AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04 EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
BEACH EROSION CONTROL AND HURRICANE PROTECTION PROJECT, DADE COUNTY, FLORIDA – SURFSIDE SEGMENT
A. SEE CONTINUATION SHEET FOR AMENDMENT DETAILS.
B. THE BID OPENING DATE REMAINS UNCHANGED @ APRIIL 17, 2019 @ 2:00 P.M. LOCAL TIME.
1. CONTRACT ID CODE PAGE OF PAGES
1 57
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer) (Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EP19B0008
X 9B. DATED (SEE ITEM 11)
26-Feb-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
12-Apr-2019
CODE
USA ENGINEER DISTRICT, JACKSONVILLE
CONTRACTING DIVISION
701 SAN MARCO BLVD
JACKSONVILLE FL 32207-8175
W912EP 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODE CODE
EMAIL:TEL:
SF 30 CONTINUATION SHEET
BEACH EROSION CONTROL AND HURRICANE PROTECTION PROJECT
SURFSIDE SEGMENT
MIAMI-DADE COUNTY, FLORIDA
W912EP19B0008 1 Amendment 0002
SUMMARY OF CHANGES
1. SPECIFICATIONS:
The text changes have been updated with additions noted by underlined text and deletions noted by line/cross-outs, and pertain only to changes made by this amendment. The entire section is replaced if there is any change. The Project Table of Contents and Submittal Register are replaced without underlines and cross-outs if there are changes to these documents. New sections are added without underlines and cross-outs.
Changes to Specifications:
Volume 1 of 2
SECTION 00800 - SPECIAL REQUIREMENTS
The following have been deleted: 999.215-4003 ELECTRONIC PROPOSALS
Volume 2 of 2
DELETE Section 01 11 00 and REPLACE with the attached revised Section 01 11 00.
DELETE Section 01 57 20 and REPLACE with the attached revised Section 01 57 20.
DELETE Section 35 30 00 and REPLACE with the attached revised Section 35 30 00.
2. DRAWINGS:
No changes.
(End of Summary of Changes)
SECTION 00800 - SPECIAL REQUIREMENTS
31.105-100 EQUIPMENT OWNERSHIP AND OPERATING
EXPENSE SCHEDULE (MAR 1995)
MAY 1999
52.223-3 Hazardous Material Identification And Material Safety Data
JAN 1997
52.249-5000 Basis for Settlement of Proposals
UNAUTHORIZED INSTRUCTIONS FROM
GOVERNMENT OR OTHER PERSONNEL
DEC 1999
DFARS 203-70 - CONTRACTOR STANDARDS OF
CONDUCT
DEC 1999
HAND-DELIVERING OFFERS TO THE
PRUDENTIAL OFFICE BUILDING IN
JACKSONVILLE
MAY 2004
PUBLIC ATTENDANCE AT PUBLIC BID
OPENINGS
FEB 2010
ESTABLISHING AUTHORITY OF PERSON(S) WHO
SIGN(S) THE OFFER
DEC 1999
DISTRIBUTING SOLICITATION AMENDMENTS
VIA FEDBIZOPPS.GOV
AUG 2016
OBTAINING INFORMATION REGARDING THIS
SOLICITATION
DEC 1999
BIDDER'S CHECKLIST --
CONSTRUCTION/DREDGING CONTRACTS
DEC 1999
NOTIFICATION TO UNSUCCESSFUL BIDDERS SEP 2006
Electronic Proposals AUG 2016
RETAINAGE FOR FAILURE TO COMPLY WITH
SUBCONTRACTING PLAN REPORTING
REQUIREMENTS
DEC 1999
U.S. ARMY CORPS OF ENGINEERS SAFETY AND
HEALTH REQUIREMENTS MANUAL, EM 385-1-1
JAN 2001
CONSTRUCTION CONTRACTOR PERFORMANCE
EVALUATIONS
FEB 2009
NOTICE TO MARINERS -- CONSTRUCTION
CONTRACTS
DEC 1999
CONTRACTORS USE OF ELECTRONIC
SOFTWARE FOR PROCESSING DAVIS-BACON
ACT CERTIFIED LABOR PAYROLLS (APRIL 2011)
SEP 2011
W912EP19B0008 00800-1 Amendment 0002
SECTION 00800 - SPECIAL REQUIREMENTS
5152.231-9000 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (MAR
2013)
(a) This special contract requirement does not apply to terminations. See 52.249-5000, Basis for Termination Settlement Proposals, and FAR Part 49.
(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region III. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-
36. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the small purchase threshold, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
(End of special contract requirement)
52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (JAN
1997)
(a) "Hazardous material", as used in this clause, includes any material defined as hazardous under the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract).
(b) The offeror must list any hazardous material, as defined in paragraph (a) of this clause, to be delivered under this contract. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. This information shall also be included on the Material Safety Data Sheet submitted under this contract.
Material Identification No.
(If none, insert "None")
W912EP19B0008 00800-2 Amendment 0002
(c) This list must be updated during performance of the contract whenever the Contractor determines that any other material to be delivered under this contract is hazardous.
(d) The apparently successful offeror agrees to submit, for each item as required prior to award, a Material Safety Data Sheet, meeting the requirements of 29 CFR 1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous material identified in paragraph (b) of this clause. Data shall be submitted in accordance with Federal Standard No. 313, whether or not the apparently successful offeror is the actual manufacturer of these items. Failure to submit the Material Safety Data Sheet prior to award may result in the apparently successful offeror being considered nonresponsible and ineligible for award.
(e) If, after award, there is a change in the composition of the item(s) or a revision to Federal Standard No.
