C.04.01-Abstract_W912EP24B0011_Naval Submarine Base Kings Bay Entrance Channel.pdf

PDF 212 KB Posted

Attached to
NAVAL SUBMARINE BASE KINGS BAY, MAINTENANCE DREDGING, ENTRANCE CHANNEL, CAMDEN COUNTY, GEORGIA AND NASSAU COUNTY, FLORIDA
Solicitation number
W912EP24B0011
Issued by

About this file

This document is an Abstract of Offers for Solicitation Number W912EP24B0011, "NAVAL SUBMARINE BASE KINGS BAY, MAINTENANCE DREDGING, ENTRANCE CHANNEL, CAMDEN COUNTY, GEORGIA AND NASSAU COUNTY, FLORIDA".

The solicitation is for maintenance dredging of the Kings Bay Entrance Channel, with the excavated material to be placed at various disposal sites. Incidental work includes turbidity monitoring, environmental species monitoring, vibration monitoring, beach fill quality control, and sea turtle/sturgeon trawling. An Option A for Fort Clinch pre-placement debris removal is also included. The solicitation is issued by the U.S. Army Corps of Engineers, Jacksonville District, and is an unrestricted requirement with a NAICS code of 237990, Dredging and Surface Cleanup Activities. The magnitude of construction is between $10,000,000 and $25,000,000, with a period of performance of 185 calendar days after receipt of the Notice to Proceed. Bids are due on or about August 12, 2024. The Abstract of Offers provides pricing details from multiple bidders for the various line items in the solicitation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NUMBER: W912EP24B0011

USA ENGINEER DISTRICT, JACKSONVILLE

PRUDENTIAL OFFICE BUILDING

701 SAN MARCO BLVD

ATTN: CESAJ-CT

JACKSONVILLE FL 32207-8175

NO. 1 NO. 2 NO. 3 NO. 4 NO. 5

BIDDER: BIDDER: BIDDER: BIDDER: BIDDER:

B. BID SECURITY B. BID SECURITY B. BID SECURITY B. BID SECURITY B. BID SECURITY

(Type & amount) (Type & amount) (Type & amount) (Type & amount) (Type & amount) C. BUSINESS SIZE: C. BUSINESS SIZE: C. BUSINESS SIZE: C. BUSINESS SIZE: C. BUSINESS SIZE:

D. ADDENDA D. ADDENDA D. ADDENDA D. ADDENDA D. ADDENDA

NUMBER OF AMENDMENTS ISSUED: 1 ACKNOWLEDGED: ACKNOWLEDGED: ACKNOWLEDGED: ACKNOWLEDGED: ACKNOWLEDGED:

CLIN NO. DESCRIPTION OF OFFERED ITEM: QUANTITY UNIT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT

BASE

0001 MOBILIZATION AND DEMOBILIZATION 1 JOB 4,820,000.00$ $4,820,000.00 7,250,000.00$ $7,250,000.00 13,250,000.00$ $13,250,000.00 8,850,000.00$ $8,850,000.00 -$ $0.00 -$ $0.00

EXCAVATION, UNCLASSIFIED

CUT-1N STA 17+00 TO STA 45+00; (P/A-NB PLACEMENT)

ESTIMATED QUANTITY (SEE NOTE 2)

0002AA FROM 0 TO 5,000 CUBIC YARDS 5,000 CUBIC YARD 23.60$ $118,000.00 45.00$ $225,000.00 51.00$ $255,000.00 50.00$ $250,000.00 -$ $0.00 -$ $0.00 0002AB FROM 5,001 TO 10,000 CUBIC YARDS 5,000 CUBIC YARD 23.60$ $118,000.00 39.00$ $195,000.00 50.00$ $250,000.00 50.00$ $250,000.00 -$ $0.00 -$ $0.00

EXCAVATION, UNCLASSIFIED

CUT-1N STA 72+00 TO STA 100+00; (P/A-NB PLACEMENT)

ESTIMATED QUANTITY (SEE NOTE 2)

0003AA FROM 0 TO 5,000 CUBIC YARDS 5,000 CUBIC YARD 20.70$ $103,500.00 39.00$ $195,000.00 53.00$ $265,000.00 50.00$ $250,000.00 -$ $0.00 -$ $0.00 0003AB FROM 5,001 TO 10,000 CUBIC YARDS 5,000 CUBIC YARD 20.70$ $103,500.00 32.00$ $160,000.00 52.00$ $260,000.00 50.00$ $250,000.00 -$ $0.00 -$ $0.00

