About this file

W912EP19B0010 Amend 0004

View the file

Other files

File Type Posted
19B0010_Abstract.pdf PDF
W912EP19B0010_Amend_0007.pdf PDF
W912EP19B0010_Amend_0006.pdf PDF
W912EP19B0010_Amend_0005.pdf PDF
19-079_DTM.xyz XYZ file
Hardbottoms_Amendment0004.zip ZIP file
19B0010_Site_Visit_Attendees.pdf PDF
W912EP19B0010_Amend_0003.pdf PDF
W912EP19B0010_Amend_0002.pdf PDF
W912EP19B0010_Amend_0001.pdf PDF
Gasparilla_Plans_20190201.pdf PDF
18-256_LEE_CO_BORROW_AREA_28_DEC_18_SB-44_NAVD88-N.xyz XYZ file
19B0010Volume2Specs.pdf PDF
19B0010Volume1Specs.pdf PDF
18-200_DTM_USACE.xyz XYZ file
Gasparilla_GDR_-_Final.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Flood Control and Coastal Emergency, Shore Protection Project, Beach Renourishment, Gasparilla Island, Lee County, Florida

A. See Continuation Sheet For Amendments details.

B. The Bid Due Date Remain Unchanged 28 Mar 2019 @ 2:00 PM Local Time.

C. All Other Terms And Conditions Remain Unchanged

1. CONTRACT ID CODE PAGE OF PAGES

1 115

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 13-Mar-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EP19B0010

X 9B. DATED (SEE ITEM 11)

22-Feb-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

13-Mar-2019

CODE

USA ENGINEER DISTRICT, JACKSONVILLE

CONTRACTING DIVISION

701 SAN MARCO BLVD

JACKSONVILLE FL 32207-8175

W912EP 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SF 30 CONTINUATION SHEET

Flood Control and Coastal Emergency, Shore Protection Project, Beach Renourishment, Gasparilla Island, Lee County, Florida

W912EP19B0010 2 Amendment 0004

SUMMARY OF CHANGES

1. SPECIFICATIONS:

DELETE Section 00800A and REPLACE with the attached revised Section 00800A.

DELETE Section 01 11 00 and REPLACE with the attached revised Section 01 11 00.

DELETE Section 01 22 00 and REPLACE with the attached revised Section 01 22 00.

DELETE Section 01 57 20 and REPLACE with the attached revised Section 01 57 20.

DELETE Section 01 57 25 and REPLACE with the attached revised Section 01 57 25.

DELETE Section 35 20 25 and REPLACE with the attached revised Section 35 20 25.

2. DRAWINGS:

DELETE Sheet ID G-01 and REPLACE with the attached revised Sheet ID G-01.

DELETE Sheet ID G-02 and REPLACE with the attached revised Sheet ID G-02.

DELETE Sheet ID G-03 and REPLACE with the attached revised Sheet ID G-03.

DELETE Sheet ID G-04 and REPLACE with the attached revised Sheet ID G-04.

DELETE Sheet ID G-05 and REPLACE with the attached revised Sheet ID G-05.

DELETE Sheet ID C-01 and REPLACE with the attached revised Sheet ID C-01.

DELETE Sheet ID C-02 and REPLACE with the attached revised Sheet ID C-02.

DELETE Sheet ID C-03 and REPLACE with the attached revised Sheet ID C-03.

DELETE Sheet ID C-04 and REPLACE with the attached revised Sheet ID C-04.

DELETE Sheet ID C-05 and REPLACE with the attached revised Sheet ID C-05.

DELETE Sheet ID C-06 and REPLACE with the attached revised Sheet ID C-06.

DELETE Sheet ID C-07 and REPLACE with the attached revised Sheet ID C-07.

DELETE Sheet ID C-08 and REPLACE with the attached revised Sheet ID C-08.

DELETE Sheet ID C-09 and REPLACE with the attached revised Sheet ID C-09.

DELETE Sheet ID C-10 and REPLACE with the attached revised Sheet ID C-10.

DELETE Sheet ID C-11 and REPLACE with the attached revised Sheet ID C-11.

DELETE Sheet ID C-12 and REPLACE with the attached revised Sheet ID C-12.

DELETE Sheet ID C-13 and REPLACE with the attached revised Sheet ID C-13.

DELETE Sheet ID C-14 and REPLACE with the attached revised Sheet ID C-14.

DELETE Sheet ID C-15 and REPLACE with the attached revised Sheet ID C-15.

DELETE Sheet ID C-16 and REPLACE with the attached revised Sheet ID C-16.

3. AVAILABLE INFORMATION:

Zipped file named “Hardbottoms_Amendment0004.zip” containing the hardbottom 2018 survey DGN file, hardbottom pre-construction monitoring report, and hardbottom Biological Monitoring Plan and beach survey XYZ file “19-079_DTM.xyz”.