313, which renders incomplete or inaccurate the data submitted under paragraph (d) of this clause, the Contractor shall promptly notify the Contracting Officer and resubmit the data.
(f) Neither the requirements of this clause nor any act or failure to act by the Government shall relieve the Contractor of any responsibility or liability for the safety of Government, Contractor, or subcontractor personnel or property.
(g) Nothing contained in this clause shall relieve the Contractor from complying with applicable Federal, State, and local laws, codes, ordinances, and regulations (including the obtaining of licenses and permits) in connection with hazardous material.
(h) The Government's rights in data furnished under this contract with respect to hazardous material are as follows:
(1) To use, duplicate and disclose any data to which this clause is applicable. The purposes of this right are to--
(i) Apprise personnel of the hazards to which they may be exposed in using, handling, packaging, transporting, or disposing of hazardous materials;
(ii) Obtain medical treatment for those affected by the material; and
(iii) Have others use, duplicate, and disclose the data for the Government for these purposes.
(2) To use, duplicate, and disclose data furnished under this clause, in accordance with subparagraph (h)(1) of this clause, in precedence over any other clause of this contract providing for rights in data.
(3) The Government is not precluded from using similar or identical data acquired from other sources.
(End of clause)
52.249-5000 Basis for Settlement of Proposals.
Actual costs will be used to determine equipment costs for a settlement proposal submitted on the
W912EP19B0008 00800-3 Amendment 0002 total cost basis under FAR 49.206-2(b). In evaluating a terminations settlement proposal using the total cost basis, the following principles will be applied to determine allowable equipment costs:
(1) Actual costs for each piece of equipment, or groups of similar serial or series equipment, need not be available in the contractor's accounting records to determine total actual equipment costs.
(2) If equipment costs have been allocated to a contract using predetermined rates, those charges will be adjusted to actual costs.
(3) Recorded job costs adjusted for unallowable expenses will be used to determine equipment operating expenses.
(4) Ownership costs (depreciation) will be determined using the contractor's depreciation schedule (subject to the provisions of FAR 31.205-11).
(5) License, taxes, storage and insurance costs are normally recovered as an indirect expense and unless the contractor charges these costs directly to contracts, they will be recovered through the indirect expense rate.
(End of clause)
UNAUTHORIZED INSTRUCTIONS FROM GOVERNMENT OR OTHER PERSONNEL
The Contractor shall not accept any instructions issued by any person, employed by the Government or otherwise, other than the Contracting Officer or the Contracting Officer's Representative (COR) acting within the limits of the COR’s authority. See the Contracting Officer's Representative clause of this contract.
DFARS 203-70 – CONTRACTOR STANDARDS OF CONDUCT
The following excerpt from DFARS subpart 203.70 is presented as a reminder:
203.7000 Policy. Government contractors must conduct themselves with the highest degree of integrity and honesty. Contractors should have standards of conduct and internal control systems that--
(1) Are suitable to the size of the company and the extent of their involvement in Government contracting;
(2) Promote such standards;
(3) Facilitate timely discovery and disclosure of improper conduct in connection with Government contracts; and
(4) Ensure corrective measures are promptly instituted and carried out.
203.7001 Procedures.
(a) A contractor's system of management controls should provide for--
(1) A written code of business ethics and conduct and an ethics training program for all employees;
(2) Periodic reviews of company business practices, procedures, policies, and internal controls for compliance with standards of conduct and the special requirements of Government contracting;
(3) A mechanism, such as a hotline, by which employees may report suspected instances of improper conduct, and instructions that encourage employees to make such reports;
(4) Internal and/or external audits, as appropriate;
(5) Disciplinary action for improper conduct;
(6) Timely reporting to appropriate Government officials of any suspected or possible violation of law in connection with Government contracts or any other irregularities in connection with such contracts; and
(7) Full cooperation with any Government agencies responsible for either investigation or corrective actions.
W912EP19B0008 00800-4 Amendment 0002
HAND-DELIVERING OFFERS TO THE PRUDENTIAL OFFICE BUILDING IN JACKSONVILLE
If the offeror intends to hand-deliver the offer, it must be delivered to the Jacksonville District’s headquarters in the Prudential Office Building, 701 San Marco Blvd, Jacksonville, FL 32207. Access to this building is controlled by security personnel. Visitors requiring access must present a drivers license, current passport, or similar positive identification. Facsimile copies are not acceptable. Security personnel are neither Government employees nor Government contractor employees. For purposes of determining whether an offer is late, delivery into the hands of security personnel will not constitute delivery to the Government. In order to ensure delivery to the Government, persons hand-delivering offers should call the contract specialist whose name appears in the solicitation and ask the specialist to send someone to the security desk to take possession of the offer. Persons hand-delivering offers should take care to arrive at the Prudential Building in sufficient time to permit completion of security requirements and delivery of the offer to the designated office prior to the time set for receipt of offers.
PUBLIC ATTENDANCE AT PUBLIC BID OPENINGS
The Jacksonville District Corps of Engineers is located in the Prudential Office Building at 701 San Marco Blvd., Jacksonville, Florida. The Jacksonville District is a tenant and, as such, must comply with all security requirements imposed by Prudential. Prudential will be implementing a new, computerized “guest pass” system. All contractors, sponsor representatives, other guests and/or visitors wishing to attend a public bid opening will be required to submit their name to the designated Contract Specialist (as shown on the face of this solicitation) at least 48 hours prior to bid opening. The Contract Specialist is responsible for assuring that the “guest list” is submitted in accordance with the requirements of the Prudential Building at least 24 hours prior to the scheduled bid opening. In addition, all such guests will be required to obtain a photo ID guest pass at the security desk on the 2nd floor of the Prudential Building; therefore, all guests should plan on arriving at least one hour prior to the time established for the bid opening.
