This document includes a pricing sheet template and details of a federal contract opportunity for vegetation removal services. The pricing sheet template is for bid item 001 to provide terrestrial vegetation removal services for 36 acres at a unit price. It requests breakdowns of direct costs for materials, labor, subcontracts, and equipment. It also specifies markups for overhead, G&A, profit, and bonds.
The federal contract opportunity is a 100% small business HUBZone set-aside issued by the USACE Jacksonville District. It seeks to award a non-personal services contract to mechanically remove and dispose of vegetation from approximately 40 acres of the Cano Martin Pena Waterway in San Juan, Puerto Rico. The contractor must provide all personnel, equipment, transportation, and other items needed to perform terrestrial and aquatic vegetation removal above land surface without removing stumps/roots, clean-up and removal of debris, shredding and transport of debris to a disposal facility.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP W912EP22R0024 Pricing Sheet Terrestrial Vegetation Removal:
THIS COST PROPOSAL BREAKDOWN SHOULD BE FURNISHED FOR EACH BID ITEM ON THE BID SCHEDULE
CLIN #: 001
QTY: 36
LINE
Item Provide terrestrial vegetation removal
UOM: Acre
A DIRECT COST (Material, Labor, Subcontracts, Equipment)
A(1)
MATERIAL
DIRECT
(Unit cost
DIRECT
(Total $)
(Breakdown of costs on attached sheets. Include items, units, quantities, unit process, as well as any applicable taxes on attached sheets ____) $0.00 $0.00
A(2)
LABOR
DIRECT
(Unit cost
DIRECT
(Total $)
(Includes crafts, wage rates, number of hours or man-days, labor burden such as payroll taxes, insurance and fringe benefits broken down on attached sheets ____) $0.00 $0.00
A(3)
SUBCONTRACTS
DIRECT
(Unit cost
DIRECT
(Total $)
(Each subcontractor's breakdown is included on attached sheets ____) $0.00 $0.00
A(4)
EQUIPMENT
DIRECT
(Unit cost
DIRECT
(Total $)
Identify type, number of hours, ownership cost, rental rates, operating cost including fuel, and maintenance. $0.00 $0.00
SUB TOTAL OF DIRECT
COST:
(A(1) THROUGH A(4)
ABOVE:) $0.00
Subcontracts MARK-UP: $0.00
COST TO PRIME: $0.00
B
PROJECT OVERHEAD COST:
(Identify expense for items applicable to overall cost of project and not included in above)
0.0
$0.00
SUB TOTAL: $0.00
C
HOME OFFICE EXPENSE (G&A)
0.0
D
PROFIT
E
PAYMENT AND PERFORMANCE BOND
PREMIUM
TOTAL COST OF WORK: $0.00