This is a Request for Proposal issued by the U.S. Army Corps of Engineers Engineering District Jacksonville to replace an existing bridge and widen the adjacent channel via drilled shaft walls. Offers are due on November 29, 2023 for a single firm fixed-price contract valued between $25-100 million with a period of performance of 1,661 calendar days. The project is located in San Juan, Puerto Rico and involves demolishing the FDR Bridge and temporary detour structures, constructing drilled shaft walls approximately 500 feet long and 24-31 feet high tied with a cap beam, and related utility relocations. Offerors must be registered in SAM.gov and the NAICS code is 237990 with a small business size standard of $45 million. Evaluation criteria are technical merit, past performance, small business participation, and price. The solicitation and any amendments will be posted on SAM.gov and the official plans and specifications are on the Corps' website. A small business subcontracting plan is required for large businesses.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
RIO PUERTO NUEVO FLOOD CONTROL PROJECT, SUPPLEMENTAL CONTRACT 2, ROOSEVELT AVENUE BRIDGE REPLACEMENT, SAN JUAN
PUERTO RICO
1. See SF30 Continuation Sheet for Amendment Details.
2. The Proposal Due Date of January 12, 2024 at 2:00pm EST remains the same.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EP23R0003
X 9B. DATED (SEE ITEM 11)
31-Aug-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
10 JAN 2024
CODE
USA ENGINEER DISTRICT, JACKSONVILLE
CONTRACTING DIVISION
701 SAN MARCO BLVD
JACKSONVILLE FL 32207-8175
W912EP 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
x 1
SF-30 CONTINUATION SHEET
Rio Puerto Nuevo Flood Control Project, Supplemental Contract 2, Roosevelt Avenue Bridge Replacement, San Juan, Puerto Rico
W912EP23R0003 1 Amendment 0008
SUMMARY OF CHANGES
1. SPECIFICATIONS:
The text changes have been updated with additions noted by green font and underlined text and deletions noted by red font and line/cross-outs and pertain only to changes made by this amendment.
The entire section is replaced if there is any change. The Section Table of Contents and Line Items and Pricing Schedule are replaced without underlines and cross-outs if there are changes to these documents.
Changes to Volume 1 Specifications:
DELETE Standard Form 1442 and REPLACE with the attached revised Standard Form 1442.
DELETE the Line Items and Pricing Schedule and REPLACE with the attached Line Items and Pricing Schedule.
Changes to Volume 2 Specifications:
No changes to Volume 2.
2. DRAWINGS:
DELETE sheet ID G-005 and REPLACE with the attached Sheet ID G-005.
DELETE sheet ID GC101 and REPLACE with the attached Sheet ID GC101.
(End of Summary of Changes)
RIO PUERTO NUEVO FLOOD CONTROL PROJECT, SUPPLEMENTAL CONTRACT 2, ROOSEVELT AVENUE BRIDGE REPLACEMENT, SAN JUAN, PUERTO RICO
DESCRIPTION: REFER TO SECTION 01 11 00 FOR COMPLETE PROJECT DESCRIPTION
DRAWINGS: SEE DFARS CLAUSE 252.236-7001, SECTION 00700.
MAGNITUDE OF CONSTRUCTION IS BETWEEN $25,000,000 - $100,000,000.00.
THIS SOLICITATION IS UNRESTRICTED. THE NAICS CODE FOR THIS PROJECT IS 237990 AND THE SMALL BUSINESS SIZE STANDARD IS $45 MILLION. YOU MUST BE REGISTERED IN THE SYSTEM FOR AWARD MANAGEMENT (WWW.SAM.GOV) TO RECEIVE AN AWARD FROM THIS SOLICITATION.
IN ACCORDANCE WITH (IAW) FAR CLAUSE 52.236-27, AN ORGANIZED SITE VISIT HAS BEEN SCHEDULED. SEE FAR 52.236-27, ALT I IN SECTION 00100 FOR
DETAILS.
OFFERORS ARE NOTIFIED THAT REAL ESTATE HAS BEEN IS NOT CURRENTLY CLEARED FOR CONSTRUCTION. BUT WILL BE BEFORE PROPOSALS ARE DUE. ONCE REAL STATE CERTIFICATION IS OBTAINED OFFERORS WILL BE NOTIFIED AT LEAST 10 DAYS BEFORE PROPOSALS ARE DUE.
**SEE BLOCK 11 - SEE SECTION 00700, FAR CLAUSE 52. 211-10 FOR PERIOD OF PERFORMANCE.
**PROPOSAL MUST BE SUBMITTED ELECTRONICALLY. SEE SECTION 00100A, PROPOSAL REQUIREMENTS AND SUBMISSION FORMAT, AND PARAGRAPH
ELECTRONICA PROPOSALS IN SECTION 00800 FOR DETAILED INSTRUCTIONS.
A PRE-PROPOSAL CONFERENCE WILL BE HELD ON SEPTEMBER 19, 2023 AT 1:00 PM, AST. FOR ATTENDANCE, UTILIZE THE LINK AND CALL-IN, https:// usace1.webex.com/meet/anelis.i.nazario-castillo; AUDIO TELECONFERENCE: 1-844-800-2712 (US TOLL FREE), 1-669-234-1177 (US TOLL); ACCESS CODE: 1999 39 5620. FOR IN-PERSON ATTENDANCE, CONTACT JORGE L. AYALA BURGOS AT 787-370-4485 ON OR BEFORE SEPTEMBER 15, 2023 AT 2:00 PM, AST.
ANELIS I NAZARIO CASTILLO 904-232-3285
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
31-Aug-2023
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______60 calendar days and complete it w ithin ________1661 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________**SECTION00700
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than__90___ calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
USA ENGINEER DISTRICT, JACKSONVILLE
CONTRACTING DIVISION
701 SAN MARCO BLVD
JACKSONVILLE FL 32207-8175
W912EP
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W912EP23R0003 84
local time __________________ (date).If this is a sealed bid solicitation, offers must be publicly opened at that time.
