Miscellanesous Repairs Specifications .pdf
PDF 3 MB Posted
- Attached to
- FY20 Miscellaneous Repairs Federal contract opportunity
- Solicitation number
- W912EQ20R0002
About this file
This pre-solicitation notice describes a multiple award task order contract opportunity for miscellaneous repairs throughout the Memphis District. Work will include repairs to levee embankments, road gravel surfacing, channel bank armoring, culvert installation and replacement, and maintenance of existing projects. The estimated average annual value is $9 million. Task orders will be issued on a firm-fixed price basis. The base period of performance is one year with four optional one-year extensions. Responses are due March 3, 2020. The solicitation seeks up to four 8(a) small business awardees. The contracting agency is the U.S. Army Corps of Engineers Memphis District.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 02_Miscellaneous Repairs.pdf | ||
| Amendment 01_ Miscellaneous Repairs 1.pdf | ||
| Sample Task Order_West Basin Scour Phase 3.pdf | ||
| Miscellaeous Repairs Plates.pdf | ||
| Miscellaneous Repairs Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SFB Misc. Repairs FY20 MISCREPAIRS
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00.00 11 SUMMARY OF WORK
01 22 00.00 11 MEASUREMENT AND PAYMENT
01 33 00 SUBMITTAL PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)
01 45 04.00 11 CONTRACTOR QUALITY CONTROL
01 57 20.00 11 ENVIRONMENTAL PROTECTION
01 57 25.00 11 STORM WATER POLLUTION PREVENTION PLAN
01 58 01.00 11 PROJECT SIGN, BARRICADES, AND TRAFFIC CONTROL SIGNS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 05 21 GEOGRID SOIL REINFORCEMENT
31 05 22 GEOTEXTILES USED AS FILTERS
31 11 00.00 11 CLEARING, GRUBBING AND STRIPPING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 15 00.00 11 AGGREGATE SURFACE COURSE
32 25 00.00 11 CULVERT REMOVAL AND INSTALLATION
32 92 32.01 11 ESTABLISHMENT OF TURF
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 31 19.00 11 STONE PROTECTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
FOR SOLICITATION
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00.00 11
SUMMARY OF WORK
1/10/08
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
1.1.2 Location
1.2 EXISTING WORK
1.3 LOCATION OF UNDERGROUND FACILITIES
1.4 UAI SUBPART 22.13 - EQUAL OPPORTUNITY FOR VETERANS (NOV 2014)
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
SECTION 01 11 00.00 11 Page 1
SECTION 01 11 00.00 11
SUMMARY OF WORK
1/10/08
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The project is a Multiple Award Task Order Contract (MATOC) for miscellaneous repairs throughout the Memphis District. Typical construction task orders may include levee embankment repairs, road gravel surfacing, channel bank riprap armoring, culvert installation/replacement and maintenance of existing projects within the Memphis District. The work on each task order will consist of furnishing all plant, labor and materials for the work to be performed. Specific items of work may include, but not be limited to:
clearing, stripping, grubbing; debris disposal; borrow pit development and excavation, stockpiling of material, processing of fill material for moisture control, embankment construction, compaction; placement of geo-textile, gravel surfacing, bedding material, riprap (grouted and un-grouted);
establishment of turf and any incidental related work according to the base MATOC specifications and supplemental specifications & plans for each individual Task Order. The project will consist of a base year and four (4) option years. The estimated average value of the work, including all Task Orders, is $9,000,000 per year.
1.1.2 Location
The work shall be located at various locations within the Memphis District. The exact location will be indicated on the contract drawings for each individual Task Order. The Contracting Officer's Representative will be available to show the exact location of the work at the organized site visit conducted for each Task Order.
1.2 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.3 LOCATION OF UNDERGROUND FACILITIES
Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated to be installed or removed, but indicated or discovered during work to be conducted or installed. For
SECTION 01 11 00.00 11 Page 2 further instructions and details, see the paragraph entitled, "OBSTRUCTIONS" in Section 00 80 00.00 11 SPECIAL CONTRACT REQUIREMENTS.
