This is a solicitation for the construction of Pump Station S-705 as part of the Comprehensive Everglades Restoration Plan in Miami-Dade County, Florida. The pump station will have a capacity of 100 cfs and will be located at the intersection of the L-31E Canal and C-102 Canal. It will pump water into the L-31E Canal segment south of C-102 and north of the Military Canal. The pump station features include manatee protective barriers, trash racks, dewatering features with stop logs, and a 72-inch culvert with a slide gate. A precast concrete control building will be constructed adjacent to the pump station structure to house remote controls. Construction activities involve installing precast concrete, piles, sheet piles, cast-in-place concrete, tremie concrete, flowable fill, an HDPE culvert, a slide gate, pumps, a pump platform, electrical work, fencing and site work. The solicitation is for a firm fixed-price construction contract to be awarded by the U.S. Army Corps of Engineers, Jacksonville District.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
1 40
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
03-Sep-2020
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
6. ISSUED BY CODE W912EP 7. ADMINISTERED BY (If other than item 6) CODE
USA ENGINEER DISTRICT, JACKSONVILLE
CONTRACTING DIVISION
701 SAN MARCO BLVD
JACKSONVILLE FL 32207-8175
See Item 6
8. NAME AND ADDRESS OF CONTRACT OR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.
W912EP20R0031
X 9B. DATED (SEE ITEM 11)
14-Aug-2020
10A. MOD. OF CONTRACT /ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. T HIS ITEM ONLY APPLIES TO AMENDMENT S OF SOLICIT ATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15 and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNT ING AND APPROPRIATION DATA (If required)
13. THISITEM APPLIESONLY TO MODIFICATIONSOF CONTRACTS/ORDERS.
IT MODIFIESTHE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES(such as changes in paying office, appropriation date, etc.) SET FORT H IN ITEM 14, PURSUANT TO THE AUT HORIT Y OF FAR 43.103(B).
C. T HIS SUPPLEMENT AL AGREEMENT IS ENTERED INTO PURSUANT TO AUT HORIT Y OF:
D. OTHER (Specify type of modification and authority)
E. IMPORT ANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
COMPREHENSIVE EVERGLADES RESTORATION PLAN; BISCAYNE BAY COASTAL WETLANDS, L-31E FLOW-WAY; CONTRACT 5A (A
PHASE I PROJECT): PUMP STATION S-705; MIAMI-DADE COUNTY, FLORIDA
A.SEE CONTINUATION SHEET FOR AMENDMENT DETAILS.
B.THE PROPOSAL DUE DATE REMAINS UNCHANGED AT SEPTEMBER 14, 2020 @ 2:00 P.M. LOCAL TIME. LOCAL TIME.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONT RACTING OFFICER (Type or print)
TEL: EMAIL:
15B. CONT RACT OR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATESOF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
30-105-04 STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
SF 30 CONTINUATION SHEET
CERP, Biscayne Bay Coastal Wetlands L-31E Flow-Way, Contract 5A (A Phase I Project): Pump Station S-705
Miami- Dade County, Florida
SUMMARY OF CHANGES
1. CONSTRUCTION SOLICITATION AND SPECIFICATIONS:
A. Changes are indicated by asterisks appearing before and after the line or lines where amendments have been made to the text and pertain only to changes made by this amendment. In some cases, replacement clauses are attached to this amendment.
B. Text changes have been updated with additions noted by underlined text and deletions noted by line/cross-outs and pertain only to changes made by this amendment. The entire section is replaced if there is any change. The Project Table of Contents and Submittal Register are replaced without underlines and cross-outs if there are changes to these documents.
Volume 1 of 2 – Contract Clauses:
DELETE Design Authentication and REPLACE with the Design Authentication.
DELETE Section 00010A, Attachment A and REPLACE with Section 00010A, Attachment A.
Volume 2 of 2 – Technical Specifications:
DELETE Section 01 52 10 and REPLACE with the attached Section 01 52 10.
DELETE Section 01 57 25 and REPLACE with the attached Section 01 57 25.
DELETE Section 33 71 02 and REPLACE with the attached Section 33 71 02.
2. DRAWINGS
N/A
(End of Summary of Changes)
W912EP20R0031 2 Amendment 0002
Amendment 0002
SECTION 00010A, Attachment A
INSTRUCTIONS FOR TECHNICAL INQUIRIES AND QUESTIONS
Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org) No Later Than (NLT) 04 September 2020 at (4:00 pm 9:00 am) Local Time. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team.
The Solicitation Number is: W912EP20R0031
The Bidder Inquiry Key is: DMU85B-NHFE98
Specific Instructions for ProjNet Bid Inquiry Access from ProjNet home page:
1. Identify the Agency. This should be marked as USACE.
2. Email. Enter the email address you would like to use for communication.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
5. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret
Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
6. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
Specific Instructions for Future ProjNet Bid Inquiry Access from ProjNet home page:
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. Identify the Agency. This should be marked as USACE.
3. Email. Enter the email address you used to register previously in ProjNet.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Click Continue. A page will then open asking you to enter the answer to your Secret Question.
6. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
W912EP20R0031 00010A-2 Amendment 0002
CERP, Biscayne Bay Coastal Wetlands, Contract 5A Miami-Dade County, Florida
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 52 10
CONTRACTING OFFICER'S FIELD OFFICE
PART 1 GENERAL
1.1 SUMMARY
1.2 SUBMITTALS
1.3 EXISTING UTILITIES
1.4 TEMPORARY SERVICES
PART 2 PRODUCTS
2.1 CONTRACTING OFFICER'S FIELD OFFICE
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.1.1 Parking
3.1.2 Janitorial Service
3.2 AVAILABILITY AND USE OF UTILITY SERVICES
3.3 FIELD OFFICE
3.3.1 Portable Office
3.3.2 Office Equipment
-- End of Section Table of Contents --
SECTION 01 52 10 Page 1 W912EP20R0031 Amendment 0002
SECTION 01 52 10
CONTRACTING OFFICER'S FIELD OFFICE
PART 1 GENERAL
1.1 SUMMARY
This section covers the requirements regarding the Contracting Officer's Field Office. See Section 01 50 02 TEMPORARY CONSTRUCTION FACILITIES and Section 01 57 20 ENVIRONMENTAL PROTECTION for requirements including silt control, portable office placement, fueling restrictions, dust control, solid waste, and cleanup. Upon completion of project, clean up and restore area in accordance with Clause CLEANING UP of Section 00700 CONTRACT CLAUSES in Volume 1. Services required in this section will be paid for by separate line item (See Section 01 22 00 MEASUREMENT AND
PAYMENT).
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Within 10 calendar days following date of receipt of Notice to Proceed and prior to mobilization to site submit following in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Contracting Officer's Field Office
1.3 EXISTING UTILITIES
See Section 01 50 02 TEMPORARY CONSTRUCTION FACILITIES.
1.4 TEMPORARY SERVICES
Furnish following services for Contracting Officer's Field Office:
a. Janitorial service.
b. Lawn service.
c. Waste removal.
d. Pest Control.
e. Potable water by the most economic means available.
f. Internet Services.
g. Telephone Services.
PART 2 PRODUCTS
2.1 CONTRACTING OFFICER'S FIELD OFFICE
Submit supplier or manufacturer scale drawings of office floor plans and site plan for Contracting Officer's Field Office with requirement indicated in paragraph CONTRACTING OFFICER'S FIELD OFFICE below. Provide a portable office in good working condition that has, at a minimum, heat
SECTION 01 52 10 Page 2 and air conditioning, running water, restroom facilities, a minimum of 1,200 square feet, and accommodates equipment required below and IT equipment to be installed by the Government. See paragraph FIELD OFFICE below. A suitable office replacement for the portable office may be accepted at the Contracting Officer's discretion.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Install Contracting Officer's Field Office ready for use no later than 30 calendar days after Notice to Proceed.
3.1.1 Parking
Provide Contracting Officer twelve gravel parking spaces at Contracting Officer's Field Office. Place parking signs reserved for use of Contracting Officer and visitors. Maintain these spaces clear of other vehicles. Designate one parking spot with sign for handicap use only.
Comply with all ADA parking requirements for size and accessibility.
3.1.2 Janitorial Service
a. Daily -- Sweep and mop floors; empty wastebaskets; service and sanitize bathrooms and other common areas; restock cleaning supplies and toiletries such as, but not limited to, hand soap, hand sanitizer, paper towels, and toilet paper.
b. Weekly -- Wash floors, windows (inside and out)
3.2 AVAILABILITY AND USE OF UTILITY SERVICES
See Section 01 50 02 TEMPORARY CONSTRUCTION FACILITIES. Provide Contracting Officer's Field Office sufficient continuous power and electric supply to assure operation of systems, including computer, light and HVAC. Provide one 20 amp dedicated circuit to support copier/printer location and communications rack located in 6 feet by 6 feet IT/storage closet. Install dedicated circuit wall termination at a central location where Government equipment will be installed.
3.3 FIELD OFFICE
Supply and maintain lockable field office separate from Contractor for use by Contracting Officer.
3.3.1 Portable Office
a. An all metal exterior, sides and roof; double-insulated walls, floor, and roof; self-contained, built-in heat and air conditioning; and 110 volt wall outlets.
b. Security guard screens, screens, and blinds for all windows.
c. Toilet facility -- A separately enclosed room properly ventilated and complying with applicable sanitary codes including hot and cold running water and operable flush type toilet.
d. Installed during site mobilization.
e. Make the portable office handicap accessible and comply with all ADA
SECTION 01 52 10 Page 3 requirements.
f. Portable office must have four offices, two on each end, with a central meeting area in between. Provide lockable individual offices.
g. Prewire portable office with network and phone drops in each office and the main conference area. Coordinate with the Contracting Officer the quantity and location of drops. Install network drops using Cat6, plenum cable from POTS terminal block in office IT closet to the end user/device locations, to include a Cat6 24 port patch panel with wall mounting brackets, and any necessary conduit boxes, face plates and jacks for a complete cable installation. Install phone drops standard cabling to support any telephony required (to include POTS, VOIP, Centrix or other similar system) and plenum cable from the office IT closet to the end user/device locations. Include pre-wiring with 2 inch conduit and CAT6 wire from the DMARK (utility pole) to the CSU/DSU location (inside the 6'x6' IT/Storage Closet). If the Telco or other telephony/network access provider positions their access point (or DMARK) in a different location, provide all cabling necessary to connect to the trailer cable plant. Locate portable office within 100 feet of utility services (telephony/network communications provider) location. Provide infrastructure to connect to the nearest services (i.e. install additional pole and services), if there are no such utilities within 100 feet. Install trailer to meet all federal, state and local codes, and applicable IT standards.
Connect the trailer cabling for phones and network to whatever handoff the telephony/network service provider provides regardless of technology.
h. Tie down office trailer per local wind and building codes.
3.3.2 Office Equipment
Provide following furnishings:
8 - Office desks with five lockable drawers (60 inches by 30 inches, laminated top), swivel chair and power strip for each (desks should be designed for use with PCs).
1 - Conference Table with ten chairs.
1 - 16-unit first aid kit, wall mounted.
1 - Fire resistant, four drawer, legal size lockable filing cabinet.
6 - Five drawer, letter size lockable filing cabinets.
1 - Table to support FAX and printer.
2 shelf sets - Four shelves high by 12 inches deep by 3 feet long
(attachable to wall).
6 - 3' x 6' Cork Bulletin Boards.
6 - 3' x 6' Dry Erase Boards.