12 Jan 2024 k3ctcain Cross-Out k3ctcain Cross-Out k3ctcain Cross-Out k3ctcain Cross-Out
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
SECTION 00010A
LINE ITEMS AND PRICING SCHEDULE
SUPPLEMENTAL CONTRACT 2: ROOSEVELT AVENUE BRIDGE REPLACEMENT
RIO PUERTO NUEVO PROJECT, PUERTO RICO
ITEM NO. ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
0001 Mobilization and Demobilization 1 Job $
0002 Erosion and Sediment Control and Turbidity Monitoring 1 Job $
0003 Environmental Species Monitoring 1 Job
0004 Vibration Control and Monitoring 1 Job $
0005 Contracting Officer's Field Office (Fixed Costs) 1 Job $
0006 Contracting Officer's Field Office (Recurring Costs) 57 Month $ $
0007 Partnering Regroups (Estimated Quantity, Note 2) 10 Each $ $
0008 As-Built Drawings & Close Out Submittals 1 Job $
0009 Clearing and Grubbing (Estimated Quantity, Note 2) 1.75 Acre $ $
0010 Demolition 1 Job $
Temporary Bypass Sheet Pile (Estimated Quantity, Note
2) 48,329 Square Feet $ $
Temporary Transverse Sheet Pile C1 and C2 (Estimated
Quanitity, Note 2) 19,275 Square Feet $ $
0013 Transition Sheet Piles (Estimated Quantity, Note 2) 19,372 Square Feet $ $
0014 Tie-Rod Anchors 1 Job $
0015 Steel H-Piling (Estimated Quanitity, Note 2) 486 Vertical Linear Foot $ $
0016 Demonstration Wall 1 Job $
0017 Drilled Shaft Axial Load Test 1 Job $
0018 Drilled Shaft - Type 5B (Estimated Quantity, Note 2) 8,160 Vertical Linear Foot $ $
0019 Drilled Shaft - Type 6B (Estimated Quantity, Note 2) 2,751 Vertical Linear Foot $ $
0020 Drilled Shaft - Type 6C (Estimated Quantity, Note 2) 7,084 Vertical Linear Foot $ $
0021 Drilled Shaft Cap Beam 1 Job $
0022 Jet Grout Seals (Estimated Quantity, Note 2) 2,698 Vertical Linear Foot $ $
0023 Jet Grouting - Ground Improvement 1 Job $
0024 Wall Guardrail (Estimated Quantity, Note 2) 403 Linear Foot $ $
0025 Wall Handrail (Estimated Quantity, Note 2) 598 Linear Foot $ $
0026 Excavation - Channel (Estimated Quantity, Note 2) 39,064 Cubic Yard
0027 Excavation - Embankment (Estimated Quantity, Note 2) 21,789 Cubic Yard
0028 Backfill - Fill #1 (Estimated Quantity, Note 2) 844 Cubic Yard $ $
W912EP23R0003 00010A-1 Amendment 0008
SUPPLEMENTAL CONTRACT 2: ROOSEVELT AVENUE BRIDGE REPLACEMENT
RIO PUERTO NUEVO PROJECT, PUERTO RICO
ITEM NO. ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
0029 Backfill - Fill #2 (Estimated Quantity, Note 2) 5,811 Cubic Yard $ $
Wall Groundwater Drains and Filter (Estimated Quantity, Note 2) 1,001 Linear Foot $ $
Permanent Bridge Abutment Groundwater Drains
(Estimated Quantity, Note 2) 214 Linear Foot $ $
0032 Finish Grading (Estimated Quantity, Note 2) 2,728 Square Yard $ $
0033 Gabion Baskets for Bedding (Estimated Quantity, Note 2) 2,858 Each $ $
0034 Riprap - Class VIII (Estimated Quantity, Note 2) 2,237 Ton $ $
0035 Riprap - Class III (Estimated Quantity, Note 2) 5,990 Ton $ $
0036 18" RCP Headwalls (Estimated Quantity, Note 2) 2 Each $ $
0037 30" RCP Headwalls (Estimated Quantity, Note 2) 2 Each $ $
0038 36" RCP Headwalls (Estimated Quantity, Note 2) 3 Each $ $
0039 54" RCP Headwalls (Estimated Quantity, Note 2) 1 Each $ $
Storm Drainage Piping - 18" RCP (Estimated Quantity, Note 2) 318 Linear Foot $ $
Storm Drainage Piping - 30" RCP (Estimated Quantity, Note 2) 59 Linear Foot $ $
Storm Drainage Piping - 36" RCP (Estimated Quantity, Note 2) 115 Linear Foot $ $
Storm Drainage Piping - 54" RCP (Estimated Quantity, Note 2) 53 Linear Foot $ $
0044 Drop Inlets/Catch Basins (Estimated Quantity, Note 2) 7 Each $ $
0045 Storm Drainage Manholes (Estimated Quantity, Note 2) 11 Each $ $
0046 Stormwater Bypass 1 Job $
0047 Procure, Install, and Remove Detour Bridge 1 Job $
0048 Detour Bridge Roadway Approaches 1 Job $
0049 Detour Bridge Abutment Caps 1 Job $
0050 Drilled Shaft - Middle Pier (Estimated Quantity, Note 2) 463 Vertical Linear Foot $ $
0051 Precast Beams (Estimated Quantity, Note 2) 30 Each $ $
0052 Middle Pier Cap (CIP) 1 Job $
0053 Bridge Slab (CIP) 1 Job $
0054 Bridge Sidewalks (CIP) (Estimated Quantity, Note 2) 334 Square Yard $ $
0055 Single Slope Barrier (CIP) (Estimated Quantity, Note 2) 421 Linear Foot $ $
W912EP23R0003 00010A-2 Amendment 0008
SUPPLEMENTAL CONTRACT 2: ROOSEVELT AVENUE BRIDGE REPLACEMENT
RIO PUERTO NUEVO PROJECT, PUERTO RICO
ITEM NO. ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
0056 Median Barrier (Estimated Quantity, Note 2) 211 Linear Foot $ $
0057 Sidewalk Barrier (Estimated Quantity, Note 2) 421 Linear Foot $ $
0058 Concrete Approach Slab (Estimated Quantity, Note 2) 446 Square Yard $ $
0059 10" DIP Waterline Relocation 1 Job $
0060 30" DIP Waterline Relocation 1 Job $
0061 Traffic Control 1 Job $
0062 Granular Subbase Course (Estimated Quantity, Note 2) 1,079 Square Yard $ $
0063 Aggregate Base Course (Estimated Quantity, Note 2) 4,473 Square Yard $ $
Asphaltic Concrete Pavement (Estimated Quantity, Note
2) 2,819 Ton $ $
0065 Milling Asphalt (Estimated Quantity, Note 2) 4,824 Square Yard $ $
0066 Lane Striping 1 Job $
0067 Permanent Access Road (Estimated Quantity, Note 2) 657 Square Yard $ $
0068 Chain Link Fencing (Estimated Quantity, Note 2) 448 Linear Foot $ $
0069 Ornamental Fencing (Estimated Quantity, Note 2) 359 Linear Foot $ $
0070 Vehicular Gates (Estimated Quantity, Note 2) 2 Each $ $
0071 Sodding (Estimated Quantity, Note 2) 3,244 Square Yard $ $
0072 Seeding (Estimated Quantity, Note 2) 4,358 Square Yard $ $
0073 Tree and Shrub Planting 1 Job $
0074 Restoration 1 Job $
Channel Bypass Overtopping - Dewater Equipment
Standby (Estimated Quantity, Note 2) 39 Month $ $
Channel Bypass Overtopping - Dewater Equipment
Operation (Estimated Quantity, Note 2) 48 Hour $ $
0077 Electrical Relocations (PREPA) 1 Job $
0078 PREPA Electrical Power Charges 1 Job $131,808.00**
0079 Telecommunications Relocations (AT&T/Liberty) 1 Job $
0080 Telecommunications Relocations (Claro) 1 Job $
0081 Telecommunications Relocations (WorldNet) 1 Job $
0082 Lighting Relocations (PRHTA) 1 Job $
0083 Bridge Lighting Charges 1 Job $160,776.00
W912EP23R0003 00010A-3 Amendment 0008
SUPPLEMENTAL CONTRACT 2: ROOSEVELT AVENUE BRIDGE REPLACEMENT
RIO PUERTO NUEVO PROJECT, PUERTO RICO
ITEM NO. ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
Municipal Tax (5.5% of the Subtotal Line Items 0001 through 0083) Job $
TOTAL BASE (LINE ITEMS 0001 THROUGH 0084) $
NOTES:
(1) Proposal must price all line items. See Section 00 10 00 "Instructions to Offerors."
(2) Quantities shown are estimated; actual quantities may vary.
See Clause 52.211-18 "Variation in Estimated Quantity" of Section 00700 contract clauses.
