This solicitation is requesting proposals for aquatic vegetation removal services along approximately 40 acres of the Cano Martin Pena Waterway in San Juan, Puerto Rico. The U.S. Army Corps of Engineers, Jacksonville District is seeking a contractor to provide all necessary personnel, equipment, transportation, and disposal services to perform terrestrial and aquatic vegetation removal above land surface without removing stumps or roots. The contractor will clean and shred debris, transport it offsite, and dispose of it at a final disposal facility. This requirement is set aside as a 100% small business HUBZone contract. The associated NAICS code is 562910.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP W912EP22R0024 Pricing Sheet Aquatic Vegetation Removal:

THIS COST PROPOSAL BREAKDOWN SHOULD BE FURNISHED FOR EACH BID ITEM ON THE BID SCHEDULE

CLIN #: 002

QTY: 4

LINE

Item Provide aquatic vegetation removal

UOM: Acre

A DIRECT COST (Material, Labor, Subcontracts, Equipment)

A(1)

MATERIAL

DIRECT

(Unit cost $)

DIRECT

(Total $)

(Breakdown of costs on attached sheets. Include items, units, quantities, unit process, as well as any applicable taxes on attached sheets ____) $0.00 $0.00

A(2)

LABOR

DIRECT

(Unit cost $)

DIRECT

(Total $)

(Includes crafts, wage rates, number of hours or man-days, labor burden such as payroll taxes, insurance and fringe benefits broken down on attached sheets ____) $0.00 $0.00

A(3)

SUBCONTRACTS

DIRECT

(Unit cost $)

DIRECT

(Total $)

(Each subcontractor's breakdown is included on attached sheets ____) $0.00 $0.00

A(4)

EQUIPMENT

DIRECT

(Unit cost $)

DIRECT

(Total $)

Identify type, number of hours, ownership cost, rental rates, operating cost including fuel, and maintenance. $0.00 $0.00

SUB TOTAL OF DIRECT COST:

(A(1) THROUGH A(4) ABOVE:) $0.00

Subcontracts MARK-UP: $0.00

COST TO PRIME: $0.00

B

PROJECT OVERHEAD COST:

(Identify expense for items applicable to overall cost of project and not included in above)

0.00%

$0.00

SUB TOTAL: $0.00

C HOME OFFICE EXPENSE (G&A) 0.0% $0.00

D PROFIT 0.0% $0.00

E PAYMENT AND PERFORMANCE BOND PREMIUM 0.0% $0.00

TOTAL COST OF WORK: $0.00