W912EP19B0010_Amend_0006.pdf
PDF 610 KB Posted
- Solicitation number
- W912EP19B0010
About this file
W912EP19B0010 Amendment 0006
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 19B0010_Abstract.pdf | ||
| W912EP19B0010_Amend_0007.pdf | ||
| W912EP19B0010_Amend_0005.pdf | ||
| W912EP19B0010_Amend_0004.pdf | ||
| 19-079_DTM.xyz | XYZ file | |
| Hardbottoms_Amendment0004.zip | ZIP file | |
| 19B0010_Site_Visit_Attendees.pdf | ||
| W912EP19B0010_Amend_0003.pdf | ||
| W912EP19B0010_Amend_0002.pdf | ||
| W912EP19B0010_Amend_0001.pdf | ||
| Gasparilla_Plans_20190201.pdf | ||
| 18-256_LEE_CO_BORROW_AREA_28_DEC_18_SB-44_NAVD88-N.xyz | XYZ file | |
| 19B0010Volume2Specs.pdf | ||
| 19B0010Volume1Specs.pdf | ||
| 18-200_DTM_USACE.xyz | XYZ file | |
| Gasparilla_GDR_-_Final.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Flood Control and Coastal Emergency, Shore Protection Project, Beach Renourishment, Gasparilla Island, Lee County, Florida
A. See Continuation Sheet For Amendments details.
B. The Bid Due Date Remain Unchanged 28 Mar 2019 @ 2:00 PM Local Time.
C. All Other Terms And Conditions Remain Unchanged
1. CONTRACT ID CODE PAGE OF PAGES
1 35
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 28-Feb-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EP19B0010
X 9B. DATED (SEE ITEM 11)
22-Feb-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Mar-2019
CODE
USA ENGINEER DISTRICT, JACKSONVILLE
CONTRACTING DIVISION
701 SAN MARCO BLVD
JACKSONVILLE FL 32207-8175
W912EP 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SF 30 CONTINUATION SHEET
Flood Control and Coastal Emergency, Shore Protection Project, Beach Renourishment, Gasparilla Island, Lee County, Florida
W912EP19B0010 2 Amendment 0006
SUMMARY OF CHANGES
1. SPECIFICATIONS:
DELETE Section 35 20 25 and REPLACE with the attached revised Section 35 20 25.
2. DRAWINGS: No change to drawings.
(End of Summary of Changes)
FCCE, Shore Protection Project, Beach Renourishment
SECTION TABLE OF CONTENTS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
SECTION 35 20 25
BEACH FILL
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 DEFINITIONS
1.3.1 Acceptance Sections
1.3.2 Compensating Slopes
1.3.3 Construction Baseline (CBL)
1.3.4 Maximum Excavation Depth
1.3.5 Target Depth
1.3.6 Hardbottom
1.3.7 Work Area
1.4 SYMBOL AND ACRONYM USE
1.5 SUBMITTALS
1.6 PROJECT SCOPE
1.6.1 Project Order of Work
1.6.2 Project Coordination
1.6.3 Project Work Permits and Responsibilities
1.6.3.1 Project Traffic and Navigation
1.6.4 Protection of Existing Structures from Construction Activity
1.6.4.1 Damages to Adjacent Property and Structures
1.6.5 Project Work Violations
1.6.6 Project Final Cleanup
1.7 ENVIRONMENTAL PROTECTION
1.7.1 Pumping of Bilges
1.7.2 Fuel Oil Transfer Operations
1.7.3 Turbidity
1.7.4 Protection of Existing Hardbottom and Cultural Resource Areas
1.7.5 Notification of Discovery of Historical Period Shipwreck Sites
1.8 GASPARILLA ISLAND STATE RECREATIONAL AREA LAND USE AGREEMENT
SPECIAL CONDITIONS FOR SOUTH REACH PLACEMENT
1.9 NOTIFICATION OF COAST GUARD
1.9.1 Navigation Aids
1.9.2 Dredging Aids
1.10 WORK AND ACCESS AREA
1.11 SIGNAL LIGHTS
1.12 CRANE AND DRAGLINE SAFETY REQUIREMENTS
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 OVERALL WORK AREA PROVISIONS
3.1.1 Construction Plans and Contract Documents
3.1.2 Staging and Access Areas
SECTION 35 20 25 Page 1 W912EP19B0010 Amendment 0006
3.1.2.1 Existing Conditions Documentation
3.1.3 Public Protection
3.1.3.1 Work Area Signs and Barriers
3.1.3.2 Dedicated Safety and Flag Person
3.1.4 Noise Control
3.1.4.1 Hauling and Excavating Equipment
3.1.4.2 Booster Pumps Noise Control
3.1.4.3 Sound Pressure Measurements
3.1.5 Buoy and Anchoring Inventory
3.1.6 Protection of Existing Vegetation
3.2 PROTECTION OF EXISTING HARDBOTTOM AND CULTURAL RESOURCE AREAS
3.3 EXCAVATION
3.3.1 General
3.3.2 Borrow Area Characteristics
3.3.3 Borrow Area Dredging
3.3.4 Overflow Dredging
3.3.5 Borrow Area Excavation Limitations
3.3.6 Unsuitable Material
3.3.7 Magnetic Anomalies
3.3.8 Probability of Rock in Borrow Area
3.3.9 Dredge Location Control
3.3.9.1 Hydraulic Dredge and Scow Control
3.3.9.2 Other Dredge Type Control
3.3.9.3 Color-Coded Plot and Dredge Track Drawing Contents
3.3.10 Deduction for Nonconforming Work
3.4 TRANSPORT OF EXCAVATED MATERIALS
3.4.1 Scow
3.4.1.1 Mis-Dump
3.4.1.2 Leakage
3.4.2 Pipeline Transportation
3.4.2.1 Submerged Pipeline
3.4.2.2 Floating Pipeline
3.4.2.3 Upland Pipeline
3.4.2.4 Visual Inspection of Pumpout and Pipeline Locations
3.4.3 Spillage and Leakage
3.4.3.1 Scows
3.4.3.2 Pipeline
3.4.4 Rock Screening and Removal
3.4.5 Existing Structures
3.5 BEACH FILL
3.5.1 General
3.5.2 Construction
3.5.2.1 Construction Equipment Limitations
3.5.2.2 Grade Stake Installation and Recovery Operations
3.5.2.3 Control of Fill
3.5.2.4 Ramps and Walkways
3.5.3 Placement
3.5.3.1 Dressing for Payment