** Estimated cost from utility provider
W912EP23R0003 00010A-4 Amendment 0008
S O
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N M
A R
K
S
IZ
E
S U
B M
IT
T E
D B
Y
D A
T E
C O
N T
R A
C T N
O
C H
E C
K E
D B
Y
D R
A W
N B
Y
IS
S
U E D
A T
E
SHEET ID
A
B
C
D
E
F
G
1 98765432
®of Engineers
US Army Corps
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
A N
S I
D
J A
C K
S O
N V
IL
L E D
IS
T R
IC
T
S
A N M
A R
C O B
L V
D
J A
C K
S O
N V
IL
L E F
L
A R
C A
D
IS
N
C A
U S
E W
A Y B
L V
D
M E
T A
IR
IE
L
A
S U
IT
E
S A
N J
U A
N P
U E
R T
O R
IC
O
R
IO
P
U E
R T
O N
U E
V O P
R O J E
C T
R O
O S
E V
E L T A
V E
N U
E B
R
ID
G E R
E P
L A
C E
M E
N T
S U
P P
L E
M E
N T
A L C
O N
T R
A C
T
D E
C E
M B
E R
G E
N E
R A
L N
O T
E S
G-005
C
R A
Y M
O N
D
G
K E
L L E
R
A L
O V
E
GENERAL NOTES:
STRUCTURAL GENERAL NOTES
SEE SHEET S-001.1.
APPROVAL DATE BY PRHTA
MARCH 13, 2020LANE WIDTH
VERTICAL ALIGNMENT
LATERAL OFFSET TO OBSTRUCTION
SIDEWALK WIDTH
DESIGN EXCEPTION
10 FT (3.05 m)
6 FT (1.83 m)
0.3%
GEOMETRIC AND BRIDGE CRITERIA
WATER UTILITY GENERAL NOTES
SEE SHEET CU001 FOR GENERAL NOTES AND UTILITY CONTACT INFORMATION.1.
S
G A
IT
A N
DESIGNATION PROJECT", DATED AUGUST 23, 2019.
& MAPPING REPORT "RE: SUS SECOND PART: UTILITY EXCAVATION AT RIO PUERTO NUEVO
TEST HOLE INFORMATION PROVIDED ON THE V SHEET SERIES IS FROM RLDA SURVEYING 5.
SHEETS (R SHEET SERIES) MAY SPECIFY ANOTHER DATUM OR MAY BE UNKNOWN.
(NAD83 NA2011) EPOCH 2010.00 ADJUSTMENT IN US SURVEY FEET. THE REFERENCE
THE U.S. VIRGIN ISLAND, AND ARE REFERENCED TO THE NORTH AMERICAN DATUM OF 1983
PLANE COORDINATES ARE BASED ON THE LAMBERT PROJECTION FOR PUERTO RICO AND 4.
UNKNOWN OR SPECIFIED ON THE REFERENCE SHEET.
02), EXCEPT REFERENCE SHEETS (R SHEET SERIES), ON WHICH OTHER DATUMS ARE
ALL ELEVATIONS REFER TO THE NATIONAL PUERTO RICO VERTICAL DATUM OF 2002 (PRVD 3.
OTHERWISE INDICATED.
DISTANCES AND ELEVATIONS ARE SHOWN IN US SURVEY FEET EXCEPT WHERE 2.
THE V SHEET SERIES, LABELED AS "TEST HOLE".
ADDITIONAL INFORMATION DESCRIBED IN SURVEY NOTE 5 HAS BEEN INTEGRATED ONTO
SURVEY). SIGNED AND SEALED SURVEY CAN BE FOUND ON FILE WITH USACE-SAJ. THE
CONTRACT NO: W912EP19D002 (TOPOGRAPHIC, HYDROGRAPHIC, AND BOUNDARY
PERIOD OF MARCH 8, 2019 TO JULY 11, 2019, AS PART OF SURVEY NO. 18-230 AND
SURVEY INFORMATION WAS OBTAINED BY RLDA SURVEY AND MAPPING DURING THE 1.
SURVEY NOTES
CONSTRUCTION SEQUENCING NOTES
SEE E, ES, AND ET SHEET SERIES FOR ELECTRICAL CONSTRUCTION SEQUENCING.4.
SEE SHEET CU050 FOR WATER UTILITY CONSTRUCTION SEQUENCING.3.
SEE CG SHEET SERIES FOR CHANNEL EXCAVATION SEQUENCING.2.
SEE SHEETS GC101 TO GC104 FOR GENERAL CONSTRUCTION SEQUENCING.1.
PAVING, GRADING, AND EROSION NOTES
THE AFFECTED AREA USING SPRINKLING, IRRIGATION, OR OTHER ACCEPTABLE METHODS.
IF WIND EROSION BECOMES SIGNIFICANT DURING CONSTRUCTION, THE CONTRACTOR SHALL STABILIZE 3.
AREAS WHERE CONSTRUCTION RELATED TRAFFIC WILL ENTER AND EXIT THE SITE.
THE CONTRACTOR SHALL PLACE STRAW, MULCH, OR OTHER SUITABLE MATERIAL ON THE GROUND IN
ADJACENT PROPERTY, STREETS, STORM SEWERS, WATERWAYS, AND EXISTING WETLANDS. IN ADDITION, CONTRACTOR SHALL PROVIDE EROSION CONTROL/SEDIMENTATION BARRIER TO PREVENT SILTATION OF 2.
BETWEEN PAVEMENT SECTIONS. SEE DETAIL B4 ON SHEET CF502.
PAVEMENT MEETS EXISTING PAVEMENT FOR THE PURPOSE OF PROVIDING A SMOOTH TRANSITION
CONTRACTOR SHALL SAW CUT, TRIM, TACK, AND MATCH EXISTING PAVEMENT AT LOCATIONS WHERE NEW 1.
PRHTA DESIGN EXCEPTIONS
22 13 VIBRATION AND MONITORING REQUIREMENTS FOR EXISTING STRUCTURES.
SHEET PILE AND DRILLED SHAFT INSTALLATION SHALL CONFORM WITH SPECIFICATION 02 3.
PROJECT SITES.
THE SPECIFICATIONS TO UNDERSTAND THE SUBSURFACE CONDITIONS AT THE RELEVANT
DRAWINGS AND OTHER INFORMATION IN THE GEOTECHNICAL DATA REPORT INCLUDED IN
THE CONTRACTOR SHALL REVIEW ALL THE BORING LOGS PROVIDED ON THE CONTRACT 2.
SPECIFICATIONS.
THE PROJECT'S GEOTECHNICAL DATA REPORT IS INCLUDED IN SECTION 00 31 32 OF THE 1.
GEOTECHNICAL NOTES:
MAINTENANCE OF TRAFFIC PLAN
SEE THE MAINTENANCE OF TRAFFIC PLANS ON SHEETS CP119 TO CP125 FOR CONSTRUCTION ACCESS. 10.
METROPISTAS TELEPHONE NUMBER IS 787-474-5999.
ADDRESS IS: CITY VIEW PLAZA 500, TORRE 1, CARRETERA #165 NUM. 48, GUAYNABO, PR, 00968.
CLOSURE TO JOSE DE DEIGO EXPRESSWAY AT LEAST 48 HOURS IN ADVANCE. METROPISTAS PHYSICAL
THE CONTRACTOR SHALL INFORM METROPISTAS TRAFFIC CONTROL CENTER OF ANY POTENTIAL LANE 9.