(End of Summary of Changes)

Section 00800A - WAGE DETERMINATIONS & OTHER ATTACHMENTS

52.200-1 LIST OF CONSTRUCTION CONTRACT ATTACHMENTS

NO. TITLE DATE NO. OF PAGES

1 NOTE 1

2 General Decision Number FL190002 01/04/2019 5 3 General Decision Number FL190120 01/04/2019 5

W912EP19B0010 00800A-1

NOTE NOTE NOTE

THIS PROJECT INCORPORATES STATEWIDE HEAVY DREDGING AND THE

HEAVY CONSTRUCTION WAGE DECISIONS FOR LEE COUNTY, FL

THE HEAVY CONSTRUCTION WAGE DECISION MAY ONLY BE APPLIED TO

OPERATIONS OCCURRING ON LAND

EXECUTIVE ORDER (EO) 13658 ESTABLISHES AN HOURLY MINIMUM WAGE

OF $10.60 FOR 2019 THAT APPLIES TO ALL CONTRACTS SUBJECT TO THE

DAVIS- BACON ACT FOR ALL HOURS PERFORMED ON THE CONTRACT IN

CALENDAR YEAR 2019.

IF YOU HAVE ANY QUESTIONS CONCERNING THE APPLICATION OF THE WAGE

DECISIONS FURNISHED FOR THIS PROJECT, PLEASE CONTACT:

FRAN RUSSELL, OFFICE OF COUNSEL, JACKSONVILLE DISTRICT, U.S. ARMY

CORPS OF ENGINEERS AT fran.g.russell@usace.army.mil

W912EP19B0010 00800A-2

General Decision Number: FL190002 01/04/2019 FL2

Superseded General Decision Number: FL20180002

State: Florida

Construction Type: Heavy Dredging

Counties: Florida Statewide.

Dredging Construction Projects FLORIDA (Excluding West of the Aucilla River and its tributary waterways)

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.60 for calendar year 2019 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.

If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.60 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2019. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate, if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/04/2019

* ENGI0025-002 10/01/2017

Rates Fringes

Dredging : (Hydraulic Dredges Over 20")

CLASS A.....................$ 38.18 13.88+a CLASS B1....................$ 33.02 13.47+a CLASS B2....................$ 31.09 13.32+a CLASS C1....................$ 30.24 13.00+a CLASS C2....................$ 29.26 12.92+a CLASS D.....................$ 24.30 12.27+a

Hydraulic Dredges Under 20" Cook........................$ 8.11 1.73+b Deckhand....................$ 7.77 1.73+b Engineer....................$ 9.59 1.73+b Launchman...................$ 8.19 1.73+b

W912EP19B0010 00800A-3

Leverman....................$ 10.03 1.73+b Mate........................$ 8.82 1.73+b Mess Cook...................$ 7.71 1.73+b Messman & Janitor...........$ 7.53 1.73+b Oiler & Fireman.............$ 8.11 1.73+b Shoreman....................$ 7.82 1.73+b Spider Barge Operator.......$ 8.68 1.73+b Spill Barge Operator........$ 8.68 1.73+b Welder......................$ 9.79 1.73+b

CLASSIFICATIONS:

CLASS A: Leverman, Operator.

CLASS B1: Licensed Tug Operator over 1000 HP, Derrick Operator, Spider/Spill Barge Operator, Timber Fork Operator, Dozer Operator, Engineer, Blaster/Driller, Fill Placer, Electrician.

CLASS B2: Licensed Boat Operator, Certified Welder.

CLASS C1: Mate, Drag Barge Operator, Welder, Assistant Fill Placer, Steward.

CLASS C2: Boat Operator.

CLASS D: Shoreman, Deckhand, Rodman, Scowman, Cook, Messman, Oiler, Janitor.

PREMIUMS: Additional 20% for hazardous material work

FOOTNOTE APPLICABLE TO ABOVE CRAFTS:

a. New Year's Day, Good Friday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.

Vacation Contribution of 8% of straight time rate multiplied by the total hours worked.

b. New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day. Plus Vacation contribution of 8% of straight time pay for all hours worked.

INCENTIVE PAY : (Add to Hourly Rate)

Operator (NCCCO License/Certification) $0.50; Licensed Tug Operator over 1000 HP (Assigned as Master) USCG licensed Master of Towing Vessels (MOTV) $1.00; Licensed Boat Operator (assigned as lead boat captain) USCG licensed boat operator $0.50; Engineer (QMED and Tankerman endorsement or licensed engineer (USCG) $0.50; Oiler QMED and Tankerman endorsement (USCG) $0.50; All classifications Tankerman endorsement only (USCG) $0.50; Deckhand or Mater AB w/Lifeboatman only (USCG) $0.25; Welder (ABS certification) $0.50

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

W912EP19B0010 00800A-4

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the

W912EP19B0010 00800A-5

wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor

W912EP19B0010 00800A-6

200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

W912EP19B0010 00800A-7

General Decision Number: FL190120 01/04/2019 FL120

Superseded General Decision Number: FL20180163

State: Florida

Construction Type: Heavy

County: Lee County in Florida.

HEAVY CONSTRUCTION PROJECTS (Including Sewer and Water Lines)

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.60 for calendar year 2019 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.