3.5.3.2 Dressing for Final Acceptance
3.5.3.3 Escarpments
3.5.4 Tolerances
3.5.5 Misplaced Materials
3.6 QUALITY CONTROL
3.6.1 Preparatory Inspection
3.6.2 Initial Inspections
3.6.3 Follow-up Inspection
3.7 QUALITY CONTROL FOR BEACH FILL
3.7.1 Compliance Criteria for Beach Fill Material
3.7.2 Beach Fill Observation and Sampling
SECTION 35 20 25 Page 2
3.7.3 Determination of Areal Extent of Noncompliant Beach Fill
3.7.4 Remediation
3.7.5 Noncompliant and Unacceptable Material Contingency Plan
3.8 INSPECTION
3.8.1 Quality Assurance Representative (QAR)
3.8.2 Failure to Comply
3.9 CONSTRUCTION FORMS AND DETAILS
-- End of Section Table of Contents --
SECTION 35 20 25 Page 3
SECTION 35 20 25
BEACH FILL
PART 1 GENERAL
1.1 SUMMARY
The project work covered by this section consists of furnishing all plant, labor, equipment, supplies, and material, and of performing all operations in connection with excavating, transporting, and placing beach fill along the project shoreline as indicated on the drawings, as described by applicable permits, and/or as specified herein. Related sections are
01 11 00 SUMMARY OF WORK, 01 57 20 ENVIRONMENTAL PROTECTION, 01 57 25
TURBIDITY AND DISPOSAL MONITORING, and 02 22 13 VIBRATION MONITORING
REQUIREMENTS FOR EXISTING STRUCTURES.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D422 (1963; R 2007) Particle-Size Analysis of Soils
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
1.3 DEFINITIONS
1.3.1 Acceptance Sections
Fill placement acceptance sections are defined as the portion of the renourished beach lying between two immediately adjacent pay profile lines.
The Contractor shall propose acceptance section designations to the Contracting Officer's Representative (COR) prior to the start of the Government pre-fill surveys for review and approval. Typical beach fill acceptance sections are measured between 500 and 1000 feet along the CBL.
This may differ depending on fill densities along the fill profile.
1.3.2 Compensating Slopes
The allowance for pay volume above the fill tolerance to compensate for vacancies within the fill template due to sediment relocated by natural forces between the time of placement and payment surveys.
1.3.3 Construction Baseline (CBL)
To closely resemble the shoreline, a Construction Baseline (CBL) was established. The CBL determines the seaward/gulfward berm crest width and the construction stationing for pre- and post-payment surveys.
SECTION 35 20 25 Page 4
1.3.4 Maximum Excavation Depth
The maximum dredge depth is shown on the plans for each borrow area. The Contractor can not remove material below this depth.
1.3.5 Target Depth
Depth within the designated borrow area limits to which the Contractor shall excavate before being permitted by the Contracting Officer to proceed to another subdivision within that borrow area, or relocate to another borrow area.
1.3.6 Hardbottom
See Section 01 57 20 ENVIRONMENTAL PROTECTION.
1.3.7 Work Area
Work area is defined as the area where Contract work is to be performed, as shown on the contract drawings, impacted by contractor operations, and additional areas agreed by the Contracting Officer.
1.4 SYMBOL AND ACRONYM USE
/ = or b/c = because CBL = Construction Baseline FDEP = Florida Department of Environmental Protection
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Unless otherwise indicated below, Shop Drawings shall be submitted no later than 30 calendar days after Notice to Proceed.
General Work Plan; G, RO
The Contractor shall submit a Work Plan for review and approval by the Contracting Officer. The work plan shall include but not be limited to the following:
a. Excavation Depth Protection: Provide a detailed description of methods and equipment to be used for each operation, and the sequence of operations, including sketches showing how the Contractor will not excavate below the maximum excavation depth at the borrow area(s) as indicated in the contract drawings.
b. Progress Map: Provide a progress schedule map of the contractor's design. The progress schedule map shall be a plan view drawing depicting the beach fill site and access areas to
SECTION 35 20 25 Page 5 used on the project. The map shall show all acceptance sections (AS), access/staging areas, and pipeline landings anticipated to be used on the project. For each AS, the information shall list the following: Anticipated quantity of material per acceptance section, projected dates for fill to be placed and completed. The map shall provide dates when access areas are to be used and ready for public use. The map will be color coordinated with the following color scheme: Red depicting an area not ready for construction; Orange depicting an area currently being worked, and Green meaning an area accepted by the Contracting Officer and ready for public use. The map shall be updated at least weekly and whenever significant changes occur to the projected dates.