IF NIGHT-TIME WORK IS CONDUCTED, IN ACCORDANCE WITH PRHTA AND MUTCD STANDARD.
THE CONTRACTOR SHALL INSTALL NIGHT-TIME LIGHTING FOR WORK ZONE ON ALL TRUCK ENTRANCES/EXITS 8.
PER THE CORRESPONDING PUERTO RICO HIGHWAY AUTHORITY STANDARD DRAWINGS.
TEMPORARY REFLECTORS SHALL BE INSTALLED ON ALL TEMPORARY CONCRETE BARRIER SECTIONS AS 7.
EXPRESSWAY.
PER DETAIL B8 ON SHEET CF502, SHALL BE USED AT EACH TRUCK ENTRANCE/EXIT AT JOSE DE DIEGO
A STABILIZED TRUCK ACCESS CONSISTING OF A PAD OF AGGREGATE UNDERLAIN WITH FIBER CLOTH, AS 6.
AND RETROREFLECTIVITY.
ALL TEMPORARY TRAFFIC CONTROL DEVICES SHALL BE PER US DOT MUTCD STANDARDS FOR COLOR, SIZE 5.
REMOVE ANY VEGETATION OBSTRUCTING THE CONSTRUCTION ACCESS.4.
TEMPORARY WORK AREAS ARE SHOWN ON REMOVAL PLANS.
REMOVALS OF ANY ITEM (FENCE, POLE LIGHT, ETC.) NECESSARY TO PROVIDE VEHICULAR ACCESS TO 3.
ADD A TYPE III BARRICADE IN FRONT OF DRUMS WITH A "CONSTRUCTION ACCESS ONLY" SIGN .
PLACE DRUMS AT 10' CENTER TO CENTER ACROSS ANY LOCATION THAT NEEDS TO BE BARRICADED. ALSO, 2.
ATTENDANT MAY BE NEEDED TO MOVE BARRICADES FOR CONSTRUCTION VEHICLE ACCESS.1.
CONTROL AND EMBANKMENT PROTECTION IS PROVIDED AND APPROVED.
CLEARING AND GRUBBING OF IN-CHANNEL SLOPES IS NOT PERMITTED UNLESS EROSION 8.
TWO EXISTING BRIDGES AND DETOUR BRIDGE FREE OF DEBRIS AND/OR VEGETATION.
CONTRACTOR SHALL MAINTAIN EXISTING PIERS, ABUTMENTS, AND ALL AREAS UNDER THE 7.
PILES. SEE GC AND CO SHEET SERIES.
0.00 BEFORE BEGINNING CONSTRUCTION ON THE LEFT CHANNEL WALL BYPASS SHEET
CONTRACTOR SHALL COMPLETE RIGHT CHANNEL SHEET PILE R3 AND EXCAVATE TO EL. 6.
SPECIFICATION 00 33 50 FOR AVAILABLE STAGE INFORMATION.
ADJUSTED WITH THE PRIOR APPROVAL FROM THE CONTRACTING OFFICER. SEE
BYPASS RESTRICTIONS FOR WORKING IN THE CHANNEL DURING DRY PERIODS MAY BE 5.
EXCAVATION REQUIREMENTS IN SPECIFICATION 31 00 00 AND CG SHEET SERIES.
CONTRACTOR SHALL NOT OBSTRUCT FLOW AREA WHEN WORKING IN-CHANNEL. SEE 4.
(NGVD 29). SEE SPECIFICATION 00 33 50 SECTION 1.0.
NUEVO. GAGE HEIGHT REFERS TO THE NATIONAL GEODETIC VERTICAL DATUM OF 1929
ANALYSIS OF THE PERIOD OF RECORD FLOW AT USGS GAGE 50049100 IN THE RIO PUERTO
DESIGNED TO MAINTAIN FLOWS UP TO A 2.5-YEAR STORM EVENT BASED ON A FREQUENCY
THE BYPASS PROVISIONS SHOWN ON THE CO300 AND CO500 SHEET SERIES ARE 3.
SITE TO EL. 14.00 AT ALL TIMES, AS SPECIFIED ON THE CO SHEET SERIES.
CONTRACTOR SHALL MEET CHANNEL BYPASS FLOW REQUIREMENTS AND PROTECT WORK 2.
OR LARGER, AT ALL TIMES TO PROVIDE THE REQUIRED CHANNEL CONVEYANCE CAPACITY.
CONTRACTOR SHALL MAINTAIN THE CHANNEL DIMENSIONS OF THE BYPASS AS SHOWN, 1.
CHANNEL BYPASS REQUIREMENTS
4.82 FT - 7.22 FT (1.47 m - 2.2 m)
DESIGN EXCEPTION: YES
DESIGN LOAD FOR STRUCTURES: SEE SHEET S-001
MAXIMUM SUPERELEVATION: 6%
MINIMUM CURVE RADIUS (METERS): 150
TYPE OF TERRAIN: LEVEL
MAXIMUM GRADE (%): 7%
DESIGN SPEED (V): 40 MPH
PERCENT OF TRUCK (T): 7%
DIRECTIONAL DISTRIBUTION (D): 50%
DESIGN HOURLY VOLUME (DHV): 2,992
AVERAGE DAILY TRAFFIC (2045): 37,400
AVERAGE DAILY TRAFFIC (2019): 28,600
CONTROL OF ACCESS: NONE
FUNCTIONAL HIGHWAY CLASSIFICATION (PRHTA): AVENUE
FUNCTIONAL HIGHWAY CLASSIFICATION (AASHTO): PRINCIPAL ARTERIAL
DESIGN CLASS CODE: U-6
STRUCTURES DESIGN CODE: U-6
HIGHWAY DESIGN CODE: U-6
ROADWAY DESIGN CRITERIA
ELECTRICAL GENERAL NOTES
OUTAGES DURING THE HURRICANE AND RAINY SEASON FROM 1 AUGUST TO 30 SEPTEMBER
OUTAGES FOR TRANSMISSION LINES MUST OCCUR BETWEEN 1 NOVEMBER TO 31 JULY, AVOIDING
TRANSMISSION AND/OR DISTRIBUTION LINES (TEMPORARY OR PERMANENT)
CONTRACTOR SHALL NOTIFY LUMA AT LEAST 6 WEEKS IN ADVANCE OF ANY RELOCATION OF
OUTAGE TIMES MUST AVOID PEAK HOURS 5:00 PM TO 11:00 PM FROM MONDAY THRU FRIDAY
DAYS
OUTAGE TIME SHALL NOT EXCEED 8 HOURS IN A DAY AND CANNOT BE MORE THAN 3 CONSECUTIVE
CONTRACTOR SHALL COMPLY WITH THE FOLLOWING REQUIREMENTS:2.
SEE SHEET E-001 FOR GENERAL NOTES AND UTILITY CONTACT INFORMATION.1.
BOUNDARY MAPS IN THE PLAN DRAWINGS, AND TO BE PROVIDED BY USACE.
REPRESENTS THE ACQUISITION DRAWINGS, WHICH ARE ALSO REFERRED TO AS THE
SHEET CS101 IS TITLED "RESERVED" ON THE INDEX OF SHEETS G-002. SHEET CS101 14.
ECOMAXX GAS STATION.
CONTRACTING OFFICER FOR THE FINAL PLAN AND CONSTRUCTION TIMELINE OF THE
SHOWN FOR REFERENCE ONLY. THE CONTRACTOR SHALL COORDINATE WITH THE
SHEET R-163 FEATURES A PRELIMINARY PLAN FOR THE ECOMAXX GAS STATION AND IS 13.