If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.60 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2019. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate, if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/04/2019

ELEC0915-003 12/01/2017

Rates Fringes

ELECTRICIAN......................$ 28.18 38%+0.35

ENGI0487-014 07/01/2013

Rates Fringes

OPERATOR: Crane All Tower Cranes Mobile, Rail, Climbers, Static- Mount; All Cranes with Boom Length 150 Feet & Over (With or without jib) Friction, Hydraulic, Electric or Otherwise;

Cranes 150 Tons & Over;

W912EP19B0010 00800A-8

Cranes with 3 Drums (When 3rd drum is rigged for work); Gantry & Overhead Cranes; Hydraulic Cranes Over 25 Tons but not more than 50 Tons;

Hydraulic/Friction Cranes;

& All Types of Flying Cranes; Boom Truck..........$ 29.05 8.80 Cranes with Boom Length Less than 150 Feet (With or without jib); Hydraulic Cranes 25 Tons & Under, & Over 50 Tons (With Oiler);

Boom Truck..................$ 28.32 8.80 OPERATOR: Drill.................$ 25.80 8.80 OPERATOR: Oiler.................$ 22.99 8.80

* IRON0397-006 07/01/2018

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 29.85 15.97

LABO1652-004 05/01/2018

Rates Fringes

LABORER: Grade Checker..........$ 22.05 7.27

PAIN0088-008 08/01/2018

Rates Fringes

PAINTER: Brush, Roller and Spray............................$ 20.21 10.73

SUFL2009-159 06/24/2009

Rates Fringes

CARPENTER........................$ 14.95 2.92

CEMENT MASON/CONCRETE FINISHER...$ 14.77 3.50

LABORER: Common or General......$ 9.72 1.31

LABORER: Landscape..............$ 7.25 0.00

LABORER: Pipelayer..............$ 11.33 0.00

LABORER: Power Tool Operator (Hand Held Drills/Saws, Jackhammer and Power Saws Only)............................$ 10.63 2.20

OPERATOR: Asphalt Paver.........$ 11.59 0.00

OPERATOR: Backhoe Loader Combo............................$ 16.10 2.44

OPERATOR: Backhoe/Excavator.....$ 14.91 1.08

W912EP19B0010 00800A-9

OPERATOR: Bulldozer.............$ 17.00 0.00

OPERATOR: Grader/Blade..........$ 16.00 2.84

OPERATOR: Loader................$ 14.75 0.00

OPERATOR: Mechanic..............$ 14.32 0.00

OPERATOR: Roller................$ 10.76 0.00

OPERATOR: Scraper...............$ 11.00 1.74

OPERATOR: Trackhoe..............$ 20.92 5.50

OPERATOR: Tractor...............$ 10.54 0.00

TRUCK DRIVER, Includes Dump Truck............................$ 11.00 0.00

TRUCK DRIVER: Lowboy Truck......$ 12.73 0.00

TRUCK DRIVER: Off the Road Truck............................$ 12.21 1.97

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), W912EP19B0010 00800A-10 a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

W912EP19B0010 00800A-11

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

W912EP19B0010 00800A-12

FCCE, Shor e Pr ot ect i on Pr oj ect , Beach Renour i shment Gaspar i l l a I s l and, Lee Count y, Fl or i da

SECTI ON TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

SECTI ON 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1. 1 REFERENCES

1. 2 WORK COVERED BY CONTRACT DOCUMENTS

1. 2. 1 Pr oj ect Descr i pt i on

1. 2. 2 Locat i on

1. 2. 3 Saf et y Requi r ement s

1. 2. 4 Wor k Per f or med by Ot her s

1. 3 COMMENCEMENT, PROSECUTI ON AND COMPLETI ON OF WORK

1. 4 LI QUI DATED DAMAGES - CONSTRUCTI ON

1. 5 PHYSI CAL DATA

1. 5. 1 Physi cal Condi t i ons

1. 5. 2 Weat her , Wat er St age and Ti de Dat a

1. 5. 3 Cont r act or I nvest i gat i on

1. 5. 4 Mar i t i me Tr af f i c

1. 5. 5 Obst r uct i on of Channel

1. 5. 6 Hydr ogr aphi c Sur veys

1. 6 LAYOUT OF WORK

1. 6. 1 Est abl i shed Pr oj ect Cont r ol

1. 6. 2 Layout

1. 6. 3 Sur vey

1. 7 DAMAGE TO WORK

PART 2 PRODUCTS ( NOT APPLI CABLE)

PART 3 EXECUTI ON ( NOT APPLI CABLE)

- - End of Sect i on Tabl e of Cont ent s - -

SECTI ON 01 11 00 Page 1 W912EP19B0010 Amendment 0004

SECTI ON 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1. 1 REFERENCES

The publ i cat i ons l i s t ed bel ow f or m a par t of t hi s speci f i cat i on t o t he ext ent r ef er enced. The publ i cat i ons ar e r ef er r ed t o i n t he t ext by t he basi c desi gnat i on onl y.

U. S. ARMY CORPS OF ENGI NEERS ( USACE)

GDR Sect i on 00 31 32, Geot echni cal Dat a Repor t f or Lee Count y Shor e Pr ot ect i on Pr oj ect , Gaspar i l l a I s l and, Lee Count y, Fl or i da

EM 385- 1- 1 Saf et y and Heal t h Requi r ement s Manual

1. 2 WORK COVERED BY CONTRACT DOCUMENTS

1. 2. 1 Pr oj ect Descr i pt i on

The wor k i ncl udes r enour i shi ng appr oxi mat el y 1. 4 mi l es of shor el i ne on t he nor t h r each and appr oxi mat el y 0. 4 mi l e of shor el i ne on t he sout h r each.