Since the map will be used by the Government for coordination with the public and to track progress, the update shall be provided prior to the weekly project progress meeting.
c. Buoy Log: The Contractor shall develop a method of inventory for all anchors, buoys, and buoy cables used in the construction of the project. This record shall be used by the Contractor to recover all buoys and anchoring equipment at the completion of the project
d. Grade Stake Log: The Contractor shall provide a sample Grade Stake Log used on the project and indicate how the log is prepared and maintained to inventory the grade stakes used on the project. The log shall include information concerning the location, installation, and recovery of all grade stakes. The Contractor shall make this log available for review by the appropriate Government personnel upon request. Upon completion of the project, the Contractor shall furnish the log to the Contracting Officer.
e. Staging and Access Area: The Contractor shall indicate if they plan on obtaining additional access or staging areas for their construction operations other than what is shown on the drawings. If the Contractor plans on obtaining additional access/staging areas, submit proposed drawings depicting the areas for Contracting Officer approval. Contractor shall also provide staging and access area existing conditions per Section 01 50 02
TEMPORARY CONSTRUCTION FACILITIES.
f. Public Protection: Provide a Contractor's plan for ensuring pedestrian, worker, and vehicular safety at each access location used by the Contractor. Submit means and methods for pedestrian protection during beach fill operations for review and approval by the Contracting Officer. Submit product information and methods of installation for orange safety fencing for crowd control.
Submit methods of staking in place and maintenance of system for duration of construction.
Relocation of Navigation Aids
Within 7 calendar days following receipt of Notice of Award, the Contractor shall notify the Commander, Seventh Coast Guard District, Miami, Florida of their plan to dredge adjacent to any aids which require relocation to facilitate dredging for each project fill segment. The notification shall be sent via Fax to 305-415-6757, ATTN: Mr. Gene Stratten. This notification shall be immediately followed by a formal written request with a copy to
SECTION 35 20 25 Page 6 the Contracting Officer. The Contractor shall also contact the U.S. Coast Guard at 305-415-6750 for information concerning the position to which the aids will be relocated.
Construction and Grade Stakes Recovery Plan; G, RO
The Contractor shall submit a Construction and Grade Stakes Recovery Plan. The plan will outline the steps that the Contractor will implement to recover all the stakes used on the project. This plan will include the use of the Grade Stake Log submitted with the General Work Plan above. A sample plan is on the web site indicated in paragraph CONSTRUCTION FORMS AND DETAILS below, with further information provided in paragraph "Grade Staking and Removal" below.
Material Screening And Removal Plan
The Contractor shall submit to the Contracting Officer a plan detailing the method for screening and removal of material. The plan shall also include the method for which the quantity of material removed is measured and the location of material disposal for acceptance by the Contracting Officer.
Noncompliant and Unacceptable Material Contingency Plan
Submit a Noncompliant Material Contingency Plan as indicated in paragraph QUALITY CONTROL FOR BEACH FILL below.
Electronic Tracking System Charts
The Contractor shall furnish required plotted charts to the Contracting Officer.
Dredge Location Control Color-Coded Plot
The Contractor shall furnish the required color-coded plots to the Contracting Officer.
SD-04 Samples
Quality Control for Beach Fill
Beach sediment samples shall be collected and stored a the on-site trailer for inspection. Refer to paragraph QUALITY CONTROL FOR BEACH FILL below for further details on sampling.
SD-07 Certificates
Notice of Intent to Dredge; G, RO
Prior to commencement of work on this contract, the Contractor will be required to notify the Commander, Seventh Coast Guard District of their intent to dredge and request that it be published in the Local Notice to Mariners. This notification must be given in sufficient time so that it appears in the Notice to Mariners at least 30 calendar days prior to the commencement at each project segment. A copy of the notification shall be provided to the Contracting Officer.
SECTION 35 20 25 Page 7
Equipment and Performance Data; G, RO
The Contractor shall furnish proof of electronic positioning equipment calibration to the Contracting Officer.
Grade Stake Recovery; G, DO
After completion of the project, the Contractor shall provide a letter to the Contracting Officer certifying that all grade stakes have been recovered in accordance with the Contractor's approved Construction and Grade Stake Recovery Plan. With the certification, the Contractor shall also furnish the completed Grade Stake log to the Contracting Officer. Refer to paragraph GRADE STAKING AND REMOVAL below.
Buoy and Anchoring Inventory Recovery; G, DO
After completion of the project, the Contractor shall provide a letter to the Contracting Officer certifying that all anchors, buoys, buoy cables used in the construction of the project have been recovered in accordance with the Contractor's approved Anchor and Buoy Recovery below. With the certification, the Contractor shall also furnish the completed Buoy and Anchoring Inventory Record
Notification of Discovery of Historical Period Shipwreck Sites
The Contractor shall immediately notify the Contracting Officer if any shipwreck, artifact, or other objects of antiquity that have scientific or historical value, or are of interest to the public, are discovered, located, and/or recovered.