GOVERNMENT.
AND ITS CORRESPONDING FUSION (LABOR AND MATERIAL) AT NO COST TO THE
PULLING COPPER WIRE (LABOR AND MATERIAL) OR PUSH/PULL/BLOW OF FIBER CABLE
TELECOMMUNICATIONS OWNERS ARE RESPONSIBLE FOR THE COST INCURRED DUE TO 12.
DISTINGUISH BETWEEN BANKS OF THE RIO PIEDRAS.
BANK OF THE RIVER. BRIDGE FEATURES UTILIZE THE TERMS "EAST" AND "WEST" TO
BANK OF THE RIVER, AND THE RIGHT CHANNEL WALL SHALL BE LOCATED ON THE EAST
RIGHT CHANNEL WALLS. THE LEFT CHANNEL WALL SHALL BE LOCATED ON THE WEST
THE PLANS AND SPECIFICATIONS REFER TO THE DRILLED SHAFT WALLS AS LEFT AND 11.
HAZARDOUS MATERIALS.
SPECIFICATION SECTION 01 57 20 FOR ADDITIONAL INFORMATION REGARDING HANDLING
PRODUCTS ARE FOUND AND STOP WORKING IN AND AROUND THAT VICINITY. REFER TO
SHALL NOTIFY THE CONTRACTING OFFICER IMMEDIATELY IF ANY PETROLEUM-BASED
EXCAVATION TO THE EXTENTS SHOWN ON THE CONTRACT DRAWINGS. THE CONTRACTOR
FOUND IN APPENDIX D OF THE SPECIFICATIONS. THE CONTRACTOR SHALL LIMIT
SAN JUAN, PR," PREPARED BY CRE, INC. AND SUBMITTED TO USACE-SAJ. REPORT CAN BE
FINAL REPORT ECOMAXX GAS STATION AND SURROUNDINGS, ROOSEVELT AVENUE #950,
BEEN IDENTIFIED IN THE REPORT TITLED: "ENVIRONMENTAL SITE ASSESSMENT ACTIVITIES
AREAS OF PETROLEUM-BASED PRODUCTS WITHIN THE LIMITS OF CONSTRUCTION HAVE 10.
BEGINNING OF WORK.
SPECIFICATIONS AND SUBMITTED TO THE CONTRACTING OFFICER PRIOR TO THE
AREA WITHIN THE CONSTRUCTION LIMITS SHALL BE TAKEN IN ACCORDANCE WITH THE
CONDITION, IF NOT SPECIFIED. A PHOTOGRAPHIC AND VIDEO SURVEY OF THE PROJECT
ACCORDANCE WITH PLANS AND SPECIFICATIONS TO DOCUMENTED PRE-CONSTRUCTION
ALL DISTURBED AREAS WITHIN THE CONSTRUCTION LIMITS SHALL BE RESTORED IN 9.
ADDITIONAL INFORMATION REGARDING WEATHER CONDITIONS.
INUNDATED DUE TO RAIN EVENTS. REFER TO SPECIFICATION SECTION 00 33 50 FOR
MANAGEMENT BEHIND BYPASS SHORING, AND UNWATERING WORKING PLATFORM AREAS
THIS INCLUDES, BUT IS NOT LIMITED TO, DEWATERING EXCAVATIONS, SURFACE WATER
CONSTRUCTION OPERATIONS TO FACILITATE UNINTERRUPTED WORKING CONDITIONS.
THE CONTRACTOR IS RESPONSIBLE FOR STORMWATER MANAGEMENT DURING 8.
BY THE CONTRACTOR.
BELOW GROUND FACILITIES THAT MAY OCCUR AS A RESULT OF THE WORK PERFORMED
THE CONTRACTOR IS RESPONSIBLE FOR REPAIRING ANY DAMAGE TO EXISTING ABOVE OR 7.
PROTECTION OF NEARBY STRUCTURES.
MONITORING REQUIRING PRE-CONSTRUCTION SURVEY AND DOCUMENTATIONS FOR
CONTRACTOR SHALL COMPLY WITH SPECIFICATION 02 22 13 VIBRATION AND NOISE
NOISE, AND/OR VIBRATIONS AS INDICATED ON APPROVED MONITORING PLANS.
SET UP OBSERVATION POINTS AND REFERENCE POINTS TO MONITOR ANY MOVEMENTS,
STRUCTURES, UTILITIES, ROADWAYS AND OTHER FACILITIES. THE CONTRACTOR SHALL
THE CONTRACTOR SHALL CONTROL OPERATIONS TO PREVENT DAMAGE TO EXISTING 6.
THE CONSTRUCTION PERIOD.
MAINTAINED AND MODIFIED AS REQUIRED BY CONSTRUCTION PROGRESS THROUGHOUT
TRAPS SUCH AS SECURED HAY BALES, SOD, STONE, SILT FENCE, ETC., WHICH SHALL BE
SEWER INLETS IN THE VICINITY OF THE PROJECT SHALL BE PROTECTED BY SEDIMENT
PROTECTION OF EXISTING STORM SEWER SYSTEMS: DURING CONSTRUCTION, ALL STORM 5.
VARIOUS UTILITY COMPANIES.
OFFICER REGARDING ANY POTENTIAL DELAYS OR INCONVENIENCES CAUSED BY THE
UTILITY COMPANIES DURING RELOCATION OPERATIONS AND SHALL NOTIFY CONTRACTING
EXCAVACIONES Y DEMOLICION". THE CONTRACTOR SHALL COORDINATE WITH THE
WHETHER SHOWN ON THE CONTRACT DRAWINGS OR MARKED BY THE "CENTRO DE
CONTRACTOR SHALL EXERCISE CAUTION WHEN CROSSING ANY UNDERGROUND UTILITY,
COMPLIANCE WITH THE "CENTRO DE EXCAVACIONES Y DEMOLICION" GUIDELINES. THE
UNDERGROUND UTILITIES IN ADVANCE OF DEMOLITION AND CONSTRUCTION, AND IN
EXCAVACIONES Y DEMOLICION" FOR THE MARKING OF THE LOCATIONS OF EXISTING
CAUTION IN AREAS OF BURIED UTILITIES AND SHALL COORDINATE WITH THE "CENTRO DE
OF ANY CONSTRUCTION ACTIVITY. THE CONTRACTOR SHALL EXERCISE EXTREME
THE GOVERNMENT ASSUMES NO RESPONSIBILITY FOR ACCURACY PRIOR TO THE START
STRUCTURES AND OTHER FEATURES AFFECTING THIS WORK PRIOR TO CONSTRUCTION.
VERIFY THE LOCATIONS, ELEVATIONS, AND DIMENSIONS OF ALL EXISTING UTILITIES,
THE TIME OF PREPARATION OF THESE CONTRACT DRAWINGS. THE CONTRACTOR SHALL
OTHER FEATURES ARE SHOWN ACCORDING TO THE BEST INFORMATION AVAILABLE AT
LOCATIONS, ELEVATIONS, AND DIMENSIONS OF EXISTING UTILITIES, STRUCTURES, AND 4.
IN THE AFFECTED AREA.