The bor r ow ar ea i s l ocat ed i n t he shoal t o t he nor t h of Boca Gr ande Pass.

Pr oj ect wor k al so i ncl udes, but i s not l i mi t ed t o, beach t i l l i ng, pi pel i ne corridor hardbottom mappi ng, const r uct i on/ v i br at i on cont r ol and moni t or i ng, t ur bi di t y moni t or i ng, envi r onment al speci es moni t or i ng, beach f i l l r emedi at i on and i nci dent al r el at ed wor k. The use of hopper dr edges i s pr ohi bi t ed.

1. 2. 2 Location

The wor k shal l be l ocat ed at Gaspar i l l a I s l and i n Lee Count y, Fl or i da.

Ref er t o cont r act dr awi ngs f or exact l ocat i on.

1. 2. 3 Saf et y Requi r ement s

See Sect i on 01 35 26 GOVERNMENTAL SAFETY REQUI REMENTS and EM 385- 1- 1.

1. 2. 4 Wor k Per f or med by Ot her s

See par agr aph PROJECT COORDI NATI ON of Sect i on 01 30 00 ADMI NI STRATI VE

PROCEDURES.

1. 3 COMMENCEMENT, PROSECUTI ON AND COMPLETI ON OF WORK

Read t hi s par agr aph i n conj unct i on wi t h t he Cl ause COMMENCEMENT, PROSECUTI ON, AND COMPLETI ON OF WORK ( FAR 52. 211- 10) of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1.

SECTI ON 01 11 00 Page 2

1. 4 LI QUI DATED DAMAGES - CONSTRUCTI ON

Ref er t o t he Cl ause LI QUI DATED DAMAGES - CONSTRUCTI ON ( FAR 52. 211- 12) of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1.

1. 5 PHYSI CAL DATA

Read t hi s par agr aph i n conj unct i on wi t h t he Cl ause PHYSI CAL DATA ( FAR

52. 236- 4) of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1.

1. 5. 1 Physi cal Condi t i ons

The i ndi cat i ons of physi cal condi t i ons on t he dr awi ngs and i n t he speci f i cat i ons ar e t he r esul t of s i t e i nvest i gat i ons by sur veys and/ or by cor e bor i ngs. When t he i ndi cat ed physi cal condi t i ons ar e t he r esul t of s i t e i nvest i gat i ons by cor e bor i ngs, t he cor e bor i ng l ogs and l abor at or y dat a ar e i n Sect i on 00 31 32 GEOTECHNI CAL DATA REPORT ( GDR) and t he cor e bor i ng l ocat i ons ar e shown on t he dr awi ngs. Al so, see t he GDR f or i nst r uct i ons concer ni ng avai l abi l i t y of cor e bor i ngs f or i nspect i on.

1. 5. 2 Weat her , Wat er St age and Ti de Dat a

See Sect i on 00 33 50 WEATHER, WATER STAGE AND TI DE DATA.

1. 5. 3 Cont r act or I nvest i gat i on

Ref er t o t he Cl ause SI TE I NVESTI GATI ON AND CONDI TI ONS AFFECTI NG THE WORK ( FAR 52. 236- 3) of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1.

1. 5. 4 Mar i t i me Tr af f i c

Mar i ne Tr af f i c i n t he pr oj ect ar ea consi st s of commer ci al , pl easur e, and smal l r ecr eat i onal vessel s of al l t ypes and si zes whi ch can be accommodat ed by exi st i ng dept hs.

1. 5. 5 Obst r uct i on of Channel

The Gover nment wi l l not under t ake t o keep t he channel f r ee f r om vessel s or ot her obst r uct i ons, except t o t he ext ent of such r egul at i ons, i f any, as may be pr escr i bed by t he Secr et ar y of t he Ar my, i n accor dance wi t h t he pr ovi s i ons of Sect i on 7 of t he Ri ver and Har bor Act appr oved 8 August 1917. The Cont r act or wi l l be r equi r ed t o conduct t he wor k i n such manner as t o obst r uct navi gat i on as l i t t l e as possi bl e, and i n case t he Cont r act or ' s pl ant so obst r uct s t he channel as t o make di f f i cul t or endanger t he passage of any vessel s, sai d pl ant shal l be pr ompt l y moved on t he appr oach of any vessel t o such an ext ent as may be necessar y t o af f or d a pr act i cabl e passage. Upon compl et i on of t he wor k t he Cont r act or shal l pr ompt l y r emove hi s pl ant , i ncl udi ng r anges, buoys, pi l es, and ot her mar ks pl aced by hi m under t he cont r act i n navi gabl e wat er s or on shor e.

1. 5. 6 Hydr ogr aphi c Sur veys

Hydr ogr aphi c sur veys ar e post ed as separ at e el ect r oni c f i l es. Sur vey number s ar e i ndi cat ed on t he dr awi ngs.