7 - 13-gallon waste baskets, one for each office and bathroom, and 2 in central meeting room.
1 - Plan Table installed in a location directed by the Contracting Officer
(may be built in) with a minimum working surface of 4 feet by 6 feet, and draftsman stool.
1 - Vertical filing plan rack sufficient for full size contract drawings.
1 - 24" x 24" x 3/4" piece of fire-retardant backboard to be installed in the 6' x 6' IT/storage closet.
1 - Wall mount rack enclosure closet, 10 U (Unit), 19" deep, locking on all sides (Example: Tripp Lite-SRW10US or equal as approved by the Contracting Officer).
1 - 7-cubic foot refrigerator.
SECTION 01 52 10 Page 4
1 - 1.5-cubic foot microwave oven.
-- End of Section --
SECTION 01 52 10 Page 5
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 57 25
TURBIDITY AND DISPOSAL MONITORING
PART 1 GENERAL
1.1 SCOPE
1.2 SUBMITTALS
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 MONITORING REQUIREMENTS
3.1.1 General
3.1.1.1 Turbidity Monitoring Equipment
3.1.2 Dredging and Disposal Locations
3.1.2.1 Station Descriptions
3.1.2.2 Turbidity
3.2 TURBIDITY TESTS
3.2.1 Testing
3.2.2 Reporting
3.2.2.1 Report Contents
3.2.2.2 Monitoring Reports
3.2.2.3 Notification
3.3 WORK DELAY
3.4 CONSTRUCTION FORMS AND DETAILS
-- End of Section Table of Contents --
SECTION 01 57 25 Page 1
SECTION 01 57 25
TURBIDITY AND DISPOSAL MONITORING
PART 1 GENERAL
1.1 SCOPE
The work covered by this section consists of furnishing all labor, materials, and equipment, and performing all work required to obtain, analyze, and report the results of turbidity and disposal monitoring.
The work zone is proximate to an Outstanding Florida Water (Biscayne National Park). Turbidity shall not exceed Biscayne National Park background turbidity within the Outstanding Florida Waters, see the OFW graphic as an appendix to this section.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Calibration Standard
The Contractor shall furnish to the Contracting Officer a copy of the operating instructions and standards used in calibrating equipment used in collecting samples for turbidity.
SD-06 Test Reports
Turbidity Monitoring
All required turbidity test reports shall be submitted (by electronic mail in Excel format) to the Contracting Officer, the Environmental Branch (CESAJ-PD-E), and SFWMD within 7 days after completion of each test and the Florida Department of Environmental Protection (FDEP) quarterly.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 MONITORING REQUIREMENTS
3.1.1 General
Inland water samples shall be obtained and analyzed for turbidity.
Sampling shall be conducted in accordance with techniques described in the latest edition of "Standard Methods" published by the American Public Health Association (APHA), American Waterworks Association (AWWA), and
SECTION 01 57 25 Page 2
Water Pollution Control Federation (WPCF), and other current techniques recognized by the scientific community and approved by the Jacksonville District, Corps of Engineers. Samples obtained for turbidity analysis shall be analyzed within 30 minutes of collection. Samples shall be taken with a sampler in a manner to obtain samples uncontaminated by water from any other depth.
3.1.1.1 Turbidity Monitoring Equipment
Monitoring required for turbidity shall be measured in Nephelometric Turbidity Units (NTU) using a standard Nephelometer. Global Positioning System (GPS) is also required to record sampling stations. The Contractor shall provide the Government with a certification, attesting to the accuracy of his testing equipment and procedure. The Contractor shall also provide the Contracting Officer with a duplicate of the standard used to calibrate his testing instrument as well as a complete set of operating instructions for the turbidity testing equipment. The Contractor and the Contracting Officer will use this standard throughout the project to maintain the calibration of the equipment.
3.1.2 Dredging and Disposal Locations
Routine monitoring shall occur at the following locations:
3.1.2.1 Station Descriptions
a. Station 1a (Compliance Turbidity): Shall be taken at the outer edge of the turbidity barrier for the C-102 and L-31E canals down current of the point of discharge and in the direction of any visible plume in the area of the worksite. If the result is greater than zero above background on the outer edge of the barrier cloth in the C102 canal, station 1c shall also be monitored.
b. Station 1b (Compliance Turbidity): Shall be taken directly downstream on the outer edge of the S705 barrier cloth in the C-102 canal. If any visible plume noted leaving the worksite (C-102 canal turbidity barrier for S705) due to construction activity and Station 1b exceeds 0 NTU above background, compliance monitoring shall also be required directly downstream of the S-21A structure within C-102 at monitoring point 1c. It should be noted that the area proximate to the construction work and up to the OFW boundary are Class III waters with allowance of 29 NTUs above background.
c. Station 1c (Compliance Turbidity): Must be 0 NTU's above background when work is being conducted in the C-102 canal and the contractor cannot maintain 0 NTU's above background at the boundary of the work area . This station shall be located at the S21A which is the boundary to the OFW. Zero NTU's above background is the standard for an OFW.
d. Station 2 (Background Turbidity): Area beyond any turbidity generated by the project and to be established upstream of the work area in the C102 canal.
3.1.2.2 Turbidity
Effective means of turbidity control, such as, but not limited to, turbidity curtains or the discontinuance of flow activity to and from the affected STA(s) cell(s), shall be employed during all maintenance
SECTION 01 57 25 Page 3 activities that may create turbidity so that turbidity shall not exceed 29 NTUs above background, beyond the limits of construction. Turbidity controls and/or preventive operation procedures shall remain in place until all turbidity has subsided and the turbidity level at the point of discharge to receiving waters meets state standards. Turbidity monitoring equipment and personnel trained to use it shall be available on site at all times during maintenance activities that result in project-generated turbidity levels in the receiving water body. Turbidity samples shall be taken during installation and removal of earthen cofferdams. Once a cofferdam is removed, the structure will be turned over to SFWMD for flushing, with the turbidity curtains still in place. Once flushing has been completed, the turbidity curtains will be removed. Additional sampling shall be performed when the Contracting Officer determines that there may be non-compliance with water quality standards. The permittee shall monitor turbidity levels at least twice daily at a minimum of 4 hours apart during these activities as follows:
a. Compliance at Station 1a., 1b., and 1c. Station 1a and 1b shall only be monitored if there is construction activity at either or both of those sites. 1c shall be monitored only if 0 NTU above background is noted outside the work zone.
b. Background at Station 2.