Daily/Monthly Report of Operations
The Contractor shall prepare on RMS and submit two (2) hard copies of the Daily Report of Operations, using either ENG Form No. 27A or ENG Form No. 4267, for each dredge and/or unloader working. This report shall be submitted on a daily basis and not in groups (groups = multi-days reports packaged together at one time). In addition to the daily report, the Contractor shall prepare a Monthly Report of Operations for each month or partial month's work on either ENG Form No. 27A or ENG Form No. 4267. The monthly report shall be submitted on or before the 7th of each month, consolidating the previous month's work. Upon completion of the job, the Contractor shall submit a consolidated job report, combining the monthly reports. The Contractor shall distribute one copy of each report to the District Engineer, ATTN:
CESAJ-EN-C; U.S. Army Engineer District, Jacksonville, P.O. Box 4970, Jacksonville, Florida 32232-0019. Reports shall be submitted on a monthly basis with daily reports accompanying the monthly report and job report.
Additionally, one copy of these forms shall be maintained by the Contractor on the dredge(s) for the Contracting Officer's inspection purpose. Further instructions on the preparation of the reports will be furnished at the Preconstruction Conference.
Notice of Misplaced Material
SECTION 35 20 25 Page 8
The Contractor shall notify the U.S. Coast Guard Marine Safety Office of any misplaced material as stated in Clause OBSTRUCTION OF NAVIGABLE WATERWAYS of Section 00700 CONTRACT CLAUSES.
Declaration of Inspection
Refer to paragraph FUEL OIL TRANSFER OPERATIONS below for submittal.
SD-11 Closeout Submittals
Grade Stake Log; G, RO
Upon completion of work, submit the grade stake log indicating recovery of all grade stakes.
1.6 PROJECT SCOPE
The Contractor shall provide the dredge and support vessels, labor, equipment, supplies, and materials to perform all operations for excavating, transporting, placing, dressing and grading (and possible tilling) beach fill on the beaches as indicated in the drawings and further specified herein. The Contractor shall accomplish the work in such a manner so as to minimize disruption to road and maritime traffic or use of the public beach as well as minimize impacts to existing infrastructure.
The use of hopper dredges is prohibited.
1.6.1 Project Order of Work
The north reach shall be completed first and south reach shall be completed second. The project shall be completed and accepted by the Contracting Officer prior to the specified project end date as provided in clause 52.211-10. Once the filling operation commences, within the fill placement site, the Contractor shall maintain a continuous filling operation without any intervening gaps until the entire project segment is completed and accepted by the Contracting Officer..
The project shall be completed and accepted by the Contracting Officer prior to the specified project end date as provided in clause COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK of Section 00700 CONTRACT CLAUSES.
1.6.2 Project Coordination
Project coordination with the Contracting Officer shall occur during all phases of construction. Coordination also includes but is not limited to coordinating with local officials including police, Public, FDEP, US Coast Guard, and others as agreed during coordination meetings. See paragraph PROJECT COORDINATION of Section 01 30 00 ADMINISTRATIVE PROCEDURES and Paragraph COORDINATION MEETING of Section 01 45 05 DREDGING/BEACH FILL
PLACEMENT - CONTRACTOR QUALITY CONTROL.
1.6.3 Project Work Permits and Responsibilities
The Contractor's attention is directed to the Clause PERMITS AND RESPONSIBILITIES of Section 00700 CONTRACT CLAUSES and paragraph PERMITS AND AUTHORIZATIONS of Section 01 57 20 ENVIRONMENTAL PROTECTION. Any other licenses or approvals required for the prosecution of the work shall be secured and paid for by the Contractor. The Contractor shall obtain any and all approvals required to conduct work in the Gulf of Mexico.
SECTION 35 20 25 Page 9
1.6.3.1 Project Traffic and Navigation
The Contractor shall so conduct their operations that they shall not close any thoroughfare nor interfere in any way with traffic on railway, highways, or on water, without the written consent of the Contracting Officer. The regulations the Contractor shall adhere to are those established by, but not necessarily limited to, the Department of the Navy, U.S. Coast Guard, Department of the Army, American Bureau of Shipping, Florida Department of Environmental Protection, Florida Department of Transportation, Florida Law Enforcement Agencies, county and municipal.
1.6.4 Protection of Existing Structures from Construction Activity
The Contractor shall be responsible for determining and documenting the pre-construction condition of existing structures within the project area.
The Contractor shall take appropriate measures to prevent damage to any structures during construction, and for performing a post-construction verification inspection of those structures previously inspected. Refer to Section 02 22 13 VIBRATION MONITORING REQUIREMENTS FOR EXISTING STRUCTURES for further details and guidelines.
1.6.4.1 Damages to Adjacent Property and Structures
Any damage to private or public property within the project boundaries, including staging site(s) and work and access areas/roads, shall be repaired promptly by the Contractor. Any damage as a result of the Contractor's operations shall be repaired at no cost to the Government.
The Contractor will not receive final payment until all damages are restored to the satisfaction of the Contracting Officer.
1.6.5 Project Work Violations
Work done in violation of these specifications or a verbal or written stop order of the Contracting Officer will be considered as unsatisfactory progress for purposes of progress payments in accordance with clause PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS of Section 00700 CONTRACT
CLAUSES.
1.6.6 Project Final Cleanup
Final cleanup, as stated in the paragraph COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK of Section 00700 CONTRACT CLAUSES, shall include the removal of all of the Contractor's plant and equipment either for disposal or reuse. Plant and/or equipment to be disposed of shall ONLY be disposed of in a manner and at locations approved by the Contracting Officer.