1.4 UAI SUBPART 22.13 - EQUAL OPPORTUNITY FOR VETERANS (NOV 2014)
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor Regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
Federal Veteran employment information-https://www.fedshirevets.gov/index.aspx
Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heroes Act http://benefits.va.gov/vow/
Army Wounded Warrior Program http://wtc.army.mil/modules/employers/index.html
U.S. Chamber of Commerce Foundation-Hiring Our Heroes https://www.uschamberfoundation.org/hiring-our-heroes
Guide to Hiring Veterans - Reference Material https://www.whitehouse.gov/sites/default/files/docs/white_house_business_council_-_guide_to_hiring_veterans_0.pdf
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --
SECTION 01 11 00.00 11 Page 3
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 11
MEASUREMENT AND PAYMENT
1/10/08
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
1.1.1 Mobilization and Demobilization
1.1.2 Environmental Protection
1.1.3 Demolition
1.1.4 Write/Amend and Maintain Stormwater Pollution Prevention Plan
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 Remobilization
1.2.2 Storm Water Pollution Prevention (SWPP)
1.2.2.1 Silt Fence
1.2.2.2 Erosion Control Berm
1.2.2.3 Temporary Environmental Seeding
1.2.2.4 Construction Exit
1.2.2.5 Vehicle Washdown Rack
1.2.3 Clearing
1.2.4 Grubbing
1.2.5 Stripping
1.2.6 Excavation
1.2.7 Geogrid
1.2.8 Geotextile
1.2.9 Corrugated Metal Pipe (CMP)
1.2.10 Polymer Coated CMP
1.2.11 Flared End Section
1.2.12 Flap Gate
1.2.13 Stone Procurement
1.2.14 Stone Placement
1.2.15 Stone Transport
1.2.16 Grout
1.2.17 Embankment, Semi-compacted
1.2.18 Embankment, Compacted
1.2.19 Additional Borrow
1.2.20 Establishment of Turf
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
SECTION 01 22 00.00 11 Page 1
SECTION 01 22 00.00 11
MEASUREMENT AND PAYMENT
1/10/08
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 Mobilization and Demobilization
a. Payment
Payment will be made for costs associated with mobilization and demobilization, as defined in Contract Clauses PAYMENT FOR MOBILIZATION
AND DEMOBILIZATION.
b. Unit of measure, Job: JA
1.1.2 Environmental Protection
a. Measurement
No measurement will be made for Environmental Protection.
b. Payment
Payment will be made for costs associated with operations necessary for environmental protection as specified in Section 01 57 20.00 11 ENVIRONMENTAL PROTECTION. This price and payment shall be considered full compensation for furnishing all plant, labor, materials, and equipment and for performing all operations necessary for "Environmental Protection." This price and payment does not include those items covered under "Storm Water Pollution Prevention;" however, it does include items incidental thereto. The Contractor shall be responsible for payment of fees associated with environmental permits, application, and/or notices obtained by the Contractor. The Contractor shall be responsible for payment of all fines/fees arriving from violation or non-compliance with Federal, State, Regional, and local laws or regulations. The Government will not provide any compensation for payments of fines/fees, in the event that fines/fees are incurred by the Contractor.
SECTION 01 22 00.00 11 Page 2
c. Unit of measure, Job: JA
1.1.3 Demolition
a. Measurement
No measurement will be made for Demolition.
b. Payment
Payment for costs associated with demolition as specified in Sections 02 41 00 DEMOLITION and 32 25 00.00 11 CULVERT REMOVAL AND INSTALLATION will be made at the contract job price, which shall constitute full compensation for furnishing all materials, equipment and labor, and transporting and disposing of demolition debris as required for the satisfactory demolition of those items as shown on the Task Order drawings. This includes all other operations incidental thereto.
c. Unit of measure, Job: JA
1.1.4 Write/Amend and Maintain Stormwater Pollution Prevention Plan
a. Measurement
No measurement will be made for Write/Amend and Maintain Stormwater Pollution Prevention Plan.
b. Payment
Payment for Write/Amend and Maintain Stormwater Pollution Prevention Plan (SWPPP) will be made at the job price for "Write/Amend and Maintain Stormwater Pollution Prevention Plan", as broken down by the percentages listed under Stormwater Pollution Prevention below. Price and payment shall constitute full compensation for initial Contractor creation and submittal of a SWPPP and application for temporary construction stormwater permit to the appropriate state agency, obtaining SWPPP approval and permit from said agency, continuous updating of the SWPPP and all other operations incidental thereto for the duration of the construction activity, and filing the notice of termination upon reaching final stabilization of the site.
c. Unit of measure, Job: JA
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract progress payments will be based are listed in Section 00 41 00.00 11 - BIDDING SCHEDULE and are described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, meeting safety requirements, tests, and reports, and for performing all work required for each of the unit price items.
1.2.1 Remobilization
a. Measurement
Measurement will be made per mile traveled.
SECTION 01 22 00.00 11 Page 3
b. Payment
For purposes of payment, when a Task Order requires the Contractor to move equipment more than 4 miles from the initial site to other sites within the same area, the Contractor shall be paid for "Remobilization" at the contract unit price per mile to the work area. The distance will be measured in miles from one site to the next in the order of performance directed by the Task Order.
c. Unit of measure, Mile: MI
1.2.2 Storm Water Pollution Prevention (SWPP)
No separate measurement or payment will be made for the work "Storm Water Pollution Prevention" required by Section 01 57 25.00 11 STORM WATER POLLUTION PREVENTION PLAN (SWPPP) except as described in the paragraphs
SILT FENCE, EROSION CONTROL BERM, TEMPORARY ENVIRONMENTAL SEEDING,
CONSTRUCTION EXIT, and VEHICLE WASHDOWN RACK below. Any additional costs associated with Storm Water Pollution Prevention, other than these listed, shall be included in the contract price under Environmental Protection.