ESTABLISHING AUTHORITY OF PERSON(S) WHO SIGN(S) THE OFFER
The Offeror shall check the paragraph below that corresponds with the Offeror’s status and shall submit appropriate documentation with the offer to confirm authority of person(s) who sign the offer.
(a) Individual. A contract with an individual shall be signed by that individual. A contract with an individual doing business as a firm shall be signed by that individual, and the signature shall be followed by the individual’s typed, stamped, or printed name and the words, “an individual doing business as ” [insert name of firm].
(b) Partnership. A contract with a partnership shall be signed in the partnership name. Before signing for the Government, the contracting officer shall obtain a list of all partners and ensure that the individual(s) signing for the partnership have authority to bind the partnership.
(c) Corporation. A contract with a corporation shall be signed in the corporate name, followed by the word “by” and the signature and title of the person authorized to sign. The contracting officer shall ensure that the person signing for the corporation has authority to bind the corporation.
W912EP19B0008 00800-5 Amendment 0002
(d) Joint venture. A contract with a joint venture may involve any combination of individuals, partnerships, or corporations. The contract shall be signed by each participant in the joint venture in the manner prescribed in paragraphs (a) through (c) above for each type of participant. When a corporation is participating, the contracting officer shall verify that the corporation is authorized to participate in the joint venture.
(e) Agent. When an agent is to sign the contract, other than as stated in paragraphs (a) through (d) above, the agent’s authorization to bind the principal must be established by evidence satisfactory to the contracting officer.
999.204-4003 DISTRIBUTING SOLICITATION AMENDMENTS VIA FEDBIZOPPS.GOV
Solicitation amendments will be distributed using the Federal Business Opportunities (FedBizOpps.Gov) system at http://www.fbo.gov.
In order to receive notification of any amendments to this solicitation, interested vendors must REGISTER TO RECEIVE NOTIFICATION on the Federal Business Opportunities website at http://www.fbo.gov. If you are not registered, the Government is not responsible with providing you with notification of any changes to this solicitation.
In addition, in order to generate a Plan Holders List, all interested bidders must also REGISTER AS INTERESTED VENDOR which is also located on the Federal Business Opportunities website at http://www.fbo.gov.
OBTAINING INFORMATION REGARDING THIS SOLICITATION
Read this paragraph in conjunction with FAR 52.214-6, Explanation To Prospective Bidders, which is located in this Section 00100. Verbal requests for information must be directed to the person whose name appears in item 9 of the SF 1442. Collect calls cannot be accepted. Written requests for explanations must be sent to the person identified in item 9 of the SF 1442 and may be sent via facsimile to 904-232-2748.
Inquiries and requests that are directed to any other person may not be relayed to the proper person and, therefore, may not be answered.
BIDDER'S CHECKLIST -- CONSTRUCTION/DREDGING CONTRACTS
The following list should be used by bidders to avoid irregularities that have occurred in past bids.
1. Have amendments to the Invitation been acknowledged on the bid form in the spaces provided? If not, acknowledgment must be made by separate letter or telegram prior to opening of bids.
2. Have prices been inserted for all bid items of the Bidding Schedule?
3. Do prices inserted include subcontractors' and suppliers' quotations, indirect costs, and profit?
4. Does the total bid amount include the costs of obtaining performance and payment bonds?
5. Have all prices and computations been checked?
W912EP19B0008 00800-6 Amendment 0002 http://www.fbo.gov/ http://www.fbo.gov/
6. Is the bid submitted on the latest bid schedule?
7. Have changes been made to the Bidding Schedule if required by amendment?
8. Are decimal points in the bid prices in the proper places?
9. Have you checked for transposition of figures in prices inserted on the Bidding Schedule?
10. Is the bid form signed, and if so, is the bid form signed by a person legally authorized to bind the bidder?
Is the bidder's address included?
11. If the bid is signed by an agent, is legal evidence of agent's authority to sign included with the bid?
12. If a bid guarantee is required, does your bid guarantee comply with the Bid Guarantee clause of the solicitation? If the bid guarantee is in the form of a bid bond is it on Standard Form 24 (REV. 10-98)? If your bid guarantee does not firmly bind you (and your sureties, if applicable) to the United States of America, YOUR BID WILL BE CONSIDERED NONRESPONSIVE.
13. If the bid guarantee is in the form of a bid bond, is it completely and properly executed, dated not later than the bid opening date, signed by Principal and Surety, corporate certificates executed, and seals affixed, all as contained in "Instructions" on Standard Form 24 (REV. 10-98)? Power of Attorney is also required to accompany the bond. Is the penal sum marked in? If an individual surety (or sureties) is (are) guaranteeing the bid bond, have the requirements of the Pledges Of Assets clause of this solicitation been satisfied and are the supporting documents included with the bond?
14. Have the appropriate boxes been checked in all paragraphs of the Representations And Certifications (Section 00101)?
15. Have all representations and certifications been submitted with the bid?
16. If required by the Invitation, is literature, data, catalogs, etc., specified by the Invitation included with the bid?
17. Have requirements of the Late Submissions, Modifications And Withdrawals Of Bids provision of this solicitation been met?
CAUTION: BIDS THAT ARE QUALIFIED BY THE BIDDER MAY BE CONSIDERED
NONRESPONSIVE.
