quality and type of seed, area covered, rate of application, quantity of seed used, and method of distribution.
d. Maintenance and Repair
Indicate the location and type of maintenance problems and remedial treatment performed.
A copy of these quality control records and tests, as well as the records of corrective action taken, shall be furnished to the Government.
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Seed
The Contractor shall furnish seed of the latest season's crop labeled in conformance with AMS Seed Act and applicable State seed laws. Seed shall be furnished in original sealed packages, bearing producer's guaranteed analysis for percentages of mixtures, purity, germination, weedseed content, and inert material, unless written exception is granted. Field mixes will be acceptable when field mix is performed on site in the presence of the Contracting Officer. Seed that is wet or moldy or that has been otherwise damaged in transit or storage will be rejected. Between 1 December and 31 May, inclusive, seed mixtures shall conform to one or more of the following "Sample Custom Mixtures" in Tables 1 and 2 provided below, unless otherwise approved by the Contracting Officer. Between 1 September and 30 November, inclusive, seed mixtures shall conform to the mixtures provided in Table 3 provided below, unless otherwise approved by the Contracting Officer. Between 1 June and 31 August, inclusive, temporary seed mixtures shall conform to the mixtures provided in Table 4 provided below, unless otherwise approved by the Contracting Officer.
SECTION 32 92 35.00 13 Page 3
Table 1. Seeding rates for native grasses to be seeded by seeder or drill. Rates are pounds of Pure Live Seed (PLS) per acre
Grass Species Sample Custom Mixture
(Variety or Origin) A (20% ) B (25%) C
Redtop 1 1 1
Big Bluestem (Kaw Roundtree) 1.6 2 2.4
Little Bluestem (Aldous, Camper, MO or KS Native
1.3 1.6 3.8
Sideoats Grama (El Reno Trailblazer)
1.5
Switchgrass (Kanlow, Alamo, Cave-in-Rock, Blackwell)
1.4 1.8
Alsike Clover 0.3
Alfalfa 1.5 1.8 0.7
Table 2. Seeding rates for native grasses to be seeded by broadcasting. Rates are pounds of Pure Live Seed (PLS) per acre
Grass Species Sample Custom Mixture
(Variety or Origin) A (20% ) B (25%) C
Redtop 1 1 1
Big Bluestem (Kaw Roundtree) 2.4 3 3.6
Little Bluestem (Aldous, Camper, MO or KS Native
2 2.4 5.8
Sideoats Grama (El Reno Trailblazer)
2.3
Switchgrass (Kanlow, Alamo, Cave-in-Rock, Blackwell)
2.1 2.6
Alsike Clover 0.5
Alfalfa 2.3 2.8 1.1
SECTION 32 92 35.00 13 Page 4
Table 3. Seeding rates for grasses seeded from 1 September - 30 November. Rates are pounds of Pure Live Seed (PLS) per acre
Grass/Legume Species Seed Rate
(Variety or Origin) Drill Broadcast
Virginia Wildrye 30 30
Alsike Clover 3.2 3.2
Buckwheat 15 15
Table 4. Seeding rates for cover crop seeded from 1 June - 31 August. Rates are pounds of
Pure Live Seed (PLS) per acre
Cover Crop Type Seed Rate
(Variety or Origin) Drill Broadcast Pearl Millet 12 15
Japanese Millet 15 17 Oats 50 60 Sorghum-Sudangrass 20 30
Wheat 70 90
SECTION 32 92 35.00 13 Page 5
2.1.2 Mulch
The Contractor shall use mulch material to protect the seeded areas as well as reduce erosion. The material used for mulching shall be threshed straw from wheat, rye, barley, or rice, applied at a rate of 2 tons per acre (4,000 lbs/AC). Furnish mulch in air-dry condition and of proper consistency for placing with commercial mulch blowing equipment. Straw shall contain no fertile seed. Mulch shall be free from noxious weeds, mold, and other deleterious materials. Use of hay for mulch will not be permitted. The Contractor shall be prepared to submit, on request, Mulch Supplier Certification.