EXCAVATION, UNCLASSIFIED

CUT-1N STA 100+00 TO STA 200+00 (P/A-F PLACEMENT)

ESTIMATED QUANTITY (SEE NOTE 2)

0004AA FROM 0 TO 37,500 CUBIC YARDS 37,500 CUBIC YARD 19.90$ $746,250.00 14.50$ $543,750.00 40.00$ $1,500,000.00 25.00$ $937,500.00 -$ $0.00 -$ $0.00 0004AB FROM 37,501 TO 75,000 CUBIC YARDS 37,500 CUBIC YARD 19.90$ $746,250.00 13.50$ $506,250.00 38.00$ $1,425,000.00 25.00$ $937,500.00 -$ $0.00 -$ $0.00

EXCAVATION, UNCLASSIFIED

CUT-1N STA 200+00 TO STA 230+00; (P/A-N PLACEMENT)

ESTIMATED QUANTITY (SEE NOTE 2)

0005AA FROM 0 TO 27,500 CUBIC YARDS 27,500 CUBIC YARD 11.95$ $328,625.00 22.50$ $618,750.00 17.00$ $467,500.00 12.50$ $343,750.00 -$ $0.00 -$ $0.00 0005AB FROM 27,501 TO 55,000 CUBIC YARDS 27,500 CUBIC YARD 11.95$ $328,625.00 22.00$ $605,000.00 16.50$ $453,750.00 12.50$ $343,750.00 -$ $0.00 -$ $0.00

EXCAVATION, UNCLASSIFIED

CUT-1N STA 230+00 TO STA 340+00; (D/A-O DISPOSAL)

ESTIMATED QUANTITY (SEE NOTE 2)

0006AA FROM 0 TO 280,500 CUBIC YARDS 280,500 CUBIC YARD 9.10$ $2,552,550.00 9.50$ $2,664,750.00 9.40$ $2,636,700.00 6.50$ $1,823,250.00 -$ $0.00 -$ $0.00 0006AB FROM 280,501 TO 561,000 CUBIC YARDS 280,500 CUBIC YARD 9.10$ $2,552,550.00 9.00$ $2,524,500.00 9.40$ $2,636,700.00 8.50$ $2,384,250.00 -$ $0.00 -$ $0.00

EXCAVATION, UNCLASSIFIED

CUT-1N NORTH SETTLING BASIN

STA 119+00 TO STA 227+50; RANGE 1250 TO RANGE 1300

(P/A-NB PLACEMENT) ESTIMATED QUANTITY (SEE NOTE 2)

0007AA FROM 0 TO 57,500 CUBIC YARDS 57,500 CUBIC YARD 15.10$ $868,250.00 12.50$ $718,750.00 43.00$ $2,472,500.00 32.50$ $1,868,750.00 -$ $0.00 -$ $0.00 0007AB FROM 57,501 TO 115,000 CUBIC YARDS 57,500 CUBIC YARD 15.10$ $868,250.00 12.00$ $690,000.00 42.50$ $2,443,750.00 32.50$ $1,868,750.00 -$ $0.00 -$ $0.00

EXCAVATION, UNCLASSIFIED

CUT-1N SOUTH TURNING BASIN

STA 11+00 TO STA 19+00

(P/A-N PLACEMENT) ESTIMATED QUANTITY (SEE NOTE 2)

0008AA FROM 0 TO 10,500 CUBIC YARDS 10,500 CUBIC YARD 11.60$ $121,800.00 15.00$ $157,500.00 24.00$ $252,000.00 15.00$ $157,500.00 -$ $0.00 -$ $0.00 0008AB FROM 10,501 TO 21,000 CUBIC YARDS 10,500 CUBIC YARD 11.60$ $121,800.00 13.50$ $141,750.00 24.00$ $252,000.00 15.00$ $157,500.00 -$ $0.00 -$ $0.00

EXCAVATION, UNCLASSIFIED

RANGE A STA 6+500 TO RANGE A2 STA 12+005.31

RANGE 1000 TO NORTH RANGE VARIES (EXCEPT FULL

CHANNEL BETWEEN STA 7+500 TO 8+500)

(P/A-F PLACEMENT) ESTIMATED QUANTITY (SEE NOTE 2)