NOTIFICATION TO UNSUCCESSFUL BIDDERS
In accordance with FAR 14.409-1, unsuccessful bidders will be notified, in writing or electronically within 3 days of contract award, that their bid was not accepted. Award synopsis as well as the Bid Abstract will be posted to the Federal Business Opportunities website at www.fbo.gov. If a bid is rejected for any reason other than price, the unsuccessful bidder will receive written notification stating the reason for rejection of the bid.
999.215-4003 ELECTRONIC PROPOSALS
(a) Definition. Electronic proposal, as used in this provision, means a proposal, revision or modification of a proposal, or withdrawal of a proposal that is transmitted to and received by the Government via Compact Disc (CD) or other means for transmitting electronic data. Flash drives will NOT be accepted.
(b) In order to be considered for award offerors must submit electronic proposals concurrent with the paper-copy proposals by the date and time established in the solicitation for receipt of proposals. In accordance with Section 00100A, Paragraph D. PROPOSAL REQUIREMENTS AND SUBMISSION FORMAT, the offeror is required to submit one electronic copy that contains all three volumes (Technical Merit, Past Performance, and Price), in separate files. The electronic proposal is in addition to any hardcopy documents required by the solicitation."
W912EP19B0008 00800-7 Amendment 0002
(c) The Government reserves the right to make award solely on the paper proposal. In the event of conflicts between paper and electronic proposals the paper copy proposal shall govern.
RETAINAGE FOR FAILURE TO COMPLY WITH SUBCONTRACTING PLAN REPORTING
REQUIREMENTS
(a) Read this paragraph in conjunction with Liquidated Damages--Small Business Subcontracting Plan (FAR 52.219-16) clause of this contract.
(b) Should the Contractor fail to submit Individual Subcontract Reports (ISR) and/or Summary Subcontract
Reports in a timely manner, the Government will consider this failure as evidence of possible failure to make a good faith effort to achieve goals contained in the Contractor's subcontracting plan. In order to protect the Government's ability to assess liquidated damages in the event the Contractor does fail to meet the goals and such failure results from a lack of good faith effort, the Contracting Officer will retain from progress payments an amount deemed sufficient to satisfy the Contractor's liability. The amount of the retainage will be determined in accordance with the following formula:
Total dollar amount proposed for subcontracting to small business multiplied by the percentage of actual progress on the contract, up to a maximum of 10% of the progress payment, will be withheld from the next progress payment that is due after the Contractor's failure to submit a required report. If one or more reports have been submitted before a failure to submit a required report, this formula will be adjusted by deducting any amounts reported as subcontracted to small business from the total dollar amount proposed to be subcontracted. See examples below.
Example 1 (No previous reports submitted) Total proposed subcontracting $500,000 Current progress payment $100,000 Percent of work completed x .10 Maximum retainage percentage x .10 Retainage $50,000 Retainage $10,000
Maximum that can be retained is $10,000
Example 2 (Previous reports submitted) Total proposed subcontracting $500,000 Current progress payment $100,000 Subcontracting previously reported($100,000) Maximum retainage percentage x .10 Percent of work completed x .10 Retainage $10,000 Retainage $40,000
Maximum that can be retained is $10,000
U.S. ARMY CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL, EM 385-
1-1
This paragraph applies to contracts and purchase orders that require the contractor to comply with EM 385-
1-1 (e.g., contracts that include the Accident Prevention clause at FAR 52.236-13 and/or other safety provisions). EM 385-1-1 and its changes are available at http://www.usace.army.mil/ceso. The Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the date the solicitation for this contract/purchase order was issued.
W912EP19B0008 00800-8 Amendment 0002 http://www.usace.army.mil/ceso
999.236-4003 CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATIONS
In accordance with the provisions of Subpart 36.201 (Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), construction contractors’ performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering and Construction Bulletin 2014-13 to fulfill this FAR requirement. For construction contracts awarded at $650,000.00 or more, the USACE will evaluate contractor's performance and prepare a performance report using the Contractor Performance Assessment Reporting System (CPARS), which is a web-based system. After an evaluation (interim or final) is written up by the USACE, the contractor will have the ability to access, review and comment on the evaluation for a period of 60 days. The evaluation will be transferred to the Past Performance Information Retrieval System (PPIRS) within 15 calendar days after issuance. However, it will remain with “Pending” status in PPIRS until the government official closes the form in CPARS. Contractors may access their own evaluations in PPIRS by registering as a user and obtaining specific software, called PKI certification, which is installed on the user's computer. The certification is a Department of Defense requirement and was implemented to provide security in electronic transactions. The average cost per certificate is about $100 - $120 per year and is purchased from an External Certificate Authorities (ECA) vendor. Current information about CPARS, PKI certification process and for contacting vendors can be found on the web site: http://www.cpars.gov. If the Contractor wishes to participate in the performance evaluation process, access to CPARS and PKI certification is the sole responsibility of the Contractor.
NOTICE TO MARINERS -- CONSTRUCTION CONTRACTS
Should the Contractor, during operations, encounter any objects on the channel bottom which could be a hazard to navigation, the Contractor shall immediately notify the Contracting Officer as to the location of said object and shall provide any other pertinent information necessary for the Contracting Officer to prepare and issue a Notice to Mariners.
(S-102) CONTRACTOR SUPPLY and USE OF ELECTRONIC SOFTWARE FOR PROCESSING DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS (April 2011) The contractor is encouraged to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Davis-Bacon Act as stated in FAR 52.222-8, PAYROLLS AND BASIC RECORDS and FAR 52.222-13, COMPLIANCE WITH DAVIS-BACON AND
RELATED ACT REGULATIONS.