2.1.3 Soil for Repairs
For fill of areas to be repaired, soil shall be of a quality at least equal to that which exists in areas adjacent to the area to be repaired. Soil used shall be free from roots, stones, and other materials that hinder grading, planting, and maintenance operations and shall be free from objectionable weed seeds and toxic substances.
2.2 SAMPLING, TESTING, AND CERTIFICATES
Sampling and testing shall be the responsibility of the Contractor and shall be performed at no additional cost to the Government. Sampling and testing shall be performed by a recognized testing agency.
2.2.1 Seed
The Contracting Officer shall be furnished duplicate signed copies of statements certifying that each container of seed delivered is labeled in accordance with the AMS Seed Act and is at least equal to the requirements specified in the paragraph entitled "Seed" above. This AMS Seed Act Certification shall be obtained from the supplier and shall be furnished on or with all copies of Seed Invoices.
PART 3 EXECUTION
3.1 AREAS TO RECEIVE SEEDING AND MULCHING
Seeding and Mulching shall take place in Spoil Area 1 and Spoil Area 2 as shown in the drawings. The Contractor shall also seed and mulch any other areas within the Right-of-Way limits, outside of Spoil Area 1 and Spoil Area 2 denuded of grass by construction operations which includes, but not limited to, repair of scour repair site access paths down the levee slope.
The Contractor shall also seed and mulch any areas required by the Contracting Officer.
3.2 COMMENCEMENT, PROSECUTION, AND COMPLETION
Seeding and mulch shall be placed no more than 14 days after construction activity temporarily or permanently ceases on any portion of the site.
Prior to prosecuting the seeding operation, the Contractor shall repair rainwash, if any, dress, and prepare the areas for seeding and mulching.
3.3 PREPARATION OF GROUND SURFACE
After areas have been brought to the indicated finish grade, remove debris and stones larger than 3 inches remaining on the surface. Correct
SECTION 32 92 35.00 13 Page 6 irregularities in finish surfaces to eliminate depressions. Provide equipment, in good condition, for the proper preparation of the ground and for handling and placing all materials.
3.3.1 Clearing
Prior to grading and finish dressing, vegetation that may interfere with seeding and mulching operations shall be removed and shall be disposed of according to Section 01 57 20.00 11 ENVIRONMENTAL PROTECTION. The surface shall be cleared of roots, cable, wire, and other materials that might hinder the work or subsequent maintenance.
3.3.2 Dressing
Surfaces to receive seeding and mulching, shall be dressed to the extent necessary to provide drainage and the specified slopes, and as necessary to remove high points and fill depressions sufficiently to provide reasonably smooth surfaces. Surfaces shall be prepared by dressing so as to produce smooth profiles and end slopes.
3.4 SEEDING
3.4.1 General
Seed sown during the season between 1 December and 31 May, inclusive, shall consist of one or more of the mixtures indicated in Tables 1 or 2 depending on the equipment used for seeding. Seed sown during the season between, 1 September and 30 November, inclusive, shall consist of the mixtures provided in Table 3. Use temporary seeding mixtures from Table 4 during the season between 1 June and 31 August, inclusive. Reseed temporarily seeded areas with seed mixtures from Tables 1 or 2 once within the appropriate seasonal time frame. No additional ground preparation or mulching will be required for temporary areas requiring reseeding. The contractor may submit an alternate seeding mixture, for Contracting Officer approval, consisting of the seed listed in Tables 1 and 2 but at different rates based on availability. A satisfactory method of sowing shall be employed, using approved Native Grass Drills, broadcast-seeders, or other approved methods. When conditions are such by reason of drought, high winds, excessive moisture, or other factors that satisfactory results are not likely to be obtained, seeding shall be halted as directed and resumed only when conditions are favorable or when the Contracting Officer approved alternative or corrective measures and procedures have been implemented. If inspection either during seeding operations or after there is a show of green indicates that areas have been left unplanted, additional seed shall be sown if so directed.
3.4.2 Methods for Seeding
Conduct thorough tillage as required so that all vegetation is controlled.