0009AA FROM 0 TO 4,500 CUBIC YARDS 4,500 CUBIC YARD 26.40$ $118,800.00 16.00$ $72,000.00 56.00$ $252,000.00 35.00$ $157,500.00 -$ $0.00 -$ $0.00 0009AB FROM 4,501 TO 9,000 CUBIC YARDS 4,500 CUBIC YARD 26.40$ $118,800.00 15.00$ $67,500.00 56.00$ $252,000.00 35.00$ $157,500.00 -$ $0.00 -$ $0.00

EXCAVATION, UNCLASSIFIED

RANGE B STA 12+005.31 TO STA 15+348.53

RANGE 1000 TO RANGE 1250+ (VARIES)

0010AA FROM 0 TO 3,500 CUBIC YARDS 3,500 CUBIC YARD 23.80$ $83,300.00 15.00$ $52,500.00 32.00$ $112,000.00 22.50$ $78,750.00 -$ $0.00 -$ $0.00 0010AB FROM 3,501 TO 7,000 CUBIC YARDS 3,500 CUBIC YARD 23.80$ $83,300.00 14.00$ $49,000.00 31.50$ $110,250.00 22.50$ $78,750.00 -$ $0.00 -$ $0.00

EXCAVATION, UNCLASSIFIED

RANGE C TO D STA 15+348.53 TO STA 15+900 AND

STA 18+500 TO STA 24+700 (INCLUDING WIDENER)

RANGE 1000 TO RANGE VARIES

0011AA FROM 0 TO 25,000 CUBIC YARDS 25,000 CUBIC YARD 12.45$ $311,250.00 15.00$ $375,000.00 17.50$ $437,500.00 18.00$ $450,000.00 -$ $0.00 -$ $0.00 0011AB FROM 25,001 TO 50,000 CUBIC YARDS 25,000 CUBIC YARD 12.45$ $311,250.00 14.00$ $350,000.00 17.50$ $437,500.00 18.00$ $450,000.00 -$ $0.00 -$ $0.00

EXCAVATION, UNCLASSIFIED

RANGE D STA 24+700 TO RANGE E STA 31+000

(P/A-NB PLACEMENT) ESTIMATED QUANTITY (SEE NOTE 2)

0012AA FROM 0 TO 25,000 CUBIC YARDS 25,000 CUBIC YARD 27.80$ $695,000.00 19.50$ $487,500.00 55.00$ $1,375,000.00 45.00$ $1,125,000.00 -$ $0.00 -$ $0.00 0012AB FROM 25,001 TO 50,000 CUBIC YARDS 25,000 CUBIC YARD 27.80$ $695,000.00 18.00$ $450,000.00 55.00$ $1,375,000.00 45.00$ $1,125,000.00 -$ $0.00 -$ $0.00

EXCAVATION, UNCLASSIFIED

RANGE E STA 31+000 TO STA 31+800

(D/A-O DISPOSAL) ESTIMATED QUANTITY (SEE NOTE 2)

0013AA FROM 0 TO 4,000 CUBIC YARDS 4,000 CUBIC YARD 22.60$ $90,400.00 27.50$ $110,000.00 26.00$ $104,000.00 30.00$ $120,000.00 -$ $0.00 -$ $0.00 0013AB FROM 4,001 TO 8,000 CUBIC YARDS 4,000 CUBIC YARD 22.60$ $90,400.00 25.00$ $100,000.00 25.00$ $100,000.00 30.00$ $120,000.00 -$ $0.00 -$ $0.00 0014 ENVIRONMENTAL SPECIES MONITORING 1 JOB 202,500.00$ $202,500.00 150,000.00$ $150,000.00 75,000.00$ $75,000.00 50,000.00$ $50,000.00 -$ $0.00 -$ $0.00 0015 TURBIDITY MONITORING 1 JOB 111,000.00$ $111,000.00 150,000.00$ $150,000.00 170,000.00$ $170,000.00 125,000.00$ $125,000.00 -$ $0.00 -$ $0.00

0016 SEA TURTLE/STURGEON TRAWL SWEEPING AND

RELOCATION

1 JOB 588,000.00$ $588,000.00 750,000.00$ $750,000.00 500,000.00$ $500,000.00 400,000.00$ $400,000.00 -$ $0.00 -$ $0.00

0017 BEACH TILLING AT NORTH BEACH PLACEMENT 4 ACRE 1,500.00$ $5,400.00 650.00$ $2,340.00 825.00$ $2,970.00 650.00$ $2,340.00 -$ $0.00 -$ $0.00