3.2 TURBIDITY TESTS
3.2.1 Testing
Whenever there is doubt as to the adequacy of the testing or validity of the results, the Contracting Officer may direct that additional tests be performed at no additional cost to the Government.
3.2.2 Reporting
The monitoring data shall be recorded on summary forms that contain the pertinent information in the following paragraphs. Example forms are on the web site indicated in paragraph CONSTRUCTION FORMS AND DETAILS below.
All data shall be forwarded (electronically) to the Contracting Officer, Environmental Branch (CESAJ-PD-E), and SFWMD within 7 days of collection and to FDEP quarterly as required by permit. Electronic mail addresses of the Corps and FDEP personnel to receive these reports will be provided at the Preconstruction Conference meeting. Reports shall be provided in Excel Spreadsheet (.xls) files.
3.2.2.1 Report Contents
a. Permit number.
b. Dates and times of sampling.
c. A statement describing the methods used in collection, handling and storage.
d. A clear description of project component activities taking place at the time of sampling.
e. A map indicating and labeling the sampling locations.
f. A statement by the individual responsible for implementation of the sampling program concerning the authenticity, precision, limits of detection, and accuracy of the data.
g. Results of the sampling.
SECTION 01 57 25 Page 4
3.2.2.2 Monitoring Reports
Monitoring reports shall also include the following information for each day that samples are taken:
a. Depth of water body.
b. Depth of sample location.
c. Antecedent weather conditions.
d. Wind direction and velocity.
3.2.2.3 Notification
If turbidity exceeds background levels by more than 29 NTU outside the worksite in the S102 canal directly outside of the turbity barrier in the C102 canal or equal or greater than 0 NTU within the OFW directly downstream of S-F21A in canal C-102, the Contractor shall immediately notify Corps PD-ES (Jim Riley 904-232-2438 or Savanna Royals 904-232-2037) and the Contracting Officer, or on the morning of the following work day if it occurs after normal work hours. In addition, project component activities contributing to elevated turbidity levels shall immediately cease, and the SFWMD and FDEP shall be notified immediately. Work shall not resume until corrective measures have been taken and turbidity has returned to acceptable levels as determined by proper testing described in subparagraph "Dredging and Disposal Locations" above.
3.3 WORK DELAY
Delays in work due to the fault or negligence of the Contractor or the Contractor's failure to comply with this specification shall not be compensable. Any adjustments to the contract performance period or price that are required as a result of compliance with this section shall be made in accordance with the provisions of the Clause SUSPENSION OF WORK of Section 00700 CONTRACT CLAUSES in Volume 1.
3.4 CONSTRUCTION FORMS AND DETAILS
See the "Construction Forms & Details" module at the following web address:
http://www.saj.usace.army.mil/About/Divisions-Offices/Engineering/Design-Branch/ Specifications-Section/
-- End of Section --
SECTION 01 57 25 Page 5
SECTION TABLE OF CONTENTS
DIVISION 33 - UTILITIES
SECTION 33 71 02
UNDERGROUND ELECTRICAL DISTRIBUTION
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.3 SUBMITTALS
1.4 QUALITY CONTROL
1.4.1 Precast Underground Structures
1.4.2 Regulatory Requirements
1.4.3 Standard Products
1.4.3.1 Alternative Qualifications
1.4.3.2 Material and Equipment Manufacturing Date
PART 2 PRODUCTS
2.1 CONDUIT, DUCTS, AND FITTINGS
2.1.1 Rigid Metal Conduit
2.1.1.1 Rigid Metallic Conduit, PVC Coated
2.1.2 Plastic Conduit for Direct Burial and Riser Applications
2.1.3 Plastic Duct for Concrete Encasement
2.1.4 Innerduct
2.1.5 Duct Sealant
2.1.6 Fittings
2.1.6.1 Metal Fittings
2.1.6.2 PVC Conduit Fittings
2.1.6.3 PVC Duct Fittings
2.1.6.4 Outlet Boxes for Steel Conduit
2.2 LOW VOLTAGE INSULATED CONDUCTORS AND CABLES
2.2.1 Conductor Types
2.2.2 Conductor Material
2.2.3 Jackets
2.2.4 Direct Buried
2.2.5 In Duct
2.2.6 Cable Marking
2.3 LOW VOLTAGE WIRE CONNECTORS AND TERMINALS
2.4 LOW VOLTAGE SPLICES
2.4.1 Heat Shrinkable Splice
2.4.2 Cold Shrink Rubber Splice
2.5 TAPE
2.5.1 Insulating Tape
2.5.2 Buried Warning and Identification Tape
2.6 PULL ROPE
2.7 GROUNDING AND BONDING
2.7.1 Driven Ground Rods
2.7.2 Grounding Conductors
2.8 CAST-IN-PLACE CONCRETE
2.9 UNDERGROUND STRUCTURES
SECTION 33 71 02 Page 1
2.9.1 Cast-In-Place Concrete Structures
2.9.2 Precast Concrete Structures, Risers and Tops
2.9.2.1 General
2.9.2.2 Design for Precast Structures
2.9.2.3 Construction
2.9.2.4 Joints
2.9.3 Handhole Frames and Covers
2.9.4 Composite/Fiberglass Handholes and Covers
2.10 CABLE SUPPORTS (RACKS, ARMS, AND INSULATORS)
2.10.1 Cable Rack Stanchions
2.10.2 Rack Arms
2.10.3 Insulators
2.11 POWERLINE SERVICES FOR PUMP STATIONS
2.11.1 FPL Responsibilities
2.11.2 Contractor Responsibilities
PART 3 EXECUTION
3.1 INSTALLATION
3.2 CABLE INSPECTION
3.3 CABLE INSTALLATION PLAN AND PROCEDURE
3.4 UNDERGROUND FEEDERS SUPPLYING BUILDINGS
3.5 UNDERGROUND STRUCTURE CONSTRUCTION
3.5.1 Cast-In-Place Concrete Structures
3.5.2 Precast Concrete Construction
3.5.3 Pulling-In Irons
3.5.4 Cable Racks, Arms and Insulators
3.5.5 Field Painting
3.6 UNDERGROUND CONDUIT AND DUCT SYSTEMS