If the contractor elects to use an electronic Davis-Bacon payroll processing system, then the contractor shall be responsible for obtaining and providing for all access, licenses and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with Davis-Bacon and related Act regulations. When the contractor uses an electronic Davis-Bacon payroll system, the electronic payroll service shall be used by the contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion. If the contractor chooses to use an electronic Davis-Bacon payroll system, then the contractor shall obtain and provide electronic system access to the Government, as required to comply with the Davis-Bacon and related Act regulations over the duration of this construction contract. The access shall include electronic review access by the Government contract administration office to the electronic payroll processing system used by the contractor.
W912EP19B0008 00800-9 Amendment 0002 http://www.cpars.gov/
The contractor’s provision and use of an electronic payroll processing system shall meet the following basic functional criteria; commercially available; compliant with appropriate Davis-Bacon Act payroll provisions in the FAR; able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract; capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records (format at http://www.rmssupport.com/guides.aspx) for export in an Excel spreadsheet to be imported into the contractor’s Quality Control System (QCS) version of Resident Management System (RMS), that in turn shall export payroll data to the Government’s Resident Management System (RMS); demonstrated security of data and data entry rights; ability to produce contractor-certified electronic versions of weekly payroll data; ability to identify erroneous entries and track the data/time of all versions of the certified Davis-Bacon payrolls submitted to the government over the life of the contract; capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic Davis-Bacon payroll processing system shall be provided to the Government during contract closeout.
All contractor-incurred costs related to the contractor’s provision and use of an electronic payroll processing service shall be included in the contractor’s price for the overall work under the contract. The costs for Davis-Bacon Act compliance using electronic payroll processing services shall not be a separately bid/proposed or reimbursed item under this contract.
W912EP19B0008 00800-10 Amendment 0002 http://www.rmssupport.com/guides.aspx
Beach Erosion Control and Hurricane Protection Project Dade County, Florida - Surfside Segment
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.3 WORK COVERED BY CONTRACT DOCUMENTS
1.3.1 Project Description
1.3.2 Location
1.3.3 Safety Requirements
1.3.4 Work Performed by Others
1.3.5 Work Restrictions
1.3.5.1 Delivery of Material
1.3.5.2 Work on the Beach
1.3.5.3 Staging Areas for Construction Equipment on the Beach
1.4 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
1.5 LIQUIDATED DAMAGES - CONSTRUCTION
1.6 PHYSICAL DATA
1.6.1 Physical Conditions
1.6.2 Weather, Water Stage and Tide Data
1.6.3 Hydrographic Surveys
1.6.4 Contractor Investigation
1.7 LAYOUT OF WORK
1.7.1 Established Project Control
1.7.2 Layout
1.7.3 Survey
1.8 DAMAGE TO WORK
1.9 EXISTING WORK
1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (31 OCT 1989)
1.10.1 Contractor Responsibility
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1 W912EP19B0008 Amendment 0002
Beach Er osi on Cont r ol and Hur r i cane Pr ot ect i on Pr oj ect Dade Count y, Fl or i da - Sur f s i de Segment
SECTI ON 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1. 1 REFERENCES
The publ i cat i ons l i s t ed bel ow f or m a par t of t hi s speci f i cat i on t o t he ext ent r ef er enced. The publ i cat i ons ar e r ef er r ed t o i n t he t ext by t he basi c desi gnat i on onl y.
U. S. ARMY CORPS OF ENGI NEERS ( USACE)
GDR Sect i on 00 31 32, Geot echni cal Dat a Repor t
EM 385- 1- 1 Saf et y and Heal t h Requi r ement s Manual
1. 2 DEFINITIONS
a. " Adver se weat her " occur s when at mospher i c condi t i ons at a def i ni t e t i me and pl ace t hat ar e unf avor abl e t o const r uct i on act i v i t i es and i s based on cl i mat ol ogi cal and met eor ol ogi cal obser vat i ons and dat a sour ces pr ovi ded i n Sect i on 00 33 50 WEATHER, WATER STAGE AND TI DE
DATA.
b. " Unusual l y sever e weat her " i s weat her t hat i s mor e sever e t han t he adver se weat her ant i c i pat ed by t he Cont r act or f or t he season or l ocat i on i nvol ved. Adver se weat her del ays ar e consi der ed unusual l y sever e weat her i f adver se weat her del ay days pr event wor k f or 50 per cent or mor e of t he Cont r act or ' s schedul ed wor k day.
1. 3 WORK COVERED BY CONTRACT DOCUMENTS
1. 3. 1 Pr oj ect Descr i pt i on
Thi s pr oj ect wi l l nour i sh cr i t i cal l y er oded shor el i ne al ong t he t own of Sur f s i de. The pr oj ect beach has a maxi mum ber m el evat i on of +6. 6 f eet , NAVD88, and a mi ni mum ber m el evat i on no l ess t han +6. 1 f eet , NAVD88. The Const r uct i on Basel i ne ( CBL) and Er osi on Cont r ol Li ne ( ECL) ar e t he same and t he wi dt h of t he ber m cr est i s 240 f eet measur ed per pendi cul ar t o t he CBL/ ECL as shown on t he dr awi ngs. The ber m wi l l s l ope at 1V: 10H t o t i e i nt o exi st i ng gr ade. The sand sour ce f or t he pr oj ect wi l l be an upl and sour ce, and mat er i al wi l l be t r uck haul ed t o t he pr oj ect l ocat i on. The upl and sour ce wi l l be sel ect ed by t he Cont r act or meet i ng cr i t er i a r equi r ed i n Sect i on 35 30 00 BEACH FI LL. and shal l be l i s t ed as appr oved wi t hi n envi r onment al r esour ce agency per mi t s. See Sect i on 01 57 20 ENVI RONMENTAL PROTECTI ON. Ot her sour ces may be avai l abl e.