The Government will pay all costs for the "Storm Water Pollution Prevention" at the contract unit price for each sub-item listed below as follows:
(1) Sixty percent of the unit price upon completion of the installation.
(2) The remaining 40 percent throughout the contract life, with a maximum of 20 percent being retained until final removal and cleanup of the premises.
The Contracting Officer will require the Contractor to furnish cost data to calculate the exact percentage to be paid upon installation.
1.2.2.1 Silt Fence
a. Measurement
Measurement for Silt Fence satisfactorily placed will be made by the linear foot.
b. Payment
Payment for Silt Fence as specified in Section 01 57 25.00 11 STORM WATER POLLUTION PREVENTION PLAN will be made at the contract unit price per linear foot for "Silt Fence" as broken down by the percentages above. Price and payment shall constitute full compensation for furnishing all plant, labor, materials and equipment, including geotextile fabric, and performing all operations necessary for the placement and maintenance of Silt Fence throughout the contract period, including final dressing and cleanup.
c. Unit of measure, Linear Foot: LF
1.2.2.2 Erosion Control Berm
a. Measurement
SECTION 01 22 00.00 11 Page 4
Measurement for Erosion Control Berm satisfactorily placed will be made by the linear foot.
b. Payment
Payment for Erosion Control Berm as specified in Section 01 57 25.00 11 STORM WATER POLLUTION PREVENTION PLAN will be made at the contract unit price per linear foot for "Erosion Control Berm" as broken down by the percentages above. Price and payment shall constitute full compensation for furnishing all plant, labor, materials and equipment, and performing all operations necessary for the installation and maintenance of the Erosion Control Berm throughout the contract period, including removal, final dressing and cleanup.
c. Unit of measure, Linear Foot: LF
1.2.2.3 Temporary Environmental Seeding
a. Measurement
Measurement for Temporary Environmental Seeding will be per acre.
b. Payment
Payment for Temporary Environmental Seeding as specified in Section 01 57 25.00 11 STORM WATER POLLUTION PREVENTION PLAN and Section 32 92 32.01 11 ESTABLISHMENT OF TURF shall be made at the contract unit price per acre for "Temporary Environmental Seeding" as broken down by the percentages above. Such price and payment shall constitute full compensation for the applicable preparation of ground surfaces;
furnishing and distributing fertilizer and seed; compaction, maintenance (e.g. mowing if necessary); and all other incidental items. This price and payment shall be considered full compensation for furnishing all plant, labor, materials, and equipment and for performing all operations necessary for Temporary Environmental Seeding.
c. Unit of measure, Acre: AC
1.2.2.4 Construction Exit
a. Measurement
Measurement for Construction Exit satisfactorily designed, constructed and maintained by the Contractor will be per each placed.
b. Payment
Payment for the temporary Construction Exit as shown on the task order drawings, including its maintenance and removal, will be made at the contract unit price per each for "Construction Exit" as broken down by the percentages above. Price and payment shall constitute full compensation for furnishing the design and all plant, labor, equipment, mechanical street sweeper and material to complete the work as specified herein and as shown on drawings including final dressing and cleanup.
c. Unit of measure, Each: EA
SECTION 01 22 00.00 11 Page 5
1.2.2.5 Vehicle Washdown Rack
a. Measurement
Measurement for Vehicle Washdown Rack satisfactorily designed, constructed and maintained by the Contractor will be per each placed.
b. Payment
Payment for the temporary vehicle washdown rack as shown on the task order drawings, including its maintenance and removal, will be made at the contract unit price per each for "Vehicle Washdown Rack" as broken down by the percentages above. Price and payment shall constitute full compensation for furnishing the design and all plant, labor, equipment, mechanical street sweeper and material to complete the work as specified herein and as shown on drawings including final dressing and cleanup.
c. Unit of measure, Each: EA
1.2.3 Clearing
a. Measurement
Measurement for Clearing shall be made by the acre, measured along the areas of work for embankment, excavation, and/or any other areas requiring clearing as indicated on the plans. For measurement purposes, the acreage will be computed to the nearest 1/10 of an acre for the satisfactorily completed and accepted work.
b. Payment
Payment for Clearing as specified in this section will be made at the contract unit price per acre for "Clearing," which price and payment shall constitute full compensation for furnishing all plant, labor, material, equipment, and performing all operations necessary for "Clearing" as specified in SECTION 31 11 00.00 11 - CLEARING, GRUBBING, AND STRIPPING. If regrowth of vegetation or trees occurs after Clearing and before placement of embankment, the Contractor is required to clear again prior to embankment construction, no payment will be made for this additional clearing.
c. Unit of measure, Acre: AC.