Unless otherwise approved in writing by the Contracting Officer, the Contractor will not be permitted to abandon pipelines, pipeline supports, pontoons, or other equipment in the disposal area, pipeline access areas, water areas, or other areas adjacent to the work site. Pilings and any other debris removed or created as a result of the execution of this contract shall be disposed of in a manner and at locations approved by the Contracting Officer.
1.7 ENVIRONMENTAL PROTECTION
The Contractor shall protect the environment during all phased of work.
See Section 01 57 20 ENVIRONMENTAL PROTECTION for additional details.
SECTION 35 20 25 Page 10
1.7.1 Pumping of Bilges
Contractors are warned that pumping oil or bilge water containing oil into navigable waters, or into areas which would permit the oil to flow into such waters, is prohibited by Section 13 of the River and Harbor Act of 1899, approved 3 March 1899 (30 Stat. 1152; 33 U.S.C. 407). Violation of this prohibition is subject to penalties provided under the referenced Act.
1.7.2 Fuel Oil Transfer Operations
In accordance with U.S. Coast Guard regulations (33 CFR 156.120), couplings used in fuel oil transfer operations on any vessel with a capacity of 250 or more barrels of oil shall be either a bolted or full-threaded connection; or a quick-connect coupling approved by the Commandant; or an automatic back-pressure shutoff nozzle used to fuel the vessel. An executed fuel oil transfer (Declaration) form signed by the tanker operator shall be submitted to the Contracting Officer for each refueling operation. The U.S. Coast Guard shall also be notified prior to any refueling. A copy of the Declaration of Inspection for Refueling is on the web site indicated in paragraph CONSTRUCTION FORMS AND DETAILS below.
1.7.3 Turbidity
Excavation, transport, and filling operations shall be performed in a manner that will minimize turbidity. The Contractor shall meet the requirements to maintain the quality of the State's waters as stipulated in Section 01 57 25 TURBIDITY AND DISPOSAL MONITORING, project permits and in the Florida Administrative Code Rule 62-3.121. The Contractor will be required to make inspections, measurements and observations required by those regulations and the FDEP permit in the vicinity of the dredge and at the placement site (beach).
1.7.4 Protection of Existing Hardbottom and Cultural Resource Areas
The Contractor shall protect hardbottom (reefs) and cultural resources during all phases of the project. The location of known offshore hardbottom areas and cultural resource areas is provided in the plans for the convenience of the Contractor. The Contractor shall avoid contact with any and all hardbottom communities. The Contractor shall not depend solely on the hardbottom mapping provided. It will be the responsibility of the Contractor to utilize scientific divers and/or any other reliable means to field verify the placement of pipes, spuds, anchors, cables, drag arms or any other objects on the bottom relative to the hardbottom survey in the drawings during placement to ensure there are no hardbottom formations in jeopardy prior to placing pipes, spuds, anchors, cables, drag arms or any other objects on the bottom. Please refer to 01 57 20 ENVIRONMENTAL
PROTECTION.
1.7.5 Notification of Discovery of Historical Period Shipwreck Sites
If any shipwreck, artifact, or other objects of antiquity that have scientific or historical value, or are of interest to the public, are discovered, located, and/or recovered, the Contractor acknowledges that:
a. The site(s), articles, or other materials are the property of the State of Florida, with title vested in the Department of State, Division of Historical Resource; and
b. shall immediately notify the Contracting Officer.
SECTION 35 20 25 Page 11
Refer to subparagraph "Preservation and Recovery of Historic, Archeological, and Cultural Resources" of Section 01 57 20 ENVIRONMENTAL
PROTECTION.
1.8 GASPARILLA ISLAND STATE RECREATIONAL AREA LAND USE AGREEMENT SPECIAL
CONDITIONS FOR SOUTH REACH PLACEMENT
The following special conditions shall apply to this use agreement:
a. Contractor shall comply with all the terms and conditions as set forth in this use agreement and State of Florida Department of Environmental Protection’s Consolidated Joint Coastal Permit No. 0358239-001-JC (the “Permit”).
b. Contractor shall meet with the Contracting Officer before undertaking construction activities in the Park. The time and frequency of such meetings shall be agreed to by the Contracting Officer and Contractor prior to mobilization activities. During the pre-construction meeting, Contracting Officer and Contractor shall determine specific needs for the staging area and agree on operational conditions of utilizing the staging area and access. Contractor shall also provide to Contracting Officer contact information of Contractor’s onsite project manager.
c. Contractor shall ensure that access to a portion of the Park is not disrupted while construction is underway, or at any time during the term of this use agreement unless approved by the Contracting Officer in advance, see special condition E.
d. Contractor shall help to protect Park facilities, plants, and other natural resources by accessing the Park at the points designated by the Contracting Officer and driving only on those beach areas within the Park, as identified by the Contracting Officer.
e. Contractor shall establish a safe zone by providing signage and fencing as needed to prevent access to the staging area(s), the worksite, and areas worked by heavy equipment.
f. Contractor shall keep fuel and other poisonous, hazardous, or flammable liquids and powders in a double-walled container with a catch basin, with the catch basin labeled as hazardous. Contractor shall conduct refueling operations within the staging areaonly.
