W912EQ-20-B-0008 Amendment 0001.pdf

PDF 155 KB Posted

Attached to
Yazoo Levee Gravel Resurfacing
Solicitation number
W912EQ20B0008
Issued by

About this file

This document includes an amendment to a federal contract solicitation and the original solicitation. The amendment modifies the original solicitation for Yazoo Levee gravel resurfacing between the U.S. Army Corps of Engineers Memphis District and offerors. It excludes resurfacing a segment of levee between mile points 37/05+41 and 37/42+48, as that segment has already been paved with asphalt and does not require gravel surfacing. The estimated value of the work under the original solicitation is between $5 million and $10 million. Offerors must submit bids by August 18, 2020 for the firm-fixed-price contract. The work consists of levee gravel resurfacing and incidental related work from mile point 0/1 to Highway 49, as shown on the plans. This project is set aside for women-owned small businesses. The NAICS code for this requirement is 237990.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912EQ20B0008

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The following have been added by full text:

Amendment 0001

YAZOO LEVEE GRAVEL RESURFACING

DESCRIPTION OF CHANGES

This amendment excludes the segment of levee between MP 37/05+41 and MP 37/42+48 from the resurfacing requirement. It was discovered during one of the site showings that this levee segment has been paved with asphalt and does not require gravel surfacing.

PLANS

1. C-116: CHANGE. Beginning at MP 37/05+41 and ending at MP 37/42+48, reach is not to be resurfaced.

2. G-001: CHANGE. Index of Drawings, resurfacing mileage update.

3. G-002: CHANGE. Typical cross section 17’, Resurfacing Stations updated

SPECIFICATION

1. 00 00 00.00 11 DEPARTMENT OF THE ARMY

a. CHANGE: Location; Mileage updated - 0/1 TO 37/05+41 AND 37/42+48 TO HWY 49.

2. 01 11 00.00 11 SUMMARY OF WORK

a. CHANGE: Project Description; Mileage updated - 0/1 TO 37/05+41 AND 37/42+48 TO HWY 49.

3. 00 41 00.00 11 BIDDING SCHEDULE

a. CHANGE: aggregate Surfacing revised to reflect updated mileage and tonnage.

(End of Summary of Changes)