This memorandum documents a pre-bid site visit for solicitation number W912EP23B0019 for maintenance dredging of the Intracoastal Waterway between Jacksonville and Miami in the vicinity of Matanzas Inlet in St. Johns and Flagler Counties, Florida. Contractors and representatives from the U.S. Army Corps of Engineers and local sponsor toured the construction access areas, pipeline routes, and beach disposal locations by vehicle and on foot. Key requirements discussed included environmental monitoring, turbidity monitoring, vibration monitoring, order of dredging operations with the breach location dredged first, beach surveys, and documentation of quantities moved. Bidders were also notified of an upcoming pre-bid teleconference on July 18, 2023 to address any outstanding questions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C.04.01-Abstract_W912EP23B0019 IWW Matanzas.pdf | ||
| B.08 W912EP23B0019 AMEND 0001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CESAJ-CD-NJ 13 July 2023
MEMORANDUM FOR CESAJ-CT-C
SUBJECT: W912EP23B0019 Intracoastal Waterway, Jacksonville to Miami, Maintenance Dredging, 12-Foot Project, Vicinity of Matanzas Inlet, St. Johns and Flagler Counties, FL Pre-Bid Site Visit
1. A pre-bid site visit for subject project was conducted on 13 July 2023, from 1000 to
1100 hours. The contractor, USACE and local sponsor/partner participants are included on the roster attachment to this memorandum.
2. The participants met at the southern construction access area near R-208 and drove north along the Summer Haven beach disposal area until reaching the current breach location near R-205. Participants viewed the current breach location, pipeline access route and the beach disposal area between R-204 and R-206. Participants then exited back south to A1A and drove north to a public parking area and accessed the beach disposal location on foot between R-201 and R-202.
3. Key project requirements discussed were: environmental monitoring, turbidity monitoring, vibration monitoring, order of placement (breach first), beach survey and
DQM.
4. Contractors in attendance were informed of the Pre-Bid Teleconference scheduled for 18 July 2023 at 1100 hrs EDT.
5. Questions from the participants that were not answered on site were directed to the
Contracting Officer through PROJNET/Dr. Checks.
If you have any questions or require additional information regarding this matter, please contact the undersigned at (561) 379-2854.
Jennifer L. Tyler Project Engineer
Enclosure:
Site Visit Roster
CF: (Electronic Distribution) CESAJ-CT-C (Voicu/Humphrey) CESAJ-CD-M (Rodriguez)