CONTRACTING OFFICER IN WRITING OF ANY CONFLICT BEFORE PERFORMING ANY WORK
DISCREPANCIES PRIOR TO CONSTRUCTION. THE CONTRACTOR SHALL NOTIFY THE
THE CONTRACTOR SHALL CHECK THE CONTRACT DRAWINGS FOR CONFLICTS AND 3.
LOCAL REGULATIONS AND ORDINANCES.
ALL WORK PERFORMED SHALL COMPLY WITH THE FEDERAL, COMMONWEALTH, AND 2.
CONTRACT DRAWINGS.
TRANSITIONS, GRADING, UTILITY RELOCATIONS, AND SITE FEATURES AS SHOWN ON THE
WORK BEYOND THE CHANNEL IMPROVEMENT LIMITS INCLUDES, BUT NOT LIMITED TO,
PERMANENT CONSTRUCTION FEATURES AS PART OF THE RIO PUERTO NUEVO PROGRAM.
WORK WITHIN THE CHANNEL IMPROVEMENT LIMITS (STA. 118+50 TO STA. 123+50) REFLECT 1.
DEMOLITION, CLEARING, AND SITE PREPARATION NOTES
OTHERWISE, IS OUTDATED AND SHALL BE DISREGARDED.
COMPLIANCE WITH LOCAL REGULATIONS. GENERAL SHEET NOTE 11 ON SHEET CD101, WHICH STATES
THE CONTRACTOR SHALL BE RESPONSIBLE TO REMOVE THE ECOMAXX SIGN AND DISPOSE OF IT IN 7.
BURNING OF DEBRIS IS NOT PERMITTED.6.
SEE CHANNEL BYPASS REQUIREMENT NOTE 8 FOR CLEARING AND GRUBBING OF IN-CHANNEL SLOPES.5.
IN A NEAT AND UNOBSTRUCTED CONDITION, BOTH DURING AND UPON COMPLETION OF WORK.
FEDERAL, COMMONWEALTH, AND LOCAL REGULATIONS. THE CONTRACTOR SHALL MAINTAIN ALL AREAS
THE CONTRACTOR AND SHALL BE PROMPTLY REMOVED FROM THE SITE IN ACCORDANCE WITH
ALL CONSTRUCTION WASTE MATERIALS AND DEMOLITION DEBRIS SHALL BECOME THE PROPERTY OF 4.
LAWS AND REGULATIONS GOVERNING DISPOSAL SITES IN PUERTO RICO.
APPROVED FACILITY. CONTRACTOR SHALL COMPLY WITH ALL FEDERAL, COMMONWEALTH AND LOCAL
DISPOSAL OF DEBRIS FROM CLEARING, GRUBBING, AND DEMOLITION SHALL BE DEPOSITED AT AN 3.
CONSTRUCTION.
SPECIFIED LANDSCAPE MATERIAL AS SHOWN ON LP SHEET SERIES IMMEDIATELY FOLLOWING
CONSTRUCTION OR DEMOLITION. DISTURBED AREAS SHALL BE SEEDED, MULCHED, OR PLANTED WITH
THE CONTRACTOR SHALL CLEAR AND GRUB ONLY THOSE PORTIONS OF THE SITE NECESSARY FOR 2.
HAND IS PERMITTED WITHIN THE CANOPY LINE OF TREES THAT ARE TO REMAIN.
BE REMOVED WITHOUT WRITTEN APPROVAL FROM THE CONTRACTING OFFICER. ONLY GRADING BY
RESPONSIBILITY TO MAINTAIN THESE TREES IN GOOD CONDITION. NO TREES SHOWN TO REMAIN SHALL
REMAIN" SHALL BE PROTECTED PER DETAIL A1 SHEET LP103. IT SHALL BE THE CONTRACTOR'S
PRIOR TO ANY SITE CLEARING, ALL TREES SHOWN ON THE CONTRACT DRAWINGS AS BEING "TO 1.
THE OWNER, ECOMAXX, SHALL BE RESPONSIBLE TO REMOVE THE ECOMAXX SIGN AND DISPOSE OF
IT IN COMPLIANCE WITH LOCAL REGULATIONS.
U
P D
A T
E D
D E
M O
L
IT
IO
N
C
L E
A R
IN
G
A
N D
S
IT
E P
R E
P A
R A
T
IO
N N
O T
E
/0
/2
AMENDMENT 0008
IE:-0.36
TE:1.93
24" Ø Concrete Pipe
(DESTROYED)
HEADW
ALL
F L
O W
R
IO
P
IE
D R
A S
24" Diameter Concrete Pipe
PIPES (NIU)
KM 3.0
SIGN
OPTIC BOX
AT&T FIBER
10" Ø CIP WATER PIPE.
IE:12.56
TE:13.65
CBW
ater Meter
Total Gas Station
GAS VALVE
IE:11.49
TE:13.71
CB
PIPES (NIU)
NO PARKING
SIGN
W
ATER PIPE
TEST HOLE # 6
W
ATER PIPE
TEST HOLE # 1
ELECTRIC CABLES"
"UNDERGROUND
AEE SIGN
EB
IE:CLOGGED
TE:13.99
SMH San Juan Gas
San Juan Gas
SAN JUAN GAS
TB
BOX
FIBER OPTIC
AT&T
BOX
CATV
TB
TB
SIGN
NO PARKING
TMH
BOX
DTOP
CATV BOX
TMH
PRICES SIGN
GAS STATION'S
GUARDRAILTMH
BOX
DTOP
PPW
GATE
EMH
LPC
METAL CANOPY
LW=33.69
L W
.3
LW
=27.66
48" Diameter Concrete Pipe
L W
.5
L W
.8
STRUCT.
CONC.
LPC
" Ø C
IP
W
A T
E R P
IP
E
" Ø C
IP
W
A T
E R P
IP
E
PPCL
ALP
STEEL PIPE
4" SCH 40 GALV
CAP
ARCHED PVC
BLACK BASE BOARD
LUMBER 2" x 12"
RECYCLED PLASTIC
STRUCTURAL
NUMBERPLATE
USGS STYLE E
INSTRUCTIONS
PER MANUFACTURER
LOCATION AND SPACING
#10 x 1 3/4" SS SCREW
"2 (T
Y P
BASE BOARD
12" BLACK
LUMBER 2" x
PLASTIC
RECYCLED
STRUCTURAL
UNISTRUT)
OVERLAP BEHIND
TAPE (SILVER) (1"
2" WIDE REFLECTIVE
UNISTRUT
HEX BOLTS PER
2-3/8" SS
COUNTERSINK
INSTRUCTIONS
PER MANUFACTURER
3/4" SS SCREWS OR
ATTACH WITH #10 x 1
NUMBERPLATE
USGS STYLE E
BASE BOARD
LUMBER 2"x12"
PLASTIC
RECYCLED
STRUCTURAL
PRVD02 DATUM
REFERENCE
ELEVATIONS TO
DATUM LABEL
C ROOSEVELT AVE.
C ROOSEVELT AVE.
36'-0" CLEAR ROADWAY
DETOUR BRIDGEVARIES41'-10"± (EXIST. EB)16'-0"±41'-7"± (EXIST. WB)
MIN.