1.2.4 Grubbing
a. Measurement
Measurement for Grubbing shall be made by the acre, measured along the areas of work for embankment, excavation, and/or any other areas requiring Grubbing as indicated on the plans. For measurement purposes the acreage will be computed to the nearest 1/10 of an acre for the satisfactorily completed and accepted work.
b. Payment
Payment for Grubbing will be made at the contract unit price per acre
SECTION 01 22 00.00 11 Page 6 for "Grubbing," which price and payment shall constitute full compensation for furnishing all plant, labor, material, equipment, and performing all operations necessary for "Grubbing" as specified in SECTION 31 11 00.00 11 - CLEARING, GRUBBING, AND STRIPPING. If regrowth of vegetation or trees occurs after Grubbing and before placement of embankment, the Contractor is required to grub again prior to embankment construction, no payment will be made for this additional grubbing.
c. Unit of measure, Acre: AC
1.2.5 Stripping
a. Measurement
Measurement for Stripping shall be made by the acre, measured along the areas of work for embankment, excavation, and/or any other areas requiring Stripping as indicated on the plans. For measurement purposes the acreage will be computed to the nearest 1/10 of an acre for the satisfactorily completed and accepted work.
b. Payment
Payment for Stripping will be made at the contract unit price per acre for "Stripping," which price and payment shall constitute full compensation for furnishing all plant, labor, material, equipment, and performing all operations necessary for "Stripping" as specified in SECTION 31 11 00.00 11 - CLEARING, GRUBBING, AND STRIPPING. No separate or direct payment will be made for stockpiling and disposition of stripped materials. All costs in connection therewith will be considered as a subsidiary obligation of the Contractor. If regrowth of vegetation or trees occurs after stripping and before placement of embankment, the Contractor is required to strip again prior to embankment construction, no payment will be made for this additional stripping.
c. Unit of measure, Acre: AC
1.2.6 Excavation
a. Measurement
Measurement for Excavation shall be as specified in Section 00 80 00.00 11 SPECIAL CONTRACT REQUIREMENTS, in the paragraph entitled LAYOUT OF WORK. The basis of measurement will be a cross section survey of the area after clearing, grubbing and stripping and a second cross section survey of the same area after the completion of the excavation. The quantity of excavation to be paid for will be computed between the before construction survey ground surface and the theoretical grades and slope lines shown on the contract drawings. No allowance or payment will be made for over-depth excavation or for the removal of any material outside the required theoretical sections unless required by the Contracting Officer. Slides caused by fault of the Contractor or excavation performed for the convenience of the Contractor shall not be measured for payment.
b. Payment
Payment for excavation will be made at the contract unit price per
SECTION 01 22 00.00 11 Page 7 cubic yard for "Excavation," which price includes all excavation of materials of whatever nature encountered as necessary to remove and construct culverts or other items to the lines and grades as shown for excavation on the Contract Drawings. Topsoil stripping will not be measured for payment under this line item, but will be included in "Stripping." Excavation in the borrow pit will not be measured for payment under this line item, but will be included in the line item for the associated fill material. Payment will include all equipment and labor necessary for excavating, transporting and stockpiling of excavated material within the site; final shaping and grading of excavated areas; all stockpiling of materials in segregated form to provide for required zoning of materials in excavation backfilling; and all other incidental operations required to complete the work as specified in Section 31 00 00 EARTHWORK.
c. Unit of measure, Cubic Yard: CY
1.2.7 Geogrid
a. Measurement
Measurement for Geogrid satisfactorily installed shall be by the square yard, measured along the areas of work, as indicated on the Task Order drawings or indicated in the field by the Contracting Officer. No allowance will be made for waste, overlaps, damaged materials, repairs, or materials used for the convenience of the Contractor.
b. Payment
Payment for Geogrid will be made at the contract unit price per square yard for "Geogrid", which price and payment shall constitute full compensation for providing all plant, labor, and equipment, and performing all operations necessary for procuring, transporting, , and the complete and satisfactory installation of the Geogrid, all as specified in SECTION 31 05 21 GEOGRID SOIL REINFORCEMENT and SECTION
31 00 00 EARTHWORK.
c. Unit of measure, Square Yard: SY
1.2.8 Geotextile
a. Measurement
Measurement for Geotextile satisfactorily installed shall be by the square yard, measured along the areas of work, as indicated on the Task Order drawings or indicated in the field by the Contracting Officer.
Allowance will be made for Geotextile in anchor and/or drainage trenches but no allowance will be made for waste, overlaps, damaged materials, repairs, or materials used for the convenience of the Contractor.
b. Payment
Payment for Geotextile will be made at the contract unit price per square yard for "Geotextile", which price and payment shall constitute full compensation for providing all plant, labor, materials, and equipment, and performing all operations necessary for the complete and satisfactory installation of the Geotextile, all as specified in
SECTION 31 05 22 - GEOTEXTILES USED AS FILTERS.