0018 BEACH TILLING AT FORT CLINCH PLACEMENT 6 ACRE 1,500.00$ $8,400.00 650.00$ $3,640.00 825.00$ $4,620.00 650.00$ $3,640.00 -$ $0.00 -$ $0.00

0019 CONSTRUCTION/VIBRATION CONTROLS AND

MONITORING AT NORTH BEACH PLACEMENT AREA (P/A-NB)

1 JOB 78,500.00$ $78,500.00 20,000.00$ $20,000.00 25,000.00$ $25,000.00 20,000.00$ $20,000.00 -$ $0.00 -$ $0.00

0020 CONSTRUCTION/VIBRATION CONTROLS AND

MONITORING AT FORT CLINCH PLACEMENT AREA (P/A-F)

1 JOB 72,450.00$ $72,450.00 20,000.00$ $20,000.00 8,000.00$ $8,000.00 20,000.00$ $20,000.00 -$ $0.00 -$ $0.00

0021 BLENDING OF NONCOMPLIANT MATERIAL 1 ACRE 8,100.00$ $8,100.00 3,000.00$ $3,000.00 1,600.00$ $1,600.00 50,000.00$ $50,000.00 -$ $0.00 -$ $0.00

0022 TRANSPORTATION AND DISPOSAL OF

UNACCEPTABLE MATERIAL - ESTIMATED QUANTITY

200 CUBIC YARD 70.00$ $14,000.00 500.00$ $100,000.00 800.00$ $160,000.00 50.00$ $10,000.00 -$ $0.00 -$ $0.00

0023 SCREENING - ESTIMATED QUANTITY 269,000 CUBIC YARD 1.50$ $403,500.00 2.30$ $618,700.00 1.50$ $403,500.00 4.00$ $1,076,000.00 -$ $0.00 -$ $0.00 0024 MEC CONSTRUCTION SUPPORT 1 JOB 290,500.00$ $290,500.00 90,000.00$ $90,000.00 110,000.00$ $110,000.00 150,000.00$ $150,000.00 -$ $0.00 -$ $0.00

0025 STANDBY TIME

(SEE NOTE 4)

72 HOURS 5,000.00$ $360,000.00 9,000.00$ $648,000.00 11,800.00$ $849,600.00 10,000.00$ $720,000.00 -$ $0.00 -$ $0.00

0026 PARTNERING REGROUP 1 EACH 8,200.00$ $8,200.00 5,000.00$ $5,000.00 2,500.00$ $2,500.00 7,500.00$ $7,500.00 -$ $0.00 -$ $0.00

TOTAL BASE (LINE ITEMS 0001 THROUGH 0026) $19,246,000.00 $21,870,180.00 $35,687,940.00 $27,169,480.00 $0.00 $0.00

OPTION A

0027 FORT CLINCH PRE-PLACEMENT DEBRIS REMOVAL 100 CUBIC YARD 220.00$ $22,000.00 500.00$ $50,000.00 80.00$ $8,000.00 50.00$ $5,000.00 -$ $0.00 -$ $0.00

TOTAL OPTION A (LINE ITEM 0027) $22,000.00 $50,000.00 $8,000.00 $5,000.00 $0.00 $0.00 TOTAL BID (LINE ITEMS 0001 THROUGH 0027) $19,268,000.00 $21,920,180.00 $35,695,940.00 $27,174,480.00 $0.00 $0.00

ABSTRACT OF OFFERS

DATE ISSUED DATE CLOSED

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation: ->

ISSUING OFFICE

July 12, 2024 August 12, 2024

NAVAL SUBMARINE BASE KINGS BAY, MAINTENANCE DREDGING, ENTRANCE

CHANNEL, CAMDEN COUNTY, GEORGIA & NASSAU COUNTY, FLORIDA

Independent Government Estimate

PROJECT TITLE

IGE BIDS (Continued)

Weeks Marine INC.Manson Construction Co. Great Lakes Dredge and Dock

Yes

BIDS BIDS (Continued)

Yes Yes

Yes

Yes

Yes

NAME AND TITLE OF CERTIFYING OFFICIAL:

Griselle Gonzalez-Aquino

Signature

BIDSBIDS (Continued)

Bidders

2024-08-13T10:26:13-0400
GONZALEZAQUINO.GRISELLE.1182038578

File details come from the government source that posted it. Updated .