1. 6 LAYOUT OF WORK

Read t hi s par agr aph i n conj unct i on wi t h t he Cl ause LAYOUT OF WORK ( FAR

52. 236- 17) of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1.

SECTI ON 01 11 00 Page 3

1. 6. 1 Est abl i shed Pr oj ect Cont r ol

The Gover nment has est abl i shed monument s al ong t he wor k s i t e( s) . Each monument i s r epr esent ed i n t he cont r act dr awi ngs by a Desi gnat i on and i n most cases, an al phanumer i c Per manent I dent i f i er ( PI D) . I nf or mat i on concer ni ng t he l ocat i on and el evat i ons can be f ound wi t hi n t he Sur vey Not es on t he pl an sheet s. The Sur vey Not es f or each i ncl uded f i el d sur vey wi l l c i t e a par t i cul ar sur vey number , and speci f y t he cont r ol used t o conduct t hat sur vey. Addi t i onal i nf or mat i on i s i ncl uded i n t he Sur vey Not es t hat must be dupl i cat ed i f an at t empt t o r ecr eat e t he subj ect sur vey i s desi r ed.

For navi gat i on channel s, t he Gover nment has est abl i shed t i dal cal i br at i on s i t es f or pr oj ect s const r uct ed and mai nt ai ned t o a t i dal dat um. Each t i dal cal i br at i on s i t e i s r epr esent ed i n t he pl an sheet dr awi ngs by St at i on I D, and i s c i t ed i n t he Sur vey Not es. Al l pr oj ect s const r uct ed and mai nt ai ned t o a t i dal dat um shal l be cal i br at ed t o t he St at i on I D speci f i ed i n t he pl an sheet dr awi ngs. I nf or mat i on r egar di ng t he l ocat i on and associ at ed benchmar ks of t he r ef er enced St at i on I D i s i ncl uded i n t he Monument Descr i pt i on sect i on of t hese speci f i cat i ons.

See Sect i on 00 31 21 CONTROL MONUMENT DESCRI PTI ONS.

1. 6. 2 Layout

Fr om t he monument s, cont r ol dat a and el evat i ons est abl i shed by t he Gover nment , t he Cont r act or shal l compl et e t he l ayout of t he wor k and shal l be r esponsi bl e f or al l measur ement s t hat may be r equi r ed f or t he execut i on of t he wor k t o t he l ocat i on and l i mi t mar ks pr escr i bed i n t he speci f i cat i ons or on t he cont r act dr awi ngs, subj ect t o such modi f i cat i ons as t he Cont r act i ng Of f i cer may r equi r e t o meet changed condi t i ons or as a r esul t of necessar y modi f i cat i ons t o t he cont r act wor k.

1. 6. 3 Survey

The Cont r act or shal l f ur ni sh, at hi s own expense, such st akes, t empl at es, pl at f or ms, equi pment , t ool s and mat er i al , and al l l abor as may be r equi r ed i n l ayi ng out any par t of t he wor k f r om t he monument s, cont r ol dat a and el evat i ons est abl i shed by t he Gover nment . I t shal l be t he r esponsi bi l i t y of t he Cont r act or t o mai nt ai n and pr eser ve al l monument s, st akes and ot her mar ks est abl i shed by t he Cont r act i ng Of f i cer unt i l aut hor i zed t o r emove t hem, and i f such mar ks or monument s ar e dest r oyed by t he Cont r act or or t hr ough hi s negl i gence, pr i or t o t hei r aut hor i zed r emoval , t hey may be r epl aced by t he Cont r act i ng Of f i cer , at hi s di scr et i on, and t he expense of r epl acement wi l l be deduct ed f r om any amount s due or t o become due t he Cont r act or . The Cont r act i ng Of f i cer may r equi r e t hat wor k be suspended at any t i me when l ocat i on and l i mi t mar ks est abl i shed by t he Cont r act or ar e not r easonabl y adequat e t o per mi t checki ng of t he wor k.

1. 7 DAMAGE TO WORK

The r esponsi bi l i t y f or damage t o any par t of t he per manent wor k shal l be as set f or t h i n Cl ause PERMI TS AND RESPONSI BI LI TI ES of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1. However , i f , i n t he j udgment of t he Cont r act i ng Of f i cer , any par t of t he per manent wor k per f or med by t he Cont r act or i s damaged by f l ood, ear t hquake, hur r i cane, or t or nado, whi ch damage i s not due t o t he f ai l ur e of t he Cont r act or t o t ake r easonabl e pr ecaut i ons or t o exer ci se sound engi neer i ng and const r uct i on pr act i ces i n

SECTI ON 01 11 00 Page 4 t he conduct of t he wor k, t he Cont r act or wi l l make t he r epai r s as or der ed by t he Cont r act i ng Of f i cer and f ul l compensat i on f or such r epai r s wi l l be made at t he appl i cabl e cont r act uni t or j ob pr i ces as f i xed and est abl i shed i n t he cont r act . I f , i n t he opi ni on of t he Cont r act i ng Of f i cer , t her e ar e no cont r act uni t or j ob pr i ces appl i cabl e t o any par t of such wor k, an equi t abl e adj ust ment pur suant t o Cl ause CHANGES of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1 wi l l be made as f ul l compensat i on f or t he r epai r s of t hat par t of t he per manent wor k f or whi ch t her e ar e no appl i cabl e cont r act uni t or j ob pr i ces. Except as her ei n pr ovi ded, damage t o al l wor k ( i ncl udi ng t empor ar y const r uct i on) , ut i l i t i es, mat er i al s, equi pment and pl ant shal l be r epai r ed t o t he sat i sf act i on of t he Cont r act i ng Of f i cer at t he Cont r act or ' s expense, r egar dl ess of t he cause of such damage.