g. Contractor shall repair any damages caused by the installation or removal of the pipeline, or by breach of the pipeline during sediment pumping operations. Contractor shall restore the affected areas to pre-existing conditions following the fulfillment of the project or demobilization. This restoration may include the removal of accidentally deposited materials, restoring grade, and planting native vegetation in the areas of damage. If any revegetation is required, the contractor is required to utilize native plant material and seed stock from the southwest gulf coast of Florida. The mixture of native species and the number of plants shall be determined by the Contracting Officer in consultation with the district biologist.
h. Contractor shall ensure that all stationary and mechanized equipment to be used has been thoroughly cleaned to help prevent exotic or invasive species from entering the Park. The Contracting Officer reserves the right to inspect and deny Park access to equipment that has not been
SECTION 35 20 25 Page 12 sufficiently cleaned.
i. Contractor shall stop work in the event the Contracting Officer observes conditions in which the general public, or cultural and natural resources, are deemed to be in imminent danger. The Contracting Officer will instruct the Contractor to stop work only on the activity which is the source of danger, not the entire dredging operation itself. The Contracting Officer will also notify Contractor’s contracting officer or project manager immediately if such an event should occur. Contractor shall work cooperatively with the Contracting Officer and district biologist to resolve issues regarding safety, access, or environmental concerns resulting from this project.
j. Contractor shall notify the Contracting Officer twenty-four (24) hours in advance before commencing any post project repairs, maintenance, revegetation, and tilling and escarpment removal.
1.9 NOTIFICATION OF COAST GUARD
1.9.1 Navigation Aids
Navigation aids located within or near the areas required to be dredged will be removed, if necessary, by the U.S. Coast Guard in advance of dredging operations. The Contractor shall not remove, change the location of, obstruct, willfully damage, make fast to, or interfere with any aid to navigation.
1.9.2 Dredging Aids
The Contractor shall obtain approval from the U.S. Coast Guard for all buoys, dredging aid markers to be placed in the water, and dredging aid markers affixed with a light prior to the installation. Dredging aid markers and lights shall not be colored or placed in a manner that they will obstruct or be confused with navigation aids.
1.10 WORK AND ACCESS AREA
Please provide any site specific notice of interest for the Contracting Officer. Anything that early on brings their attention to the work, but do not provide guidance on execution (just general information). Comply with work and access area requirements indicated herein and in Section 01 57 20
ENVIRONMENTAL PROTECTION.
1.11 SIGNAL LIGHTS
The Contractor shall display signal lights and conduct operations in accordance with the General Regulations of the Department of the Army and of the Coast Guard governing lights and day signals. Lights and day signals shall be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations.
Lights shall be displayed on dredge pipe lines, and day signals shall be displayed by vessels of more than 65 feet in length and floating plant vessels moored or anchored in a fairway or navigable channels where other vessels pass. Lights and days signals shall also comply with the requirements of Section 01 57 20 ENVIRONMENTAL PROTECTION, the Secretary of the Army, and Commandant U.S. Coast Guard Instruction M16672.2, Navigation Rules: International-Inland (COMDTINST M16672.2), or 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 89 (Inland) as applicable.
SECTION 35 20 25 Page 13
1.12 CRANE AND DRAGLINE SAFETY REQUIREMENTS
All cranes and draglines used in performing the Work set forth in these specifications shall comply with EM 385-1-1. Please refer to Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS for further details.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 OVERALL WORK AREA PROVISIONS
The construction and borrow area limits available to the Contractor for accomplishing the work are shown on the drawings. The Contractor shall accomplish the work in such a manner so as to minimize disruption to road traffic and use of the public beach as well as keep all work areas in a neat, orderly and in a safe manner. The Contractor will be required to maintain all access roads and all other work areas within or without the project boundaries free from dust and noise which would cause a hazard or nuisance to others.
3.1.1 Construction Plans and Contract Documents
A minimum of one (1) complete set of construction plans (drawings) and contract documents (with permits and Notice to Proceed placards) shall be kept in the construction site field office. The dredge must have a complete set of drawings, including borrow area coordinates, at all times to avoid dredging outside of the borrow areas.
3.1.2 Staging and Access Areas
a. The final limits of the staging and access areas indicated on the drawings shall be field-determined by the Contracting Officer in coordination with the local sponsor and the Contractor. It shall be the responsibility of the Contractor to investigate and obtain any additional areas which may be necessary for their construction operations. The additional areas will be subject to the approval of the Contracting Officer.
b. The access and staging areas shall be restored to the pre-construction condition upon project completion at cost to the Contractor.
c. The staging areas shall be kept neat, orderly and in a safe manner.
d. The Contractor shall cordon off and/or fence the staging areas to secure all staging areas from the public.
e. The staging areas shall be restored to the pre-construction condition upon project completion at cost to the Contractor.
f. For staging areas on the beach, construction equipment shall be located off the beach as much as practicable during sea turtle monitoring. Regardless of time, all construction pipes that are placed on the beach shall be located as far landward as possible without compromising the integrity of the existing or reconstructed dune system. Temporary storage of pipes shall be off the beach to the
SECTION 35 20 25 Page 14 maximum extent possible. If the pipes are placed on the beach, they shall be placed in a manner that will minimize the impact to nesting habitat and shall not compromise the integrity of the dune systems.
