INDUSTRY DAY.CORALNURSERY.07.23-24.2024.FinalVersion.pdf
PDF 1 MB Posted
- Attached to
- INDUSTRY DAY - PORT EVERGLADES DEEPENING PROJECT, DREDGING ENVIRONMENTAL UPDATES AND CORAL NURSERY NEEDS
- Solicitation number
- W912EP24Z0026
About this file
This document is an industry day agenda and related federal contract opportunity announcement for the Port Everglades Deepening project.
The U.S. Army Corps of Engineers is hosting a two-day industry day event on July 23-24, 2024 to provide an overview of the project, including environmental updates and coral nursery needs. The event will include breakout sessions for industry feedback on topics such as artificial reef and boulder reef creation, coral nursery capabilities, relocation of corals/sponges/octocorals, and outplanting benthic organisms. The government is seeking information to support the project's monitoring and adaptive management plan, particularly from coral reef practitioners with experience in executing, monitoring, and overseeing similar mitigation projects. Registration for the breakout sessions is required by July 16, 2024, and space is limited to 5 representatives per firm. No reimbursement will be provided for costs associated with attending the event or providing feedback.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Industry Day Coral Reef_Contracting Presentation.pdf | ||
| 20240705_PEV-Coral_Industry_Day_SAJ_Qs.docx | DOCX document | |
| Save the Date Port Everglades Industry Day_v1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INDUSTRY DAY AGENDA
Meeting Goals:
a. Update the environmental industry on the status of the project including an overview of the proposed mitigation and the proposed coral reef nursery needs.
b. Obtain feedback from industry in the fields of expertise.
Agenda:
1. Introduction
2. Project Overview
3. Updated Contracting Schedule
4. Environmental and Mitigation Overview
5. Questions
File Name
MEETING GUIDELINES
• Please hold questions until the end of the presentation.
• Additional questions can be sent to the Project mailbox at Porteverglades@usace.army.mil mailto:Porteverglades@usace.army.mil
BREAKOUT SESSIONS SCHEDULE
Tuesday, July 23, 2024 Wednesday, July 24, 2024
0900-1000: Presentation 0800-0900: Breakout Session 8 1000-1100: Breakout Session 1 0900-1000: Breakout Session 9 1100-1200: Breakout Session 2 1000-1100: Breakout Session 10 1200-1300: Lunch 1100-1200: Breakout Session 11 1300-1400: Breakout Session 3 1200-1300: Lunch 1400-1500: Breakout Session 4 1300-1400: Breakout Session 12 1500-1600: Breakout Session 5 1400-1500: Breakout Session 13 1600-1700: Breakout Session 6 1500-1600: Breakout Session 14 1700-1800: Breakout Session 7 1600-1700: Breakout Session 15 1700-1800: Breakout Session 16
PROPOSED UPCOMING CONTRACTS:
DREDGING AND CONSTRUCTION
US Coast Guard Station Reconfiguration Contract award estimate - Fall 2025
Marine Dredging: ~6M cubic yards (CY) dredged from new Federal channel, placed in nearby Ocean Dredged Material Disposal Site (ODMDS)
Contract award estimate - Fall 2028
File Name
Spilllage Zones and Relocation Mitigation Sites Coral Needs Nursery Needs To Outplant Order of Work & Time Frames Project Monitoring: Dredging Project Monitoring: Mitigation Sites Potential Strategies for Coral Nursery Execution
Environmental Update and Coral Needs Topics
8SPILLAGE ZONES & RELOCATION
(CORALS, OCTOCORALS AND SPONGES)
https://usace-my.dps.mil/:p:/g/personal/marie_g_burns_usace_army_mil/EaXulXKIaA1Gm1ngJW_F YTEBtRWFdn1x7r 9keEUY 7R A?e=aIboEM
Monitoring Based Mitigation Area (100% relocation of ESA corals; relocation of needed coral species from the yellow zone)
Monitoring Only
Direct & 100% Functional Loss Mitigation (100% relocation corals 3cm or greater)
Mitigation Sites: 100% Functional Loss and Potential Monitoring
Mitigation NRE: Natural Reef Enhancement:
Relocation, Outplanting and all ESA corals.
Osborn Tire Reef: Tire Removal & NRE sites.
Artificial Reef: Relocation (no ESA) and Outplanting- 25 acres max.
enhancement
Osborn Tire Reef
Artificial Reef Site
CORAL NEEDS
Note: The mitigation for indirect impacts with less than 100% functional loss coral numbers are based on best available information. Future revisions are based on the receipt of the completion of an on-going field survey and the results of the DEP and NMFS Functional Analysis, but MAY be up to 3 million corals.