PART 2 PRODUCTS ( NOT APPLI CABLE)

PART 3 EXECUTI ON ( NOT APPLI CABLE)

- - End of Sect i on - -

SECTI ON 01 11 00 Page 5

SECTI ON TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

SECTI ON 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1. 1 SUMMARY

1. 2 RESI DENT MANAGEMENT SYSTEM ( RMS)

1. 2. 1 Def i ni t i on

1. 2. 2 I nst r uct i ons

1. 3 SUBMI TTALS

1. 4 JOB PAYMENT I TEMS

1. 4. 1 Mobi l i zat i on and Demobi l i zat i on ( Li ne I t em 0001)

1. 4. 2 Const r uct i on/ Vi br at i on Cont r ol and Moni t or i ng ( Li ne I t em 0009)

1. 4. 3 Tur bi di t y Moni t or i ng ( Li ne I t em 0010)

1. 4. 4 Envi r onment al Speci es Moni t or i ng ( Li ne I t em 0011)

1. 5 UNI T PRI CE PAYMENT I TEMS

1. 5. 1 Beach Fi l l ( Li ne I t ems 0002 and 0003)

1. 5. 1. 1 Payment

1. 5. 1. 2 Measur ement

1. 5. 1. 3 Uni t of Measur e

1. 5. 2 Remedi at i on of Noncompl i ant Mat er i al ( Li ne I t em 0004)

1. 5. 2. 1 Payment

1. 5. 2. 2 Measur ement

1. 5. 2. 3 Uni t of Measur e

1. 5. 3 Scr eeni ng of Unaccept abl e Mat er i al ( Li ne I t em 0005)

1. 5. 3. 1 Payment

1. 5. 3. 2 Measur ement

1. 5. 3. 3 Uni t of Measur e

1. 5. 4 Removal of Unaccept abl e Mat er i al ( Li ne I t em 0006)

1. 5. 4. 1 Payment

1. 5. 4. 2 Measur ement

1. 5. 4. 3 Uni t of Measur e

1. 5. 5 Beach Ti l l i ng ( Li ne I t ems 0007 and 0008)

1. 5. 5. 1 Payment

1. 5. 5. 2 Measur ement

1. 5. 5. 3 Uni t of Measur e

1. 5. 6 St andby Ti me ( Li ne I t em 0012)

1. 5. 6. 1 Measur ement and Payment

1. 5. 6. 2 Uni t of Measur e

1. 5. 7 Par t ner i ng Regr oup ( Li ne I t em 0013)

1. 5. 7. 1 Payment

1. 5. 7. 2 Measur ement

1. 5. 7. 3 Uni t of Measur e

PART 2 PRODUCTS ( NOT APPLI CABLE)

PART 3 EXECUTI ON

SECTI ON 01 22 00 Page 1

3. 1 PAYMENT PROCEDURES

3. 1. 1 Request i ng Pr ogr ess Payment

3. 1. 2 Opt i ons and Modi f i cat i on CLI NS

- - End of Sect i on Tabl e of Cont ent s - -

SECTI ON 01 22 00 Page 2

SECTI ON 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1. 1 SUMMARY

Thi s sect i on descr i bes how Li ne I t ems wi l l be measur ed and pai d f or when maki ng pr ogr ess payment s. Wor k t o be measur ed i s descr i bed i n speci f i cat i on sect i ons l i s t ed f or each Li ne I t em. Measur ement pr ocedur es f or payment , r equi r ed quant i t y sur vey or pr ocur ement document at i on and payment r est r i ct i ons ar e descr i bed i n appl i cabl e speci f i cat i on sect i ons.

Al l ocat e cost s f or wor k not speci f i cal l y ment i oned t o t he Li ne I t em most c l osel y associ at ed wi t h wor k i nvol ved. Unl ess t her e i s a speci f i c Li ne I t em f or admi ni st r at i ve cost s, such as Qual i t y Cont r ol and Saf et y, al l ocat e such cost s pr opor t i onal l y acr oss al l Li ne I t ems.

1. 2 RESI DENT MANAGEMENT SYSTEM ( RMS)

1. 2. 1 Definition

The t er ms " Cont r act Li ne I t em Number ( CLI N) " and " Li ne I t em" ar e i nt er changeabl e her ei n ( e. g. : CLI N 0001 i s Li ne I t em 0001) . The t er m " CLI N" i s a cont r act i ng t er m used i n t he Resi dent Management Syst em ( RMS) payment dat a base.