SECTION 01 22 00.00 11 Page 8
c. Unit of measure, Square Yard: SY
1.2.9 Corrugated Metal Pipe (CMP)
a. Measurement
Measurement for Corrugated Metal Pipe shall be made by the linear foot. Such measurement will be made in the field and will be based on the installed pipe length as determined and approved by the Contracting Officer.
b. Payment
Payment for the Corrugated Metal Pipe will be made at the contract unit price per linear foot for "Corrugated Metal Pipe (CMP), XX-inch Dia.", which price and payment shall constitute full compensation for furnishing, assembling and installing the pipe in accordance with the manufacturer's directions and all other operations incidental thereto;
all as specified in SECTION 32 25 00.00 11 CULVERT REMOVAL AND INSTALLATION and as applicable to the culvert. Trench excavation, pipe bedding material, and trench backfill shall all be paid under "Excavation", "Bedding Material", "Embankment, Compacted", respectively.
c. Unit of measure, Linear Foot: LF
1.2.10 Polymer Coated CMP
a. Measurement
Measurement for Polymer Coated CMP shall be made by the linear foot.
Such measurement will be made in the field and will be based on the installed pipe length as determined and approved by the Contracting Officer.
b. Payment
Payment for the Polymer Coated CMP will be made at the contract unit price per linear foot for "Polymer Coated CMP, XX-inch Dia.", which price and payment shall constitute full compensation for furnishing, assembling and installing the pipe in accordance with the manufacturer's directions and all other operations incidental thereto;
all as specified in SECTION 32 25 00.00 11 CULVERT REMOVAL AND INSTALLATION and as applicable to the culvert. Trench excavation, pipe bedding material, and trench backfill shall all be paid under "Excavation", "Bedding Material", "Embankment, Compacted", respectively.
c. Unit of measure, Linear Foot: LF
1.2.11 Flared End Section
a. Measurement
Measurement for Flared End Section satisfactorily installed shall be per each installed.
b. Payment
SECTION 01 22 00.00 11 Page 9
Payment for Flared End Section will be made at the contract unit price per each for "Flared End Section, XX-inch Dia.", which price and payment shall constitute full compensation for furnishing and installing the Flared End Section in accordance with the manufacturer's directions and all other operations incidental thereto; all as specified in SECTION 32 25 00.00 11 CULVERT REMOVAL AND INSTALLATION and as applicable to the culvert. Trench excavation, pipe bedding material, and trench backfill shall all be paid under "Excavation", "Bedding Material", "Embankment, Compacted", respectively.
c. Unit of measure, Each: EA
1.2.12 Flap Gate
a. Measurement
Measurement for Flap Gate satisfactorily installed shall be per each installed.
b. Payment
Payment for the Flap Gate will be made at the contract unit price per each for "Flap Gate, XX-inch Dia.", which price and payment shall constitute full compensation for furnishing and installing the Flap Gate in accordance with the manufacturer's directions; and all other operations incidental thereto; all as specified in SECTION 32 25 00.00 11 CULVERT REMOVAL AND INSTALLATION and as applicable to the culvert.
c. Unit of measure, Each: EA
1.2.13 Stone Procurement
a. Measurement
Measurement for "Riprap, R-90 Procurement", "Riprap, R-200 Procurement", "Riprap, R-400 Procurement", "Riprap, R-650 Procurement", "Bedding Material Procurement", and "Aggregate Surface Course Procurement" shall be by the ton (2,000 pounds). Aggregate shall be measured by weighing each truckload to the nearest 1/10 ton, and the final quantity of the whole sum for Riprap rounded to the nearest whole ton. When Riprap is delivered by truck, the material shall be measured for payment, in the presence of a Government Inspector, unless the Contracting Officer waives such right, by weighing on approved, accurately calibrated scales furnished by and at the expense of the Contractor. Scales shall be of sufficient length to permit simultaneous weighing of all axle loads and shall be inspected, tested and sealed as directed to assure accuracy within 0.5 percent throughout the range of the scales. Scales shall be checked and certified before any material hauling; also, rechecked and re-certified whenever a variance is suspected. Individual weight tickets for each truckload of Riprap shall be furnished to the Government Inspector at the time of delivery. At a minimum, all weight tickets shall have the contract number or project name, the gross weight, the vehicle identity and empty weight, and the net load weight. Scales that produce this information printed on the weight tickets are preferred. Weight certificates furnished by a Public Weighmaster, where available, will be acceptable, when authorized by the Contracting Officer. The Contractor has the option to use certified, and otherwise acceptable, SECTION 01 22 00.00 11 Page 10 scales that are Contractor furnished, quarry/supplier furnished, or commercial/public facilities.
b. Payment
Payment for Stone Procurement will be made at the contract unit price per ton for "Riprap, R-90 Procurement", "Riprap, R-200 Procurement", "Riprap, R-400 Procurement", "Riprap, R-650 Procurement", "Bedding Material Procurement", and "Aggregate Surface Course Procurement", which price and payment shall include all costs of furnishing stone products, as specified in SECTION 35 31 19.00 11 STONE PROTECTION.
c. Unit of measure, Ton: TN
1.2.14 Stone Placement
a. Measurement
No separate measurement for Stone Placement shall be made; instead, measurement for Stone Placement shall be identical to the quanity indicated on the corresponding line of Stone Procurement.
b. Payment
Payment will be made at the contract unit price per ton for "Riprap, R-90 Placement", "Riprap, R-200 Placement", "Riprap, R-400 Placement", "Riprap, R-650 Placement", "Bedding Material Placement", and "Aggregate Surface Course Placement" which price and payment shall include all costs of on-site storage, handling, placing. and maintaining stone products, as specified in SECTION 35 31 19.00 11 STONE PROTECTION.