Provide a smooth surface for ample fine soil particles to insure good seed coverage and soil contact. Roll or culti-pack seedbed before seeding so that ground surface is firm enough for a person on foot to sink less than 1/2". Use a "Brillion-type" seeder or a drill with seed box and metering equipment designed for the seed being sown. Place the seed at 1/8" to 1/4" and use press wheels to insure good seed-soil contact. Seed shall be drilled or broadcasted with approved sowing equipment and distributed uniformly over the areas. Seed shall not be broadcast during winds in excess of 10 miles per hour.
SECTION 32 92 35.00 13 Page 7
3.4.3 Compacting
Immediately upon completion of seeding operations, surfaces shall be compacted by one pass of a cultipacker, corrugated roller, or other approved equipment weighing 100 to 160 pounds per linear foot of roller.
Drilled seed does not require follow-up compaction.
3.4.4 Damage to Seeding
The Contractor shall be fully responsible for any damage to the seeded areas caused by his operations. Areas that become damaged shall be repaired without additional cost to the Government. Additionally, areas that become damaged as a result of poor workmanship or failure to meet the requirements of the specifications may be ordered to be repaired and reseeded to specification requirements, without additional cost to the Government
3.5 APPLICATION OF MULCH
Mulch shall be spread uniformly in a continuous blanket, using 2 tons per acre of straw mulch. Straw mulch shall be spread either by hand or by a manure spreader or by a modified grain combine with straw-spreader attachment or by a blower-type mulch spreader. Mulching shall be started at the windward side of relatively flat areas, or at the upper part of a steep slope, and continued uniformly until the area is covered. The mulch shall not be bunched. Immediately after spreading, straw mulch shall be anchored to the soil by a V-type-wheel land packer, a scalloped-disk, tackifier, punch roller, or other suitable equipment operated parallel to the embankment centerline. Straw mulch with tackifier shall not be applied during or immediately before rainfall. The Contracting Officer will determine the number of passes needed for anchoring, not to exceed three.
3.6 INSPECTION AND ACCEPTANCE
Acceptance of the seeded and mulched areas will be determined by visual inspection. Existence of rainwash damage will not be acceptable. 60% of the unit price payment for seeding and mulching will be made upon application of seeding and mulching and the remaining 40% of the unit price payment will be made upon final acceptance by the Contracting Officer.
Acceptance of the turfing areas may be obtained in 1,000 foot intervals along the spoil areas.
-- End of Section --
SECTION 32 92 35.00 13 Page 8
| Binder1.pdf |
| West Basin Scour BID Sheet |
| Binder2.pdf |
| West Basin Scour SPEC |
| Binder3.pdf |
| 32 92 35.00 13 - West Basin Phase 3 |
| DIVISION 32 - EXTERIOR IMPROVEMENTS |
| 32 92 35.00 13 - SEEDING AND MULCHING - SOUTHEAST MO LRDD |
| 32 92 35.00 13 - SEEDING AND MULCHING - SOUTHEAST MO LRDD |
| PART 1 GENERAL |
| 1.1 SCOPE |
| 1.2 REFERENCES |
| 1.3 SUBMITTALS |
| 1.4 QUALITY CONTROL |
| PART 2 PRODUCTS |
| 2.1 MATERIALS |
| 2.1.1 Seed |
| 2.1.2 Mulch |
| 2.1.3 Soil for Repairs |
| 2.2 SAMPLING, TESTING, AND CERTIFICATES |
| 2.2.1 Seed |
| PART 3 EXECUTION |
| 3.1 AREAS TO RECEIVE SEEDING AND MULCHING |
| 3.2 COMMENCEMENT, PROSECUTION, AND COMPLETION |
| 3.3 PREPARATION OF GROUND SURFACE |
| 3.3.1 Clearing |
| 3.3.2 Dressing |
| 3.4 SEEDING |
| 3.4.1 General |
| 3.4.2 Methods for Seeding |
| 3.4.3 Compacting |
| 3.4.4 Damage to Seeding |
| 3.5 APPLICATION OF MULCH |
| 3.6 INSPECTION AND ACCEPTANCE |
File details come from the government source that posted it. Updated .