1. 3. 2 Location
Pr oj ect wor k i s l ocat ed 1 mi l e sout h of Baker s Haul over I nl et i n t he t own of Sur f s i de, Fl or i da bet ween DEP Monument s R- 31 t o R- 36. 5.
SECTI ON 01 11 00 Page 2
1. 3. 3 Saf et y Requi r ement s
See Sect i on 01 35 26 GOVERNMENTAL SAFETY REQUI REMENTS and EM 385- 1- 1.
1. 3. 4 Wor k Per f or med by Ot her s
See par agr aph PROJECT COORDI NATI ON of Sect i on 01 30 00 ADMI NI STRATI VE
PROCEDURES.
1. 3. 5 Wor k Rest r i ct i ons
Wor k wi l l be per mi t t ed 6 days per week. Wor k i s per mi t t ed:
Monday t hr ough Thur sday - 7: 00 a. m. unt i l 7: 00 p. m Fr i day - 7: 00 a. m. unt i l 5: 00 p. m.
Sat ur day - 9: 00 a. m. unt i l 5: 00 p. m.
No const r uct i on on Sundays
No wor k i s per mi t t ed on t he f ol l owi ng days:
Sat Apr i l 20 - East er / Passover Fr i Apr i l 26 & Sat Apr i l 27 - Passover Sat May 25- Mon May 27 ( i ncl usi ve) - Memor i al Day weekend Mon June 10 - June Shavuot Thur s Jul y 4, 2019 - I ndependence Day Sat Aug 31 - Mon Sept . 2, 2019 ( i ncl usi ve) - Labor Day weekend Mon Sept 30 & Tues Oct 1 - Rosh Hashanah Wed Oct 9 Oct - Yom Ki ppur ( st op at 5pm on Tues Oct 8) Mon Oct 14 & Tues Oct 15 - Sukkot Mon Oct 21 - Semi ni ALzer et Mon Oct 22 - Scmchat Tor ah Thur s Nov 21- Sat Nov 23 - Thanksgi v i ng Wed Dec 25 - Chr i st mas ( st op at 5pm on Tues Dec 24)
Addi t i onal l y dur i ng Chanukah, Mon Dec 23 - Mon Dec 30, 2019, wor k i s onl y per mi t t ed bet ween 7: 00 a. m. unt i l 4: 30 p. m. Pl ease not e, sundown t i mes ar e not not ed i n Sect i on 00 33 50 WEATHER, WATER STAGE AND TI DE DATA, but t he l i nks pr ovi ded wi l l assi st , or sundown shal l be at t he t i mes di r ect ed by t he Cont r act i ng Of f i cer .
The Cont r act or shal l onl y use t he access ar eas shown on t he dr awi ngs and descr i bed her ei n. Any addi t i onal access or st agi ng ar eas needed by t he Cont r act or wi l l need t o be appr oved by t he Cont r act i ng Of f i cer and coor di nat ed wi t h t he Town of Sur f s i de at t he Cont r act or ' s expense. The Cont r act or shal l not oper at e or st or e equi pment beyond t he l i mi t s of const r uct i on shown on t he dr awi ngs. Al l const r uct i on equi pment shal l y i el d t o emer gency vehi c l es i n t r ansi t as needed t hr oughout t he dur at i on of t he pr oj ect .
1. 3. 5. 1 Del i ver y of Mat er i al
Del i ver y of t he mat er i al f r om t he Cont r act or ' s sel ect ed sour ce t o t he desi gnat ed st agi ng and access ar eas shown on t he dr awi ngs wi l l be per mi t t ed bet ween t he hour s.
1. 3. 5. 2 Wor k on t he Beach
No wor k shal l be per f or med seawar d of t he Er osi on Cont r ol Li ne ( ECL) pr i or t o sunr i se or af t er sunset . Sunr i se and sunset wi l l var y dependi ng on t he t i me of year ; however , no wor k wi l l be per mi t t ed pr i or t o 7: 00am or af t er 7: 00pm shoul d t he sun r i se bef or e 7: 00am and/ or t he sun set af t er 7: 00pm.
SECTI ON 01 11 00 Page 3
1. 3. 5. 3 St agi ng Ar eas f or Const r uct i on Equi pment on t he Beach
See Sect i on 01 57 20 f or per i ods when st agi ng ar eas f or const r uct i on equi pment on t he beach i s not per mi t t ed.
1. 4 COMMENCEMENT, PROSECUTI ON AND COMPLETI ON OF WORK
Read t hi s par agr aph i n conj unct i on wi t h t he Cl ause COMMENCEMENT, PROSECUTI ON, AND COMPLETI ON OF WORK ( FAR 52. 211- 10) of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1.
1. 5 LI QUI DATED DAMAGES - CONSTRUCTI ON
Ref er t o t he Cl ause LI QUI DATED DAMAGES - CONSTRUCTI ON ( FAR 52. 211- 12) of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1.
1. 6 PHYSI CAL DATA
Read t hi s par agr aph i n conj unct i on wi t h t he Cl ause PHYSI CAL DATA ( FAR
52. 236- 4) of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1.
1. 6. 1 Physi cal Condi t i ons
The i ndi cat i ons of physi cal condi t i ons on t he dr awi ngs and i n t he speci f i cat i ons ar e t he r esul t of s i t e i nvest i gat i ons by sur veys and/ or by cor e bor i ngs. When t he i ndi cat ed physi cal condi t i ons ar e t he r esul t of s i t e i nvest i gat i ons by cor e bor i ngs, t he cor e bor i ng l ogs and l abor at or y dat a ar e i n Sect i on 00 31 32 GEOTECHNI CAL DATA REPORT ( GDR) and t he cor e bor i ng l ocat i ons ar e shown on t he dr awi ngs. Al so, see t he GDR f or i nst r uct i ons concer ni ng avai l abi l i t y of cor e bor i ngs f or i nspect i on.