Excavation for the placement of stone products shall be considered incidental to this item of work.
c. Unit of measure, Ton: TN
1.2.15 Stone Transport
a. Measurement
No separate measurement for Stone Transport shall be made; instead, measurement for Stone Transport shall be identical to the quanity indicated on the corresponding line of Stone Procurement.
b. Payment
Payment will be made at the contract unit price per ton for "Riprap, R-90 Transport", "Riprap, R-200 Transport", "Riprap, R-400 Transport", "Riprap, R-650 Transport", "Bedding Material Transport", and "Aggregate Surface Course Transport" which price and payment shall include all costs of handling and transport from the procurement location to the project site as specified in SECTION 35 31 19.00 11 STONE PROTECTION.
c. Unit of measure, Ton: TN
1.2.16 Grout
a. Measurement
Measurement for Grout will be made for the actual volume of Grout
SECTION 01 22 00.00 11 Page 11 placed as specified in the Task Order drawings or indicated in the field by the Contracting Officer. The total quantity of Grout will be computed from the weights and specific gravities of the component materials used in accordance with the design mix. The necessary tests and computations for determining the volume of grout, except batch weighting of component materials, will be made by the Contractor at his expense. In lieu of measurement as specified hereinbefore, certified volume tickets from the batch plant will be accepted as measurement if grout is mixed at a commercial batch plant and delivered by truck.
b. Payment
Payment for Grout will be made at the contract unit price per cubic yard for "Grout," which price and payment shall constitute full compensation for furnishing all materials, equipment and labor, manufacturing, transporting, placing the Grout and curing as required, and performing all other operations incidental thereto; all as specified in SECTION 35 31 19.00 11 STONE PROTECTION.
c. Unit of measure, Cubic Yard: CY
1.2.17 Embankment, Semi-compacted
a. Measurement
Measurement for Embankment, Semi-compacted shall be as specified in Section 00 80 00.00 11 SPECIAL CONTRACT REQUIREMENTS, in the paragraph entitled QUANTITY SURVEYS. The basis for the measurement will be cross sections of the areas to be filled, overlaid by the theoretical sections of the completed embankment constructed within the specified tolerance. Cross sections of the existing area to be filled shall be taken after clearing, grubbing, stripping, and, where applicable, excavation and after those areas have been graded out so that no depressions are present and the surface is ready to have fill introduced, but prior to commencement of benching operations if required. The cubic yardage to be paid for will be determined by the average end area method between the cross sections of the areas to be filled and the theoretical cross sections of the completed embankment.
Embankment not constructed to specified grade and section including allowable tolerance as indicated on the Contractor's compliance survey will not be accepted. No allowance or payment will be made for embankment material placed outside the required theoretical grade and section. Unless otherwise approved by the Contracting Officer, the Contractor is to use on-site material obtained from the required excavations and/or from the existing levee slide to be repaired for fill material. Any additional fill material required shall be measured and paid for as specified for "Additional Borrow" below. Placement of Embankment, Semi-compacted shall be in accordance with paragraph "Semi-compacted Backill" in SECTION 31 00 00 EARTHWORK.
b. Payment
Payment for Embankment, Semi-compacted will be made at the contract unit price per cubic yard for "Embankment, Semi-compacted," which price and payment shall constitute full compensation for furnishing all equipment and performing all labor for processing, placement and compaction of fill material as specified in SECTION 31 00 00 EARTHWORK and all other operations incidental thereto.
SECTION 01 22 00.00 11 Page 12
c. Unit of measure, Cubic Yard: CY
1.2.18 Embankment, Compacted
a. Measurement
Measurement for Embankment, Compacted shall be as specified in Section 00 80 00.00 11 SPECIAL CONTRACT REQUIREMENTS, in the paragraph entitled QUANTITY SURVEYS. The basis for the measurement will be cross sections of the areas to be filled, overlaid by the theoretical sections of the completed embankment constructed within the specified tolerance. Cross sections of the existing area to be filled shall be taken after clearing, grubbing, stripping, and, where applicable, excavation and after those areas have been graded out so that no depressions are present and the surface is ready to have fill introduced, but prior to commencement of benching operations if required. The cubic yardage to be paid for will be determined by the average end area method between the cross sections of the areas to be filled and the theoretical cross sections of the completed embankment. Embankment not constructed to specified grade and section including allowable tolerance as indicated on the Contractor's compliance survey will not be accepted. No allowance or payment will be made for embankment material placed outside the required theoretical grade and section. Unless otherwise approved by the Contracting Officer, the Contractor is to use on-site material obtained from the required excavations and/or from the existing levee slide to be repaired for fill material. Any additional fill material required shall be measured and paid for as specified for "Additional Borrow" below. Materials used for and placement of Embankment, Compacted shall be in accordance with paragraph "Compacted Backfill", including all subparagraphs, in SECTION 31 00 00 EARTHWORK.