1. 2. 2 Instructions

See Sect i on 01 45 00 RESI DENT MANAGEMENT SYSTEM CONTRACTOR MODE ( RMS CM) f or mor e i nf or mat i on on CLI Ns, schedul e of val ues of pay act i v i t i es and const r uct i on schedul e, and payment pr ocedur es. The Cont r act or mode user manual wi t h i n- dept h i nst r uct i ons can be downl oaded f r om t he RMS web si t e i ndi cat ed i n Sect i on 01 45 00 RESI DENT MANAGEMENT SYSTEM CONTRACTOR MODE

( RMS CM) .

1. 3 SUBMITTALS

Gover nment appr oval i s r equi r ed f or submi t t al s wi t h a " G" desi gnat i on;

submi t t al s not havi ng a " G" desi gnat i on ar e f or i nf or mat i on onl y. When used, a desi gnat i on f ol l owi ng t he " G" desi gnat i on i dent i f i es t he of f i ce t hat wi l l r evi ew t he submi t t al f or t he Gover nment . Tr ansmi t submi t t al i t ems i n accor dance wi t h Sect i on 01 33 00 SUBMI TTAL PROCEDURES. Submi t t he f ol l owi ng pr econst r uct i on submi t t al i t ems no l at er t han 30 cal endar days af t er Not i ce t o Pr oceed:

SD- 01 Pr econst r uct i on Submi t t al s

Schedul e of Val ues; G, RO

Pr ovi de a br eakdown of j ob i t ems i nt o pr oposed pay act i v i t i es as par t of t he i ni t i al pr oj ect schedul e. Schedul e of Val ues wi l l become basi s f or CLI N and Pay Act i v i t y dat a i n t he RMS payment dat a base.

SECTI ON 01 22 00 Page 3

SD- 07 Cer t i f i cat es

Request f or Pr ogr ess Payment ; G, RO

Submi t mont hl y i n accor dance wi t h subpar agr aph " Request i ng Pr ogr ess Payment " bel ow.

1. 4 JOB PAYMENT I TEMS

Payment i t ems f or t he wor k of t hi s cont r act f or whi ch cont r act l ump sum payment s wi l l be made ar e l i s t ed i n t he LI NE I TEMS AND PRI CI NG SCHEDULE wi t h t he uni t " JOB" and descr i bed bel ow. Al l cost s f or i t ems of wor k, whi ch ar e not speci f i cal l y ment i oned t o be i ncl uded i n a par t i cul ar j ob or uni t pr i ce payment i t em, shal l be i ncl uded i n t he l i s t ed j ob i t em most c l osel y associ at ed wi t h t he wor k i nvol ved. The j ob pr i ce and payment made f or each i t em l i st ed shal l const i t ut e f ul l compensat i on f or f ur ni shi ng al l pl ant , l abor , mat er i al s, and equi pment , and per f or mi ng any associ at ed Cont r act or qual i t y cont r ol , envi r onment al pr ot ect i on, meet i ng saf et y r equi r ement s, t est s and r epor t s, and f or per f or mi ng al l wor k r equi r ed f or whi ch separ at e payment i s not ot her wi se pr ovi ded.

Pr ogr ess payment s f or j ob CLI Ns wi l l be made i n accor dance wi t h t he Payment s Under Fi xed- Pr i ce Const r uct i on Cont r act s c l ause of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1. Submi t a l i s t of pay act i v i t i es, ( Schedul e of Val ues) t o br eakdown bi d f or each j ob CLI N. The Schedul e of Val ues shal l be submi t t ed f or Gover nment appr oval wi t h t he basel i ne schedul e submi t t al ( see Sect i on 01 32 01 PROJECT SCHEDULE) . An unbal anced Schedul e of Val ues and Pay Act i v i t y Schedul e wi l l be r et ur ned f or r evi s i on. I f t hi s cont r act cont ai ns ei t her t he Cont i nui ng Cont r act s c l ause or t he Cont i nui ng Cont r act s ( Al t er nat e) c l ause, t he Cont r act or shoul d t ake i nt o account t he amount r eser ved f or cont r act payment s when pr epar i ng t he const r uct i on schedul e.

1. 4. 1 Mobi l i zat i on and Demobi l i zat i on ( Li ne I t em 0001)

Payment wi l l be made f or cost s associ at ed wi t h or i nci dent al t o mobi l i zat i on and demobi l i zat i on and est abl i shment of i ni t i al pr oj ect management and coor di nat i on. See Cl ause PAYMENT FOR MOBI LI ZATI ON AND DEMOBI LI ZATI ON of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1.

1. 4. 2 Const r uct i on/ Vi br at i on Cont r ol and Moni t or i ng ( Li ne I t em 0009)

Payment wi l l be made f or cost s associ at ed wi t h or i nci dent al t o t he pr ot ect i on of exi st i ng st r uct ur es f r om const r uct i on act i v i t i es and moni t or i ng. See Sect i on 02 22 13 VI BRATI ON MONI TORI NG REQUI REMENTS FOR

EXI STI NG STRUCTURES.