Draft Final Port Everglades Deepening Project-Coral Habitat Mitigation Implementation Plan (Amended May 2024)
Mitigation Option Area
(ac) USACE Scleractinian Coral Density Requirement (ac-1) Scleractinian Corals Required for Biological
Enhancement*
Mitigation for direct and indirect impacts with 100% functional loss 701,628
Natural Reef Enhancement (57, two-acre sites) 114 4,389 500,386
Tire Removal 27 5,439 146,852
Boulder Reef 5 10,878 54,390
Mitigation for indirect impacts with less than 100% functional loss 638,370
Natural Reef Enhancement (25, two-acre sites) 50 4,065 203,250
Boulder Reef 20 10,878 435,120
Grand Total 1,339,998
NURSERY NEEDS TO OUTPLANT
Coral Species Mix Needed
ORDER OF WORK AND TIME FRAMES
Pre-dredging (est. 2-3 yrs)
Dependent on completion of the Record of Decision* (est. 2025)
During dredging (est. 6 yrs) (est. 2028-2033)
Post-dredging (est. 3-5 yrs) (est. 2034-2039)
Site-selection Coral propagation Coral propagation Construction of artificial reefs Coral outplanting (in phases) at distances >2 km Coral outplanting (in phases) at distances >500 m – 2 km
Expansion of land-based facilities
Natural reef enhancement at distances >2 km
Coral outplanting of disease susceptible species
Creation or expansion of in-situ nurseries
Relocation and mitigation monitoring
Natural reef enhancement at distances >500 m – 2 km
Cleaning or performing remedial actions to prepare natural degraded reefs for relocation
Continue tire removal mitigation activities
Spoil shoal mitigation activities
Relocation of corals, octocorals and sponges
Cleaning and maintenance of mitigation reefs with biological enhancement
Mitigation monitoring
Begin tire removal to allow relocation of organisms
Adaptive management (contingency plans if success criteria is not met)
Cleaning and maintenance
Removal of tires from portions of the Osborn Tire Reef.
Additional site-selection (as needed) Adaptive management (contingency plans if success criteria is not met)
*Note: Completed NEPA, LOA Blasting permit, WQC and BO needed to sign the ROD
PROJECT MONITORING
Dredge Related sedimentation monitoring.
• Purpose: Detect unanticipated indirect impacts.
• Measure Unforeseen Impacts: distribution, spatial extent ,severity (functional degradation / loss), and persistence.
• Before-After Control-Impact (BACI):
design. pre-, during-, and post-construction monitoring of assessment and reference stations
14MITIGATION MONITORING
(CORALS, OCTOCORALS AND SPONGES)
Reference Sites:
Reconnaissance and Characterization Survey
Mitigation Sites Monitoring
• Primary Field Monitoring Team
• Third-Party Monitoring Team
Adaptive Management Plan Rapid Assessment Monitoring https://usace-my.dps.mil/:p:/g/personal/marie_g_burns_usace_army_mil/EaXulXKIaA1Gm1ngJW_F YTEBtRWFdn1x7r 9keEUY 7R A?e=aIboEM
15POTENTIAL STRATEGIES FOR CORAL
NURSERY NEEDS
PORT EVERGLADES DEEPENING PROJECT (PEV)
NURSERY CORALS
GOAL: PRODUCE CORAL NUMBERS & SPECIES MIX FOR PEV MITIGATION
FL Coral Reef Restoration and Recovery Initiative
Clearinghouse: Nursery Capacity & Best Management Practices
NURSERY 4
NURSERY
NURSERY
NURSERY
LARGE NURSERY
USACE
Information Exchange
6/11/2024
1PORT EVERGLADES DEEPENING PROJECT
NURSERY CORALS
GOAL: CORAL NUMBERS & SPECIES MIX FOR PEV MITIGATION
FL Coral Reef Restoration and
Recovery Initiative Clearinghouse: Nursery
Capacity & Best Management Practices
NURSERY 4
NURSERY 3
NURSERY 2
NURSERY 1
LARGE NURSERY/
USACE
Contractor
Information
Exchange
6/11/2024
QUESTIONS
Contacts:
Mr. Steve Meyers, Project Manager Phone: (O) 904-232-3657 © 904-238-4461 Email: Stephen.K.Meyer@usace.army.mil
Ms. Nikki Edelenbos, NEPA Biologist Coastal Navigation Phone:904-232-1157 Email: Dominique.N.Edelenbos@usace.army.mil
Ms. Marie Burns, Navigation Program Environmental Lead Phone: 904-897-5196 Email: marie.g.burns@usace.army.mil
| Slide Number 1 |
| INDUSTRY DAY Agenda |
| Meeting guidelines |
| BREAKOUT SESSIONS SCHEDULE |
| Slide Number 5 |
| PROPOSED UPCOMING Contracts: Dredging and Construction |
| � |
| Spillage Zones & Relocation �(Corals, Octocorals and Sponges) |
| �� |
| cORAL Needs |
| Nursery needs to outplant |
| Order of work and TIME FRAMES |
| Project Monitoring |
| Mitigation Monitoring� (Corals, Octocorals and sponges) |
| Potential Strategies for Coral� nursery needs |
| QUESTIONS |
File details come from the government source that posted it. Updated .