1. 6. 2 Weat her , Wat er St age and Ti de Dat a
See Sect i on 00 33 50 WEATHER, WATER STAGE AND TI DE DATA.
1. 6. 3 Hydr ogr aphi c Sur veys
Hydr ogr aphi c sur veys ar e post ed as separ at e el ect r oni c f i l es. Sur vey number s ar e i ndi cat ed on t he dr awi ngs.
1. 6. 4 Cont r act or I nvest i gat i on
Ref er t o t he Cl ause SI TE I NVESTI GATI ON AND CONDI TI ONS AFFECTI NG THE WORK ( FAR 52. 236- 3) of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1.
1. 7 LAYOUT OF WORK
Read t hi s par agr aph i n conj unct i on wi t h t he Cl ause LAYOUT OF WORK ( FAR
52. 236- 17) of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1.
1. 7. 1 Est abl i shed Pr oj ect Cont r ol
The Gover nment has est abl i shed monument s al ong t he wor k s i t e( s) . Each monument i s r epr esent ed i n t he cont r act dr awi ngs by a Desi gnat i on and i n most cases, an al phanumer i c Per manent I dent i f i er ( PI D) . I nf or mat i on concer ni ng t he l ocat i on and el evat i ons can be f ound wi t hi n t he Sur vey Not es on t he pl an sheet s. The Sur vey Not es f or each i ncl uded f i el d sur vey wi l l c i t e a par t i cul ar sur vey number , and speci f y t he cont r ol used t o
SECTI ON 01 11 00 Page 4 conduct t hat sur vey. Addi t i onal i nf or mat i on i s i ncl uded i n t he Sur vey Not es t hat must be dupl i cat ed i f an at t empt t o r ecr eat e t he subj ect sur vey i s desi r ed.
For navi gat i on channel s, t he Gover nment has est abl i shed t i dal cal i br at i on s i t es f or pr oj ect s const r uct ed and mai nt ai ned t o a t i dal dat um. Each t i dal cal i br at i on s i t e i s r epr esent ed i n t he pl an sheet dr awi ngs by St at i on I D, and i s c i t ed i n t he Sur vey Not es. Al l pr oj ect s const r uct ed and mai nt ai ned t o a t i dal dat um shal l be cal i br at ed t o t he St at i on I D speci f i ed i n t he pl an sheet dr awi ngs. I nf or mat i on r egar di ng t he l ocat i on and associ at ed benchmar ks of t he r ef er enced St at i on I D i s i ncl uded i n t he Monument Descr i pt i on sect i on of t hese speci f i cat i ons.
See Sect i on 00 31 21 CONTROL MONUMENT DESCRI PTI ONS.
1. 7. 2 Layout
Fr om t he monument s, cont r ol dat a and el evat i ons est abl i shed by t he Gover nment , t he Cont r act or shal l compl et e t he l ayout of t he wor k and shal l be r esponsi bl e f or al l measur ement s t hat may be r equi r ed f or t he execut i on of t he wor k t o t he l ocat i on and l i mi t mar ks pr escr i bed i n t he speci f i cat i ons or on t he cont r act dr awi ngs, subj ect t o such modi f i cat i ons as t he Cont r act i ng Of f i cer may r equi r e t o meet changed condi t i ons or as a r esul t of necessar y modi f i cat i ons t o t he cont r act wor k.
1. 7. 3 Survey
The Cont r act or shal l f ur ni sh, at hi s own expense, such st akes, t empl at es, pl at f or ms, equi pment , t ool s and mat er i al , and al l l abor as may be r equi r ed i n l ayi ng out any par t of t he wor k f r om t he monument s, cont r ol dat a and el evat i ons est abl i shed by t he Gover nment . I t shal l be t he r esponsi bi l i t y of t he Cont r act or t o mai nt ai n and pr eser ve al l monument s, st akes and ot her mar ks est abl i shed by t he Cont r act i ng Of f i cer unt i l aut hor i zed t o r emove t hem, and i f such mar ks or monument s ar e dest r oyed by t he Cont r act or or t hr ough hi s negl i gence, pr i or t o t hei r aut hor i zed r emoval , t hey may be r epl aced by t he Cont r act i ng Of f i cer , at hi s di scr et i on, and t he expense of r epl acement wi l l be deduct ed f r om any amount s due or t o become due t he Cont r act or . The Cont r act i ng Of f i cer may r equi r e t hat wor k be suspended at any t i me when l ocat i on and l i mi t mar ks est abl i shed by t he Cont r act or ar e not r easonabl y adequat e t o per mi t checki ng of t he wor k.