3.6.1 Requirements
3.6.2 Treatment
3.6.3 Conduit Cleaning
3.6.4 Jacking and Drilling Under Roads and Structures
3.6.5 Multiple Conduits
3.6.6 Conduit Plugs and Pull Rope
3.6.7 Conduit and Duct Without Concrete Encasement
3.6.7.1 Encasement Under Roads and Structures
3.6.8 Duct Encased in Concrete
3.6.8.1 Connections to Existing Underground Structures
3.6.8.2 Connections to Existing Concrete Pads
3.6.8.3 Connections to Existing Ducts
3.6.8.4 Partially Completed Duct Banks
3.6.8.5 Removal of Ducts
3.6.9 Duct Sealing
3.7 CABLE PULLING
3.7.1 Cable Lubricants
3.8 CABLES IN UNDERGROUND STRUCTURES
3.8.1 Cable Tag Installation
3.9 CONDUCTORS INSTALLED IN PARALLEL
3.10 LOW VOLTAGE CABLE SPLICING AND TERMINATING
3.11 CABLE END CAPS
3.12 GROUNDING SYSTEMS
3.12.1 Grounding Electrodes
3.12.2 Grounding Connections
3.12.3 Grounding Conductors
3.12.4 Ground Cable Crossing Expansion Joints
3.12.5 Fence Grounding
3.13 EXCAVATING, BACKFILLING, AND COMPACTING
3.13.1 Reconditioning of Surfaces
SECTION 33 71 02 Page 2
3.13.1.1 Unpaved Surfaces
3.13.1.2 Paving Repairs
3.14 CAST-IN-PLACE CONCRETE
3.14.1 Concrete Slabs (Pads) for Equipment
3.14.2 Sealing
3.15 FIELD QUALITY CONTROL
3.15.1 Performance of Field Acceptance Checks and Tests
3.15.1.1 Low Voltage Cables, 600-Volt
3.15.1.2 Grounding System
3.15.2 Follow-Up Verification
-- End of Section Table of Contents --
SECTION 33 71 02 Page 3
SECTION 33 71 02
UNDERGROUND ELECTRICAL DISTRIBUTION
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO HB-17 (2002; Errata 2003; Errata 2005, 17th Edition) Standard Specifications for Highway Bridges
AMERICAN CONCRETE INSTITUTE (ACI)
ACI 318M (2014; ERTA 2015) Building Code Requirements for Structural Concrete & Commentary
ACI SP-66 (2004) ACI Detailing Manual
ASTM INTERNATIONAL (ASTM)
ASTM B1 (2013) Standard Specification for Hard-Drawn Copper Wire
ASTM B3 (2013) Standard Specification for Soft or Annealed Copper Wire
ASTM B8 (2011; R 2017) Standard Specification for Concentric-Lay-Stranded Copper Conductors, Hard, Medium-Hard, or Soft
ASTM C139 (2017) Standard Specification for Concrete Masonry Units for Construction of Catch Basins and Manholes
ASTM C309 (2011) Standard Specification for Liquid Membrane-Forming Compounds for Curing Concrete
ASTM C478 (2018) Standard Specification for Circular Precast Reinforced Concrete Manhole Sections
ASTM C857 (2016) Standard Practice for Minimum Structural Design Loading for Underground Precast Concrete Utility Structures
SECTION 33 71 02 Page 4
ASTM C990 (2009; R 2014) Standard Specification for Joints for Concrete Pipe, Manholes and Precast Box Sections Using Preformed Flexible Joint Sealants
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 81 (2012) Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Ground System
IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National Electrical Safety Code
IEEE Stds Dictionary (2009) IEEE Standards Dictionary: Glossary of Terms & Definitions
INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)
NETA ATS (2017; Errata 2017) Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
ANSI C119.1 (2016) Electric Connectors - Sealed Insulated Underground Connector Systems Rated 600 Volts
NEMA RN 1 (2005; R 2013) Polyvinyl-Chloride (PVC) Externally Coated Galvanized Rigid Steel Conduit and Intermediate Metal Conduit
NEMA TC 2 (2013) Standard for Electrical Polyvinyl Chloride (PVC) Conduit
NEMA TC 6 & 8 (2013) Standard for Polyvinyl Chloride (PVC) Plastic Utilities Duct for Underground Installations
NEMA TC 9 (2004) Standard for Fittings for Polyvinyl Chloride (PVC) Plastic Utilities Duct for Underground Installation
NEMA WC 70 (2009) Power Cable Rated 2000 V or Less for the Distribution of Electrical Energy--S95-658
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2019; TIA 19-1; TIA 19-2; TIA 19-3; TIA
19-4; ERTA 1 2019) National Electrical Code
SOCIETY OF CABLE TELECOMMUNICATIONS ENGINEERS (SCTE)
ANSI/SCTE 77 (2013) Specification for Underground Enclosure Integrity
SECTION 33 71 02 Page 5
TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)
TIA-758 (2012b) Customer-Owned Outside Plant Telecommunications Infrastructure Standard
U.S. DEPARTMENT OF AGRICULTURE (USDA)
RUS Bull 1751F-644 (2002) Underground Plant Construction
UNDERWRITERS LABORATORIES (UL)
UL 44 (2018) UL Standard for Safety Thermoset-Insulated Wires and Cables
UL 467 (2013; Reprint Jun 2017) UL Standard for Safety Grounding and Bonding Equipment
UL 486A-486B (2018) UL Standard for Safety Wire Connectors
UL 510 (2017) UL Standard for Safety Polyvinyl Chloride, Polyethylene and Rubber Insulating Tape
UL 514A (2013; Reprint Aug 2017) UL Standard for Safety Metallic Outlet Boxes
UL 514B (2012; Reprint Nov 2014) Conduit, Tubing and Cable Fittings
UL 6 (2007; Reprint Nov 2014) Electrical Rigid Metal Conduit-Steel
UL 651 (2011; Reprint Nov 2018) UL Standard for Safety Schedule 40, 80, Type EB and A Rigid PVC Conduit and Fittings
UL 854 (2004; Reprint Nov 2014) Standard for Service-Entrance Cables
UL 94 (2013; Reprint Sep 2017) UL Standard for Safety Tests for Flammability of Plastic Materials for Parts in Devices and Appliances
1.2 DEFINITIONS
a. Unless otherwise specified or indicated, electrical and electronics terms used in these specifications, and on the drawings, are as defined in IEEE Stds Dictionary .