The staging areas shall not be used for stockpiling of beach fill material.
g. The Contractor shall be responsible for providing and maintaining access necessary for his equipment and plant to and from the work site, mooring area, and disposal area. The Contractor shall ascertain the environmental conditions which can affect the access such as climate, winds, currents,waves, depths, shoaling, and scouring tendencies.
3.1.2.1 Existing Conditions Documentation
At all access sites and staging areas to be used, the Contractor shall:
a. Photo-document the condition of the access location prior to disrupting the site.
b. Limit access width through existing vegetation to 20 feet or less.
c. Replace any fencing, signage or curbing disturbed by the Contractor's activities.
d. Restore and revegetate the access route with native dune plants subject to the approval of the Contracting Officer. Revegetation of access and staging areas shall be with sod (non-dune areas) or viable plant units (dune areas) at 18-inch maximum spacing with species and diversity equivalent to preconstruction conditions. Revegetation shall include a survival warranty of 90 percent of the plant material for 90 days. Vegetation shall be installed with fertilization and irrigation, or with initial irrigation, fertilization and approved water-absorbent polymeric gels, at no additional expense to the Government. Shrubs and trees shall be replaced to preconstruction conditions per the requirements of Section 01 57 20 ENVIRONMENTAL PROTECTION.
3.1.3 Public Protection
a. The Contractor will be required to exclude the public for safety purposes from the work areas in the vicinity of the hydraulic fill placement, grading and transporting operations, or any other area which may present a safety risk to the public, such as the discharge end of their pipeline and all associated equipment such as fuel tanks, booster bumps, etc.
b. All equipment transiting the beach outside the Contractor's designated work area (i.e. beyond the beach fill discharge areas that are otherwise already temporarily closed to public with orange safety fencing) shall be escorted by a safety vehicle (e.g. ATV, utility vehicle, or truck). Each person operating any vehicle on the beach shall be required to take the City of Jacksonville's beach driving safety course which shall be scheduled with the city at Preconstruction Conference.
c. The Contractor shall minimize the areas closed to the public.
d. The Contractor shall be responsible for providing and maintaining all water and land access routes necessary for their equipment and
SECTION 35 20 25 Page 15 plant to and from the work sites.
e. The Contractor shall ascertain the environmental conditions which can affect water and land access, such as climate, terrain, winds, current, waves, swells, depths, shoaling, and scouring tendencies.
3.1.3.1 Work Area Signs and Barriers
The Contractor shall install warning signs to warn the public and all commercial and recreational boats of all construction activities.
a. Any existing signs, buoys or other structures within the work lines shall be protected and/or removed and later replaced by the Contractor as directed.
b. The Contractor shall be required to erect, maintain, and move as necessary, a restrictive barrier around the active construction zone including the area of discharge of the hydraulic pipeline (or other mechanical off loader), where bulldozers are working, or any other active area where Work may present a safety hazard to the public. In the vicinity of the discharge, the barrier shall be constructed so as to prevent the public from approaching the discharge from any direction closer than 100 feet, and will provide an area sufficient in size for the safe progression of the Work. The Contractor shall post signs in a conspicuous manner designating the closed area.
c. The Contractor shall post signs in a conspicuous manner stating
"DANGER - HIGH PRESSURE DISCHARGE FROM DREDGE".
d. Enforcement shall be the Contractor's responsibility at no additional cost to the Government. The enforcement shall be coordinated with local enforcement agencies, and will be subject to approval of the Contracting Officer.
3.1.3.2 Dedicated Safety and Flag Person
The Contractor shall have a dedicated safety and flag person on site at all times, whose sole responsibility is preventing the public from entering the work area. Additionally, the Contractor shall place a safety person at the discharge end of the disposal pipeline. The safety person shall be present at all times during discharge operations and will maintain radio communication between the dredge and the disposal operation.
3.1.4 Noise Control
3.1.4.1 Hauling and Excavating Equipment
All hauling and excavation equipment including dredges used on this work shall be equipped with satisfactory mufflers or other noise abatement devices. The Contractor shall conduct his operations so as to comply with all federal, state, and local laws or ordinances pertaining to noise abatement. The use of horns, bells, or the use of whistle signals shall be held to the minimum necessary in order to insure as safe and as quiet an operation as possible.
3.1.4.2 Booster Pumps Noise Control
Booster pumps used on this work shall be equipped with satisfactory mufflers and/or other sound abatement devices to reduce engine noise. A
SECTION 35 20 25 Page 16 sound barrier of the Contractor's own design will be constructed landward of booster pumps in order to reflect noise waterward. The Contractor shall conduct his operations so as to comply with all Federal, State, and local laws pertaining to noise.
3.1.4.3 Sound Pressure Measurements
a. Sound pressure measurements shall be made with a sound level meter and shall be reported to the Contracting Officer under provisions for contractor quality control.
b. The measurements shall be made by personnel qualified to make such measurements and whose credentials have been verified by the Contracting Officer.
c. For Land based equipment other than booster pumps, sound pressure measurements shall be made at distances of 50 feet, 100 feet, 300 feet, and 500 feet from each major piece of equipment such as draglines, dump trucks, dewatering pumps, pneumatic drills, bulldozers, etc., at locations approved by the Contracting Officer. The measurements shall be taken during operations every 4 weeks.
d. Sound pressure measurements shall be made by the Contractor at 50-foot, 100-foot, 200-foot, and 300-foot distances from the (1) dredge, (2) booster pumps, if any, and (3) dredge pipeline at locations approved by the Contracting Officer. These measurements shall be taken during pumping operations every 4 weeks. The sound pressure measurements and type of material being dredged at the time measurements are taken shall be reported to the Contracting Officer.