b. Payment
Payment for Embankment, Compacted will be made at the contract unit price per cubic yard for "Embankment, Compacted," which price and payment shall constitute full compensation for furnishing all equipment and performing all labor for processing, placement, testing and compaction of fill material as specified in SECTION 31 00 00 EARTHWORK and all other operations incidental thereto.
c. Unit of measure, Cubic Yard: CY
1.2.19 Additional Borrow
a. Measurement
Measurement for Additional Borrow shall be as specified in Section 00 80 00.00 11 SPECIAL CONTRACT REQUIREMENTS, in the paragraph entitled QUANTITY SURVEYS. The basis for the measurement will be cross sections of the areas remaining to be filled, overlaid by the theoretical sections of the completed embankment constructed within the specified tolerance. Cross sections of the areas remaining to be filled shall be taken after clearing, grubbing, stripping, any required excavation, and placement and compaction of all available on-site material as specified above for the appropriate embankment item, but prior to commencement of benching operations if required. The cubic yardage to be paid for will be determined by the average end area method between the cross sections of the areas remaining to be filled and the theoretical cross sections of the completed embankment. Embankment not constructed to specified
SECTION 01 22 00.00 11 Page 13 grade and section including allowable tolerance as indicated on the Contractor's compliance survey will not be accepted. No allowance or payment will be made for embankment material placed outside the required theoretical grade and section. Unless otherwise approved by the Contracting Officer, the Contractor is to obtain the additional borrow material from a Contractor supplied borrow area. Materials provided shall meet the requirements of the embankment item for which they are being obtained as specified above and in SECTION 31 00 00
EARTHWORK.
b. Payment
Payment for Additional Borrow will be made at the contract unit price per cubic yard for "Additional Borrow," which price and payment shall constitute full compensation for acquiring,testing and getting approval of a borrow source; furnishing all material, equipment and labor; and performing all operations necessary for the excavation and hauling of suitable fill material to the job site as specified in SECTION 31 00 00 EARTHWORK. Placement and compaction of fill material shall not be measured for payment under this item, but shall be included with the appropriate embankment item above. Payment for this item shall include any construction of ramps, unwatering (to be defined as the removal and disposal of storm water, seepage water, and any other water impounded on the ground surface within the construction limits that is identified by the Contracting Officer as an impediment to the construction) and development of borrow area; all operations necessary to establish and maintain haul road trafficability such as but not limited to clearing, grubbing, stripping, scraping, grading, smoothing, compacting, matting or rafting, installation and removal of low water crossings, dust abatement, and any other operations necessary to maintain the road, and, upon project completion, returning the haul road to its before construction state or better; and all other operations incidental thereto.
c. Unit of measure, Cubic Yard: CY
1.2.20 Establishment of Turf
a. Measurement
Measurement for Establishment of Turf shall be by the acre, measured along the slopes of the areas turfed within the right-of-way limits and computed to the nearest 1/10 of an acre for the satisfactorily completed and accepted work. Measurement for Establishment of Turf shall be limited to those areas specified in the Task Order drawings or indicated in the field by the Contracting Officer.
b. Payment
Payment for Establishment of Turf will be made at the contract unit price per acre for "Establishment of Turf," which price and payment shall constitute full compensation for furnishing all plant, labor, equipment, materials, and performing all operations necessary for Establishment of Turf as specified in SECTION 32 92 32.01 11 ESTABLISHMENT OF TURF. No payment for turfing will be made until acceptance by the Contracting Officer or his/her representative.
c. Unit of measure, Acre: AC
SECTION 01 22 00.00 11 Page 14
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --
SECTION 01 22 00.00 11 Page 15
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
11/25/08
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal
1.1.2 Submittal Descriptions (SD)
1.1.3 Approving Authority
1.1.4 Work
1.2 SUBMITTALS
1.3 SUBMITTAL REGISTER
1.4 CONTRACTOR USE OF SUBMITTAL REGISTER
1.5 APPROVING AUTHORITY USE OF SUBMITTAL REGISTER
1.6 COPIES DELIVERED TO THE GOVERNMENT
1.7 PROCEDURES FOR SUBMITTALS
1.7.1 Reviewing, Certifying, Approving Authority
1.7.2 Constraints
1.7.3 Scheduling
1.7.4 Variations
1.7.4.1 Considering Variations
1.7.4.2 Proposing Variations
1.7.4.3 Warranting That Variations Are Compatible
1.7.4.4 Review Schedule Is Modified
1.8 CONTRACTOR'S RESPONSIBILITIES
1.9 FORMAT OF SUBMITTALS
1.9.1 Transmittal Sheet
1.9.2 Identifying Submittals
1.10 SUBMISSION AND CONTROL OF SUBMITTALS
1.10.1 Submittals Required from the Contractor
1.10.1.1 Submittal Procedures and Deviations
1.10.1.2 Control of Submittals
1.10.1.3 O&M Data
1.11 SUBMITTAL CLASSIFICATION
1.11.1 Government Approved
1.11.2 Information Only
1.12 APPROVED SUBMITTALS
1.13 DISAPPROVED SUBMITTALS
1.14 WITHHOLDING OF PAYMENT
1.15 GENERAL
1.16 SUBMITTAL REGISTER
1.17 SCHEDULING
1.18 TRANSMITTAL SHEET (ENG FORM 4025)
1.19 GOVERNMENT APPROVED SUBMITTALS
1.20 INFORMATION ONLY SUBMITTALS
1.21 STAMPS
PART 2 PRODUCTS (Not Used)
SECTION 01 33 00 Page 1
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
11/25/08
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal
Contract Clauses "FAR 52.236-5, Material and Workmanship," paragraph (b) and "FAR 52.236-21, Specifications and Drawings for Construction," paragraphs (d), (e), and (f) apply to all "submittals."