b. In the text of this section, the words conduit and duct are used interchangeably and have the same meaning.
c. In the text of this section, "medium voltage cable splices," and "medium voltage cable joints" are used interchangeably and have the same meaning.
SECTION 33 71 02 Page 6
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Precast underground structures ; G, DO
SD-03 Product Data
Precast concrete structures ; G, DO
Sealing Material
Handhole frames and covers ; G, DO
Composite/fiberglass handholes ; G, DO
Cable supports (racks, arms and insulators); G, DO
SD-06 Test Reports
Field Acceptance Checks and Tests ; G, RO
Cable Installation Plan and Procedure
Six copies of the information described below in 8-1/2 by 11 inch binders having a minimum of three rings from which material may readily be removed and replaced, including a separate section for each cable pull. Separate sections by heavy plastic dividers with tabs, with all data sheets signed and dated by the person supervising the pull.
a. Site layout drawing with cable pulls numerically identified.
b. A list of equipment used, with calibration certifications.
The manufacturer and quantity of lubricant used on pull.
c. The cable manufacturer and type of cable.
d. The dates of cable pulls, time of day, and ambient temperature.
e. The length of cable pull and calculated cable pulling tensions.
f. The actual cable pulling tensions encountered during pull.
1.4 QUALITY CONTROL
1.4.1 Precast Underground Structures
Submittal required for each type used. Provide calculations and drawings for precast manholes and handholes bearing the seal of a registered professional engineer including:
SECTION 33 71 02 Page 7
a. Material description (i.e., f'c and Fy).
b. Manufacturer's printed assembly and installation instructions.
c. Design calculations.
d. Reinforcing shop drawings in accordance with ACI SP-66 .
e. Plans and elevations showing opening and pulling-in iron locations and details .
f. Precast underground structures provided by the utility provider
1.4.2 Regulatory Requirements
In each of the publications referred to herein, consider the advisory provisions to be mandatory, as though the word, "must" had been substituted for "should" wherever it appears. Interpret references in these publications to the "authority having jurisdiction," or words of similar meaning, to mean the Contracting Officer. Equipment, materials, installation, and workmanship must be in accordance with the mandatory and advisory provisions of IEEE C2 and NFPA 70 unless more stringent requirements are specified or indicated.
1.4.3 Standard Products
Provide materials and equipment that are products of manufacturers regularly engaged in the production of such products which are of equal material, design and workmanship. Products must have been in satisfactory commercial or industrial use for 2 years prior to bid opening. The 2-year period must include applications of equipment and materials under similar circumstances and of similar size. The product must have been for sale on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2-year period. Where two or more items of the same class of equipment are required, these items must be products of a single manufacturer; however, the component parts of the item need not be the products of the same manufacturer unless stated in this section.
1.4.3.1 Alternative Qualifications
Products having less than a 2-year field service record will be acceptable if a certified record of satisfactory field operation for not less than 6000 hours, exclusive of the manufacturers' factory or laboratory tests, is furnished.
1.4.3.2 Material and Equipment Manufacturing Date
Products manufactured more than 3 years prior to date of delivery to site are not acceptable, unless specified otherwise.
PART 2 PRODUCTS
2.1 CONDUIT, DUCTS, AND FITTINGS
2.1.1 Rigid Metal Conduit
UL 6 .
SECTION 33 71 02 Page 8
2.1.1.1 Rigid Metallic Conduit, PVC Coated
NEMA RN 1, Type A40, except that hardness must be nominal 85 Shore A durometer, dielectric strength must be minimum 400 volts per mil at 60 Hz, and tensile strength must be minimum 3500 psi .
2.1.2 Plastic Conduit for Direct Burial and Riser Applications
UL 651 and NEMA TC 2, EPC-80.
2.1.3 Plastic Duct for Concrete Encasement
NEMA TC 6 & 8 Type EPC-80 per UL 651 and NEMA TC 2.
2.1.4 Innerduct
Provide corrugated or solid wall polyethylene (PE) or PVC innerducts, or fabric-mesh innerducts, with pullwire. Size as indicated.
2.1.5 Duct Sealant
UL 94 , Class HBF. Provide high-expansion urethane foam duct sealant that expands and hardens to form a closed, chemically and water resistant, rigid structure. Sealant must be compatible with common cable and wire jackets and capable of adhering to metals, plastics and concrete. Sealant must be capable of curing in temperature ranges of 35 degrees F to 95 degrees F . Cured sealant must withstand temperature ranges of -20 degrees F to 200 degrees F without loss of function.