Sound pressure measurements shall be made twice at the direction of the Contracting Officer during the first 4 weeks of use of whistle signals and drill barges in operation at 50-foot, 100-foot, 200-foot, and 300-foot distances.
e. Temperature, atmospheric pressure and general weather conditions shall also be recorded with the measurements.
f. In addition to the testing indicated above, more testing may be requested by the Contracting Officer.
3.1.5 Buoy and Anchoring Inventory
The Contractor shall inventory all anchors, buoys, and buoy cables deployed in the prosecution of work in a manner acceptable to the Contracting Officer. The Contractor shall use this information to account for and recover these items upon completion of work.
3.1.6 Protection of Existing Vegetation
In areas where the design fill template would cover existing vegetation greater than 25 square feet in area, the Contractor shall avoid impacts as much as possible or as directed by the Contracting Officer. In these areas, the Contractor can slope down at 1V:3H to existing grade so that existing vegetation is not covered as much as practicable
3.2 PROTECTION OF EXISTING HARDBOTTOM AND CULTURAL RESOURCE AREAS
The Contractor must adhere to Dredge and Vessel exclusion outfall avoidance zones and "no dredge or work areas" shown on Plans. All mobilization and
SECTION 35 20 25 Page 17 demobilization activities and vessel usage during the project into and from the project area shall occur through the ingress/egress corridor which shall be field located and verified by scientific divers relative to the hardbottom survey in the drawings to avoid impacting existing hardbottom areas during pipeline laydown. No floating (individual or rafted) equipment is allowed over hardbottom and/or reef areas. The Contractor shall not anchor, place spuds, lay pipeline or place any other object on the hardbottom or within the cultural buffer zone. The Contractor shall operate vessels other than survey or crew boats solely within the ingress/egress corridor which shall be field located and verified by scientific divers relative to the hardbottom survey in the drawings to avoid impacting existing hardbottom areas during pipeline laydown. The Contractor shall train all subcontractors and work crews involved with dredging, pipeline installation, and equipment movements and storage on the procedures to be used to avoid impacts to offshore hardbottom communities and identified cultural resources. The training shall include methods or procedures to be used to avoid impacts and insure hardbottom and cultural resource protection. If damage to hardbottoms is detected, the damage shall be reported to the Contracting Officer immediately. The Contractor may be required to perform mitigation for unapproved substantial impacts to hardbottoms at no cost to the Government.
3.3 EXCAVATION
3.3.1 General
All excavation for beach fill shall be performed within the limits and depths of each borrow area shown on the drawings. Borrow areas provided for each fill segment are permitted for that particular beach fill segment and cannot be used interchangeable between project fill segments. Existing conditions of the borrow area are represented on the hydrographic survey and core boring logs in the Geotechnical Data Report (See Section 01 11 00 SUMMARY OF WORK). Excavation shall be performed in a uniform and continuous manner so as to avoid creating multiple holes, valleys, or ridges. If continuous reaches of rock are encountered in the borrow area, the Contractor shall change the location and depth of excavation within the borrow limits when necessary to provide the best fill material available at no additional cost to the Government. The Contractor shall remove no material deeper than the maximum elevation shown on the plans for each area of the borrow area. The Contractor's dredge equipment may extend and disturb material below the maximum excavation depth, provided that the post construction survey of the borrow area does not show that material was removed below the maximum excavation depth. The location of unsuitable material encountered within the borrow area shall be noted on the Contractor's Quality Control Report (copy appended to the end of Section 01 45 05 DREDGING/BEACH FILL PLACEMENT - CONTRACTOR QUALITY CONTROL). If the Contracting Officer determines the quality of beach fill is being adversely affected, that location shall be avoided in future passes of the dredge.
3.3.2 Borrow Area Characteristics
The characteristics of the materials in the borrow areas may be as generally indicated by the sediment boring logs and grain size distribution curves area located in Section 00 31 32 GEOTECHNICAL DATA REPORT (GDR).
The descriptions of the material found within the GDR are based on the site investigations and core borings and only describe the materials obtained from those investigations. The Contractor is solely responsible for any interpretation or conclusions drawn therefrom. The Contractor may visit
SECTION 35 20 25 Page 18 the location to view the core samples prior to the start of construction.
The Contractor shall provide a five (5) day notice to the Contracting Officer or their represent agent of their requested visit. The material found in each of the borrow area sediment core borings (vibracores) is indicative only of the sand at that discrete location. The CONTRACTOR should be aware that it is possible for material of differing characteristics to be present in the borrow areas, including material differing from that contained in the vibracores.
3.3.3 Borrow Area Dredging
The borrow area and each subdivision, unless otherwise directed by the Contracting Officer shall be completely excavated to the target depth before relocating the dredge to another borrow area or subdivision.
Excavation shall be performed in a uniform and continuous manner so as to avoid creating multiple holes, valleys, or ridges. The borrow area shall be dredged to maximize the removal of sand from each sub-area of each provided borrow area. The purpose of this requirement is to avoid "wasting" sediment which could be used to renourish the beach now and in the future.
3.3.4 Overflow Dredging
Overflow is considered a part of the dredging process and is permitted…
This is the start of the file's text. The full file is on GovTribe.