1.1.2 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by SD numbers and titles as follows.
SD-01 Preconstruction Submittals
Certificates of Insurance.
Surety Bonds.
Construction Progress Schedule.
Work Plan.
Submittal Register.
Schedule of Prices.
Accident Prevention Program.
Quality Control Plan.
Environmental Protection Plan.
List of Proposed Subcontractors.
List of Proposed Products.
List of Barges.
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials or equipment for some portion of the work.
SECTION 01 33 00 Page 3
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-05 Design Data
Calculations, mix designs, analyses or other data pertaining to a part of work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accordance with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a supplier, installer or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
SECTION 01 33 00 Page 4
Text of posted operating instructions.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
1.1.3 Approving Authority
Approving authority rests with the Contracting Officer and his/her Authorized Representative(s). Approval actions and correspondence with the Contractor shall be made through the Wynne Area Office or Caruthersville Area Office , as designated in the Task Order.
1.1.4 Work
As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Submittal register.; G
1.3 SUBMITTAL REGISTER
Submit the submittal register at least seven days prior to the prework conference. Verify that all submittals required for the project are listed and add any missing submittals. Complete the following on the register:
Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
1.4 CONTRACTOR USE OF SUBMITTAL REGISTER
Update the following fields.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to Area Engineer.
Column (l) List date of submittal transmission.
SECTION 01 33 00 Page 5
Column (q) List date approval received.
1.5 APPROVING AUTHORITY USE OF SUBMITTAL REGISTER
Update the following fields.
Column (b).
Column (l) List date of submittal receipt.
Column (m) through (p).
Column (q) List date returned to Contractor.
1.6 COPIES DELIVERED TO THE GOVERNMENT
Deliver one copy of submittal register updated by Contractor to Government with each invoice request.
1.7 PROCEDURES FOR SUBMITTALS
1.7.1 Reviewing, Certifying, Approving Authority
The Contractor Quality Control (CQC) organization shall be responsible for reviewing and certifying that submittals are in compliance with contract requirements. Approving authority on submittals ultimately rests with the Contracting Officer, and his/her Authorized Representative(s). Approval of all submittals will be made through the Wynne Area Office or Caruthersville Area Office .
1.7.2 Constraints
a. Submittals listed or specified in this contract shall conform to provisions of this section, unless explicitly stated otherwise.
b. Submittals shall be complete for each definable feature of work;
components of definable feature interrelated as a system shall be submitted at same time.
c. When acceptability of a submittal is dependent on conditions, items, or materials included in separate subsequent submittals, submittal will be returned without review.
d. Approval of a separate material, product, or component does not imply approval of assembly in which item functions.
1.7.3 Scheduling
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential requirements to resubmit.
b. Except as specified otherwise, allow review period, beginning with receipt by approving authority, that includes at least 15 working days for submittals for Contracting Officer's Authorized Representative approval and 20 working days for submittals for Contracting Officer approval. Period of review for submittals with Contracting Officer approval begins when Government receives
SECTION 01 33 00 Page 6 submittal from CQC organization. Period of review for each resubmittal is the same as for initial submittal.
1.7.4 Variations
Variations from contract requirements require Government approval pursuant to contract Clause entitled "FAR 52.236-21, Specifications and Drawings for Construction" and will be considered where advantageous to Government.
1.7.4.1 Considering Variations
Discussion with Wynne Area Office or Caruthersville Area Office prior to submission, will help ensure functional and quality requirements are met and minimize rejections and resubmittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
1.7.4.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. If lower cost is a benefit, also include an estimate of the cost saving. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
1.7.4.3 Warranting That Variations Are Compatible
When delivering a variation for approval, Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.7.4.4 Review Schedule Is Modified
In addition to normal submittal review period, a period of 15 working days will be allowed for consideration by the Government of submittals with variations.
1.8 CONTRACTOR'S RESPONSIBILITIES
a. Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and contract documents.
b. Transmit submittals to the Government in accordance with the approved Submittal Register.