1. 8 DAMAGE TO WORK
The r esponsi bi l i t y f or damage t o any par t of t he per manent wor k shal l be as set f or t h i n Cl ause PERMI TS AND RESPONSI BI LI TI ES of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1. However , i f , i n t he j udgment of t he Cont r act i ng Of f i cer , any par t of t he per manent wor k per f or med by t he Cont r act or i s damaged by f l ood, ear t hquake, hur r i cane, or t or nado, whi ch damage i s not due t o t he f ai l ur e of t he Cont r act or t o t ake r easonabl e pr ecaut i ons or t o exer ci se sound engi neer i ng and const r uct i on pr act i ces i n t he conduct of t he wor k, t he Cont r act or wi l l make t he r epai r s as or der ed by t he Cont r act i ng Of f i cer and f ul l compensat i on f or such r epai r s wi l l be made at t he appl i cabl e cont r act uni t or j ob pr i ces as f i xed and est abl i shed i n t he cont r act . I f , i n t he opi ni on of t he Cont r act i ng Of f i cer , t her e ar e no cont r act uni t or j ob pr i ces appl i cabl e t o any par t of such wor k, an equi t abl e adj ust ment pur suant t o Cl ause CHANGES of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1 wi l l be made as f ul l compensat i on f or t he r epai r s of t hat par t of t he per manent wor k f or whi ch t her e ar e no appl i cabl e cont r act uni t or j ob pr i ces. Except as her ei n
SECTI ON 01 11 00 Page 5 pr ovi ded, damage t o al l wor k ( i ncl udi ng t empor ar y const r uct i on) , ut i l i t i es, mat er i al s, equi pment and pl ant shal l be r epai r ed t o t he sat i sf act i on of t he Cont r act i ng Of f i cer at t he Cont r act or ' s expense, r egar dl ess of t he cause of such damage.
1. 9 EXI STI NG WORK
I n addi t i on t o " FAR 52. 236- 9, Pr ot ect i on of Exi st i ng Veget at i on, St r uct ur es, Equi pment , Ut i l i t i es, and I mpr ovement s" :
a. Remove or al t er exi st i ng wor k i n such a manner as t o pr event i nj ur y or damage t o any por t i ons of t he exi st i ng wor k whi ch r emai n.
b. Repai r or r epl ace por t i ons of exi st i ng wor k whi ch have been al t er ed dur i ng const r uct i on oper at i ons t o mat ch exi st i ng or adj oi ni ng wor k, as appr oved by t he Cont r act i ng Of f i cer . At t he compl et i on of oper at i ons, exi st i ng wor k shal l be i n a condi t i on equal t o or bet t er t han t hat whi ch exi st ed bef or e new wor k st ar t ed.
1. 10 TI ME EXTENSI ONS FOR UNUSUALLY SEVERE WEATHER ( 31 OCT 1989)
Thi s pr ovi s i on speci f i es t he pr ocedur e f or t he det er mi nat i on of t i me ext ensi ons f or unusual l y sever e weat her i n accor dance wi t h t he Cl ause DEFAULT ( FI XED- PRI CE CONSTRUCTI ON) of Sect i on 00700 CONTRACT CLAUSES i n Vol ume 1. I n or der f or t he Cont r act i ng Of f i cer t o awar d a t i me ext ensi on under t hi s c l ause, t he f ol l owi ng condi t i ons must be sat i sf i ed:
a. The weat her exper i enced at t he pr oj ect s i t e dur i ng t he cont r act per i od must be f ound t o be unusual l y sever e; t hat i s , mor e sever e t han t he adver se weat her ant i c i pat ed f or t he pr oj ect l ocat i on dur i ng any gi ven mont h.
b. The unusual l y sever e weat her must act ual l y cause a del ay t o t he compl et i on of t he pr oj ect . The del ay must be beyond t he cont r ol and wi t hout t he f aul t or negl i gence of t he Cont r act or .
1. 10. 1 Cont r act or Responsi bi l i t y
The pr oj ect ar ea may be af f ect ed by st or my, wi ndy and/ or r ai ny weat her , i ncl udi ng t hunder st or ms, dur i ng any t i me of t he year . The Cont r act or shal l be r esponsi bl e f or obt ai ni ng i nf or mat i on concer ni ng r ai n, wi nd and wave condi t i ons t hat coul d i nf l uence saf et y, haul i ng and pl acement oper at i ons pr i or t o submi t t i ng a pr oposal or bi d.
a. Cont r act or shal l r esear ch t he pr oj ect s i t e condi t i ons and i ncor por at e pot ent i al adver se weat her del ays i nt o t hei r schedul e pr i or t o submi t t i ng a pr oposal or bi d. The Cont r act or shal l devel op a schedul e of mont hl y ant i c i pat ed adver se weat her based on t he equi pment t o be used t o compl et e t he pr oj ect and det er mi ne t he condi t i ons t hat woul d cause t hem t o cease oper at i ons usi ng t he sour ces pr ovi ded i n Sect i on 00 33 50 WEATHER, WATER STAGE AND TI DE DATA. The Cont r act or ' s pr ogr ess schedul e must r ef l ect t hese ant i c i pat ed adver se weat her del ays i n al l weat her dependent act i v i t i es.
b. Upon acknowl edgment of t he Not i ce t o Pr oceed ( NTP) and cont i nui ng t hr oughout t he cont r act , t he Cont r act or wi l l r ecor d on t he dai l y CQC r epor t t he occur r ence of adver se weat her and unusual l y sever e weat her wi t h t he pur pose t o not e i mpact t o nor mal l y schedul ed wor k. Act ual adver se weat her del ay days must pr event wor k on cr i t i cal act i v i t i es
SECTI ON 01 11 00 Page 6 f or 50 per cent or mor e of t he Cont r act or ' s schedul e t o be consi der ed " unusual l y sever e weat her " .
c. The number of act ual adver se weat her del ay days shal l i ncl ude days i mpact ed by act ual adver se weat her , be cal cul at ed chr onol ogi cal l y f r om t he f i r st t o t he l ast day of each mont h, and be r ecor ded as f ul l days.
I f t he number of act ual adver se weat her del ay days exceeds t he number of days ant i c i pat ed f or adver se weat her by t he Cont r act or , t he Cont…