6'-0"
CHANNEL C/L
PILES (TYP), SEE REF. DWGS
EXIST. BRIDGE PRECAST
RIGHT CHANNEL WALL
FRONT FACE OF
LEFT CHANNEL WALL
FRONT FACE OF
CONST. DIV01�
D.S. NO. 49
LEFT CHANNEL WALL
D.S. NO. 50
RIGHT CHANNEL WALL
D.S. NO. 26
CHANNEL WALL
RIGHT
2A
2A
2B
2B
2A
2A
B CONST. DIV01
SHELF
UTILITY
2A
D.S. NO. 26
LEFT CHANNEL WALL
SEE SHEET CP109
TEMP. DRAINAGE
SEE SHEET CP109
TEMP. DRAINAGE
119+00
120+00
121+00
D
D
D
H
E
H
E
H
H
H
H
H
H
T
T
S O
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N M
A R
K
S
IZ
E
S U
B M
IT
T E
D B
Y
D A
T E
C O
N T
R A
C T N
O
C H
E C
K E
D B
Y
D R
A W
N B
Y
IS
S
U E D
A T
E
SHEET ID
A
B
C
D
E
F
G
1 98765432
®of Engineers
US Army Corps
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
A N
S I
D
J A
C K
S O
N V
IL
L E D
IS
T R
IC
T
S
A N M
A R
C O B
L V
D
J A
C K
S O
N V
IL
L E F
L
A R
C A
D
IS
N
C A
U S
E W
A Y B
L V
D
M E
T A
IR
IE
L
A
S U
IT
E
S A
N J
U A
N P
U E
R T
O R
IC
O
R
IO
P
U E
R T
O N
U E
V O P
R O J E
C T
R O
O S
E V
E L T A
V E
N U
E B
R
ID
G E R
E P
L A
C E
M E
N T
S U
P P
L E
M E
N T
A L C
O N
T R
A C
T
D E
C E
M B
E R
PRVD02
NUT (TYP.)
WASHER AND
U-BOLT W/
1/2" DIA. SS
UNISTRUT
SS HEX BOLTS PER
COUNTERSINK 2-3/8"
STEEL PIPE
4" SCH 40 GALV
BASE BOARD
LUMBER 2"x12"
PLASTIC
RECYCLED
STRUCTURAL
INSTRUCTIONS
MANUFACTURER
SCREWS OR PER
WITH #10 x 1 3/4" SS
NUMBERPLATE ATTACH
USGS STYLE E
PLASTIC CAP
FLUSH MOUNT
WITH REMOVABLE,
BOARD AND PLUG
1" HOLE IN BASE
L
L
L
B1
SCALE: 1" = 20'
A1
SCALE: 1" = 10'
20' 40'0
10' 20'0
C1
L
L
PHASE I PLAN - INSTALL DRILLED SHAFTS AND DETOUR BRIDGE
C1 C1
GC101
R A
Y M
O N
D
G
K E
L L E
R
A L
O V
E
O
N S
T R
U C
T
IO
N S
E Q
U E
N C
E O
F
STA. 121+47.50
END CAP BEAM
STA. 121+52.71
END CAP BEAM
#587
BRIDGE
EXIST. EB
STA. 120+07.75
BEGIN CAP BEAM
#586
BRIDGE
EXIST. WB
CHANNEL LINING TO BE REMOVED DURING PHASE
LIMITS OF EXISTING BRIDGE STRUCTURE OR EXISTING CONCRETE
APPROXIMATE LIMITS OF CHANNEL EXCAVATION
LEGEND
OF PHASE
BEGINNING
PHASE
END OF
A7
STAFF GAUGE DETAIL
SCALE: 1/2" = 1'=0" 0 2' 4'1'
FRONT VIEW SIDE VIEW
A9
SCALE: N.T.S.
MOUNTING DETAIL
NO TRAFFIC
TRAFFIC PATTERN AT END OF PHASE
TRAFFIC PATTERN AT BEGINNING OF PHASE
GENERAL SHEET NOTES
R
IO
P
IE
D R
A S
F L
O W
R
SEE GENERAL SHEET NOTE 4
INSTALLATION
STUB
10" WATER MAIN
EXIST.
OUTFALL B-4
CHANNEL LINING
EXIST. 10" CONC.
OUTFALL B-3
L1
R3
ABUTMENT
EAST DETOUR BRIDGE
ABUTMENT
WEST DETOUR BRIDGE
SHEET PILES
RETAIN TEMP. SHEET PILES
RETAIN TEMP.
APPROACH
WEST DETOUR
APPROACH
EAST DETOUR
STA. 12A0+08.60
BEGIN BEAM CAP
WATER MAIN
10" D.I.
WATER MAIN
30" D.I.
PHASE I - TYPICAL SECTION - BRIDGE DECK ONLY
S
G A
IT
A N
SEE SHEET CU102
VALVE BOX C
SEE SHEET LP101 FOR TREE INVENTORY PLAN.7.
APPROACH.
ECOMAXX GAS STATION, IN THE VICINITY OF THE WEST DETOUR BRIDGE
SEE SHEET G-005 FOR POTENTIAL TRACES OF FOSSIL FUEL NEAR THE 6.
CONTRACTING OFFICER.
BEEN ATTAINED. REMOVAL REQUIRES REVIEW AND AUTHORIZATION BY THE
SHAFT CONCRETE PLACEMENT OR THE FULL COMPRESSIVE STRENGTH HAS
EXTRACTED UNTIL 28 DAYS AFTER COMPLETION OF ADJACENT DRILLED
TEMPORARY BYPASS AND TRANSVERSE SHEET PILES SHALL NOT BE 5.
CHANNEL ACCORDINGLY. SEE SHEET CO101 FOR STAFF GAUGE LOCATIONS.
FOR MONITORING RIVER STAGES AND ADJUSTING WORK WITHIN THE
ORIENT GAUGE TO FACE THE EAST BANK. CONTRACTOR IS RESPONSIBLE
DOWNSTREAM PROJECT LIMITS DURING CONSTRUCTION, PER DETAIL A7.
CONTRACTOR SHALL INSTALL A STAFF GAUGE AT THE UPSTREAM AND 4.
SEE SHEET CD101 FOR DEMOLITION PLAN.3.
GEOMETRY OF EXISTING BRIDGE TO BE REMOVED.
SEE R SHEET SERIES FOR EXISTING BRIDGE PLANS SHOWING LOCATION AND 2.
SERIES.
ELECTRICAL CONDUIT TEMPORARY CROSSINGS. SEE ES SHEET J.
WATER MAIN INSTALLATION SEQUENCING. SEE SHEET CU050.I.
EXCAVATION AND DISPOSAL. SEE CG SHEET SERIES.H.
AND CO101.
TEMPORARY SHEET PILE INSTALLATION. SEE SHEET CG101 TO CG104 G.
DRILLED SHAFT CONSTRUCTION. SEE CO SHEET SERIES.F.
AND CO SHEET SERIES.
PROVISIONS TO MAINTAIN BYPASS REQUIREMENTS. SEE SHEET G-005 E.
PERMANENT BRIDGE CONSTRUCTION. SEE SB100 SHEETS.D.
SERIES.
STAGED DEMOLITION OF EXISTING WB/EB BRIDGES. SEE GC SHEET C.
DETOUR BRIDGE INSTALLATION. SEE SHEET SB102.B.
GC104.
SEQUENCING OVER FOUR PHASES OF CONSTRUCTION. SEE GC101 TO A.
EACH FEATURE OF WORK LISTED BELOW:
THESE GC SHEETS AND THE PARTICULAR SEQUENCING ESTABLISHED FOR
WORK IN ACCORDANCE WITH THE CONSTRUCTION SEQUENCE SHOWN IN
01 11 00. THE PCL PLAN SHALL INTEGRATE THE FOLLOWING FEATURES OF
PLAN IN ACCORDANCE WITH THE SPECIFICATION SECTION
CONTRACTOR SHALL SUBMIT THE PRE-CONSTRUCTION LOGISTICS (PCL) 1.