1. 4. 3 Tur bi di t y Moni t or i ng ( Li ne I t em 0010)

Payment wi l l be made f or cost s associ at ed wi t h or i nci dent al t o obt ai ni ng, anal yzi ng, and r epor t i ng t he r esul t s of moni t or i ng f or t ur bi di t y. See Section 01 57 25 TURBI DI TY AND DI SPOSAL MONI TORI NG.

1. 4. 4 Envi r onment al Speci es Moni t or i ng ( Li ne I t em 0011)

Payment wi l l be made f or cost s associ at ed wi t h or i nci dent al t o speci es moni t or i ng r equi r ed i n Sect i on 01 57 20 ENVI RONMENTAL PROTECTI ON, including moni t or i ng of har dbot t om/ r eef communi t i es and oper at i onal box

SECTI ON 01 22 00 Page 4 f or pr ot ect i on of har dbot t om/ r eef communi t i es; per f or mi ng condi t i on sur veys and moni t or i ng of har dbot t om/ r eef communi t i es t o l ocat e and ver i f y each pi pel i ne cor r i dor mappi ng; upl and moni t or i ng of shor ebi r ds; manat ee obser ver ( c l amshel l dr edge) ; and moni t or i ng sea t ur t l es.

1. 5 UNI T PRI CE PAYMENT I TEMS

Payment i t ems f or t he wor k of t hi s cont r act on whi ch t he cont r act uni t pr i ce payment s wi l l be made ar e l i s t ed i n t he LI NE I TEMS AND PRI CI NG SCHEDULE and descr i bed bel ow. The uni t pr i ce and payment made f or each i t em l i st ed shal l const i t ut e f ul l compensat i on f or f ur ni shi ng al l pl ant , l abor , mat er i al s, and equi pment , and per f or mi ng any associ at ed Cont r act or qual i t y cont r ol , envi r onment al pr ot ect i on, meet i ng saf et y r equi r ement s, t est s and r epor t s, and f or per f or mi ng al l wor k r equi r ed f or each of t he uni t pr i ce i t ems.

Each Uni t Pr i ce CLI N may be a s i ngl e pay act i v i t y i t em or may be br oken down i nt o pay act i v i t i es wi t h smal l er quant i t i es equal t o CLI N t ot al .

Cont r act uni t pr i ce mul t i pl i ed by agr eed quant i t y i s f ul l compensat i on.

1. 5. 1 Beach Fi l l ( Li ne I t ems 0002 and 0003)

1. 5. 1. 1 Payment

a. Payment wi l l be made f or cost s associ at ed wi t h or i nci dent al t o bar r i cades and si gns, debr i s r emoval , pi pel i ne cr ossi ng r amps and wal kways, excavat i on and t r anspor t at i on of beach f i l l , const r uct i ng t he beach pr of i l e and f i nal dr essi ng; escar pment s; noi se cont r ol ; di ve r epor t s; i nst al l at i on, oper at i on, or mai nt enance of t he el ect r oni c posi t i onal moni t or i ng equi pment and condi t i on sur veys. See Sect i ons

01 57 20 ENVI RONMENTAL PROTECTI ON, 01 57 25 TURBI DI TY AND DI SPOSAL

MONI TORI NG, and 35 20 25 BEACH FI LL.

b. I n addi t i on t o t he above, payment wi l l be made f or i n- pl ace beach f i l l t o t he t ol er ance l i ne i ndi cat ed on bot h ber m and sl ope.

Payment quant i t i es wi l l be det er mi ned by t he Gover nment usi ng aver age end ar ea met hod of cal cul at i on, except i n l ocat i ons wher e a Const r uct i on Basel i ne ( CBL) Poi nt s of I nt er sect i on ( PI ) exi st i ng bet ween t wo st at i ons and at t he end t aper s/ t r ansi t i ons. At t hese t wo l ocat i ons, Di gi t al Ter r ai n Model ( DTM) sur f ace- t o- sur f ace met hod of cal cul at i on shal l be used. When beach f i l l i s pl aced above t he sl ough zone t o compensat e f or wave act i on, payment wi l l be based on a cut and f i l l cal cul at i on. No payment wi l l be made f or mat er i al pl aced i n excess of t he t ol er ance t empl at e A( T) i ndi cat ed on t he dr awi ngs.

1. 5. 1. 2 Measurement

a. The maps and/ or dr awi ngs al r eady pr epar ed ( c l ause CONTRACT DRAWI NGS, MAPS, AND SPECI FI CATI ONS of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1) ar e bel i eved t o r epr esent accur at el y t he exi st i ng condi t i ons at t he t i me t he sur veys wer e per f or med, but t he dept hs and el evat i ons shown t her eon may be ver i f i ed and cor r ect ed by el evat i ons and soundi ngs t aken bef or e commenci ng t he wor k. Once quant i t i es wi t hi n a speci f i ed r each or sect i on have been det er mi ned t hr ough t he use of i n- pl ace measur ement , t hey wi l l not be r eopened except on evi dence of col l usi on, f r aud, or obvi ous er r or .

b. Beach f i l l sat i sf act or i l y pl aced wi l l be measur ed f or payment by use of t he aver age end ar ea met hod and Di gi t al Ter r ai n Model ( DTM)

SECTI ON 01…

This is the start of the file's text. The full file is on GovTribe.