2.1.6 Fittings
2.1.6.1 Metal Fittings
UL 514B .
2.1.6.2 PVC Conduit Fittings
UL 514B , UL 651 .
2.1.6.3 PVC Duct Fittings
NEMA TC 9.
2.1.6.4 Outlet Boxes for Steel Conduit
Outlet boxes for use with rigid or flexible steel conduit must be cast-metal cadmium or zinc-coated if of ferrous metal with gasketed closures and must conform to UL 514A .
2.2 LOW VOLTAGE INSULATED CONDUCTORS AND CABLES
Insulated conductors must be rated 600 volts and conform to the requirements of NFPA 70 , including listing requirements, or in accordance with NEMA WC 70. Wires and cables manufactured more than 24 months prior to date of delivery to the site are not acceptable. Service entrance conductors must conform to UL 854 , type USE.
SECTION 33 71 02 Page 9
2.2.1 Conductor Types
Cable and duct sizes indicated are for copper conductors and THHN/THWN unless otherwise noted. Conductors No. 10 AWG and smaller must be solid. Conductors No. 8 AWG and larger must be stranded. All conductors must be copper.
2.2.2 Conductor Material
Unless specified or indicated otherwise or required by NFPA 70 , wires in conduit, other than service entrance, must be 600-volt, Type XHHW conforming to UL 44 . Copper conductors must be annealed copper complying with ASTM B3 and ASTM B8.
2.2.3 Jackets
Multiconductor cables must have an overall PVC outer jacket.
2.2.4 Direct Buried
Single-conductor and multi-conductor cables must be of a type identified for direct burial.
2.2.5 In Duct
Cables must be single-conductor cable.
2.2.6 Cable Marking
Insulated conductors must have the date of manufacture and other identification imprinted on the outer surface of each cable at regular intervals throughout the cable length.
Identify each cable by means of a fiber, laminated plastic, or non-ferrous metal tags, or approved equal, in each manhole, handhole, junction box, and each terminal. Each tag must contain the following information; cable type, conductor size, circuit number, circuit voltage, cable destination and phase identification.
Conductors must be color coded. Provide conductor identification within each enclosure where a tap, splice, or termination is made. Conductor identification must be by color-coded insulated conductors, plastic-coated self-sticking printed markers, colored nylon cable ties and plates, heat shrink type sleeves, or colored electrical tape. Control circuit terminations must be properly identified. Color must be green for grounding conductors and white for neutrals; except where neutrals of more than one system are installed in same raceway or box, other neutrals must be white with a different colored (not green) stripe for each. Color of ungrounded conductors in different voltage systems must be as follows:
a. 208/120 volt, three-phase
(1) Phase A - black
(2) Phase B - red
(3) Phase C - blue
b. 480/277 volt, three-phase
SECTION 33 71 02 Page 10
(1) Phase A - brown
(2) Phase B - orange
(3) Phase C - yellow
c. 120/240 volt, single phase: Black and red
2.3 LOW VOLTAGE WIRE CONNECTORS AND TERMINALS
Must provide a uniform compression over the entire conductor contact surface. Use solderless terminal lugs on stranded conductors.
a. For use with copper conductors: UL 486A-486B .
2.4 LOW VOLTAGE SPLICES
Provide splices in conductors with a compression connector on the conductor and by insulating and waterproofing using one of the following methods which are suitable for continuous submersion in water and comply with ANSI C119.1 .
2.4.1 Heat Shrinkable Splice
Provide heat shrinkable splice insulation by means of a thermoplastic adhesive sealant material applied in accordance with the manufacturer's written instructions.
2.4.2 Cold Shrink Rubber Splice
Provide a cold-shrink rubber splice which consists of EPDM rubber tube which has been factory stretched onto a spiraled core which is removed during splice installation. The installation must not require heat or flame, or any additional materials such as covering or adhesive. It must be designed for use with inline compression type connectors, or indoor, outdoor, direct-burial or submerged locations.
2.5 TAPE
2.5.1 Insulating Tape
UL 510 , plastic insulating tape, capable of performing in a continuous temperature environment of 80 degrees C.
2.5.2 Buried Warning and Identification Tape
Provide detectable tape in accordance with Section 35 41 00 EMBANKMENT
CONSTRUCTION.
2.6 PULL ROPE
Plastic or flat pull line (bull line) having a minimum tensile strength of 200 pounds .
SECTION 33 71 02 Page 11
2.7 GROUNDING AND BONDING
2.7.1 Driven Ground Rods
Provide copper-clad steel ground rods conforming to UL 467 not less than 3/4 inch in diameter by in length. Sectional type rods may be used for rods 20 feet or longer.
2.7.2 Grounding Conductors
Stranded-bare copper conductors must conform to ASTM B8, Class B, soft-drawn unless otherwise indicated. Solid-bare copper conductors must conform to ASTM B1 for sizes No. 8 and smaller. Insulated conductors must be of the same material as phase conductors and green color-coded, except that conductors must be rated no more than 600 volts. Aluminum is not acceptable.
2.8 CAST-IN-PLACE CONCRETE
Provide concrete for encasement of underground ducts and other electrical work in accordance with Section 03 31 01 CAST-IN-PLACE STRUCTURAL CONCRETE
FOR CIVIL WORKS.
2.9 UNDERGROUND STRUCTURES
Provide precast concrete underground structures or standard type cast-in-place manhole types as indicated, conforming to ASTM C857 and ASTM C478. Top, walls, and bottom must consist of reinforced concrete.