POLES
EXIST. LIGHT
TRAFFIC TO EXISTING EASTBOUND BRIDGE.
SHIFT EASTBOUND TRAFFIC TO DETOUR BRIDGE AND SHIFT WESTBOUND 17
CP202.
CONSTRUCT DETOUR BRIDGE APPROACHES. SEE SHEETS CP109 AND 16
SEE ELECTRICAL SHEETS.
BRIDGE AND ROADWAY. DEMOLISH EXISTING LIGHTING POLES IN MEDIAN.
INSTALL, CONNECT, AND ENERGIZE TEMPORARY LIGHTING ON DETOUR 15
CAP EXISTING UTILITY CONDUITS. SEE ELECTRICAL SHEETS.
REMOVE ABANDONED CABLES FROM EXISTING BRIDGE. DEMOLISH AND 14
ACROSS BRIDGE. SEE ELECTRICAL SHEETS.
INSTALL POWER AND COMMUNICATION CABLES IN TEMPORARY CONDUITS 13
BRIDGE. SEE E AND ES SHEET SERIES FOR LIGHTING SEQUENCING.
INSTALL TEMPORARY LIGHTING CONDUITS AND SERVICE AT TEMPORARY 12
ELEVATION.
UTILITY DUCT BANKS. SEE SHEET SB102 FOR DETOUR BRIDGE PLAN AND
INSTALL DETOUR BRIDGE SUPERSTRUCTURE INCLUDING SIDEWALK AND 11
SHEET PILES ARE INSTALLED IN PHASE IV.
TEMPORARY BYPASS SHEET PILES L1 AND R3 UNTIL UPSTREAM BYPASS
CONSTRUCTED CHANNEL WALL DRILLED SHAFTS. RETAIN UPSTREAM
REMOVE BYPASS SHEET PILE WALLS L1 AND R3 IN FRONT OF 10
PILES, AND ANY REMAINING CAP BEAMS. SEE SHEETS SB113 AND SB114.
CONSTRUCT EAST AND WEST DETOUR BRIDGE ABUTMENTS, HP14X89 9
CONSTRUCTED PRIOR TO REMOVING BYPASS SHEET PILE WALL L1.
SHEET CF101 FOR OUTLET LOCATIONS. CAP BEAM SHALL BE
UPSTREAM FLOW DIRECTION INCLUDING HEADWALL AT OUTFALL B-3, SEE
CONSTRUCT LEFT CHANNEL WALL DRILLED SHAFTS NO. 26 TO 49 IN AN 8
CO SHEET SERIES.
CREATE A WORKING PLATFORM FOR CHANNEL WALL CONSTRUCTION. SEE
INSTALL TEMPORARY BYPASS SHEET PILE WALL L1 AND BACKFILL TO 7
FINISHED PRIOR TO THE INSTALLATION OF SHEET PILE L1.
UPON COMPLETION OF BYPASS SHEET PILE WALL R3 AND SHALL BE
TRANSITION GRADING BETWEEN PHASES. THIS EXCAVATION MAY BEGIN
REQUIREMENTS. SEE SHEETS CO101 AND CG101 FOR DETAILS, INCLUDING
EXCAVATE AREAS AS SHOWN TO ELEVATION 0.00 TO PROVIDE BYPASS 6
TEMPORARY SHEET PILE VARIES. SEE SHEET CO501 AND R-105.
R-001 FOR AS-BUILT. INSTALL TEMPORARY SHEET PILE C1. TOP OF
DEMOLISH AND REMOVE CHANNEL LINING TO LIMITS SHOWN. SEE SHEET 5
R3.
SHALL BE CONSTRUCTED PRIOR TO REMOVING BYPASS SHEET PILE WALL
CHANNEL AT APPROX. STA. 122+75 SHALL REMAIN IN SERVICE. CAP BEAM
OUTLET LOCATIONS. THE EXISTING 30" CIP WATER MAIN CROSSING THE
DIRECTION, INCLUDING HEADWALL AT OUTFALL B-4. SEE SHEET CF101 FOR
CHANNEL WALL DRILLED SHAFTS NO. 26 TO 50 IN AN UPSTREAM FLOW
INSTALL TEMPORARY BYPASS SHEET PILE WALL R3 AND CONSTRUCT RIGHT 4
PROTECT 30" WATER MAIN DURING THE INSTALLATION.
TEST. SEE SHEET CO101 FOR LOCATIONS AND CO302 FOR DETAILS.
CONSTRUCT DEMONSTRATION WALL AND DRILLED SHAFT FOR AXIAL LOAD 3
ELECTRICAL SHEETS.
BRIDGE WITH NEW CONDUITS. SEE SHEETS CP109 TO CP118 AND
EXISTING ELECTRICAL HANDHOLES/MANHOLES ACROSS TEMPORARY
WITH TRAFFIC CONTROL PLAN TO OPEN CUT ROAD AND CONNECT
APPROACH OVER TEMPORARY BRIDGE. SEE ELECTRICAL SHEETS. COMPLY
INSTALL TEMPORARY ELECTRICAL AND COMMUNICATION CONDUITS TO 2B
WATER UTILITY CONSTRUCTION SEQUENCING PLAN.
WATER MAIN TO LIMITS SHOWN ON SHEET CD101. SEE SHEET CU050 FOR
CAPS AT PHASE I LIMITS. INSTALL 10” WATER MAIN. REMOVE EXISTING 10"
INSTALLATION ON WEST SIDE OF CHANNEL. INSTALL MECHANICAL JOINT
INSTALL VALVE BOX C AND PHASE I 30” WATER MAIN, INCLUDING STUB 2A
WEST SIDE OF CHANNEL.
CHANNEL. DEMOLISH CONCRETE STRUCTURE AND METAL CANOPY ON
REMOVE AND DISPOSE ECOMAXX GAS STATION SIGN ON WEST SIDE OF 1
PHASE I CONSTRUCTION SEQUENCE
NORTH
PLAN
GC101
A1
GC101
A1
GC101
A9
THE OWNER, ECOMAXX, REMOVE AND DISPOSE OF THE ECOMAXX GAS
STATION SIGN ON THE WEST SIDE OF THE CHANNEL. CONTRACTOR
WILL DEMOLISH CONCRETE STRUCTURE AND METAL CANOPY ON WEST
SIDE OF THE CHANNEL.
U
P D
A T
E D
P H
A S
E I
C O
N S
T R
U C
T
IO
N S
E Q
U E
N C
E N
O T
E
/0
/2
AMENDMENT 0008
| B.08 W912EP23R0003_RPN CNT 2_Amendment0008 |
| B.08 W912EP23R0003_RPN CNT 2_Amendment0008 |
| B.08 W912EP23R0003_RPN CNT 2_Amendment0008 |
| B.08 W912EP23R0003_RPN CNT 2_Amendment0007 |
| W912EP23R0003P0007 |
| RPN CNT2_Am0008 (1) (1) |
| SF30_Cont_sheet_am0008 |
| SF1442_am0008 |
| B.08 W912EP23R0003_RPN CNT 2_Amendment0008 |
| Bid Schedule_00010A_CNT2_AMD0008 |
G-005 GC101 from Ready to Advertise Submittal -- RPN CNT2 PLANS -- 01232023