This is a pre-bid conference presentation for solicitation W912EP25B0011, issued by the US Army Corps of Engineers Jacksonville District for the Fort Pierce Beach Renourishment project in St. Lucie County, Florida. The project involves constructing a beach berm along 5,400 feet of shoreline south of Fort Pierce Inlet between FDEP Range Monuments R-34 and T-39, with beach-compatible sand to be dredged from Capron Shoal located four miles southeast of the project site.

The contract is an unrestricted firm-fixed-price contract with an estimated magnitude of $10-25 million. Key dates include: pre-bid conference on December 31, 2024; site visit on December 30, 2024; ProjNet questions due by January 8, 2025; and bid opening on January 21, 2025 at 2:00 PM EST. The period of performance requires work to commence within 60 days of NTP, with Area B completion by May 15, 2025, Area A completion by May 30, 2025, and full project completion by June 30, 2025. The contractor must self-perform 40% of the work and provide a bid guarantee of 20% of bid price or $3 million, whichever is less. The scope includes environmental species monitoring, sea turtle trawling, turbidity monitoring, beach tilling, quality control, screening, MEC construction support, and vibration monitoring.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Working Today to Build a Better Tomorrow

Pre-Bid Conference

Presented by:

Jacksonville District

December 31, 2024

SOLICITATION NO. W912EP25B0011

FORT PIERCE BEACH RENOURISHMENT,

ST. LUCIE COUNTY, FLORIDA

Thank you for joining, we will begin shortly.

Please mute your microphone.

PRE-BID CONFERENCE: AGENDA

• INTRODUCTION

• PROJECT OVERVIEW

• CONTRACTING OVERVIEW

• OTHER ADMINISTRATIVE ITEMS

• RESOURCES

• CLOSING REMARKS

PROJECT OVERVIEW

PRE-BID CONFERENCE: PROJECT OVERVIEW

SOLICITATION NUMBER: W912EP25B0011

PROJECT TITLE: Fort Pierce Beach Renourishment, St. Lucie County, Florida.

DESCRIPTION OF WORK: Project work includes construction of a beach berm along approximately 5,400 feet of shoreline immediately south of Fort Pierce Inlet between Florida Department of Environmental Protection (FDEP) Range Monuments R-34 and T-39. Beach compatible sand for the project will be dredged from Capron Shoal, located approximately four miles southeast of the project site in state waters. Due to the extensive hardbottom areas located offshore of the fill area, offshore pipeline access to the beach site is prohibited.

Offloading the beach fill will be done inside the South Jetty of Fort Pierce Inlet, as shown on the plans. A staging area and beach access to the beach placement area are located at the end of Seaway Drive and near the south jetty offloading area. Work also includes but is not limited to environmental species monitoring, sea turtle trawling (hopper dredges only), turbidity monitoring, beach tilling, beach fill quality control, screening, MEC construction support, and vibration control and monitoring.

CONTRACTING OVERVIEW

Griselle Gonzalez-Aquino, Contracting Officer

Email: Griselle.Gonzalez@usace.army.mil

Nicole Batista-Cruz, Contract Specialist Email: Nicole.M.Batista-Cruz@usace.army.mil mailto:Griselle.Gonzalez@usace.army.mil mailto:Nicole.M.Batista-Cruz@usace.army.mil

PRE-BID CONFERENCE: ACQUISITION APPROACH

• Solicitation No. W912EP25B0011

• Contracting Method: FAR Part 14 Sealed Bidding - Invitation for Bid (IFB), Unrestricted.

• Type of Contract: Firm-Fixed Price (FFP). (FAR clause 52.216-1)

• Transmission Method: Electronically via Procurement Integrated Enterprise Environment (PIEE). Bids must be received by the Government no later than January 21, 2025, at 1:00 pm (EST). Please see Section 00100 Electronic Bids, for more details.

• Bid Opening: January 21, 2025, at 2:00 pm (EST) via Webex. You must be registered in the system for award management (SAM) to receive an award from this solicitation.

PRE-BID CONFERENCE: GENERAL INFORMATION

• Estimated Magnitude of Construction: $10,000,000.00 - $25,000,000.00.

• Applicable North American Industry Classification System (NAICS): 237990 (Exception), Dredging and Surface Cleanup Activities. The Small Business Size Standard for dredging is $37.0 million.

• Estimated Period of Performance: The Contractor shall be required to (a) commence work under this contract within 60 calendar days after the date the Contractor receives the Notice to Proceed (NTP) and be off the beach no later than 15 May 2025 for Area B and 30 May 2025 for Area A, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 30 June 2025. (FAR clause 52.211-10)

For clarification:

- Area A is the area between the south jetty (pump off location) Florida Department of Environmental Protection (FDEP) Range monument R-34 to R-37 where our contractor will need to be off the beach by 30 May 2025.

- Area B is south of R-37 where all beach fill activities will need be out of that area by 15 May 2025.

PRE-BID CONFERENCE: GENERAL INFORMATION

• Liquidated Damages: $5,231.00 for each calendar day of delay until the work is completed or accepted. (FAR clause 52.211-12)

• Performance of Work by the Contractor: 40% (FAR clause 52.236-1)

• Bid Guarantee: electronic copy of the bid guarantee shall be submitted with the bid. The bid guarantee shall be 20% of bid price or $3,000,000.00, whichever is less. (FAR 52.228-1)

• Payment and Performance Bonds: awardee must submit payment and performance bonds equal to the total bid price within 10 days of contract award. (SF1442 block 12)

SITE VISIT:

• Held on December 30, 2024, at 10:00 am EST.

TECHNICAL INQUIRIES AND QUESTIONS:

• ProjNet closes on January 8, 2025, at 5:00 pm, EST.

• All Inquiries must be submitted via ProjNet for an official answer.

ALL AMENDMENTS MUST BE ACKNOWLEDGED (IF ANY)

PRE-BID CONFERENCE: OTHER ADMINISTRATIVE ITEMS

PRE-BID CONFERENCE: RESOURCES

System for Award Management (SAM):

www.sam.gov

Procurement Integrated Enterprise Environment (PIEE):

https://piee.eb.mil/

ProjNet:

www.projnet.org http://www.sam.gov/ https://piee.eb.mil/ http://www.projnet.org/

PRE-BID CONFERENCE: QUESTIONS

Please submit any questions via ProjNet.

ProjNet closes on January 8, 2025, by 5PM EST.

Solicitation Number is: W912EP25B0011 Bidder Inquiry Key is: I43KKN-4DK7ZC

PRE-BID CONFERENCE: CLOSING REMARKS

Thank you!

����Solicitation No. W912EP25B0011��FORT PIERCE BEACH RENOURISHMENT, �ST. LUCIE COUNTY, FLORIDA����
PRE-Bid CONFERENCE: AGENDA
Slide Number 3
��PRE-bid CONFERENCE: PROJECT OVERVIEW��
Slide Number 5
PRE-bid CONFERENCE: Acquisition APPROACH
PRE-bid CONFERENCE: GENERAL INFORMATION
PRE-bid CONFERENCE: GENERAL INFORMATION
��PRE-bid CONFERENCE: OTHER ADMINISTRATIVE ITEMS��
��PRE-bid CONFERENCE: resources��
PRE-bid CONFERENCE: Questions
�PRE-bid CONFERENCE: CLOSING REMARKS�

File details come from the government source that posted it. Updated .