Walls and bottom must be of monolithic concrete construction. Locate duct entrances and windows near the corners of structures to facilitate cable racking. Covers must fit the frames without undue play. Form steel and iron to shape and size with sharp lines and angles. Castings must be free from warp and blow holes that may impair strength or appearance. Exposed metal must have a smooth finish and sharp lines and arises. Provide necessary lugs, rabbets, and brackets. Set pulling-in irons and other built-in items in place before depositing concrete. Install a pulling-in iron in the wall opposite each duct line entrance. Cable racks, including rack arms and insulators, must be adequate to accommodate the cable.
2.9.1 Cast-In-Place Concrete Structures
Concrete must conform to Section 03 31 01 CAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORKS. Construct walls on a footing of cast-in-place concrete except that precast concrete base sections may be used for precast concrete manhole risers. Concrete block must conform to ASTM C139.
2.9.2 Precast Concrete Structures, Risers and Tops
Precast concrete underground structures may be provided in lieu of cast-in-place subject to the requirements specified below. Precast units must be the product of a manufacturer regularly engaged in the manufacture of precast concrete products, including precast manholes.
2.9.2.1 General
Precast concrete structures must have the same accessories and facilities as required for cast-in-place structures. Likewise, precast structures must have plan area and clear heights not less than those of cast-in-place structures. Concrete materials and methods of construction must be the
SECTION 33 71 02 Page 12 same as for cast-in-place concrete construction, as modified herein.
Slope in floor may be omitted provided precast sections are poured in reinforced steel forms. Concrete for precast work must have a 28-day compressive strength of not less than 5000 psi . Structures may be precast to the design and details indicated for cast-in-place construction, precast monolithically and placed as a unit, or structures may be assembled sections, designed and produced by the manufacturer in accordance with the requirements specified. Structures must be identified with the manufacturer's name embedded in or otherwise permanently attached to an interior wall face.
2.9.2.2 Design for Precast Structures
ACI 318M . In the absence of detailed on-site soil information, design for the following soil parameters/site conditions:
a. Angle of Internal Friction (phi) = 30 degrees
b. Unit Weight of Soil (Dry) = 110 pcf , (Saturated) = 130 pcf
c. Coefficient of Lateral Earth Pressure (Ka) = 0.33
d. Ground Water Level = 3 feet below ground elevation
e. Vertical design loads must include full dead, superimposed dead, and live loads including a 30 percent magnification factor for impact.
Live loads must consider all types and magnitudes of vehicular (automotive, industrial, or aircraft) traffic to be encountered. The minimum design vertical load must be for H20 highway loading per
AASHTO HB-17.
f. Horizontal design loads must include full geostatic and hydrostatic pressures for the soil parameters, water table, and depth of installation to be encountered. Also, horizontal loads imposed by adjacent structure foundations, and horizontal load components of vertical design loads, including impact, must be considered, along with a pulling-in iron design load of 6000 pounds .
g. Each structural component must be designed for the load combination and positioning resulting in the maximum shear and moment for that particular component.
h. Design must also consider the live loads induced in the handling, installation, and backfilling of the manholes. Provide lifting devices to ensure structural integrity during handling and installation.
2.9.2.3 Construction
Structure top, bottom, and wall must be of a uniform thickness of not less than 6 inches . Thin-walled knock-out panels for designed or future duct bank entrances are not permitted. Provide quantity, size, and location of duct bank entrance windows as directed, and cast completely open by the precaster. Size of windows must exceed the nominal duct bank envelope dimensions by at least 12 inches vertically and horizontally to preclude in-field window modifications made necessary by duct bank misalignment.
However, the sides of precast windows must be a minimum of 6 inches from the inside surface of adjacent walls, floors, or ceilings. Form the
SECTION 33 71 02 Page 13 perimeter of precast window openings to have a keyed or inward flared surface to provide a positive interlock with the mating duct bank envelope. Provide welded wire fabric reinforcing through window openings for in-field cutting and flaring into duct bank envelopes. Provide additional reinforcing steel comprised of at least two No. 4 bars around window openings. Provide drain sumps a minimum of 12 inches in diameter and 4 inches deep for precast structures.
2.9.2.4 Joints
Provide tongue-and-groove joints on mating edges of precast components.
Shiplap joints are not allowed. Design joints to firmly interlock adjoining components and to provide waterproof junctions and adequate shear transfer. Seal joints watertight using preformed plastic strip conforming to ASTM C990. Install sealing material in strict accordance with the sealant manufacturer's printed instructions. Provide waterproofing at conduit/duct entrances into structures, and where access frame meets the top slab, provide continuous grout seal.
2.9.3 Handhole Frames and Covers
Frames and covers of steel must be welded by qualified welders in accordance with standard commercial practice. Steel covers must be rolled-steel floor plate having an approved antislip surface. Hinges must be of stainless steel with bronze hinge pin , 5 by 5 inches by approximately 3/16 inch thick, without screw holes, and must be for full surface application by fillet welding. Hinges must have nonremovable pins and five knuckles. The surfaces of plates under hinges must be true after the removal of raised antislip surface, by grinding or other approved method.
2.9.4 Composite/Fiberglass Handholes and Covers
ANSI/SCTE 77 . Provide handholes and covers of polymer concrete, reinforced with heavy weave fiberglass with a design load (Tier rating) appropriate for or greater than the intended use. All covers are required to have the Tier level rating embossed on the surface and this rating must not exceed the design load of the box.
2.10 CABLE SUPPORTS (RACKS, ARMS, AND INSULATORS)
The metal portion of racks and arms must be zinc-coated after fabrication.
2.10.1 Cable Rack Stanchions
The wall bracket or stanchion must be 4 inches by approximately 1-1/2 inch by 3/16 inch channel steel, or 4 inches by approximately 1 inch glass-reinforced nylon with recessed bolt mounting holes, 48 inches long (minimum) in manholes. Slots for mounting cable rack arms must be spaced at 8 inch intervals.
2.10.2 Rack Arms
Cable rack arms must be steel or malleable iron or glass reinforced nylon and must be of the…